This approval sheet declares that the Acceptance Test Procedure (ATP) has been performed at the below location.
PO No : 4100002061 Site ID(PO) : TNR327
Site Name(PO) : N3TLONGAYAN Scope : Collocated 4G
Site ID/Site Name
On Air Date : 05-Oct-22 : TNR327 / N3TLONGAYAN
(Actual)
Azimuth -/140/300
Bandwidth 20
RRU RRU4480 B1 B3
BBU BB6630
Milestone Date
Site MOS : 03-Oct-22
Site Installation : 03-Oct-22
Site Connected : 04-Oct-22
Site On Air : 05-Oct-22
Checklist : COMPLETE
And the work has been considered as complete and satisfactory fulfil the standard technical requirements in Telkomsel project.
This certificate is fully signed by Telkomsel and Vendor on the date stated under this document and shall be enforced legally.
This certificate shall valid and binding under Indonesian laws and regulations.