1.)
Mobilization and Temp.
Facility
A. Initial Requirements
Mobilization & Demobilization 1.00 lot
Toll 2.00 cars 3,000.00 3,000.00
Gasoline 2.00 cars 8,000.00 8,000.00
Material Delivery 2.00 trips 4,000.00 4,000.00
Site Clearing and Hauling 2.00 trips 5,000.00 5,000.00
20,000.00
C. Labor
Foreman 2.00 1.00 pax 750.00 1,500.00
Laborers 2.00 2.00 pax 750.00 3,000.00
4,500.00
D. Equipment Consumables
Tent Barracks 1.00 set 4500.00 4500.00
Sleeping Bag 3.00 sets 700.00 2100.00
6,600.00
E. Subtotal 31,100.00
2.) Fencing of Lot Boundary thru
burrowing G.I. Pipe on G.I.
Wire Strapping
Effective Area of Work = 81m of 102m
A. Materials
G.I. PIPE SCHED 20 2" x 20' 27.00 pcs 1,404.00 37,908.00
#12 PVC COATED G.I. WIRE 25m 10.00 roll 2,940.00 29,400.00
67,308.00
B. Labor
Foreman 12.00 1.00 pax 750.00 9,000.00
Laborers 12.00 2.00 pax 600.00 14,400.00
23,400.00
C. Equipments & Consumables
Epoxy Enamel 4.00 gal 1768.00 7072.00
Shovel 3.00 sets FREE FREE
Heavy Duty Pliers 2.00 sets FREE FREE
Welding Machine 1.00 sets FREE FREE
Welding 7210 Mig Spindle 1.00 sets 1,200.00 1,200.00
8,272.00
D. Subtotal 98,980.00
LF - ARCHITECTURE OPC
Client: ANDRE PABLO FAUSTO Date: 19/10/2022
Project Address: Badihoy st. ext. Pinsao Proper, Baguio City
Project Description: Fencing
Prepared By: