ATTENTION : Date March 9 2021

PROJECT :

ITEM DESCRIPTION OF WORK QTY UNIT material cost labor cost unit cost TOTAL AMOUNT

1.0 mobilization / demobilization 1.00 lot 40,000.00 40,000.00

2.0 Excavation/Embankment 126.72 cu.m 1,100.00 1,100.00 139,392.00

3.0 Footing Concreting 9.98 cu.m 3,300.00 1,320.00 4,620.00 46,107.60

4.0 Footing Rebars 12mm dia x6m 88.00 pcs 234.00 93.60 327.60 28,828.80

5.0 Column Concreting 10.73 cu.m 3,300.00 1,320.00 4,620.00 49,572.60

6.0 Column Rebars 10mm dia 316.00 pcs 169.00 67.60 236.60 74,765.60

7.0 Formworks phenolic 3/4 x6m 22.00 pcs 1,100.00 440.00 1,540.00 33,880.00

8.0 Coco lumber 2x2x8' 30.00 pcs 120.00 48.00 168.00 5,040.00

Supply & Installation of 6 inches CHB with rebars


9.0 10mm and mortar 561.60 sqm 950.00 380.00 1,330.00 746,928.00

10.0 Tie wires #16 12.00 roll 800.00 320.00 1,120.00 13,440.00

11.0 Plastering works 1,123.20 sqm 400.00 160.00 560.00 628,992.00

Sub Total 1,806,946.60


Vat inclusive 216,833.59

Grand Total 2,023,780.19