A PEKERJAAN PENDAHULUAN
1 Pembuatan Papan Nama Proyek 1.00 unit 289,620.00 289,620.00 - 289,620.00 100.00%
B PEK. STRUKTUR
- Pek. Lantai Kerja Bawah Pondasi, tebal 5 cm 19.60 m² 59,390.00 1,164,044.00 - 1,164,044.00 100.00%
- Bekisting Pondasi dgn Pas. Bata ad. 1:5 14.40 m² 175,160.00 2,111,420.68 410,883.32 2,522,304.00 83.71%
- Beton f'c = 19,3 Mpa ( K-225 ) 4.32 m³ 1,364,130.00 5,630,211.94 262,829.66 5,893,041.60 95.54%
- Tul. Pokok (Besi Ulir) 116.16 kg 19,090.00 1,206,079.26 1,011,385.82 2,217,465.08 54.39%
- Tul. Bantu (Besi Ulir) 116.16 kg 19,090.00 1,206,079.26 1,011,385.82 2,217,465.08 54.39%
- Beton f'c = 19,3 Mpa ( K-225 ) 1.92 m³ 1,364,130.00 2,502,316.42 116,813.18 2,619,129.60 95.54%
- Tul. Pokok (Besi Polos) 409.08 kg 19,090.00 4,247,496.51 3,561,837.03 7,809,333.53 54.39%
- Tul. Pinggang (Besi Ulir) 103.02 kg 19,090.00 1,069,678.41 897,003.72 1,966,682.13 54.39%
- Beton f'c = 19,3 Mpa ( K-225 ) 4.32 m³ 1,364,130.00 5,630,211.94 262,829.66 5,893,041.60 95.54%
- Tul. Sudut (Besi Ulir) 280.30 kg 19,090.00 2,910,321.68 2,440,517.96 5,350,839.64 54.39%
- Tul. Tengah (Besi Ulir) 280.30 kg 19,090.00 2,910,321.68 2,440,517.96 5,350,839.64 54.39%
- Beton f'c = 19,3 Mpa ( K-225 ) 6.08 m³ 1,364,130.00 7,924,002.00 369,908.40 8,293,910.40 95.54%