Question/request: Send checklist for PMI VIT installation before commissioning attendance.

Answer: Please turn your attention to the attached cable diagrams. All of the components illustrated in
the cable diagrams must be installed and all cables must be in place according to cable diagram.
Below you have an overview of the installation.

Question/request: Investigate what job service engineer should do during the commissioning.

Answer: For the commissioning procedure please turn your attention to the enclosed documents
“[REF] PMI VIT, Commissioning, rev 2” and “PMI VIT, Final commissioning procedure [20150510]” in
the commissioning folder.

Question/request: Distribute PMI VIT commissioning procedure

Answer. The commissioning procedure is attached in this e-mail.