1. Compressive strength results are satisfactory.

2. However, Contractor to properly mention the location of sample with reference to grids or area.
This is with view to trace the loaction in case required.
3. Contractor to prepare and submit the log sheet of test results for documentation and reference
purposes.
4. Contractor to submit original hard copies from third party.

Daud Aslam
Sr. Projects Manger

06-10-2021