Day Shade Dept.

Duration Departmet Activity

1. Process understanding from department.


6 2. Machine Detail & Process Flow Chart.
3. Per day Machine Capacity.
4. Fabric Testing, Machine parameter.
FD1 & 5. Per day Machine Capacity.
Dyeing 2 6. Water uses & its Diagran.
FD2
7. Chemical recipe(Liquir Ratio).
8. Electrical Diagram.
7 9. Production Record.
10. Process Route Card.
11. Dyeing fault identification and root cause.
Responsible Person

Mr. Rawfur Rahman


Mr. Alamgir