You are on page 1of 151

HAMAD INTERNATIONAL AIRPORT EXPANSION PROJECT

CONCOURSE D & E WORKS

Material Submittal Approval Request for


(Pipe Fittings for Fuel Hydrant System (Temporary
Loop))
(Manufacturer: Van Leeuwen Pipe and Tube Arabia)

Document No. : ME-00065-A7110-CN-MCC-P-00-MAR-00001-00


Issue Status : For Approval
Project Phase : Construction Stage

Subcontractor’s
AMANA Qatar Contracting
name
Approved by: Checked and Reviewed by: Approved by:

Name Manny Abulencia Rony Seyouri Salah Al Moukhtar

Sr. Project
Job Title Coordinator Engineer QA/QC Manager Project Director
- Mechanical

Signature

Date 17-Nov-22

Document No. ME-00065-A7110-CN-MCC-P-00-MAR-00001-00

Current version of this document is available online on the local intranet in electronic format. Page 1 of 154
TABLE OF CONTENTS

1. LEED & GSAS Material Approval Request


2. Manufacturer company profile & ISO certificates
3. Product/technical data sheets
4. Project specifications
5. Drawing
6. Compliance Statement
7. Typical Material Test Report
8. Bill of Quantity
9. Material Submittal Previous Approvals for HIA.
10. Certificate of Origin (COO)

Document No. ME-00065-A7110-CN-MCC-P-00-MAR-00001-00

Current version of this document is available online on the local intranet in electronic format. Page 2 of 154
1. LEED & GSAS Material Approval Request

Document No. ME-00065-A7110-CN-MCC-P-00-MAR-00001-00

Current version of this document is available online on the local intranet in electronic format. Page 3 of 154
GSAS Materials Submittal Form Project : HIA - Fuel Hydrant System Contractor : ____________________
Name D&E Diversion Name

Subcontractor : __________AMANA________________________ Submittal No. : _____________________________

: __Manny Abulencia___ : ____11/16/2022_____ Material Cost (QAR) : _________Varies___________


Prepared by Name & Signature Date Required for all materials in Divisions 3-10, 31.6, 32.1, 32.3, 32.9. Do not include subcontractor
equipment or labor costs.

Product Name : SBC BEND (Elbows, Tees and End Cap___ Product No. : _______________________________________

Vendor Name : _______VANLEEUWEN_______________ Country of Origin : _____________KOREA________________

Verified by Contractor’s Approved GSAS


: _________________________________________ : _______________________________________
Certified Green Professional (CGP)
Name & Signature Date

Remark/Comment:______________________________________________________________________________________________________________
__________________________________________________________________________________________________________________________________
__________________________________________________________________________________________________________________________________

Applicable Credit(s)
Select  & fill relevant section below if the product
 S.7 – Heat Island Effect is a site surface finish
 S.10 – External Lighting is an exterior light fixture
 E1 to E6 – Energy is a wall / roof / glazing / HVAC equipment / light fixture / energy meter
 W.1 to W.3 – Water is a water fixture / water meter
 M.1 – Locally Sourced Materials is manufactured or assembled locally with content or components either coming from local or foreign origins
 M.2 – Materials Eco-Labeling is with GSAS approved certification for eco-labeling
 M.3 – Recycled Content of Materials is with recycled content (do not consider MEP systems and equipment)
 M.7 - Responsible Sourcing of Materials is with GSAS approved certification - Suppliers of timber products must hold FSC Chain of Custody certification
 IE.1 - Thermal Comfort is an air terminal device
 IE.8 - Acoustics is related to noise pollution (HVAC equipment / air terminal device) or noise control (finishing / door / glazing)
 IE.9 - Low-VOC Materials is with GSAS approved certification (interior and/or exterior)
 MO.4 - Leak Detection Systems is related to refrigerant or water leak detection
Page 4 of 154

P a g e 1|3 GSAS D&B 2019 - Submittal Form [Rev.1 - 04/11/2020]


S.7 – Site criterion 7: Heat Island Effect Use light colored, reflective materials for building exterior roofing and site surface finishes
Color of Material: ___________________________________________ Total Area (m2) covered by Material: _________________________________________
Albedo Value or Solar Reflectance (SR): ________________________  Lab Test Report has been provided with SR level highlighted

S.10 – Site criterion 10: External Lighting


Fixture Type: ______________________________________________ Fixture Wattage (W): _____________________________________________________

E.1 to E.5 – Energy criteria


 Glazing
U-value (W/m2.K): _________________________ Solar Factor (g-value): _______________________ Visual Lighting Transmittance (VLT-%): ________

 Insulation
Type: _______________ Installation:  Vertical Density (kg/m3): ______ Thickness (mm): ______ R-value (m2.K/W): _____
 Horizontal
 HVAC Equipment (AHU, FCU, CRAC, DX Unit, Fan)
Total Air Flow Rate (l/s): _____________________ Fan Power Consumption (kW): ___________________ Specific Fan Power (W/l/s): _________________
(provide calculation as Evidence)
Total Cooling Capacity (kW): __________________ Heat Recovery Efficiency (%): ____________________ Air Filter MERV Rating: _____________________

 Lighting System
Type: ____________________________________ Wattage: __________________________________ Lighting Power Density (W/m²): ______________
(provide calculation as Evidence)

 Domestic Water Heater


Type:  Electric Tank Capacity (l): _____________________ Electric Consumption (kW): ____________ Heater Efficiency (%): ______________
 Solar
 Water Pumps
Type: _________________________ Automated Control System:  Yes Power Consumption (kW): ___________
 No
 Energy Metering
Energy Meter Type: _______________________________________________  Energy Meter Integrated with BMS (provide BMS schedule of points as Evidence)

W.1 – Water criteria: Water Demand Performance


 Water Fixture  Irrigation System
Flow Rate (l/min): ________________ Flush Rate (l/min): _______________
(for flow fixture) (for flush fixture) System Name: ________________ System Type: ___________________

W.3 – Water criteria: Water Sub-Metering


Water Meter Type: ________________________________________________  Water Meter Integrated with BMS (provide BMS schedule of points as Evidence)
Page 5 of 154

P a g e 2|3 GSAS D&B 2019 - Submittal Form [Rev.1 - 04/11/2020]


M.1 – Materials criterion 1: Locally Sourced Materials Required for all materials in Divisions 3-10, 31.6, 32.1, 32.3, 32.9.
Manufacturing Location / Address: ____________________________________ Final Assembly Location / Address: ___________________________________
 Manufacturer’s documentation confirming location of plant from which this Percentage of Local Content:  Locally Assembled
product will be obtained has been provided  Less than 25%
 25% - 50%
 For products assembled from multiple components, a list of all material
 50% - 75%
components is attached
 More than 75%

M.2 – Materials criterion 2: Materials Eco-Labelling Use building materials and products with enhance environmental, health & resources conservation attributes.
 Single-Attribute Material  Multi-Attribute Material  with Environmental Product Declaration (EPD)
 GSAS approved certification for eco-labelling provided  Other certification, please specify: _________________________________

M.3 – Materials criterion 3: Recycled Content of Materials Required for all materials in Divisions 3-10, 31.6, 32.1, 32.3, 32.9 (Exclude MEP systems & equipment)
 Single Material Component  Assembly Composed of Various Materials
Percentage (%) of Recycled Content: _______________________________ Average (%) of Recycled Content: _________________________________
 Manufacturer’s documentation with recycled content highlighted has been provided to support this claim.

M.7 – Materials criterion 7: Responsible Sourcing of Materials


Timber Product  Yes Other Product, please specify: _______________________________________
 No
 Supplier FSC Chain of Custody Certification provided  GSAS approved certification for responsibly sourced materials provided

IE.1 – Indoor Environment criterion 1: Thermal Comfort


Air Outlet Type: ___________________________________________________ Outlet Throw at T50 [T0.25]: ________________________________________

IE.8 – Indoor Environment criterion 8: Acoustics


 Finishing Materials
 Ceiling Tiles  Flooring Tiles  Wall Panels  Windows  Doors Sound Absorption Coefficient: _________________

 HVAC Equipment (AHU, FCU, CRAC, DX Unit, Fan)  Air Outlet


Frequency 125 Hz 250 Hz 500 Hz 1000 Hz 2000 Hz 4000 Hz Type: ________________________ NC Level: ________________________
Sound Power
Level (dB)

IE.9 – Indoor Environment criterion 9: Low-VOC Materials Required for all materials used in the interior and exterior.
Material with zero or close-to-none rates of VOC emissions  Yes Application  Interior
 No  Exterior
 GSAS approved certification provided  Other certification, please specify: _________________________________

MO.4 – Management & Operations criterion 4: Leak Detection Systems


 Water Leak Detector  Integrated with BMS
Location: __________________________________
 Refrigerant Leak Detector (provide BMS schedule of points as Evidence)
Page 6 of 154

P a g e 3|3 GSAS D&B 2019 - Submittal Form [Rev.1 - 04/11/2020]


LEED Materials Submittal Form Project : HIA - Fuel Hydrant System Contractor : ____________________
Name D&E Diversion Name

Subcontractor : __________AMANA________________________ Submittal No. : _____________________________

: __Manny Abulencia___ : ____11/16/2022_____ Material Cost (QAR/US$) : _____________________________


Prepared by Name & Signature Date Required for all materials in Divisions 3-10, 31.6, 32.1, 32.3, 32.9. Do not include subcontractor
equipment or labor costs.

Product Name : SBC BEND (Elbows, Tees and End Cap___ Product No. : _______________________________________

Vendor Name : _______VANLEEUWEN_______________ Country of Origin : _____________KOREA________________

Verified by Contractor’s Approved LEED


: _________________________________________ : _______________________________________
Accredited Professional (AP)
Name & Signature Date
Remark/Comment:______________________________________________________________________________________________________________
_________________________________________________________________________________________________________________________________
_

Applicable Credit(s)
Select  & fill relevant section below if the product
 SSc7.1/SSc7.2 – Heat Island Effect is a roof or hardscape
 EAp2/EAc1 – Minimum / Optimize Energy is a wall or roof element / insulation / glazing
Performance
 WEp1/WEc3 – Water Use Reduction is a water fixture
 MRc4 – Recycled Content is with recycled content (do not consider MEP systems and equipment)
 MRc5 – Regional Materials is extracted, harvested or recovered, as well as manufactured, within 500 miles (or 800 Km) of the project (do not
consider MEP systems and equipment)
 MRc7 – Certified Wood is a new wood product permanently installed in the project
 IEQc4.1 – L.E.M.: Adhesives & Sealants is an adhesive, sealant or sealant primer
 IEQc4.2 – L.E.M.: Paints & Coatings is a paint or coating
 IEQc4.3 – L.E.M.: Flooring Systems is a carpet, carpet cushion, hard surface flooring (vinyl, linoleum, laminate, wood, ceramic, rubber & wall base)
 IEQc4.4 – L.E.M.: Composite Wood & is a particleboard, medium density fiberboard, plywood, wheatboard, strawboard, panel substrates & door cores
Agrifiber Products
 IEQc5 – Indoor Chemical & Pollutant is a permanent entryway system (grates, grilles, slotted systems, roll-out mats)
Source Control
Page 7 of 154

P a g e 1|4 LEED v3 - Submittal Form [Rev.1 - 11/02/2021]


SSc.7.1/SSc7.2 – LEED™ Sustainable Sites Credits 7.1/7.2: Heat Island Effect – NonRoof / Roof
Use light colored, reflective materials for building exterior roofing and site surface finishes
Color of Material: ___________________________________________ Total Area (m2) covered by Material: _________________________________________
Solar Reflectance Index (SRI): ________________________________  Lab Test Report has been provided with SRI value highlighted

EAp2/EAc1 – LEED™ Energy and Atmosphere Prerequisite 2/Credit 1: Minimum/Optimize Energy Performance
 Glazing
U-value (W/m2.K): ________________________ Solar Factor (g-value): _______________________ Visual Lighting Transmittance (VLT-%): ________

 Insulation
Type: ______________ Installation:  Vertical Density (kg/m3): ______ Thickness (mm): ______ R-value (m2.K/W): _____
 Horizontal

WEp1/WEc3 – LEED™ Water Efficiency Prerequisite 1/Credit 3: Water Use Reduction


 Flow Fixture Flow Rate (l/min): ________________  Flush Fixture Flush Rate (l/min): _______________

MRc4 – LEED™ Materials and Resources Credit 4: Recycled Content. Required for all materials in Divisions 3-10, 31.6, 32.1, 32.3, 32.9
 Manufacturer’s documentation with recycled content highlighted has been
provided to support this claim. Total Recycled Content in this Product/Assembly : %_____________

 For a composite product/material, a list of all the components in the assembly is


attached providing required information as shown to the right. Post-Consumer Content: % _________ Pre-Consumer Content: %_____

MRc5 – LEED™ Materials and Resources Credit 5: Regional Materials [Harvested/Extracted/Salvaged & Manufactured]
Required for all materials in Divisions 3-10, 31.6, 32.1, 32.3, 32.9. Manufacturing refers to the final assembly of components into the building product that is furnished and installed by the tradesmen.
Option 1 – Within a radius of 500 miles (800 Km) from project site
 Manufacturer’s documentation confirming location of extraction/harvesting/
Address of Material Point of
salvage from which raw materials were obtained has been provided. : _____________ Miles from Project Site
Origin (Point of Extraction)
 Manufacturer’s documentation confirming location of plant from which this
product will be obtained has been provided Address of Manufacturing Plant
: _____________ Miles from Project Site
 Map Printout indicating distance to Project Address has been provided. (Point of Final Assembly)
Option 2 – Alternative Compliance Path (ACP) [total weighted average travelled distance from project site does not exceed 500 miles (800 Km)]
If material/product is shipped by more than one transportation mode: Distance by Rail : ____________ Miles from Project Site
 Map Printout indicating total travel distance from extraction or harvest through Distance by Inland Waterway : ____________ Miles from Project Site
fabrication and delivery to project site has been provided
 Documentation showing traveled distance for each transportation mode as shown Distance by Sea : ____________ Miles from Project Site
to right
 For products assembled from multiple components, a list of all material Percentage (by weight) this Component Contributes to
: %____________
components is attached providing information as shown to right. Total Product Assembly is
Page 8 of 154

P a g e 2|4 LEED v3 - Submittal Form [Rev.1 - 11/02/2021]


MRc7 – LEED™ Materials and Resources Credit 7: Certified Wood Required for all materials in Divisions 3-10, 31.6, 32.1, 32.3, 32.9
 Yes
Is this Product FSC Certified?
 No
FSC Certification No. : ___________________________________ FSC Claim of the Product : %_____________________________
Total Cost of New Wood Material : $__________________________________ Cost of FSC Wood Material Only : $______________________________
 A breakdown of the product components and final FSC Claim calculations has been provided

IEQc4.1 – LEED™ Indoor Environmental Quality Credit 4.1 – Low Emitting Materials: Adhesives & Sealants
Required for all materials used in the interior. Check appropriate box below to indicate specific product type (LEED™ VOC limit is indicated in g/L for each):
Welding & Installation Adhesives Substrate Adhesives Sealants Sealant Primer
 Non-vinyl backed installation(150)  PVC welding (510)  Metal to metal (30)  Architectural (250)  Architectural [non-porous] (250)
 Carpet pad installation (150)  CPVC welding (490)  Plastic foams (120)  Roadways (250)  Architectural [porous] (775)
 Wood flooring installation (150)  ABS welding (400)  Porous material  Roofing material  Other (750) - Specify: ________
 Ceramic tile installation (130)  Plastic cement welding (350)  except wood (120) installation (450)
 Dry wall & panel installation (200)  Cove base installation (150)  Wood (30)  PVC welding (480)
 Subfloor installation (200)  Adhesive primer for plastic (650)  Fiberglass (200)  Other (420) - Specify: ____
 Rubber floor installation (150)  All others (250) - Specify: _______
 VCT & asphalt tile install. (150)

 Manufacturer’s documentation (MSDS, MDS, or Test Report) has been provided with VOC information circled.
Area of Usage/Application Total Qty of Product Used in Interior Product VOC Level VOC Content Test Method
 Interior Product
 Exterior Product : ______________________ Gallons : ______________ Grams/Liter : _____________________________

IEQc4.2 – LEED™ Indoor Environmental Quality Credit 4.2 – Low Emitting Materials: Paints & Coatings Required for all interior materials
 Manufacturer’s documentation (MSDS, MDS, or Test Report) has been provided with the VOC level highlighted. Product Category
(as per LEED Reference Guide)
For Architectural Paints - based on Manufacturer’s stated Gloss Level - this product
 Flat  Non-Flat : _______________________________
is:
Area of Usage/Application Total Qty of Product Used in Interior Product VOC Level VOC Content Test Method
 Interior Product
 Exterior Product : ______________________ Gallons : ______________ Grams/Liter : _______________________________

IEQc4.3 – LEED™ Indoor Environmental Quality Credit 4.3 – Low Emitting Materials: Flooring Systems
Required for all flooring system component materials
Product Category
 Manufacturer’s documentation (Certification, MSDS, MDS, or Test Report) has been provided with all applicable (as per LEED Reference Guide)
information highlighted for each component of the floor system indicating compliance with LEED Requirements. : ______________________________
1. Flooring: Applicable Certificate/Test Report has been provided for the flooring
system (Green Label Plus, Floorscore, CDPH test).  Certification : No____________________________.
 Carpet and Rug Institute Green Label Plus program (GLP)
 Floorscore  Test Report (CDPH Standard Method V1.1-2010)
 California Department of Public Health (CDPH) Standard Method V1.1-2010 Page 9 of 154

P a g e 3|4 LEED v3 - Submittal Form [Rev.1 - 11/02/2021]


IEQc4.3 [Cont’d]
Required for all flooring system component materials

2. Concrete, wood, bamboo and cork floor finishes such as sealer, stain and finish:
 Supporting documentation (MSDS, MDS, or Test Report) has been provided for the VOC content
 All coatings are listed under IEQc4.2.
3. Adhesives and Grout:
 Supporting documentation (MSDS, MDS, or Test Report) has been provided for the VOC content
 All adhesives and grout are listed under IEQc4.1.

IEQc4.4 – LEED™ Indoor Environmental Quality Credit 4.4 – Low Emitting Materials: Composite Wood & Agrifiber Products
Required for all interior permanent composite
Product Category
 Manufacturer’s documentation has been provided highlighting declaration that no urea formaldehyde resins have (as per LEED Reference Guide)
been added to this product : _____________________________

IEQc5 – LEED™ Indoor Environmental Quality Credit 5 – Indoor Chemical and Pollutant Source Control
Permanent Entryway System: Dimension (Length x Width) in cm

 Grates  Grilles  Slotted System  Roll-out Matt  Other: _________ : _______________________________

Page 10 of 154

P a g e 4|4 LEED v3 - Submittal Form [Rev.1 - 11/02/2021]


2. Manufacturer company profile & ISO certificates

Document No. ME-00065-A7110-CN-MCC-P-00-MAR-00001-00

Current version of this document is available online on the local intranet in electronic format. Page 11 of 154
SUPPLIER’S PROFILE
M/s. VAN LEEUWEN PIPE AND TUBE ARABIA

Page 12 of 154
Global network
The addresses and contact details for all of our sites are available at:
www.vanleeuwen.com/locations. Our employees look forward to assisting you...

The global network of the Van Leeuwen Pipe and Tube Group.

Pipes are everywhere


In structures such as bridges, construction
cranes and stadiums. In means of trans-
portation, such as cars, trucks and boats.
In furniture, buildings, oil platforms, dairy
plants, lampposts... There was good reason Van Leeuwen Pipe and Tube Group B.V.
why one of Van Leeuwen’s former slogans

Van Leeuwen
Lindtsedijk 120, 3336 LE Zwijndrecht
PO Box 50, 3330 AB Zwijndrecht
was: the entire world revolves around The Netherlands
pipes. Today we profile ourselves as ‘more Telephone: +31 78 625 25 25
E-mail: vlptg@vanleeuwen.nl
than tubes’. Because we have become Internet: www.vanleeuwen.com ISO 9001

more than just a distribution company of more than tubes.


tubes and pipes.
more than tubes.

International Network Distribution Expertise Worldwide Stocks Customized Services Global Sourcing Project Management

Page 13 of 154
www.vanleeuwen.com
Markets and customers
Industry
In the Industry market the sectors we serve include the cylinder manufacturing, transportation, automotive, mechanical engineering,
agricultural machinery, and lifting and hoisting equipment sectors. We supply the builders of steel structures, ships, bridges, stadiums and
windmills.

We offer a broad range of pipe and tube products and semi-finished goods, technological knowledge and knowledge of applications, online
applications such as a Certificate Portal, and logistics services, including customer-dedicated stocks and mechanical treatments, such as
laser and plasma cutting, bending, cutting and angular cutting, shot-blasting and red-leading.

Fluid Power Equipment Manufacturing Steel Constructions


Products and services
Our products
We offer any steel pipes, hollow sections, fittings, flanges and valves, axles and bar steel
imaginable, in accordance with any desired qualities and standards. In carbon steel, as
well as stainless and alloyed steel. We also supply specialized materials such as duplex

Van Leeuwen Pipe and Tube Group and super duplex. We offer all materials in accordance with current standards in the
Industry and Energy markets such as ASTM, API, ANSI, EN, ISO and DIN.

‘Van Leeuwen has the requisite technical


The Van Leeuwen Pipe and Tube Group is a globally knowledge in-house for delivering continuously
operating trading company that specializes in steel pipes with flexibility and speed.’
and pipe and tube applications. We offer a broad range
of customized pipe and tube products and services using Energy Our services
a worldwide network of stock-keeping branches. Each In the Energy market, we serve the (suppliers to the) mid and downstream industry, such as the storage of oil and gas, refineries, Customized treatments: including sawing, shot-blasting, machining and cutting
• 
the petrochemical and chemical industries, gas processing facilities, and water companies. We supply companies involved in power of materials, coating and chemical cleaning.
day our employees apply their specialist knowledge generation, such as coal and gas-fired power plants, sustainable energy and hydroelectric power. Van Leeuwen also supplies contractors Logistics services: worldwide sourcing network, stocks at strategic locations,
• 
of sourcing, project management, logistics and stock involved in drilling and production platforms, floating production storage and offloading (FPSO) platforms and operators in the subsea technical advice, inspections and material testing and express deliveries.
segment. Project management: ensuring that the right products are delivered on time
• 
planning on behalf of customers in the Industry and and with the right treatments; managing dedicated project stocks on-site.
Energy markets. We offer technical and logistics expertise, segment-specific stocks and project management, and our broad knowledge about steel
types, ranging from high strength to super duplex.
‘Thanks to its international presence and
distribution expertise, Van Leeuwen can provide
More than tubes Process Power Offshore/Oil and Gas

We have constantly evolved since us with high-quality pipes, anywhere in the


being founded in 1924: with more
products and services, as well as
world.’
a network comprising dozens of
largely stock-keeping branches in
Europe, the Middle East, Australia,
Quality, Safety and Environment
Quality, safety and healthy ways of working, and sustainability are a priority for
Asia and North and South America.
our company. We operate in accordance with ISO 9001:2015. Our Approved
We continuously strive for a match
Manufacturers List (AML) only contains certified suppliers, approved based on strict
between supply and demand in our
selection criteria. We pursue an active safety policy based on the Occupational
market, between the customer’s
Health and Safety Assessment Series (OHSAS 18001) standard. We adhere to the
wishes and solutions, between
international CSR guideline, ISO 26000, with regard to sustainability and an energy-
innovative developments and their
conscious approach to work.
application within our business and
that of our customers.
For a full overview of our products and services, visit www.vanleeuwen.com.
Page 14 of 154
Markets and customers
Industry
In the Industry market the sectors we serve include the cylinder manufacturing, transportation, automotive, mechanical engineering,
agricultural machinery, and lifting and hoisting equipment sectors. We supply the builders of steel structures, ships, bridges, stadiums and
windmills.

We offer a broad range of pipe and tube products and semi-finished goods, technological knowledge and knowledge of applications, online
applications such as a Certificate Portal, and logistics services, including customer-dedicated stocks and mechanical treatments, such as
laser and plasma cutting, bending, cutting and angular cutting, shot-blasting and red-leading.

Fluid Power Equipment Manufacturing Steel Constructions


Products and services
Our products
We offer any steel pipes, hollow sections, fittings, flanges and valves, axles and bar steel
imaginable, in accordance with any desired qualities and standards. In carbon steel, as
well as stainless and alloyed steel. We also supply specialized materials such as duplex

Van Leeuwen Pipe and Tube Group and super duplex. We offer all materials in accordance with current standards in the
Industry and Energy markets such as ASTM, API, ANSI, EN, ISO and DIN.

‘Van Leeuwen has the requisite technical


The Van Leeuwen Pipe and Tube Group is a globally knowledge in-house for delivering continuously
operating trading company that specializes in steel pipes with flexibility and speed.’
and pipe and tube applications. We offer a broad range
of customized pipe and tube products and services using Energy Our services
a worldwide network of stock-keeping branches. Each In the Energy market, we serve the (suppliers to the) mid and downstream industry, such as the storage of oil and gas, refineries, Customized treatments: including sawing, shot-blasting, machining and cutting
• 
the petrochemical and chemical industries, gas processing facilities, and water companies. We supply companies involved in power of materials, coating and chemical cleaning.
day our employees apply their specialist knowledge generation, such as coal and gas-fired power plants, sustainable energy and hydroelectric power. Van Leeuwen also supplies contractors Logistics services: worldwide sourcing network, stocks at strategic locations,
• 
of sourcing, project management, logistics and stock involved in drilling and production platforms, floating production storage and offloading (FPSO) platforms and operators in the subsea technical advice, inspections and material testing and express deliveries.
segment. Project management: ensuring that the right products are delivered on time
• 
planning on behalf of customers in the Industry and and with the right treatments; managing dedicated project stocks on-site.
Energy markets. We offer technical and logistics expertise, segment-specific stocks and project management, and our broad knowledge about steel
types, ranging from high strength to super duplex.
‘Thanks to its international presence and
distribution expertise, Van Leeuwen can provide
More than tubes Process Power Offshore/Oil and Gas

We have constantly evolved since us with high-quality pipes, anywhere in the


being founded in 1924: with more
products and services, as well as
world.’
a network comprising dozens of
largely stock-keeping branches in
Europe, the Middle East, Australia,
Quality, Safety and Environment
Quality, safety and healthy ways of working, and sustainability are a priority for
Asia and North and South America.
our company. We operate in accordance with ISO 9001:2015. Our Approved
We continuously strive for a match
Manufacturers List (AML) only contains certified suppliers, approved based on strict
between supply and demand in our
selection criteria. We pursue an active safety policy based on the Occupational
market, between the customer’s
Health and Safety Assessment Series (OHSAS 18001) standard. We adhere to the
wishes and solutions, between
international CSR guideline, ISO 26000, with regard to sustainability and an energy-
innovative developments and their
conscious approach to work.
application within our business and
that of our customers.
For a full overview of our products and services, visit www.vanleeuwen.com.
Page 15 of 154
Markets and customers
Industry
In the Industry market the sectors we serve include the cylinder manufacturing, transportation, automotive, mechanical engineering,
agricultural machinery, and lifting and hoisting equipment sectors. We supply the builders of steel structures, ships, bridges, stadiums and
windmills.

We offer a broad range of pipe and tube products and semi-finished goods, technological knowledge and knowledge of applications, online
applications such as a Certificate Portal, and logistics services, including customer-dedicated stocks and mechanical treatments, such as
laser and plasma cutting, bending, cutting and angular cutting, shot-blasting and red-leading.

Fluid Power Equipment Manufacturing Steel Constructions


Products and services
Our products
We offer any steel pipes, hollow sections, fittings, flanges and valves, axles and bar steel
imaginable, in accordance with any desired qualities and standards. In carbon steel, as
well as stainless and alloyed steel. We also supply specialized materials such as duplex

Van Leeuwen Pipe and Tube Group and super duplex. We offer all materials in accordance with current standards in the
Industry and Energy markets such as ASTM, API, ANSI, EN, ISO and DIN.

‘Van Leeuwen has the requisite technical


The Van Leeuwen Pipe and Tube Group is a globally knowledge in-house for delivering continuously
operating trading company that specializes in steel pipes with flexibility and speed.’
and pipe and tube applications. We offer a broad range
of customized pipe and tube products and services using Energy Our services
a worldwide network of stock-keeping branches. Each In the Energy market, we serve the (suppliers to the) mid and downstream industry, such as the storage of oil and gas, refineries, Customized treatments: including sawing, shot-blasting, machining and cutting
• 
the petrochemical and chemical industries, gas processing facilities, and water companies. We supply companies involved in power of materials, coating and chemical cleaning.
day our employees apply their specialist knowledge generation, such as coal and gas-fired power plants, sustainable energy and hydroelectric power. Van Leeuwen also supplies contractors Logistics services: worldwide sourcing network, stocks at strategic locations,
• 
of sourcing, project management, logistics and stock involved in drilling and production platforms, floating production storage and offloading (FPSO) platforms and operators in the subsea technical advice, inspections and material testing and express deliveries.
segment. Project management: ensuring that the right products are delivered on time
• 
planning on behalf of customers in the Industry and and with the right treatments; managing dedicated project stocks on-site.
Energy markets. We offer technical and logistics expertise, segment-specific stocks and project management, and our broad knowledge about steel
types, ranging from high strength to super duplex.
‘Thanks to its international presence and
distribution expertise, Van Leeuwen can provide
More than tubes Process Power Offshore/Oil and Gas

We have constantly evolved since us with high-quality pipes, anywhere in the


being founded in 1924: with more
products and services, as well as
world.’
a network comprising dozens of
largely stock-keeping branches in
Europe, the Middle East, Australia,
Quality, Safety and Environment
Quality, safety and healthy ways of working, and sustainability are a priority for
Asia and North and South America.
our company. We operate in accordance with ISO 9001:2015. Our Approved
We continuously strive for a match
Manufacturers List (AML) only contains certified suppliers, approved based on strict
between supply and demand in our
selection criteria. We pursue an active safety policy based on the Occupational
market, between the customer’s
Health and Safety Assessment Series (OHSAS 18001) standard. We adhere to the
wishes and solutions, between
international CSR guideline, ISO 26000, with regard to sustainability and an energy-
innovative developments and their
conscious approach to work.
application within our business and
that of our customers.
For a full overview of our products and services, visit www.vanleeuwen.com.
Page 16 of 154
Global network
The addresses and contact details for all of our sites are available at:
www.vanleeuwen.com/locations. Our employees look forward to assisting you...

The global network of the Van Leeuwen Pipe and Tube Group.

Pipes are everywhere


In structures such as bridges, construction
cranes and stadiums. In means of trans-
portation, such as cars, trucks and boats.
In furniture, buildings, oil platforms, dairy
plants, lampposts... There was good reason Van Leeuwen Pipe and Tube Group B.V.
why one of Van Leeuwen’s former slogans

Van Leeuwen
Lindtsedijk 120, 3336 LE Zwijndrecht
PO Box 50, 3330 AB Zwijndrecht
was: the entire world revolves around The Netherlands
pipes. Today we profile ourselves as ‘more Telephone: +31 78 625 25 25
E-mail: vlptg@vanleeuwen.nl
than tubes’. Because we have become Internet: www.vanleeuwen.com ISO 9001

more than just a distribution company of more than tubes.


tubes and pipes.
more than tubes.

International Network Distribution Expertise Worldwide Stocks Customized Services Global Sourcing Project Management

Page 17 of 154
www.vanleeuwen.com
Global network
The addresses and contact details for all of our sites are available at:
www.vanleeuwen.com/locations. Our employees look forward to assisting you...

The global network of the Van Leeuwen Pipe and Tube Group.

Pipes are everywhere


In structures such as bridges, construction
cranes and stadiums. In means of trans-
portation, such as cars, trucks and boats.
In furniture, buildings, oil platforms, dairy
plants, lampposts... There was good reason Van Leeuwen Pipe and Tube Group B.V.
why one of Van Leeuwen’s former slogans

Van Leeuwen
Lindtsedijk 120, 3336 LE Zwijndrecht
PO Box 50, 3330 AB Zwijndrecht
was: the entire world revolves around The Netherlands
pipes. Today we profile ourselves as ‘more Telephone: +31 78 625 25 25
E-mail: vlptg@vanleeuwen.nl
than tubes’. Because we have become Internet: www.vanleeuwen.com ISO 9001

more than just a distribution company of more than tubes.


tubes and pipes.
more than tubes.

International Network Distribution Expertise Worldwide Stocks Customized Services Global Sourcing Project Management

Page 18 of 154
www.vanleeuwen.com
Appendix C – Documented Procedures
Document ID Document Title
PR GLOG-01 E Receiving inspection stock deliveries
PR GLOG-02 E Stock count
PR GLOG-03 E Maintenance of buildings and warehouse equipment
PR GLOG-04 E Handling of material certificates
PR GLOG-05 E Handling of test, re-stamping and inspection sales orders
PR GLOG-06 E Collection export goods (FCA loading place)
PR GLOG-07 E Forwarding export deliveries (FCA/FOB/CTP/CFR/CIF/DDU/DDP)
PR GLOG-08 E Identification and traceability
PR GLOG-09 E Control of inspection and testing equipment
PR GMAN-01 E Organization structures, responsibilities, authorizations and competences
PR GMAN-02 E Management review
PR GMAN-04 E Handling of (special) customer complaints
PR GMAN-05 E Control of business processes
PR GMAN-06 E Management of information systems
PR GPUR-01 E Selection of AML manufacturers
PR GPUR-02 E Selection of project specific manufacturers and additional processors
PR GPUR-03 E Performance evaluation manufacturers
PR GPUR-04 E Handling of nonconforming products
PR GPUR-05 E Service provision
PR GPUR-06 E Compiling and management of product specifications
PR EGY SAL-10 E Guideline for assessment of project inquiry
PR EGY SAL-14 E Guideline for the handling of project orders
PR EGY SAL-19 E Instructions for buy-back
PR GSAL-02 E Handling of customer enquiries and orders
PR GSAL-03 E Evaluation of customer complaints
PR GSAL-04 E Customer satisfaction survey
PR EM SFE-01 Transporter Company Safety, Security, Health & Environment Check
PR EM SFE-02 Truck loading instruction for PFF regarding deliveries
PR EM QA-05 E PMI procedure
PR GQA-01 E Developing, coding, modifying and distribution of quality and safety management documents
PR GQA-02 E Internal audits
PR GQA-03 E Quality Plans

Page 19 of 154
Page 20 of 154
No part of this Manual Quality Assurance, Occupational Health & Safety, and Social Responsibility may be reproduced or used in
any form without written permission of the Van Leeuwen Pipe and Tube Group in Zwijndrecht, The Netherlands.

Page 21 of 154
Table of Contents

Profile of the Van Leeuwen Pipe and Tube Group ............................................................................................................. 3


The Van Leeuwen Identity .............................................................................................................................................. 3
Our Ambitions and Strategy ........................................................................................................................................... 3
Our Portfolio ................................................................................................................................................................... 4
Statement from the Executive Committee ......................................................................................................................... 5
1. Subject and Field of Application ..................................................................................................................................... 6
1.1 Field of Application ISO 9001 .................................................................................................................................... 6
1.2 Field of Application OHSAS 18001 ............................................................................................................................ 6
2. Normative Referral ......................................................................................................................................................... 6
3. Terms and Definitions ..................................................................................................................................................... 6
4. Quality and Occupational Health & Safety Management Systems ................................................................................. 7
5. Management Responsibility ........................................................................................................................................... 9
6. Resource Management ................................................................................................................................................. 10
6.1 Human Resources ................................................................................................................................................... 10
6.2 Infrastructure and Information Systems ................................................................................................................. 10
7. Realization of Products and Services ............................................................................................................................ 11
7.1 Planning of Product Realization .............................................................................................................................. 11
7.2 Customer-Related Processes .................................................................................................................................. 12
7.3 Procurement ........................................................................................................................................................... 12
7.4 Operations .............................................................................................................................................................. 13
7.5 Measurement, Analysis, and Improvements .......................................................................................................... 14
Quality of Suppliers and Procured Goods ................................................................................................................. 14
Customer Satisfaction ............................................................................................................................................... 14
Performance of Internal Processes ........................................................................................................................... 15
7.6 Continuous Improvement ....................................................................................................................................... 15
Appendix A – Sites With ISO 9001 Certification .................................................................................................................. i
Appendix B – Sites with OHSAS 18001 Certification .......................................................................................................... iv
Appendix C – Documented Procedures .............................................................................................................................. v

Document ID: MA GMAN-08 E


Total Number of Pages: 22
Revision Number: 22
Revision Date: 25 July 2018

Page 22 of 154
Profile of the Van Leeuwen Pipe and Tube Group
The Van Leeuwen Pipe and Tube Group is a globally operating trading company specialized in steel pipes and pipe &
tube applications for the Industry and Energy markets. What started out as a one-man company in 1924 in
Zwijndrecht, the Netherlands, has now grown into a global network of over fifty operating facilities in more than 20
countries on five continents, the majority of these being stock-holding branches. We offer a broad range of
customized pipe and tube products in various grades from stock, as well as a wide range of services. By applying our
specialist knowledge of sourcing, project management, logistics, and stock planning we help our customers achieve
their goals each and every day.

The Van Leeuwen Identity


Van Leeuwen is proud of its products and services, its history, and the entrepreneurial spirit that has moved the
company forward since 1924. We place great value on long-term continuity, and therefore look for long-term growth
instead of short-term profits. In doing so, we constantly focus on our customers and their ambitions: we are customer
oriented and dedicated to serving their needs. The strength of our worldwide logistics network ensures our ability to
efficiently deliver our products and services on a global scale, and allows us to further expand our knowledge and
experience. In this way, we also strive to stimulate innovative entrepreneurship. Our global network also means we
are connected with our markets, customers, and suppliers – anywhere in the world.

We strive to be a globally leading specialist in the supply of high quality steel pipes and pipe and tube applications,
while remaining true to our roots as a family-owned business. We achieve these goals by engaging in long-term
relationships with our stakeholders, and by delivering high-quality products and services to our customers in the
Industry and Energy markets. In all our actions, from procurement to the final delivery to the customer, we will uphold
the highest quality and safety standards in a socially responsible manner.

Our Ambitions and Strategy


At Van Leeuwen, we are constantly working to strengthen our leading position in the Industry and Energy markets in
Europe, Asia and the America’s and to continue our growth in the rest of the world. We do so via a process of directed
growth and the provision of enhanced services. In addition to organic growth, we are always looking for potential
acquisitions that help us grow in areas where we do not yet have in-house expertise, or in geographical areas where
we do not yet have a strong presence. Ultimately, it is our goal to provide our customers an unparalleled level of
service through a product and service package that is as complete as possible, all on a truly global scale.

With every new branch we open and every acquisition we make, we are looking to expand our product and service
portfolio along with our global footprint. By doing so, we are positioning Van Leeuwen for sustained growth in both
existing markets and new markets, in terms of product specialisms and geographies.

Ambition:
A globally
leading
Markets specialist
Strategy
Portfolio - Global Footprint
Identity - Organic Growth - Industry & Energy
- Extensive Stock - Targeted
- Family Owned Range Acquisitions
- Long-Term Focus - Valuable Services
- Customer Oriented

Page 23 of 154
Our Portfolio
Van Leeuwen’s core business is the trading of steel pipes and related products. Additionally, we offer an increasing
number of valuable services to our customers.

We have an extensive range of steel pipes and related products on stock. Our current stock range includes pipes,
tubes, hollow sections, bar steel, beams, valves, and components in varying grades and specifications of carbon, alloy,
stainless, and duplex steels. Keeping these products on stock enables us to quickly respond to our customers’
demands. Our large network of suppliers allows us to competitively source all products we carry on stock, and to fulfill
any special needs our customers may have.

In addition to our product range, we offer many value-adding services. These include material treatments, testing and
inspection, strength calculations, stock management and logistic services, project management and MRO, digital
services, and technical information.

Van Leeuwen’s combination of an extensive stock range and valuable services makes us the partner of choice for all
steel piping and tubing needs.

Page 24 of 154
Statement from the Executive Committee
The Executive Committee of the Van Leeuwen Pipe and Tube Group is dedicated to supplying high quality products
and services to the full satisfaction of our customers, to providing a safe working environment for our employees, and
to encouraging socially responsible behavior by everyone associated with Van Leeuwen. Supported by our policies on
Quality, Safety, and Social Responsibility, we work tirelessly on the continuous improvement of all aspects of our
operations. This way, we strive to ensure long-term relationships with our customers and stakeholders, as well as the
long-term growth of our company.

Quality
Van Leeuwen operates according to the ISO 9001 Quality Management standard. Market and customer requirements,
now and in the future, are leading in the further ambitions and development of our company. Our global stock
availability and logistics network, order and project handling capabilities, and carefully selected manufacturers
support us in achieving our ambitions. Our quality management system actively supports the implementation and
continuous improvement of our processes related to:

- Purchasing, stock-holding, additional processing, inspection, testing;


- Execution of customer orders received, including delivery of products and services, and;
- Carrying out all activities arising from acquired projects.

Occupational Health and Safety


We are committed to providing a healthy and safe work environment for our employees, to fulfilling the requirements
of applicable (local) laws and regulations regarding our business activities, and to working on the continuous
improvement of all aspects of occupational health and safety as outlined in OHSAS 18001. We have therefore
implemented a policy of:

- Prevention of illness and injury of our employees during work-related activities, such as order handling and
the packaging and dispatching of materials;
- Avoiding material damages, and;
- Care for the safety of visitors and sub-contractors at our sites.

Social Responsibility
At Van Leeuwen, we consider it an ongoing responsibility to combine the growth and long-term continuity of the
company with the well-being of our employees and the sustainability of the environment we operate in. It is our firm
belief that respect for human rights and the environment, fair labor and operating practices, and community
involvement & development, as mentioned in the ISO 26000 guideline, are essential to our way of doing business.

We are dedicated to the continuous improvement of our organization. To this end, we have appointed a Manager
Corporate Quality, Safety, and Environment and supporting local officers who coordinate and supervise the company’s
efforts in this area on behalf of the Executive Committee of the Van Leeuwen Pipe and Tube Group.

J.M. Sassen M.A.L.W.J. van Engelen


CEO Member of the Executive Committee
Van Leeuwen Pipe and Tube Group Van Leeuwen Pipe and Tube Group

Page 25 of 154
1. Subject and Field of Application
The Quality and Occupational Health & Safety management systems of the Van Leeuwen Pipe and Tube Group apply
to “Sales, procurement, stock-holding, and distribution of carbon steel, alloy, and stainless steel pipes and tubes,
hollow sections, valves, fittings, flanges, bars, structural steel, and related products, and services including cutting, re-
stamping as per Directive 2014/68/EU, and material finishing”.

1.1 Field of Application ISO 9001


As quality is of the utmost importance to Van Leeuwen, we strive to have all our branches ISO 9001 certified. Most
branches currently have this certification, and it is our goal to have new branches certified within three years of start-
up or acquisition. All sites with ISO 9001 certification are listed in Appendix A.

Since Van Leeuwen is a trading company, design and development are not part of our core activities.

1.2 Field of Application OHSAS 18001


At Van Leeuwen we have placed high priority on health and safety in the workplace. The OHSAS 18001 standard is the
starting point for our efforts in this area in all of our branches. The sites with OHSAS 18001 certification are listed in
Appendix B.

2. Normative Referral
The Quality and Occupational Health & Safety management systems of the Van Leeuwen Pipe and Tube Group have
been formulated with the objectives and organizational structure of the company in mind, and are in accordance with
the most recent version of the ISO 9001 and OHSAS 18001 standards, respectively. The Social Responsibility
management system will also be formulated in order to conform to the goals and structure of the company, and will
be compliant with the ISO 26000 guideline upon implementation.

3. Terms and Definitions


In the Quality management system of the Van Leeuwen Pipe and Tube Group, the terms and definitions as described
in the latest edition of ‘EN ISO 9000: Quality Management Systems – Fundamentals and vocabulary’ apply.

Page 26 of 154
4. Quality and Occupational Health & Safety Management Systems
The Quality and Occupational Health & Safety management systems of the Van Leeuwen Pipe and Tube Group
describe how the business processes employed by the Group and its companies are controlled. As a trading company,
the scope of these processes is from receiving a customer enquiry up to and including delivering the requested
products, services, and documents to the customer. This also includes the safety policies that must be adhered to in
all aspects of the day-to-day operations within the companies in the Group.

The implementation of the internal business processes is described in the relevant management system procedures.
The Van Leeuwen Pipe and Tube Group’s procedures are leading for the regions, and sites. Where required, they will
be supported by local procedures. In the event of disputes regarding the translation of documents for the Quality and
Occupational Health & Safety management systems, the authorized editions of the Van Leeuwen Pipe and Tube Group
are binding. This follows from the organizational structure of the Van Leeuwen Pipe and Tube Group:

The Manager Corporate Quality, Safety, and Environment (QSE) will regularly check whether the management systems
and all accompanying documents meet the applicable standards. Further responsibilities include the controlled
distribution of the documentation regarding the management systems, and any approved modifications. These
responsibilities are shared with local QSE officers at the regions, and/or sites.

With the statement of the Executive Committee regarding quality, safety and social responsibility as a starting point,
the Quality and Occupational Health & Safety management systems within Van Leeuwen are structured as follows:

Page 27 of 154
The internal business processes by which the companies within the Van Leeuwen Pipe and Tube Group fulfill the
requests and requirements of our customers are focused on the continuous improvement of all aspects of our
performance:

In our efforts towards the continuous improvement of our internal processes, we regularly measure the outcomes of
these processes. In order to interpret these measurements, Key Performance Indicators (KPIs) are employed on a
group-level. Regional and site managers may additionally establish KPIs for the control of (local) sub-processes. These
KPIs are subsequently used to formulate actions at a strategic and operational level that will lead to continuous
improvements of our processes and operations.

Page 28 of 154
5. Management Responsibility
The Statement from the Executive Committee serves as the foundation for the operational functioning of the Quality,
Occupational Health & Safety, and Social Responsibility management systems of the Van Leeuwen Pipe and Tube
Group and its companies. Management is responsible for the identification of management objectives that control the
business processes within Van Leeuwen. Additionally, management is responsible for the realization of these
objectives and for the execution of assignments, orders, and policies. Finally, a Manager Corporate Quality, Safety,
and Environment (QSE) will ensure maintenance of, and adherence to, all quality and safety management systems.

In order to control the business processes within the Van Leeuwen Companies, management objectives are identified
by the Executive Committee. Regional and site management are responsible for identifying objectives for the sub-
processes, as well as the implementation of actions required for the achievement of these objectives. Progress
towards their achievement is measured by means of KPIs. These are periodically reported to the Executive Committee
and are discussed with regional and site management during management reviews. Based on these discussions, new
objectives for the improvement of business processes, as well as corrective actions in case of non-conformities, are
identified and implemented.

Within this framework of objectives divisional, regional, and site management are responsible for the customer-
oriented and cost-effective functioning of their respective organizations. Additionally, they will ensure that all policies
regarding quality, safety, and social responsibility are implemented and understood by all employees. To that end,
they will make the necessary resources and qualified personnel available and will safeguard that the requirements
stemming from the management systems are adhered to. The responsibilities and required competencies of
employees, as well as the functional relationships between them, are documented in organizational diagrams, job
profiles, and procedures in the management systems.

The Executive Committee has appointed a Manager Corporate QSE for the Van Leeuwen Pipe and Tube Group, who
reports directly to the Executive Committee. The Manager Corporate QSE has full authority to ensure that all quality
and safety management systems are maintained to the latest standards and that they are adhered to. Local Quality
Assurance and Safety officers support the Manager Corporate QSE and report to their respective site’s management.

The Manager Corporate QSE performs an annual performance evaluation of the quality and safety systems of the Van
Leeuwen Pipe and Tube Group. This report is the basis for an annual assessment by the Executive Committee of the
functioning of the group’s policies and quality & safety systems. Additionally, a semiannual management review per
region and site is carried out with respect to the performance of these policies and systems.

Page 29 of 154
6. Resource Management
Van Leeuwen is dedicated to ensuring our Quality and Occupational Health & Safety systems are implemented and
well-maintained, and that our processes are continuously improved. Therefore, the required resources will be
allocated by senior management. Similarly, resources will be provided to ensure customer satisfaction by meeting
their requirements. Keys to achieving these two goals are human resources and an appropriate infrastructure, which
includes information systems.

6.1 Human Resources


All personnel of the Van Leeuwen Pipe and Tube Group and its companies have adequate theoretical knowledge and
practical skills to fulfill their jobs within our organization. To ensure their knowledge and skills are maintained at a high
level, Van Leeuwen provides training courses where required. The Executive Committee is responsible for formulating
the strategic policies that serve as a starting point for these courses. Taking local legislation into account, specific
attention will be paid to quality and safety in the workplace, environmental sustainability and labor conditions, and
the related rights and obligations of both the employee and the employer. All training courses taken by employees are
registered and archived.

Training plans for the divisions, regions, and sites are developed locally. The plans for key employees are reviewed
annually during a Group HR meeting with the Manager Corporate Human Resources. Local training plans are
supplemented by corporate Project Management and Management Excellence programs.

In addition to continuously improving the capabilities of our employees, their health and safety is a key focal point.
Each site has procedures in place for the notification, registration, and reporting of accidents in the workplace, and
more importantly, the prevention of accidents.

6.2 Infrastructure and Information Systems


The infrastructure at Van Leeuwen consists of three main components: buildings, equipment, and information and
communication systems. Buildings and equipment are necessary for the execution of our business processes, while
the information and communication systems support these processes.

In order to ensure safe and efficient operations, site managers are responsible for the systematic examination and
maintenance of all buildings (offices and warehouses), equipment, and machinery on their respective sites. Within the
context of local legislation and regulations, focal points are working conditions, health and safety, and the
environment. Van Leeuwen and its companies will always be in full compliance with all legislation and regulations
imposed on operations.

The information and communication systems are set up and maintained in accordance with the Van Leeuwen Pipe
and Tube Group’s IT strategy, which is applicable to all divisions, regions, and sites. Divisional and regional directors,
as well as the site managers, are supported by the Group’s Manager IT.

The setup and maintenance of the information and communication systems includes, at a minimum, the following:

 Managing the hardware and software;


 Guaranteeing the continuity of the information and communication systems, including ensuring a back-up
function;
 The implementation and maintenance of a help-desk function, and;
 Protecting the company’s data by allocating access authorizations and using protection systems (e.g. anti-
virus and firewall software).

10

Page 30 of 154
7. Realization of Products and Services
All companies within the Van Leeuwen Pipe and Tube Group provide our customers with products and services that
meet their specifications and requirements. We do so by carefully planning our product realization and managing our
customer-related processes, procurement, and operations. Additionally, we engage in the constant measurement,
analysis, and improvement of our activities. Central in all our efforts is the customer:

Planning

Continuous
Improvement Customer Procurement

Operations

7.1 Planning of Product Realization


At Van Leeuwen, we supply products that are in accordance with customer specifications as well as internationally
accepted norms and standards. We maintain detailed product descriptions and specifications. In order to ensure that
the products we procure are of high quality we utilize an Approved Manufacturers List (AML). Potential suppliers are
selected by following applicable group-procedures, and after successful completion of the procedure they are placed
on the AML. The AML is maintained centrally at the responsibility of the Manager Corporate QSE.

The majority of our products have material certificates which describe, for example, the material’s origin, history,
quality, tolerances, and more. A system is in place for random inspections of quality and potential defects upon
reception of products in our warehouses. We also carry out additional testing if the customer so desires.

The range of products Van Leeuwen companies carry on stock is determined by the regional and local directors, and is
managed by the respective sites’ logistics managers. Our business processes are carried out systematically in a
customer-oriented, cost-effective manner, and are supported by the necessary records.

The Manager Corporate QSE manages the following information in the Quality Assurance information system:

 Approved manufacturers;
 Product specifications;
 Quality assurance data regarding manufacturers and suppliers;
 Quality system documents of the group, divisions, regions, and sites, and;
 Norms and standards.

All documents are assessed and approved by authorized staff before they are made available to users through an
internal electronic network.

11

Page 31 of 154
7.2 Customer-Related Processes
Van Leeuwen provides customers with product information via the company website, by means of offline brochures,
and through direct communication. Additional information is made available to customers upon request.

All our products and services are supplied in conformance with the specifications and conditions that have been
agreed upon with the customer. Additionally, they comply with applicable statutory and regulatory requirements. Any
orders or projects are planned and carried out by the divisions, regions, or sites based on the stock range and delivery
programs of approved manufacturers, and where applicable conform to the customer’s requirements and
specifications regarding specific suppliers.

Before quotations and contracts are finalized and signed, any discrepancies with the original enquiry by the customer
will be identified and remedied. Supplementary requirements and contract changes by the customer are reassessed
by the responsible managers before they are accepted. All documents relating to submitted quotations and acquired
orders and projects are managed in accordance with the applicable procedures.

We take customer feedback very seriously. Any customer complaint will be handled professionally by our employees.
In case of customer complaints, we will work with our customer to remedy the situation, while also investigating the
cause of the complaint in order to take corrective and preventive actions.

7.3 Procurement
The Van Leeuwen Pipe and Tube Group has developed procedures for the procurement of products and services from
our suppliers. We procure from manufacturers that are approved under the responsibility of the Van Leeuwen Pipe
and Tube Group and have been placed on our Approved Manufacturers List.

We distinguish between procurement for stock and customer-specific procurement. Stock procurement is carried out
based on anticipated demand, product availability, and the applicable product specifications. Quotations from
manufacturers on the AML are requested, and based on these quotations the best supplier is selected. In case of
customer-specific procurements, product requirements are established in cooperation with the customer. Similarly to
stock procurement, these requirements determine the supplier selection. Before an order is placed at a manufacturer,
all purchase documents are assessed on completeness and accuracy by authorized staff.

Upon arrival of procured goods at a Van Leeuwen site, the required documentation is verified and a random quality
check is performed, all in accordance with established procedures and with the use of suitable equipment. Incoming
goods are assigned a unique identification code and, when approved, they are registered in our information systems
in a manner that allows recall or replacement at a later stage if non-conformities are discovered. In addition to our
own quality inspections, customers may inspect products at manufacturers’ sites or at Van Leeuwen premises upon
request. All inspection reports are archived and maintained in conformance with requirements and regulations.

12

Page 32 of 154
7.4 Operations
High quality product and service provision are Van Leeuwen’s core strengths. Therefore, the underlying processes
need to be well-managed. This starts with product descriptions, and continues with work instructions, equipment,
measurement and testing, product storage, and care for both our own and our customers’ properties.

Accurate and complete article descriptions are available to our employees and customers. These detailed article
descriptions, including the type of product, steel grades and qualities, and dimensions, are stored in our information
systems. Where applicable, production-heat codes are included. In this way, products that are stored in our
warehouses and those that have been sold to our customers can be traced back to individual production batches at
suppliers. This helps ensure that any non-conformity can be investigated and remedied.

To ensure a consistent process, detailed work instructions are made available to all employees. These work
instructions detail how specific tasks should be approached, and which steps need to be taken in order to complete a
task successfully and satisfactory. Group procedures may be supported by local procedures and work instructions if
the specific nature of the business or local regulations require so.

The use of suitable equipment is of the utmost importance for high-quality performance and a safe work
environment. All machines that are used at Van Leeuwen sites have been acquired specifically for their assigned tasks.
Only qualified and authorized personnel may operate machinery and perform maintenance. All maintenance is
executed periodically, or sooner if required, under strict safety guidelines. Van Leeuwen provides safety equipment
such as steel-toe boots to all employees who require them. For access to some areas, such as warehouses and
distribution locations (with the exception of clearly marked safe zones), the wearing of safety equipment is mandatory
to all, including office personnel and visitors.

Equipment for measuring and testing is available. This equipment is regularly calibrated in conformance with
regulations. Calibration, measuring, and testing are only carried out by competent and certified employees. In this
way, the validity of the outcomes is safeguarded. All calibrations, as well as the outcomes of measurements and
testing, are recorded and maintained in Van Leeuwen’s information systems.

The location, outfitting, and equipment of Van Leeuwen sites are carefully managed in order to ensure optimum
storage conditions for all stocked products. These stocked items are regularly inspected both quantitatively and
qualitatively according to established procedures. For specific products, some Van Leeuwen sites use automated
storage systems. Products with limited turnover are
identified promptly and actions are taken to ensure
they do not decline in quality. Storage,
conservation, packaging, and delivery all take place
in accordance with established procedures,
regulations, and – where applicable – with
customer requirements.

The Operations departments actively support the


logistic business processes of the divisions, regions,
and sites. Their aim is to provide a cost-effective
logistical operation that ensures the provision of
optimum service levels. Operations Managers are responsible for the creation of operational procedures for logistics
and expedition. The procedures are based on the strategy formulated by the divisional and regional directors and site
managers.

Whenever a customer’s property is on Van Leeuwen premises, employees of the Van Leeuwen Pipe and Tube Group
will exercise care when handling this property. If property is lost, damaged, or found unsuitable for use, it will be
registered and the customer will be immediately informed. A customer’s property can include physical property as
well as intellectual property and personal data.

13

Page 33 of 154
7.5 Measurement, Analysis, and Improvements
Within the Van Leeuwen Pipe and Tube Group measurement, analysis, and improvement are focused on three main
areas. These are (1) the quality of suppliers and procured goods, (2) customer satisfaction, and (3) the performance of
our internal processes. All measurements and analyses serve as input for the continuous improvement of Van
Leeuwen’s business processes. In addition, they can be useful investigative tools in case of incidental non-
conformance to rules, regulations, and standards.

Quality of Suppliers and Procured Goods


Supplier performance data is collected on a regular basis. At the reception of purchased goods random quality
inspections are carried out. Furthermore, any non-compliance with requirements of Van Leeuwen or our customers is
recorded. This non-compliance can be in various areas, such as
product characteristics and quality, accompanying documentation,
or delivery performance. Recorded data is combined with other
inputs on supplier performance and analyzed. Where necessary,
actions for improvement are agreed upon with manufacturers.

In case non-conforming products are discovered, they are


reworked or repaired, rejected, destroyed, or released to the
customer under concession. Reworked and repaired products are
tested and inspected to ensure they are up to standard. All non-
conforming products, the nature of the non-conformity, any
actions taken subsequent to the discovery of the non-conformity, and concessions obtained from the customer are
recorded and maintained. Overall performance is recorded in a central database.

Customer Satisfaction
The satisfaction of our customers with our products and services is critical to the long-term prospects of the Van
Leeuwen Pipe and Tube Group. We therefore invest great effort in understanding how satisfied our customers are,
and where we can improve our products, services, and processes.

Customer satisfaction is monitored by ongoing surveys carried out by the sites and regions. The objective of these
surveys is to gain insights into how our customers perceive the quality of the products and services provided by Van
Leeuwen, and what improvements can be made. The customers are selected based on several criteria that may
depend on the area of focus for that specific survey. For example, only customers that have purchased more than a
pre-determined value could be asked to participate in a particular survey.

The outcomes of all surveys are assessed and discussed by the regions, and sites during Management Review
meetings. The results of the surveys are then reported to the Manager Corporate QSE, who in turn reports the results
to the Executive Committee. The outcomes of these surveys serve as inputs for group-wide, divisional, regional, or
site-specific improvement programs.

In addition to customer surveys, Van Leeuwen records any customer complaint received. All complaints are analyzed
in order to determine the cause of the complaint. Corrective and preventive measures will then be taken. Similarly,
the success rate of quotations sent by Van Leeuwen companies is recorded and analyzed so that improvements can be
made.

14

Page 34 of 154
Performance of Internal Processes
To ensure that internal processes are working as they should, internal audits of all sites are regularly carried out. Their
purpose is to check for conformity to all regulations and requirements. The audits are performed by trained staff who
are independent of the business function that is audited. The results of these internal audits are reported to the staff
concerned. In case of non-conformity to rules and/or regulations, the problem must be remedied within six months (in
case of minor violations) or three months (in case of major violations) of the audit. Follow-up audits will be performed
to ascertain whether the measures taken have been adequate. The results of the internal audits are also used as the
basis for continuous improvement programs.

The Manager Corporate QSE monitors the execution of all internal audits, the reporting of non-conformities, and the
actions taken to remedy any non-conformity. Results are aggregated in a Performance Evaluation, which is
subsequently reported to the Executive Committee.

Whereas internal audits are conducted periodically, the day-to-day performance of the internal business processes is
measured in terms of Key Performance Indicators. These KPIs are based on the data reported through the ERP and
information systems. They are analyzed for trends and potential opportunities or issues. In case of deviations from
predetermined norms, or in some cases at the discretion of the responsible manager, analyses will be performed in
order to determine causes. Corrective or preventive measures will then be taken.

7.6 Continuous Improvement


We carefully plan our product realization and manage our customer-related processes, procurement, and product and
service provision. In addition, we constantly measure and analyze our performance in these areas. All this has one
goal: to continuously improve our processes, so that we can offer the best products and services to our customers’ full
satisfaction.

15

Page 35 of 154
Appendix A – Sites With ISO 9001 Certification
Head Office
Van Leeuwen Pipe and Tube Group B.V.
P.O. Box 50
3330 AB Zwijndrecht
Lindtsedijk 120
3336 LE Zwijndrecht
The Netherlands
Country/Region Site
The Netherlands P. van Leeuwen Jr’s Buizenhandel B.V.
P.O. Box 1
3330 AA Zwijndrecht
Lindtsedijk 100
3336 LE Zwijndrecht

Teuling Staal B.V.


Lindtsedijk 100
3336 LE Zwijndrecht
Van Leeuwen Precisie B.V.
P.O. Box 771
7400 AT Deventer
Hamburgweg 6
7418 ES Deventer
Van Leeuwen Stainless B.V.
P.O. Box 19
4153 ZG Beesd
Industrieweg 26
4153 BW Beesd
Belgium N.V. Van Leeuwen Buizen België
Schaarbeeklei 189
1800 Vilvoorde
Czech Republic Van Leeuwen Pipe and Tube s.r.o.
Vyškov
Krátká 3b
682 01 Vyškov-Předměstí 753
United Kingdom Van Leeuwen Ltd.
Nine Lock Works
Mill Street
DY5 2SX, Brierley Hill, West Midlands
Van Leeuwen Ltd.
Warth Business Centre
Warth Road
BL9 9TB, Bury, Lancashire
Van Leeuwen Ltd.
Brunel Road
Skippers Lane Industrial Estate
TS6 6JA, Middlesbrough, North Yorkshire
Van Leeuwen Ltd.
Unit 1A, Rotunda Business Centre
Thorncliffe Road
S35 2PG, Chapeltown, Sheffield, South Yorkshire

Page 36 of 154
Country/Region Site
France Van Leeuwen Tubes S.A.S.
63, Rue Général Hoche
76600 Le Havre
Van Leeuwen Tubes S.A.S.
P.O. Box 18
69881 Meyzieu Cedex
2, Avenue des Pays-Bas
69330 Meyzieu
Van Leeuwen Tubes S.A.S.
22, Rue du Quatre Septembre
75002 Paris
Asia Van Leeuwen Pipe and Tube (Singapore) Pte. Ltd.
4, Pioneer Place
627893, Singapore
Singapore
Van Leeuwen Pipe and Tube (Thailand) Ltd.
B. Grimm Alma Link Building, 10th floor
25 Soi Chidlom, Ploenchit,
Lumpini, Patumwan, Bangkok 10330
Thailand
Van Leeuwen Pipe and Tube (Thailand) Ltd.
Chonburi Industrial Estate (Bo-Win)
341 Moo 6, Highway No. 331 KM91
District Bo-Win, Amphur Sri Racha
20230 Chonburi Province
Thailand
Van Leeuwen Tube (Malaysia) Sdn.
Bhd. (22415-U)
Suite 11-02, Level 11, Merana IGB
The Boulevard, Lingkaran Syed Putra
59200 Kuala Lumpur
Malaysia
Van Leeuwen Pipe and Tube (Malaysia) Sdn.
Bhd. (59074-V)
Suite 11-02, Level 11, Merana IGB
The Boulevard, Lingkaran Syed Putra
59200 Kuala Lumpur
Malaysia
PT. Van Leeuwen Pipe and Tube Indonesia
th
Wisma 46, Kota BNI, 36 Floor
JI Jend Sudirman Kav. 1
Jakarta 10220
Indonesia

ii

Page 37 of 154
Country/Region Site
Middle East Van Leeuwen Pipe and Tube (Middle East) LLC
P.O. Box 47144
Al Karamah St., International Tower Suite 2105,
Adjacent to ADNEC,
Abu Dhabi
United Arab Emirates
Van Leeuwen Pipe and Tube Gulf FZE
P.O. Box 261145
OilFields Supply Center, B11, Jebel Ali free zone
Dubai
United Arab Emirates
Van Leeuwen KSA
P.O. Box 79420
United Business Systems Co / Van Leeuwen KSA
Prince Sultan St.,
Qurtoba Sehamiya Tower, Office 602
Al-Khobar 31952
Saudi Arabia

Van Leeuwen Pipe and Tube Oman


Division of Patron Energy
Building no 1060, Plot No. 15
Way No 3709
115 South Ghubra
Oman
Australia Van Leeuwen Pipe and Tube Australia PTY Ltd. (Adelaide)
1/261 Schumacher Road
Wingfield, SA 5013
Van Leeuwen Pipe and Tube Australia PTY Ltd. (Brisbane)
16 General Macarthur Place
Redbank, QLD 3201
Van Leeuwen Pipe and Tube Australia PTY Ltd. (Melbourne)
1/82 Greens Road
Dandenong South, VIC 3175
Van Leeuwen Pipe and Tube Australia PTY Ltd. (Perth)
31-35 Vulcan Road
Canning Vale, WA 6155
Van Leeuwen Pipe and Tube Australia PTY Ltd. (Sydney)
95-113 Lee Holm Road
St. Mary’s, NSW 2760

iii

Page 38 of 154
Appendix B – Sites with OHSAS 18001 Certification
Country/Region Site
The Netherlands Van Leeuwen Pipe and Tube Group B.V. (Head Office)
P.O. Box 50
3330 AB Zwijndrecht
Lindtsedijk 120
3336 LE Zwijndrecht
P. van Leeuwen Jr’s Buizenhandel B.V.
P.O. Box 1
3330 AA Zwijndrecht
Lindtsedijk 100
3336 LE Zwijndrecht

Teuling Staal B.V.


Lindtsedijk 100
3336 LE Zwijndrecht

France Van Leeuwen S.A.S.


P.O. Box 18
69881 Meyzieu Cedex
2, Avenue des Pays-Bas
69330 Meyzieu

Singapore Van Leeuwen Pipe and Tube (Singapore) Pte. Ltd.


4, Pioneer Place
627893, Singapore
Singapore

iv

Page 39 of 154
Appendix C – Documented Procedures
Document ID Document Title
PR GLOG-01 E Receiving inspection stock deliveries
PR GLOG-02 E Stock count
PR GLOG-03 E Maintenance of buildings and warehouse equipment
PR GLOG-04 E Handling of material certificates
PR GLOG-05 E Handling of test, re-stamping and inspection sales orders
PR GLOG-06 E Collection export goods (FCA loading place)
PR GLOG-07 E Forwarding export deliveries (FCA/FOB/CTP/CFR/CIF/DDU/DDP)
PR GLOG-08 E Identification and traceability
PR GLOG-09 E Control of inspection and testing equipment
PR GMAN-01 E Organization structures, responsibilities, authorizations and competences
PR GMAN-02 E Management review
PR GMAN-04 E Handling of (special) customer complaints
PR GMAN-05 E Control of business processes
PR GMAN-06 E Management of information systems
PR GPUR-01 E Selection of AML manufacturers
PR GPUR-02 E Purchases from Project Specific Manufacturers, Additional Processors and Stockholders
PR GPUR-03 E Approved Manufacturer Management
PR GPUR-04 E Handling of nonconforming products
PR GPUR-05 E Service provision
PR GPUR-06 E Compiling and management of product specifications
PR GPUR-07 E Purchases from NON-AML manufacturers
PR EGY SAL-10 E Guideline for assessment of project inquiry
PR EGY SAL-14 E Guideline for the handling of project orders
PR EGY SAL-19 E Instructions for buy-back
PR GSAL-02 E Handling of customer enquiries and orders
PR GSAL-03 E Evaluation of customer complaints
PR GSAL-04 E Customer satisfaction survey
PR EM QA-05 E PMI procedure
PR GQA-01 E Developing, coding, modifying and distribution of quality and safety management documents
PR GQA-02 E Internal audits
PR GQA-03 E Quality Plans

Page 40 of 154
vi

Page 41 of 154
▣ List of Certificate

No. Certificate Association Certi. No. Scope Valid Date

Manufacture and Sales of steel butt-welding pipe


KSA
fittings for ordinary use & fuel gas, steel butt-
1 ISO 9001 (Korean Standards QMS-2431 11 July, 2024
welding pipe fittings, steel plate butt-welding pipe
Association)
fittings and forged.

Manufacture and Sales of steel butt-welding pipe


KSA
fittings for ordinary use & fuel gas, steel butt-
2 ISO 14001 (Korean Standards EMS-1165 13 November, 2023
welding pipe fittings, steel plate butt-welding pipe
Association)
fittings and forged.

Manufacture and Sales of steel butt-welding pipe


KSA
fittings for ordinary use & fuel gas, steel butt-
3 ISO 45001 (Korean Standards HSS-0090 12 November, 2023
welding pipe fittings, steel plate butt-welding pipe
Association)
fittings and forged.

HSB Manufacture of seamless and welded Pipes,


4 PED (Hartford Steam HSB IE-20-02-034 Fittings and Flages including Industrial Metal 04 March, 2023
Boiler Ireland Limited) Forming.

배관용 강제 맞대기 용접식 관 이음쇠


공업용, 캡: 50A ~ 500A.
공업용, 45̊ , 90̊ 엘보 L형: 50A ~ 1000A
한국표준협회 공업용, 리듀서 동심1형: 50X40A ~ 600X400A
5 KS B 1543 제 16-0358 호 24 May, 2022
(KSA) 공업용, 리듀서 동심2형: 650X600A ~
1000X900A
공업용, T 같은 지름: 50A ~ 1000A
공업용, T 다른 지름: 50AX40A ~ 1000X900A

Page 42 of 154
Page 43 of 154
Page 44 of 154
Page 45 of 154
Page 46 of 154
Page 47 of 154
Page 48 of 154
Page 49 of 154
Page 50 of 154
3. Product/technical data sheets

Document No. ME-00065-A7110-CN-MCC-P-00-MAR-00001-00

Current version of this document is available online on the local intranet in electronic format. Page 51 of 154
Pipes & Fittings - Material Supply
SI # Category Manufacturer, Origin Applicable Pipes / Fittings Size per Manufacturer

1 Fittings - Bends, Elbow, Tees & Caps SBC Bend - South Korea All applicable sizes

NOTE: COATING AND LINING WILL BE SUBMITTED SEPARATELY

Page 52 of 154
Page 53 of 154
Page 54 of 154
Page 55 of 154
Page 56 of 154
Page 57 of 154
Page 58 of 154
Page 59 of 154
Page 60 of 154
4. Project specifications

Document No. ME-00065-A7110-CN-MCC-P-00-MAR-00001-00

Current version of this document is available online on the local intranet in electronic format. Page 61 of 154
PROJECT SPECIFICATION

SECTION 33 52 43.10
FUEL SYSTEM GENERAL PROVISIONS

A7111 CENTRAL CONCOURSE APRON

Hamad International Airport


Terminal Building Expansion Project

1 30-Oct-20 AN CS CS NE

0 31-Dec-2019 TYPSA JCR AAF AFL

REV DATE BY CHK APP

Project No. HIAEP-013

Hamad International Airport


Terminal Building Expansion Project 33 52 43.10/ 0. Rev. 1

Page 62 of 154
Hamad International Airport
Terminal Building Expansion Project 33 52 43.10/ 1. Rev. 1

Page 63 of 154
SECTION 33 52 43.10
FUEL SYSTEM GENERAL PROVISIONS

PART 1 - GENERAL

1.1 SUMMARY

A Work in this section includes furnishing all materials, labor and supervision necessary for
the construction of miscellaneous fuel system modifications. The work shall include all pipe,
fittings, valves, appurtenances and activities as specified herein and shown on the
drawings. All testing, inspection and flushing shall be provided as specified to provide a
complete and operational system.

B All permits and licenses that are required by governing authorities for the performance of
work shall be procured and paid for by the Contractor.

1.2 QUALIFICATIONS OF BIDDERS

A The Aviation Fuel Distribution System work shall be completed by a Contractor who
conforms to the following requirements:

1. Contractor must have been involved in the construction of commercial aviation fueling
industry projects for a minimum of ten (10) years.
2. Contactor must have successfully completed three (3) projects similar in complexity
and scope within the last five (5) years. The projects shall include installing internally
coated steel piping above and belowground, the installation of isolation valve vaults,
installation of horizontal fuel tanks, and construction of concrete vaults. The
Contractor shall provide a description of the referenced projects and client references
to include contact name, phone number and organization.
3. Contractor must have developed and implemented an aviation fuel system flushing
plan, using a method that utilizes flushing into mobile tankage. The flushing plan must
have incorporated the fuel quality requirements of ATA 103/JIG and EI-1540, EI 1541,
EI-1560 and EI-1585. Provide a list of projects with appropriate descriptions where
flushing plans have been developed and implemented by the Contractor.
4. Contractor has as a member of his team, a tunneling subcontractor who has
successfully completed a minimum of three tunneling projects of similar length and
diameter in the past ten (10) years. The tunneling subcontractor shall provide a
description of the referenced projects and client references to include contact name,
phone number and organization.
5. Contractor has as a member of his team, a controls subcontractor who has
successfully completed three (3) PLC based Emergency Fuel Shutoff Systems
(EFSO) projects requiring the integration and transmission of data for viewing at a
remote location (e.g. Tank Farm) for airport terminals with hydrant fueling systems.
The controls subcontractor shall provide a description of the referenced projects and
client references to include contact name, phone number and organization.

1.3 REFERENCES

A Refer to each individual section in this division for a list of applicable references from each
of the following organizations:

Hamad International Airport


Terminal Building Expansion Project 33 52 43.10/ 2. Rev. 1

Page 64 of 154
1. Energy Institute
a. EI 1540 Design, construction, commissioning, maintenance and testing of aviation
fuelling facilities
b. EI 1541 Requirements for internal protective coating systems used in aviation fuel
handling systems.
c. EI 1560 Recommended practice for the operation, inspection, maintenance and
commissioning of aviation fuel hydrant systems and hydrant system extensions.
d. EI 1585 Guidance in the cleaning of aviation fuel hydrant systems at airports
2. Air Transport Association (ATA)
3. American Petroleum Institute (API)
4. National Fire Protection Association (NFPA)
5. Underwriters Laboratories (UL)
6. American Society of Mechanical Engineers (ASME)
7. American Society for Testing and Materials (ASTM)
8. Environmental Protection Agency (EPA)
9. Factory Mutual Engineering Division (FM)
10. Industrial Risk Insurance (IRI)
11. Military Specifications (Mil)
12. Occupational Safety & Health Administration (OSHA)
13. Petroleum Equipment Industry (PEI)
14. Federal Aviation Administration (FAA)
15. Joint Inspection Group (JIG)

1.4 DEFINITIONS

A “Piping” includes in addition to pipe, all fittings, valves, sleeves, hangers, and other supports
and accessories related to such piping.

B The words “furnish and install”, “provide”, “furnish”, and “install” are used to mean the
Contractor shall furnish and completely install the system, service, equipment, or material
named along with other associated devices, equipment, material, wiring, piping, etc. as
required. System shall be a complete operating installation, and shall conform to the codes,
standards and guidelines applicable to this type of project.

C It is the intent of the specifications and drawings to call for finished work, tested and ready
for operation.

1. All apparatus, appliances, materials, or work not shown on drawings but mentioned in
specifications, or vice versa, and/or all incidental accessories necessary to make
work complete and ready for operation, even though not specified or shown on
drawings, shall be furnished and installed without increase in contract price.
2. Should there be discrepancies or questions of intent, refer matter to the Contracting
Officer’s Technical Representative (COTR) in writing for a decision before ordering
any equipment or materials or before starting any related work.

Hamad International Airport


Terminal Building Expansion Project 33 52 43.10/ 3. Rev. 1

Page 65 of 154
1.5 COMPLIANCE SUBMITTALS

A Submittals are required for all material specified in Divisions XX XX XX.XX. If material or
equipment is shown on the drawings to be included in this project but is not specified, the
Contractor shall bring this to the immediate attention of the COTR. Submittals are required
for all material and equipment incorporated into this project whether specified or not.

B Submittals are required for the proposed subcontractors primarily responsible for
tunneling/micro-tunneling, fuel pipe installation, EFSO controls and leak detection.

C The Contractor’s attention is called to the COTR’s review of Compliance Submittals. This
review shall be completed and the submittal returned to the Contractor before starting
procurement, installation or fabrication.

D The Contractor’s submission of a compliance submittal constitutes that he has both verified
and coordinated all dimensional data, quantities, field conditions, catalog data, and
compliance with the specification or he assumes full responsibility for doing so.

E Compliance Submittals shall include all components and units associated with
decommissioning the existing fuel hydrant system and fabrication of the new hydrant fueling
system as specified in the following Fuel System Work sections:

1. Fuel System Inspection, Testing and Flushing 330850.10


2. Fuel System Emergency Fuel Shutoff System 330950.11
3. Fuel System General Provisions 335243.10
4. Fuel System Piping Specialties 335243.11
5. Fuel System Pipe, Fittings and Installation 335243.13
6. Fuel System General Valves 335243.15
7. Fuel System Service Pits and Valve Vault Covers 335243.20
8. Fuel System Coating 335280.10
9. Fuel System Cathodic Protection System 335343.91
10. Fuel System Cathodic Protection System Testing 335343.92
11. Fuel System Pumps 335243.23
12. Fuel System Excavation, bedding and backfill 312323.13

F Submittal Formats are as follows:

1. Product Information: Submit manufacturer’s data sheets identifying equipment


size, descriptions, materials, ratings, etc.
2. Drawings: Submit drawings which graphically show relationship of various
components of the work, schematic diagrams of systems, details of fabrication,
layouts of particular elements, connections and other relational aspects of the work.
3. Instructions: Preprinted material describing installation of a product, system or
material, including special notices and material safety data sheet, if any, concerning
impedance, hazards and safety precautions.
4. Statements: A document required of the Contractor, or through the Contractor, from a
supplier, installer, manufacture, or other lower tier Contractor. The purpose of which
is to confirm the quality or orderly progression of a portion of the work by

Hamad International Airport


Terminal Building Expansion Project 33 52 43.10/ 4. Rev. 1

Page 66 of 154
documenting procedures, acceptability of methods or personnel, qualifications or
other verifications of quality.
5. Reports: Reports of inspections or tests, including analysis and interpretation of test
results. Each report shall be properly identified. Test methods used shall be identified
and test results shall be recorded.
6. Certificates: Statement signed by an official authorized to certify on behalf of the
manufacturer of a product, system or material, attesting that the product, system or
material meets specified requirements. The statement must be dated after the award
of this contract, must state the Contractor’s name and address, must name the
project and location, and must list the specific requirements that are being certified.
7. Records: Documentation to record compliance with technical or administrative
requirements.
8. Submittal Review Action:
a. Approved: Indicates information is sufficient in detail and adeq uately organized
for performance of the review. Material conforms to the intended functional
requirements of the contract documents and is approved for fabrication,
procurement and incorporation into the project as submitted.
b. Approved as Noted/No Resubmittal Required: Indicates information submitted is
sufficient in detail and adequately organized for performance of the review.
Material conforms to the intended functional requirements of the contract
documents and is approved for fabrication, procurement and incorporation into
the project as noted. Submitted item is not considered by the reviewer to be a
critical element of the project and/or noted comments are minimal in quantity and
complexity so that no additional review is necessary. Copies with limited marks
are acceptable to all parties as permanent record documents.
c. Approved as Noted/Resubmit: Indicates information submitted is sufficient in
detail and adequately organized for performance of the review. Item generally
conforms to the intended functional requirements of the contract documents and
is approved for fabrication, procurement and incorporation into the project as
noted. Submitted item is not considered by the reviewer to be a critical element of
the project but noted comments are sufficient in quantity or complexity so that
resubmission is appropriate to assure responsive action, or copies with marks are
not acceptable to all parties as permanent record documents. Item must be
resubmitted responsive to the reviewers’ comments.
d. Revise/Resubmit: Indicates information submitted may not be sufficient in detail
or adequately organized for performance of the review. Item may appear to
conform to the intended functional requirements of the contract documents but
certain elements do not or lack sufficient information to be evaluated. Item is not
approved for fabrication, procurement or incorporation into the project. Submitted
item is considered by the reviewer to be a critical element of the project and/or
noted comments are sufficient in quantity or complexity so that resubmission is
necessary to assure acceptable responsive action and conformance with the
contract documents. Item must be resubmitted responsive to the reviewers’
comments.
e. Rejected/Resubmit: Indicates information submitted is not sufficient in detail, is
not adequately organized for performance of the review, or does not conform to
the intended functional requirements of the contract documents. Item is not
approved for fabrication, procurement or incorporation into the project. Item must
be resubmitted responsive to the contract documents and reviewers comments.
f. No Action Required: Indicates item has been submitted for informational
purposes only and no action response or comments are needed by the reviewer.
Item should be retained in project files.

Hamad International Airport


Terminal Building Expansion Project 33 52 43.10/ 5. Rev. 1

Page 67 of 154
g. Not Subject to Review: Indicates submission of item was not required by the
contract documents and is not part of the reviewers’ contractual project scope.
Item is being returned without review or comment.

1.6 QUALITY ASSURANCE

A Materials and equipment shall be new, unused, and shall bear manufacture’s name, model
number, and other identification marking.

B Materials and equipment shall be standard product of manufacturer regularly engaged in


the production of required type of material or equipment for at least 5 years (unless
specifically exempted by COTR) and shall be manufacturer’s latest design having published
properties.

C If more than one unit of the same type of equipment is required, (i.e., control valves, manual
valves, etc.) they shall be products of a single manufacturer.

D All equipment, materials, components, coatings, and accessories provided shall be suitable
for use with the specific product. The following table is provided to indicate the basic design
conditions of the components:

SERVICE PRESSURE TEMPERATURE SPECIFIC GRAVITY

Jet Fuel 1,896kPa (275 psig) -29 to 43oC (-20 to 110F) 0.810.05

E The Contractor is responsible for protecting all equipment and material from loss or damage
until the system is completed and accepted by the COTR.

F The Contractor shall be responsible for coordinating with the manufacturer for installation of
the equipment furnished. The Contractor shall be responsible for warranty work required
and shall coordinate with the manufacturer of the equipment to accomplish warranty work
including any labor and additional cost for such warranty work. The equipment manufacturer
shall provide the Contractor with installation manuals and instructions. The Contractor shall
receive and install this equipment for a complete furnished and installed installation
including all accessories as specified within these specifications and as shown on drawings.

G The Contractor shall check equipment delivered to job site by the equipment supplier
against approved Compliance Submittals or other required documentation. The Contractor
shall report all discrepancies, shortages, or lack of data to the COTR and equipment
supplier for adjustments within one week after equipment is received. If such report is not
made within one week, it shall be assumed no discrepancies, shortages or lack of data has
been found.

H Contractor shall provide the following for all equipment furnished:

1. All rough-ins for equipment and accessories


2. Installation of loose trim provided with equipment by the equipment supplier
3. Furnish and install all piping connections, valves, unions, control valves, drains and
other accessories as indicated on the plans and as specified here within these
documents.

Hamad International Airport


Terminal Building Expansion Project 33 52 43.10/ 6. Rev. 1

Page 68 of 154
I The products of specific manufacturers have been used as the basis of design. Any
changes to the structure, piping, controls and electrical connections that result from the use
of other manufacturers shall be coordinated with all other trades by the Contractor and
approved in writing on letterhead by the COTR before the ordering of the equipment from
the manufacturer. Any resultant modifications required shall be performed without incurring
additions to the contract price.

J The bid shall be based only on products specified. The Contractor shall verify delivery dates
for timeliness before submitting his bid. Desired product substitutions shall be brought to the
COTR’s attention prior to bidding. No consideration shall be given to substitutions after bids
are received.

K Unless this Contractor states in writing at the time of pricing any and all exclusions to these
specifications or drawings in his bid proposal, this Contractor shall furnish and install at the
job site the equipment, material, labor and services as specified herein and shown on the
drawings for the amount of his bid.

1.7 DRAWINGS

A Drawings are diagrammatic and indicate the general arrangement of systems and work
included in the contract. Drawings are not to be scaled. All drawings and details shall be
examined and coordinated by the Contractor to establish exact location of piping and
equipment. Where conflicts occur, the Contractor shall inform the COTR immediately.

B The Contractor shall follow all contract drawings in laying out work and shall check shop
drawings of other trades to verify spaces in which work will be installed.

1.8 MAINTENANCE MANUALS

A In addition to the requirements specified in the General Conditions, at the project’s


completion, the Contractor shall submit a complete system Operating and Maintenance
Manual (O&M). The manual at a minimum shall include the following:

1. The manual shall be composed of typed instruction sheets with large drawing sheets
(not reduced) folded in with reinforced margin. It shall have a post binder system so
that the sheets can be easily substituted and shall have a hard cover.
2. The manual shall be organized into systems and shall contain the manufacturer’s
complete detailed operating and maintenance instructions with data sheets for each
piece of equipment furnished under this project.
3. Include a spare parts list for each major piece of equipment furnished for the project
including but not limited to:
4. Manual Valves
5. Leak detection system
6. Service pits
7. EFSO system
8. Leak detection system
9.8. Hydrant Cart Test Stand

Hamad International Airport


Terminal Building Expansion Project 33 52 43.10/ 7. Rev. 1

Page 69 of 154
10.9. Provide a comprehensive list of maintenance procedures for preventative
maintenance and troubleshooting; repair and reassembly, aligning and adjusting, and
disassembly.

1.9 NAMEPLATES

A All major equipment items shall have a permanent, stamped metal, nameplate. The
nameplate shall be permanently attached to the equipment in a manner such that it does
not hinder the operation of the equipment. All nameplates shall be protected from overspray
during field painting operations. Nameplates shall generally include the applicable items in
the following list:

1. Manufacturer’s Size and Type


2. Serial Number
3. Design Capacity
4. Design Pressure
5. Design Temperature
6. Code Conformance

1.10 CODE REQUIREMENTS AND PERMITS

A All work indicated on the contract drawings and herein specified shall conform with all
applicable codes or laws of the State of Virginia Qatar and any other governmental bodies
having jurisdiction and shall be installed to the satisfaction of the inspecting authority.

B Any deviations from the contract documents or specifications required for conformance with
the applicable codes or laws shall be made without change in contract price, but not until
such deviations have been brought to the attention of, and approved in writing, by the
COTR.

C The applicable codes and laws shall govern the minimum requirements only. Where the
drawings or specifications call for materials, construction limitations, or other similar
requirements in excess of the code requirements, the drawings and specifications shall be
followed.

D The Contractor shall obtain and pay for permits and licenses, and shall pay all fees and
taxes and give all notices bearing on the conduct of the work as drawn and specified.
Certificates of compliance, approval, or acceptance from all authorities having jurisdiction
over the work shall be obtained and delivered to the COTR.

E All work indicated on the drawings and herein specified shall conform with all applicable
standards of the National Fire Protection Association, American Petroleum Institute,
American National Standards Institute and American Society for Testing and Materials.

F All work indicated on the drawings, and herein specified, or tasks required in the
performance of the work but not specifically indicated in the drawing or specifications, shall
conform to the applicable requirements of the Occupational Safety and Health
Administration (OSHA) as provided in 29 CFR. Applicable requirements include, but are not
limited to, Part 1910 – Occupational Safety and Health Standards and Part 1926 – Safety
and Health Regulations for Construction.

Hamad International Airport


Terminal Building Expansion Project 33 52 43.10/ 8. Rev. 1

Page 70 of 154
G All equipment, materials, and specialties shall be installed and connected in accordance
with the best engineering practice and standards for this type of work. Unless otherwise
specified or shown on the drawings, the recommendations and instructions of the
manufacturer shall be followed for installing the work.

H The Contractor shall promptly notify the COTR in writing, of any instances in the
specifications or on the drawings that are in conflict with any of the aforementioned
authorities so that any required changes shall be adjusted before the contract is awarded. If
the Contractor performs any work contrary to such laws, rules, regulations or
recommendations, without notice, he shall bear all cost arising therefrom.

PART 2 - PRODUCTS

Not Applicable

PART 3 - EXECUTIONS

3.1 GENERAL INSTALLATION

A Contractor shall be responsible for the safety and protection from loss or damage of all
equipment and material received until all the work under this contract is complete and the
Contractor has received final acceptance. Protect all equipment and material during storage
and prior to start-up, which shall include the coverings of all openings, protection against
water intrusion or accumulation, protection against rust and other damage, etc.

B Contractor shall ensure that all equipment installed as part of this contract shall be properly
aligned, adjusted and lubricated before final acceptance.

C Contractor shall spot paint all equipment where the shop paint has been damaged or flaked
off.

D Furnish all bolts, studs, nuts and gaskets for makeup of all connections to the equipment
and replace all gaskets, bolts and fasteners damaged or as directed during the flushing
process.

E All connections to equipment shall be made with socket welds, unions or flanges.

3.2 REQUIREMENTS

A Mechanical and electrical designs are based on the requirements for the specified
manufacturers listed in the equipment specification. Conduit sizes are selected on the basis
of specified equipment. Increased manufacturers requirements necessitating piping
changes, additional power conductors, controls, foundations, etc., or any changes required
to accommodate any alternate or substitute manufacturer’s equipment, other than as shown
on drawings shall be provided without any increase in contract price by Contractor.

B Manufacturers, where specifically called for, must provide factory tests, unit installation
observations, unit start-up and tests, etc., as specified. Signed reports shall be submitted to
the COTR upon completion of these services. Subletting of these services will not be
permitted. Compliance Submittals shall be accompanied with a letter of certification by the

Hamad International Airport


Terminal Building Expansion Project 33 52 43.10/ 9. Rev. 1

Page 71 of 154
manufacturer that the specified services shall be provided. Failure to do so shall be cause
to reject the Compliance Submittals.

C The contract drawings are in part schematic, intended to convey the scope of work and
indicate the general layout, design, and arrangement. The Contractor shall follow these
drawings in the layout of his work and shall consult general construction drawings, electrical
drawings, and all other drawings for this project. Contractor shall verify all existing site
conditions to determine all conditions affecting the work shown or specified. The contract
drawings are not to be scaled and the Contractor shall verify areas in which the work is to
be installed.

D Follow drawings in laying out work, check drawings of other trades to verify spaces in which
work will be installed, and maintain maximum space conditions at all points. Where space
conditions appear inadequate, COTR shall be notified before proceeding with installation.

E All work shall be performed by trained personnel of the particular trade involved and shall
be done in neat and workmanlike manner as approved by the COTR.

1. Work shall be performed in cooperation with other trades and scheduled to allow
timely and efficient completion of project.
2. Furnish other trades advance information on locations and sizes of frames, boxes,
sleeves and openings needed for work. Also furnish information and shop drawings
necessary to permit other trades affected to install their work properly without delay.
3. Where there is evidence that work of one trade will interfere with work of other trades,
all trades shall assist in working out space conditions to make satisfactory
adjustments.

F Work installed before coordinating with other trades causing interference with work of such
other trades shall be changed to correct such condition without increase in contract price
and as directed by COTR.

G Where specific details and dimensions are not shown on the drawings, the Contractor shall
take measurements and make layouts as required for the proper installation of the work and
for coordination with all other work on the project. In case of any discrepancies between the
drawings and the specifications, it shall be assumed by the signing of the Contract that the
higher cost (if any difference in costs) is included in the contract price. The Contractor shall
perform the work in accordance with the drawings or with the specifications, as determined
and approved by the COTR.

H The Contractor shall be responsible for a scheduled sequence in performing the work so
that it will not interfere with the Authority’s operation. Before any work is started, the
Contractor shall consult with the COTR and arrange a satisfactory schedule.

1. Make temporary alterations as required to execute work so that all operations and
services are maintained with the minimum possible interruption.
2. Temporary shut-downs shall be segregated and shall be of the shortest possible
duration. All facilities shall be kept in continuous operation unless Authority grants
specific written permission to the contrary.

I It is the responsibility of the Contractor to monitor the construction area for the presence of
flammable vapors and to assure the proper construction methods and equipment is used if
hazardous conditions exist.

Hamad International Airport


Terminal Building Expansion Project 33 52 43.10/ 10. Rev. 1

Page 72 of 154
3.3 EXISTING CONDITIONS

A Each bidder shall inspect the site as required for knowledge of existing conditions. Failure to
obtain such knowledge shall not relieve the successful bidder of the responsibility to meet
existing conditions in performing the work under the contract.

B Where new work cannot be installed without changes in existing plant, facility, or systems or
where it is indicated on drawings to re-work an existing installation, this contract shall
include alterations to existing work as required to install new work. Additions to the contract
cost will not be allowed because of the Contractor’s failure to inspect existing conditions.

C Existing conditions indicated on the drawings are taken from the best information available
on previous contract drawings and from visual site inspection. They are not to be construed
as “As Built” conditions, but are to indicate the intent of this work. It shall be the
responsibility of the Contractor to verify all existing conditions at the project site and to
perform the work as required to meet the existing conditions and the intent of this work
indicated.

D Unless specified otherwise, all existing material and equipment shown or required to be
removed from existing construction and not shown to be reused or turned over to the
Authority shall become the property of the Contractor and shall be promptly removed from
the site.

E Any existing material or equipment which is to be reused or is to remain in place and which
is damaged by this Contractor in performing the contract work shall be repaired to the
satisfaction of the Authority or shall be replaced with new equipment and material.

3.4 STORING MATERIALS

A Unless otherwise arranged for by the Contractor, buildings of the Authority shall not be used
for Contractor storage or job office purposes. Open or exposed space for storage of
material and location of temporary job facilities will be allocated to the Contractor. The
Contractor, at his own expense, shall provide any temporary structures such as trailers and
sheds, as may be required for this purpose.

3.5 CUTTING AND PATCHING

A The responsibility for the cutting of existing masonry and concrete which is required for the
installation of new work shall be by the Contractor. The Contractor shall coordinate with the
Authority before any cutting and obtain approval from the Contracting Officer’s Technical
Representative (COTR) prior to any cutting.

B Cutting shall be done with extreme care and in such a manner that the strength of the
structure will not be endangered. Wherever possible, openings in concrete or masonry
construction shall be by concrete saw or rotary core drill. Openings in any construction shall
be cut the minimum size required for the installation of the work.

C Where openings or holes are cut in existing construction and the cutting breaks existing
electrical circuitry, control circuitry, communications, conduit, or wiring, then it shall be the
responsibility of the Contractor to have the circuitry, conduit, and rewiring re-routed as
required and as approved by the COTR. Temporary completion shall be provided where
necessary before the permanent re-routing and completion work is finished. All costs for this

Hamad International Airport


Terminal Building Expansion Project 33 52 43.10/ 11. Rev. 1

Page 73 of 154
work shall be the responsibility of the Contractor and no additions will be allowed to the
contract price.

D Where existing work is removed from openings in existing construction and the opening is
not to be reused for new work, the opening shall be filled and patched to match existing
adjacent construction.

3.6 BASES, FOUNDATIONS, SUPPORTS AND ATTACHMENTS

A The Contractor shall provide all structural steel, concrete, and materials necessary to
properly support and anchor equipment and lines provided under this contract.

B All equipment and materials shall be securely attached in an approved manner.


Attachments shall be of a strong and durable nature and suitable for the service required.

C Concrete bases shall be provided where shown on the drawings. Equipment which is to be
grouted in place shall be grouted with non-shrink grout.

D All equipment shall be mounted, aligned, adjusted, and serviced in accordance with
manufacturer’s recommendations before system testing and final acceptance of the system.

3.7 ELECTRICAL COORDINATION

A All electrical products and their installation shall conform unless otherwise specifically noted,
to applicable standards of the National Electrical Manufacturers Association, NFPA 70,
Division 33 of these specifications, and shall also be listed by Underwriter’s Laboratories,
Inc. and/or other agencies, as required.

3.8 TESTING LABORATORY SERVICES

A The Contractor shall secure the services of an independent testing laboratory approved by
the COTR to perform all testing, witnessing and certification of materials. This applies to
coating integrity, fuel acceptability, pressure tests and weld examinations.

B The cost for all laboratory services will be the responsibility of the Contractor.

C The laboratory shall:

1. Cooperate with the Contracting Officer’s Technical Representative (COTR), Authority


and Contractor; and provide qualified personnel promptly on notice.
2. Perform specified inspections, sampling and testing of materials and methods of
construction:
a. Comply with specified standards; ASTM, other recognized authorities and as
specified.
b. Ascertain compliance with requirements of contract documents.
3. Promptly notify the Contracting Officer’s Technical Representative (COTR), Authority
and Contractor of irregularities or deficiencies of work, which are observed during
performance of services.
4. Promptly submit 2 copies of reports of inspections and test to the COTR including:

Hamad International Airport


Terminal Building Expansion Project 33 52 43.10/ 12. Rev. 1

Page 74 of 154
a. Date Issued
b. Project Title and Number
c. Testing Laboratory Name and Address
d. Name and Signature of Inspector
e. Date of Inspection or Sampling
f. Record of Temperature and Weather
g. Date of Test
h. Identification of Product and Specification Section
i. Location in Project
j. Type of Inspection or Test
k. Observations Regarding Compliance with Contract Documents
5. Perform additional pre-approved services as required by the Contracting Officer’s
Technical Representative (COTR), Authority and Contractor.

Hamad International Airport


Terminal Building Expansion Project 33 52 43.10/ 13. Rev. 1

Page 75 of 154
6. The laboratory is not authorized to:
a. Release, revoke, alter, or enlarge on, requirements of contract documents
b. Approve or accept any portion of work
c. Perform any duties of the Contractor

D The Contractor shall:

1. Coordinate laboratory services, cooperate with laboratory personnel, provide access


to project and to manufacturer’s operations.
2. Furnish to laboratory preliminary representative samples of materials to be tested, in
required quantities.
3. Furnish labor and facilities:
a. To provide access to work to be tested
b. To obtain and handle samples at the site
c. To facilitate inspections and tests
d. For laboratory’s use for storage of test samples
4. Arrange with laboratory and pay for pre-approved additional samples and tests
required for Contractor’s convenience.
5. The Authority shall reserve the right to request the Contractor to obtain the services of
a separate, equally qualified independent testing laboratory, to perform additional
inspections, sampling and testing required when initial test indicate work does not
comply with contract documents. The Contractor shall pay the costs of such retesting.

3.9 WARRANTY BY CONTRACTOR

A Warrant all systems, equipment, materials and components installed under these
specifications for a period of not less than one (1) year from time of beneficial use of the
facility and systems by the Authority.

3.10 FIELD QUALITY CONTROL

A Be responsible for periodic inspections for conformance with the approved SPPP. The
results of the periodic inspections shall be submitted to the COTR upon completion.

END OF SECTION

Hamad International Airport


Terminal Building Expansion Project 33 52 43.10/ 14. Rev. 1

Page 76 of 154
PROJECT SPECIFICATION

SECTION 33 52 43.11
FUEL SYSTEM PIPING SPECIALITIES

A7111 CENTRAL CONCOURSE APRON

Hamad International Airport


Terminal Building Expansion Project

0 31-Dec-2019 TYPSA PCD AAF AFL

REV DATE BY CHK APP

Project No. HIAEP-013

Hamad International Airport


Terminal Building Expansion Project 33 52 43.11 / 0. Rev. 0

Page 77 of 154
SECTION 33 52 43.11
FUEL SISTEM PIPING SPECIALITIES

PART 1 - GENERAL

1.1 DESCRIPTION

A The work and components specified in this section are directly related to, but not limited to,
Section 33 52 43.13 - “Pipe, Fittings and Installation.”

B This section of the specification includes piping specialty items that are not considered
general piping materials, but are contiguous to the overall piping system.

C The Contractor shall provide the necessary labor and materials to install the items specified
herein, and as indicated on the Contract Drawings.

D All materials shall be of a domestic manufacturing process and shall be certified as such in
the Compliance Submittals.

E All components shall be suitable for use in aviation fuel systems with the fuel characteristics
specified in Section 33 52 43.10 – “General Provisions”.

1.2 RELATED SECTIONS

A Section 33 52 43.10 – Fuel System General Provisions

B Section 33 52 43.13 – Fuel System Pipe, Fittings & Installation

C Section 33 52 80.10 – Fuel System Coatings

D Section 33 08 50.10 – Fuel System Inspection, Testing and Flushing

1.3 SUBMITTALS

A Submit Compliance Submittals in accordance with Section 33 52 43.10 Fuel System


General Provisions.

B Product Information: Submit manufacturer’s data sheets identifying the make, model, type,
material, size, pressure rating, etc.

1.4 QUALITY CONTROL

A All piping specialties shall be in compliance with the applicable codes and standards such
as ASTM, ANSI, API, etc. as specified in Section 33 52 43.10 – “General Provisions”.

B The Contractor shall prepare and provide compliance submittals for all piping specialties
including the manufacturer, type, materials, and certifications required.

Hamad International Airport


Terminal Building Expansion Project 33 52 43.11 / 1. Rev. 0

Page 78 of 154
C For the purpose of standardization and conformance, components will be specified using a
manufacturer name and model number. It should be noted, the term “or approved equal”,
will be added so as not to limit the manufacturers listed.

PART 2 - MATERIALS

2.1 INSULATING KITS

A It is required to provide an insulation kit prior to transitioning underground at the Signature


fillstand to separate electrical charges between aboveground and underground piping.
Insulating kits shall also be used as indicated on the drawings to electrically isolate all
hydrant pit valves and to electrically isolate the motor operated valves from the cathodic
protection system. Insulating kits are also to be used where above grade piping transitions
to below grade piping.

B The gasket material is required to be fireproof and pass the requirements of the API 6FB,
3rd edition fire test. When required, the gasket material shall be manufactured by Pikotek
Model VCFS or approved equal.

C Joints shall consist of weldneck flanges or a weldneck flange with mating valve flange and a
flange insulation gasket.

D The insulation gasket assembly shall consist of a Polytetrafluoroethylene (PTFE) spring-


energized primary sealing element and an E-ring secondary seal all seated in a metal core.
The gasket assembly shall have 750-800 VPM dielectric strength and 448MPa (65,000 psi)
compressive strength. The gaskets have a thickness of 0.78cm (0.308 inch) for pipe
diameters sized 15cm (6 inches) to 36cm (14 inches).

E Insulating washers shall be G10 epoxy glass material, 0.32cm (1/8 inch) thick (minimum).
Dielectric strength shall be compatible with minimum insulating values of insulating sleeves
and gaskets. Furnish double quantity of insulating and cadmium-plated steel washers for
“full” insulation of flanges.

F Insulating sleeves shall be of spiral wound Mylar, 0.08cm (1/32 inch) wall thickness length
as required to match thickness of two series 150 raised face flanges plus insulation. Gasket
shall provide “full” insulation of studs, minimum dielectric strength shall be 4000 VPM.

G Flange assemblies shall provide a minimum resistance of 1,000 ohms measured between
each stud and both flanges (when dry).

2.2 PIPE SLEEVES

A To center, support, insulate and protect piping as it passes the concrete walls and slabs, a
pipe sleeve unit or series of components shall be used. Components shall be PSI Link-Seal
Model WS or approved equal.

B Sleeve sizes through 25.4cm (10 inches) shall be Schedule 40 steel pipe or standard wall
thickness. Sleeve sizes 30.5cm (12 inches) and larger shall have a 0.95cm (0.375 inch) wall
thickness or standard wall thickness.

Hamad International Airport


Terminal Building Expansion Project 33 52 43.11 / 2. Rev. 0

Page 79 of 154
C Provide an anchor collar of the same type of steel as the sleeve. The collar shall be welded
all around on both sides to the sleeve at the point on the sleeve that positions at the mid-
point of the structural wall or pad when the sleeve is in place.

D Sleeves shall be 5.1cm (2 inches) nominal pipe sizes larger for pipes less than 10.2cm (4
inch) diameter and two pipe sizes larger for pipes 10.2cm (4 inches) nominal diameter and
larger. Coordinate sleeve dimension with sleeve seal specified herein.

E Sleeves through walls and pads shall be cast in place. Piping shall be installed centered in
sleeve. Use one link seal unit at each end of the sleeve through walls to keep the
containment pipe in proper alignment.

F Firmly bolt a pipe insulator around the fuel pipe to prevent damage to the pipe coating.
Shoe height of runners shall be as required to center the pipeline in the sleeve. Insulator
shall be a segmented collar molded of high-density polyethylene with runners.

G To protect the seals and insulators, install a boot to permit ample movement of the carrier
pipe in a lengthwise, side, and vertical direction. The boot shall be oil, jet fuel, and water-
resistant double-accordion bellows-type molded. The bands shall be 1.3cm (1/2 inch) wide
stainless steel thumb- screw type with rounded edges which are easily tightened by hand or
by pliers.

2.3 PIPE SLEEVE SEAL

A Provide and install expanding seals at the end of all fuel piping buried in a casing and for pit
penetrations. Seal shall be as manufactured by PSI Link-Seal Model OS-316 suitable for -
40 to 210 degrees standard insulating type. The casing shall always be electrically isolated
from the carrier. Casing shall be 2 pipe sizes larger than the carrier pipe.

B Where sleeves are installed in dike walls, both sleeve and link seal shall be as fabricated by
PSI. The sleeve shall be configured with minimum dimensions and characteristics shown on
the drawings. Sleeves may be field fabricated or may be supplied by PSI. Regardless,
dimensions called out on the drawings shall be maintained as a minimum.

C Maintain electrical isolation from sleeve to rebar and from sleeve to piping.

2.4 PIPE SLEEVE INSULATORS

A Insulator shall be a segmented collar molded of high-density polyethylene with runners.


Components shall be manufactured by PSI or approved equal.

B Shoe height of runners shall be as required to center the pipeline in the sleeve.

C Insulator shall be bolted around the fuel pipe without damage to the coating.

2.5 SLEEVE BOOTS

A Boots shall be oil, chemical, and water resistant double accordion bellows type molded.
Components shall be manufactured by PSI or approved equal

B Boot shall permit ample movement of the carrier pipe lengthwise, side, and vertical
direction.

Hamad International Airport


Terminal Building Expansion Project 33 52 43.11 / 3. Rev. 0

Page 80 of 154
C The boot shall be a minimum of 3/8" thick with circumferential ribs molded in the inner
surface where bands are applied to increase the contact pressure for a tighter joint.

D The bands shall be 1.3cm (1/2 inch) wide stainless steel thumb screw type with rounded
edges which are easily tightened by hand or pliers.

E The boot shall have an extra thickness at the sleeve edge to protect the boot from damage
during backfill.

F The remainder of the boot shall be a minimum of 0.5cm (3/16 inch) thick.

G The boot shall be slipped on the fuel pipe before any tie-in weld is made.

2.6 15 GALLON SUMP SEPARATOR

A Provide a Schultz 56.8L (15 gallons), stainless steel sump separator or approved equal.
Unit shall be self-contained designed to separate water and dirt from fuel. Mount unit so top
is a maximum of 1.2m (4 feet) above ground to allow pouring of fuel samples into the
separator and high enough to enable draining of water from the separator with a 18.9L (5
gallons) bucket under the drain valve piping.

B Separator shall be piped to allow water to be drained by gravity by a 1.9cm (¾ inch) ball
valve with cam-lock and dust cap into bucket. A downstream hand pump shall draw off
clean product and return it to the storage. The clean suction line shall be 1.9cm (¾ inch)
and shall have a flanged insert check valve and spring return closed ball valve. All valves
shall be as specified in Section 33 52 43.15.

C Hand pump shall be as specified in Section 33 52 43.23.

2.7 HIGH POINT AND LOW POINT CONNECTIONS:

A Contractor shall provide and install 5.1cm (2 inches) dry break connections for each high
point vent and low point drain. Material shall be aluminum with male NPT connection and
Viton seals. Unit shall be Dixon model DDA200ALMNPT, or approved equal.

PART 3 - EXECUTIONS

3.1 INSTALLATION

A All components shall be installed in the piping system as indicated on the Contract
Drawings. Where exact dimensions are not indicated, the drawings may be scaled to
determine an approximate location.

B The Contractor shall be responsible for providing the necessary labor and materials to
install the component.

C The Contractor shall be responsible for providing the proper clearances of all components
to assure adequate operational and maintenance clearances.

3.2 INSPECTION AND TESTING

Hamad International Airport


Terminal Building Expansion Project 33 52 43.11 / 4. Rev. 0

Page 81 of 154
A The work will be inspected for approved manufacturer, component type and final
installation.

B The Contractor shall be responsible for the adjustments of all devices to assure proper
function of the device is provided.

3.3 FIELD QUALITY CONTROL

A Be responsible for periodic inspections for conformance with the approved SPPP. The
results of the periodic inspections shall be submitted to the COTR upon completion.

END OF SECTION

Hamad International Airport


Terminal Building Expansion Project 33 52 43.11 / 5. Rev. 0

Page 82 of 154
PROJECT SPECIFICATION

SECTION 33 52 43.13
FUEL SYSTEM PIPE, FITTING AND INSTALLATION

A7111 CENTRAL CONCOURSE APRON

Hamad International Airport


Terminal Building Expansion Project

1 30-Oct-20 An CS CS NE

0 31-Dec-2019 TYPSA JCR AAF AFL

REV DATE BY CHK APP

Project No. HIAEP-013

Hamad International Airport


Terminal Building Expansion Project 33 52 43.13 / 0. Rev. 1

Page 83 of 154
Hamad International Airport
Terminal Building Expansion Project 33 52 43.13 / 1. Rev. 1

Page 84 of 154
SECTION 33 52 43.13
FUEL SYSTEM PIPE, FITTINGS AND INSTALLATION

PART 1 - GENERAL

1.1 SUMMARY

A This Section of the specifications describes and provides for the furnishing, installing and
testing of pipe and piping components for the aviation fueling system.

1.2 PRODUCTS INSTALLED BUT NOT SUPPLIED UNDER THIS SECTION

A Not applicable

1.3 RELATED SECTIONS

A Section 33 52 80.10 – Fuel System Coatings

B Section 33 08 50.10 – Fuel System Inspection, Testing and Flushing

C Section 33 53 43.92 – Fuel System Cathodic Protection System

1.4 REFERENCES

A American Society for Testing and Materials (ASTM)

1. A53 - Pipe, Steel, Black, and Hot Dipped, Zinc Coated Welded and Seamless
2. A105 - Forging, Carbon Steel, for Piping Components
3. A193 – Alloy-Steel and Stainless Steel Bolting Materials for High-Temperature
Service
4. A194 - Carbon and Alloy Steel Nuts for Bolts for High Pressure and High
Temperature Service
5. A234 - Piping Fitting of Wrought Carbon Steel and Alloy Steel for Moderate and
Elevated Temperatures
6. D1655 - Standard Specification for Aviation Turbine Fuels

B American Society of Mechanical Engineers (ASME)

1. B1.20.1 – Pipe Threads, General Purpose


2. B16.5 - Pipe Flanges and Flanged Fittings
3. B16.9 – Factory Made Wrought Steel Butt Welding Fittings
4. B16.9 - Factory Made Wrought Steel Butt Welding Fittings
5. B16.11 - Forged Steel Fittings, Socket Welding and Threaded
6. B16.25 - Buttwelding Ends
7. B31.1 - Power Piping
8. B31.3 - Chemical Plant and Petroleum Refinery Piping

Hamad International Airport


Terminal Building Expansion Project 33 52 43.13 / 2. Rev. 1

Page 85 of 154
C American Petroleum Institute (API):

1. RP 1110 – Pressure Testing of Liquid Petroleum Pipelines


2. Spec 5L - Line Pipe
3. Std. 601.21 - Metallic Gaskets for Piping, Double-Jacketed Corrugated and Spiral
Wound

D Federal Specifications (FS) QQ-P-416 - Plating, Cadmium

E National Electrical Manufacturer’s Association (NEMA)

1.5 DEFINITIONS

A Unless otherwise specified, the working pressure ratings as used in these specifications for
valves, fittings, unions, and other piping specialties refer to pressure ratings in pounds per
square inch above atmosphere (PSIG) in accordance with applicable ASME Standards.
This document also provides the reference to the respective International Metric System.

B The use of the word "piping" shall be interpreted to include all pipe, valves, fittings, flanges,
supports, or accessories for any particular portion of the work, or system to which the word
"piping" is applied.

1.6 SUBMITTALS

A General: Compliance Submittals shall be in accordance with Section 33 52 43.10, Fuel


System General Provisions.

B Product Information: Submit manufacturer’s data sheets identifying equipment size,


materials, pressure ratings, etc.

1. Piping
2. Fittings (include specialty hot tap and line plug)
3. Flanges and Gaskets
4. Bolts, Nuts and Washers

C Reports

1. Radiograph Test Reports

D Certificates:

1. Pipe
2. Fittings (include specialty hot tap and line plug)
3. Flanges and Gaskets
4. Bolts, Nuts and Washers
5. Welder Performance Qualification (WPQ)
6. Welding Procedure Specifications (WPS)

Hamad International Airport


Terminal Building Expansion Project 33 52 43.13 / 3. Rev. 1

Page 86 of 154
7. Piping System Installation
8. Test Equipment and Results

E Records:

1. Procedure Qualification Records (PQR)

1.7 QUALITY ASSURANCE

A All pipe and piping materials shall be provided by a manufacturer and fabricator approved by
the COTR.

B Welding operations, qualification of welders and welding procedures shall comply with
ASME B31.3 and the ASME Boiler and Pressure Vessel Code, Section I and Section IX.
Certified copies of the welding procedure, the procedure qualification, and the welder,
qualification certification must be submitted prior to beginning any welding operations.

C Welders must be qualified to position 6G of ASME B31.3, tested on the type of pipe used in
this project, and must have been qualified within the six months preceding this project or the
welder shall be re-qualified.

D Contractor is responsible for all costs associated with procedure and welder qualifications.

E Internal Coating shall comply with EI 1541 “Requirements for internal protective coating
systems used in aviation fuel handling systems”. Material warranty shall be 10 years.
Certified copies of the quality control procedures and results of the internal pipe coating
application shall be submitted.

F Certified copies of the quality control procedures and results of the internal pipe coating
application shall be submitted.

G No foreign materials or components, supplied as part of this Section, shall be utilized. The
use of the words “domestic materials” or “no foreign materials” shall mean all materials shall be
of U.S. origin. The Contractor shall certify this condition in the compliance submittals. If at any
time, the COTR determines that any flanges, fittings, bolts or nuts are not of U.S. origin, the
Authority shall be entitled to replace the components without need for individual testing for
conformance to technical specifications. Contractor shall be responsible for all costs
associated with such replacement.

H The installation shall include all necessary materials, coating, supports, controls, valves and
fittings, hereinafter described or called for on the Contract Drawings accompanying these
specifications, or as necessary to make the installation complete.

I The drawings and specifications shall be considered complementary, one to the other, so
that materials and labor indicated, or called for, or implied by the one and not the other,
shall be supplied and installed as though specifically called for by both.

J All materials and equipment provided under these specifications shall be new, unused
products of manufacturers regularly engaged in production of such equipment for a
minimum of 5 years. All products shall conform to the applicable code or standard for its
manufacturing, fabricating and installation.

Hamad International Airport


Terminal Building Expansion Project 33 52 43.13 / 4. Rev. 1

Page 87 of 154
PART 2 - MATERIALS

2.1 PIPING MATERIALS

A The piping system is a combination of above ground and below ground piping. All above
ground piping shall be of single wall construction. Below ground piping is single wall
construction; however, a casing system is required for the two taxiway crossings. These two
casings require wax fill between the casing and carrier piping.

B All direct buried piping connections shall be welded. Welded joints shall conform to the
standards set forth in the ASME B31.3 Code for Petroleum Refinery Piping.

C Threaded joints are only allowed for small bore piping that has no internal pressure such as
vent or atmospheric drain piping. Threaded joints shall be American Standard for Pipe
Threads, ASME B1.20.1. All burrs shall be removed. Pipe ends shall be reamed out to size
of bore and all chips shall be removed. Teflon pipe thread sealant shall be used on the male
threads only and shall not extend past the end of the pipe.

D Furnish and install flanges where shown and at connections to all equipment. Flanged
connections are only allowed above ground or within pits/vaults. Flanges shall not be direct
buried except at temporary line plug (stopple) connections.

E Unless otherwise specified herein or stipulated on the Drawings, all flanges shall be
matched on piping, valve or equipment as to size, and shall be constructed from materials
equivalent to the piping. Flanges shall be raised face.

F Pipe fittings shall be of standard manufacture of materials, weight, and quality


corresponding to the pipe with which they are used.

G Fittings such as elbows, tees, reducers and caps shall be used for all changes in piping
direction, intersections, size changes and end closures unless otherwise stipulated on the
Drawings or specified herein.

H The manufacturer or supplier of the piping materials shall provide a certificate of the
inspection, stating origin of manufacture and that all material has been manufactured,
sampled, tested and inspected in accordance with the specified ASTM, API and other
identified specification and has found to meet those requirements.

I All piping shall be stamped with specification and grade. Shop coated pipe shall have
specification and grade stenciled on the coating.

J Galvanized piping is not allowed in the aircraft fueling system.

2.2 PIPING SPECIFICATIONS

A The following table is provided to indicate the basic design conditions of the components
within this section of the specification:

Hamad International Airport


Terminal Building Expansion Project 33 52 43.13 / 5. Rev. 1

Page 88 of 154
SPECIFIC
SERVICE SYMBOL PRESSURE TEMPERATURE
GRAVITY

Jet Fuel JF 1,896kPa (275 psig) -29 to 43oC (-20 to 110F) 0.810.05

Drain D 103kPa (15 psig) -29 to 43oC (-20 to 110F) 0.810.05

Vent V 0kPa (0 psig) -29 to 43oC (-20 to 110F) 0.810.05

B The following table is provided to indicate the various materials of construction for the
design service required by this specification.

ITEM 2” AND SMALLER 2 ½” AND LARGER

ASTM A53 Grade B ASTM A53 Grade B or API 5L Grade B


Schedule 80 Grade B, ERW or Seamless
Carrier Pipe:
Seamless 6.4 to 25.4cm (2 1/2 to 10 inches) - Sch. 40
30.5cm (12 inches) and over – 1.0cm (0.375-inch)

Note: Where applicable, use double random lengths to minimize the number of welds required

Socket Weld Butt – Weld


Joints:
End preparation to ASME B16.25

Note: Atmospheric pressure small-bore piping may be threaded. Socket welded and threaded
connections are only allowed above ground or within pits/vaults.

68kg (150lb) ASME B16.5 68kg (150lb) ASME B16.5

Carbon Steel ASTM A105 Carbon Steel ASTM A105

Weld Neck Raised-Face

6 x 4 Hydrant Valves will be supplied with ANSI


Flanges:
Socket Weld Raised-Face 300# RF flanged inlet connections. For each of
In uncontained locations the these connections, use 300 lb. ANSI, carbon
connection must be butt welded steel ASTM A181/A181M Class 70 weld neck RF
flanges.

Note: Flange face and ASME rating to be compatible with corresponding component.

Socket Weld Buttweld, ASME B16.9


Carbon Steel per ASTM A234 ASTM
ASTM A105, Grade 2 A181/A181M Class 70 or ASTM
Fittings:
A105/A105M
1,360kg (3,000 lb) Grade B, wall thickness
to match pipe

Hamad International Airport


Terminal Building Expansion Project 33 52 43.13 / 6. Rev. 1

Page 89 of 154
Note: Bushings shall not be used except as noted.

Carbon Steel, Teflon Carbon Steel, Teflon


Bolts: Coated Machine Bolts Coated Machine Bolts
ASTM A193, Grade B7B8 ASTM A193, Grade B7

Note: Studs may be used for corresponding equipment.

ITEM 2” AND SMALLER 2 ½” AND LARGER

Nuts to be heavy hexagon ASTM


ASTM A194, Grade 2H
Nuts A194, Grade 2H
Teflon Coated Teflon Coated

Note: Nuts shall be properly torqued to manufacturer’s recommendations.

Flexitallic Type CG Flexitallic Type CG


304 Stainless Steel Windings 304 Stainless Steel Windings
Gaskets:
with Non-Asbestos Filler with Non-Asbestos Filler
Conform to A.P.I. 601.21 Conform to A.P.I. 601.21

Note: Gaskets to be 1/8” in thickness - ring style for R.F. flanges.

C The interior and exterior coating for all pipe and piping materials shall be as specified in
Section 33 52 80.10, Fuel System Coating.

D Welded elbows shall be long radius unless otherwise shown.

E Changes in direction of pipe of other than 45 degrees or 90 degrees shall be made as


follows:

1. With long radius welds cut to proper angle and shop beveled.
2. Or, at the option of the Contractor, with long radius pipe bends. Pipe roundness shall
be maintained to factory tolerance for straight pipe lengths. Submit shop drawings of
all bends and bending procedures for approval.
3. Bends of 10 degrees or less shall be miter joints.

F Tee Connections:

1. Branch connections may be used in lieu of butt welding tees for sizes below 3" only,
and only above ground or within pits/vaults. Branch connections shall not be used in
direct buried piping unless otherwise indicated by the Contract Drawings.
2. Branch connections shall be weldolets, sockolets, socket-welded nipolets, or socket-
welded elbolets, as manufactured by Bonney Forge or equal.
3. Material shall be ASTM A105, Grade 2, standard weight steel, and shall conform to
ASME B16.11.
4. Use for all vent and instrument connections.
5. If approved by the COTR, the Contractor may use fabricated branch connections in
lieu of butt welded tees for direct buried applications. Connections shall be
sweepolets or insert-weldolets as manufactured by Bonney Forge or equal. All welds
on these connections shall be full penetration butt welds and shall be radiographed.

Hamad International Airport


Terminal Building Expansion Project 33 52 43.13 / 7. Rev. 1

Page 90 of 154
G Vault Sump Piping:

1. To facilitate pumping out of vault sumps, a drop pipe and quick coupling shall be
used. The quick coupling assembly shall be Dixon Model DDA200ALMNPT or
approved equal.
2. The assembly shall be a dry break coupling adapter and protective dust cap of
aluminum construction.
3. Use aluminum Schedule 40, 5cm (2 inches) threaded pipe and fittings for fabricating
the drop pipe at the vault sump.

H Fittings for Threaded Fuel Pipe:

1. Threads of threaded jointed piping shall be full, clean, sharp, and true.
2. Bushings shall not be used except as noted on the drawings.
3. 3,000 pound forged steel conforming to ASME B16.11.

2.3 TESTING EQUIPMENT

A The Contractor shall provide all necessary devices to test the completed piping system.
Items shall include but, not be limited to the following:

1. Air compressors:
a. Air compressors shall be equipped with condensate dryer system and filter
capable of generating oil-free air at -29 oC (-20F) dew point.
b. Air compressors shall have sufficient capacity to bring the system pressure in a
maximum of 60 minutes.
2. Pressure and temperature recorders:
a. Provide certified and calibrated test instruments capable of recording direct
temperature, pressure and time in the same scale and chart.
b. Submit data for test instruments and certificates of calibration.
3. Temporary piping:
a. Provide all piping, fittings, valves, gauges and equipment required for inspection
and testing.

2.4 FUELS

A The Contractor shall perform hydrostatic testing of the new pipe. The Fuel System Operator
will provide the Jet A fuel required for the hydrostatic testing. The fuel shall meet ASTM
D1665, latest revision specification for Jet A Aviation Turbine Fuel.

PART 3 - EXECUTIONS

3.1 CLEAN PIPING REQUIREMENTS

A The importance of keeping the interior of all piping systems clean during construction is
critical. The Contractor is required to keep the interior of the carrier piping, and the annular
space between carrier pipe and casing pipe, clean from all visible dirt or foreign matter at all

Hamad International Airport


Terminal Building Expansion Project 33 52 43.13 / 8. Rev. 1

Page 91 of 154
times and under all conditions. If for any reason the inside of the piping contains dirt or
foreign matter, the Contractor shall correct this condition to the COTR's satisfaction with all
necessary material, labor and equipment for cleaning being furnished at the Contractor's
expense. The following measures shall be taken to assure cleanliness of the system:

1. The pipe and fittings shall be delivered to the job site sealed. The seals are not to be
removed until the pipe is installed. After each day's work, the open ends of all pipe
being installed shall be sealed closed with an expansion type weatherproof and
watertight seal manufactured for this purposes. At the Contractors option, weld caps
or plate steel may be welded into place on the end of the pipe.
2. All fittings and valves shall be kept in a covered dry storage area until installation.
3. Pipe shall not be installed or stored in areas or ditches containing water or mud.
4. At openings for branches in piping, all material that falls into the pipe must be
removed before welding in the branch fittings.

3.2 HANDLING PIPE

A The shipment, delivery, and installation of all pipe and accessories shall be handled in such
manner as to ensure a sound undamaged condition. Particular care shall be taken not to
damage pipe coating when storing pipe. No other pipe or materials of any kind shall be
placed inside a pipe or fitting after the coating has been applied.

B Perform the hauling of pipe and other materials in such a manner as to prevent damage to
pipe and material. If damage is sustained, Contractor shall be responsible for repair or
replacement cost.

3.3 FABRICATION AND INSTALLATION

A All piping materials, fabrication, installation and application shall be in compliance with the
latest requirements of the code for Petroleum Refinery Piping ASME B31.3, and all state
and local regulations when applicable.

B All temporary piping required for construction, testing, flushing and start-up shall be
furnished by the Contractor. Such piping shall remain the property of the Contractor; and it
shall be his responsibility to dismantle and remove it from the premises when no longer
required.

C End Preparation: The base metals for all butt-welding pipe joints shall be prepared to
provide for proper "fit-up" in accordance with ASME B16.25. Ends shall be prepared by
machining or flame cutting. Hand flame cutting is only allowed subject to approval by the
COTR and only where the use of machine or automatic machine flame cutting is
impractical. Hand flame cuttings shall be ground smooth. No welded joint shall be made
where either flame cut or machine cut ends provide a spacing between the pipe so large
that more than one stringer bead is required to completely close the pipe. Where flame
cutting by hand is employed, the included angle or bevel at the end of the pipe shall be not
less than plus or minus 5 degrees from that which is required elsewhere in these
specifications for machine cut beveled ends. Pipe end for socket welding shall be reamed
for the full inside diameter to remove all burrs and obstructions.

D All pipe shall follow the routes shown on the drawings and shall be placed accurately to
measurements indicated or established from the work. Pipe shall be placed clear of

Hamad International Airport


Terminal Building Expansion Project 33 52 43.13 / 9. Rev. 1

Page 92 of 154
equipment, and other work. Changes in direction shall be made by use of fittings for
standard angles and by trimmed fittings for angles other than standard. Reference earlier
paragraphs in this section.

E Any damage to the internal or external pipe coatings by bending or handling, including
lineup of pipe joints, shall be the responsibility of the Contractor and shall be repaired to
equal the original coating. Repair of the internal coating damaged by field welding of pipe
joints is not required.

F Proper pipe joint alignment and separation shall be accomplished without the use of
backing rings.

G Weld spatter shall be removed around welds leaving a smooth clean surface.

H Pipe shall be fabricated to measurements established on the job and shall be carefully
worked into place without springing or forcing.

I Flanges and unions shall not be placed in a location that will be inaccessible after
completion of the work.

J All piping and equipment shall be properly supported and guided. Anchors shall be provided
where shown and where required to absorb or transmit thrust and eliminate vibration or
pulsation.

K Changes in pipe size shall be made with reducing fittings. The Contractor shall pay special
attention to the type of reducer, and its orientation, shown on the Contract Drawings.
Bushings shall not be used unless otherwise shown.

L Flanged joints shall be accurately centered and aligned prior to installation of bolts so as to
prevent mechanical pre-stressing of the flanges, pipe and equipment.

M For Buried Piping refer Section 31 23 23.13 Fuel System Excavation, Bedding & Backfill for
trench excavation, backfill and compaction requirements.

N Install pipe so as to be clear of contacts with other pipes, pipe sleeves, casings, reinforcing
steel, conduits, cables, or other metallic structures. Minimum separation from non-metallic
utilities is 30.5cm (12 inches) and from metallic utilities is 61cm (24 inches). Should
uncovered field conditions result in clearances less than this, bring to the attention of the
COTR for resolution prior to installing the new piping.

O Verify all measurements before commencing work. Submit discrepancies for clarification
before proceeding.

P Arrange all piping with proper slopes, without sags, traps, or pockets.

Q Provide high point vents, pump outs, and low point drains as required and indicated on the
drawings.

3.4 WELDING

A Qualifications of welders shall be done by Contractor in accordance with ASME B31.3,


Petroleum Refinery Piping, on the project site, witnessed by the COTR and before being
allowed to make construction welds. Certified test results for each welder employed by the

Hamad International Airport


Terminal Building Expansion Project 33 52 43.13 / 10. Rev. 1

Page 93 of 154
Contractor shall be kept in the contractor's field office for inspection by the COTR.
Performance test records of welders issued by a previous employer, in lieu of qualification
tests conducted by the Contractor, will not be acceptable. The Contractor shall assume the
costs for all tests.

B Welding and fabrication shall be accomplished in accordance with ASME B31.3 latest
edition. Before welding, the piping or other equipment shall be carefully lined up so that no
part is offset; flanges and branches shall be set square and true. This alignment must be
preserved during the welding operation. If tack welds are used, they must be of the same
quality and made by the said procedure as the completed weld. Backing rings shall not be
used. No weld metal shall project within the pipe so as to restrict its area or cause danger of
its loosening and falling into the pipe. The piping shall not be split, bent, flattened or
otherwise injured before, during or after installation. During erection, care shall be taken to
remove all dirt, scale and other foreign matter from inside the piping before tying in sections,
valves, equipment or fittings.

C All welded joints shall be made as recommended by the standards of the American Welding
Society and B31.3. The welding shall ensure complete penetration of the deposited metal
with the base metal. The filler shall be suitable for use with the base metal. Mitered joints
shall not be used except where specifically allowed in this specification or on the Drawings.

D All manual welds shall be made using downhill welding procedure. Shop welds utilizing
machine-welding procedures do not have to qualify to the downhill requirement. Machine-
welding procedures must be qualified and submitted to the COTR.

E Inspection and Repair:

1. All below ground welds (100%) shall be radiographed in accordance with these
specifications. All socket welds and fillet welds shall be inspected with magnetic
particle testing.
2. Any weld that is determined to be defective by the testing laboratory shall be repaired
in accordance with ASME B31.3. The Contractor shall be responsible for all costs
associated with the weld repair.

F Qualifications and Approval:

1. Welding procedures that are intended to be used on the job shall be submitted for
approval. The Contractor shall be responsible to assure that all welding procedures,
welders, and welding operators have been qualified in accordance with applicable
code requirements before work is started. Shop and field procedures shall be
submitted to the COTR for approval. The procedure specifications shall be as follows:
a. Include copies of the qualification test records as evidence that the procedures
have been qualified in accordance with the latest revisions of the following code:
 ASME B31.3 - Chemical Plant and Petroleum Refinery Piping
b. Developed for the conditions of this Contract and be complete and specific, and if
necessary, differentiate between shop and field welding.
c. Welder Performance Qualification Test Certificates:
 Furnish welder performance qualification test certificates prior to starting work for
position 6G for the pipe being installed as part of this project made in strict
compliance with the above code.
2. Submit qualification test records for each welder on the project and keep record files.

Hamad International Airport


Terminal Building Expansion Project 33 52 43.13 / 11. Rev. 1

Page 94 of 154
3. Costs: Costs incident to procedure and welders qualification tests shall be the
responsibility of the Contractor.

G Each welder shall identify each of his welds with a specific code or identifier. The Contractor
shall keep an as built fabrication drawing on the site that identifies the location of each weld
made and also indicates the welder who made the weld. The weld shall be made with a “low
stress” steel stamp or permanent ink marking.

H The Authority reserves the right to place welding inspectors (at the Authority’s cost) in the
shop where off site welding is taking place.

3.5 CONNECTION TO ACTIVE PIPING

A Active piping shall not be cut, tapped or disturbed until the Contractor has obtained the
necessary written approvals from the COTR and the Fuel System Operator.

B Each active fuel line shall be substantially drained prior to cutting into the line. Fuel shall not
remain in the piping as it is cut. The contractor shall exercise extreme caution during the
cutting of existing piping and shall not use cutting torches and spark producing cutting tools
and methods.

C The Contractor shall have the necessary number of drip pans and vacuum trucks on site
during cutting operations. Any and all fuel spilled during the cutting procedure shall be
immediately cleaned up and removed from the site by the Contractor at no additional cost to
the Contract.

D The Contractor shall take adequate measures for fire protection during modifications to
existing piping and equipment. Such measures shall include, as a minimum but not limited
to, the following precautions:

1. Do not cut, bevel, weld, grind or otherwise generate sparks near open sources or
spills of jet fuel.
2. Provide a fire extinguisher, 9.5L (2.5 gallons) Class AB Foam Type, at each welding
operation.
3. Protect adjacent services from weld splatter and sparks by use of welding blankets.
4. Obtain necessary hot work permits from the Airport.
5. Notify the Airport Fire Department at least 48 hours in advance of the intended
operation. In the event the Fire Department elects to have equipment present during
the operation, the Contractor shall coordinate the construction area with the Fire Chief
to allow proper positioning of equipment.

E Welding to existing piping:

1. Flow nitrogen through piping and weld area to eliminate all measurable oxygen.
2. Weld piping in accordance with API, NFPA and 0SH A requirements.
3. Use Plidco fittings to eliminate welding directly within the vapor space of existing
piping.

F Plidco Fittings:

Hamad International Airport


Terminal Building Expansion Project 33 52 43.13 / 12. Rev. 1

Page 95 of 154
1. Plidco fittings (“weld + ends”) shall be employed at each saw cut into existing
underground piping. Each fuel line shall be substantially drained prior to cutting into
the line.
2. Follow the manufacturer’s printed installation procedure. Flow fuel prior to weld-out.
3. Installing Plidco “weld +ends”:
a. The existing piping shall be cleaned of all old coating in the area where the Plidco
is to be installed. The pipe shall be cleaned of burrs and other surface
irregularities that might damage the Plidco seals during operation.
b. Slide Plidco “weld + ends” completely over one end of pipe. Mark off one-half of
Plidco “weld + ends” coupling length from middle of gap in pipe joints. Slide fitting
back to mark to divide coupling equally over joint.
c. After coupling is positioned, torque clamping and thrust screws tight, following the
manufacturers installation instructions for torque values and sequence.
d. Pipeline shall be put in operation. Thrust screws shall be burned off flush. Ends
of coupling shall be fillet-welded around circumference, including seal welding of
thrust screws. Clamping screws shall be cut or burned off and seal-welded also.
e. For critical, limited schedule, tie-in operations the Contractor shall have an extra
pair of seals on hand for each size of Plidco coupling.

3.6 WELD INTEGRITY TESTING

A All butt welds for field and shop fabricated piping for belowground installation (including
those welds within a pit/vault) shall be 100 percent radiographed. All socket welds for field
and shop fabricated piping for installation within a pit or vault, shall be 100 percent magnetic
particle inspected. Ten percent of the aboveground piping shall be randomly selected for
radiographic and/or magnetic particle inspection.

B All fillet welds on hot tap weldolets and on Plidco couplings shall be magnetic particle
tested.

C Piping where factory welds have been performed, must also be radiographed or tested by
an approved testing laboratory with results provided to the Contractor upon delivery and
receipt of the piping. Forward results of the testing to the COTR.

D All weld integrity-testing costs, including test reports and interpretation, are the responsibility
of the Contractor. An independent testing laboratory employed by the Contractor, and
subject to approval by the COTR, shall perform the weld integrity testing. All testing shall be
performed in accordance with ASME B31.3.

E One film negative of each radiograph shall be made. Each negative shall be identified as to
location. Negatives shall be turned over to the Authority at the end of the project. An expert
interpretation by a recognized testing laboratory shall be submitted in report form for every
weld to the COTR throughout the progress of the work. The report shall show date of test,
location, area, film number, weld number and other pertinent information.

F Permanent radiographic identification stamps shall be located on the piping near the welds.

G The Independent Laboratory making the tests shall interpret test results and any defects
found shall be repaired by the Contractor and a new radiograph taken of the repair. The
cost for inspection of defective welds shall be the responsibility of the Contractor at no cost
to the Authority.

Hamad International Airport


Terminal Building Expansion Project 33 52 43.13 / 13. Rev. 1

Page 96 of 154
H The Contractor shall coordinate the weld integrity testing with the testing lab, making certain
that adequate notices are given that the welds are available for testing.

I Backfilling of the piping shall not commence until tests have been approved by the COTR
and pressure tests have been completed.

3.7 PNEUMATIC PRESSURE TESTING OF FUEL PIPING

A General: The entire newly installed, fuel distribution piping shall be pneumatically pressure
tested after all joints are completed, in accordance with ASME B31.3 and API RP 1110.
Sections of the system may be tested and accepted in order to expedite the work or as
required due to phasing requirements. These sections shall be tagged by the Contractor to
indicate compliance with the tests.

B Install temporary closures or other fittings, including plugs, weld caps, blind flanges, etc., as
necessary to facilitate the testing process.

C Test Procedure: Tests shall be made with clean dry-filtered and oil-free compressed air –
negative 29 oC (-20 oF) pressure dew point – or compressed nitrogen gas and shall be made
in accordance with all applicable codes particularly with regard to safety precautions and
the following:

1. A preliminary check of the fuel distribution piping at 172kPa (25psig) shall be made.
2. The pressure shall be increased gradually in steps, providing sufficient time to allow
the piping to equalize strains during the test, and to be checked for leaks. Final test
pressure shall be 689kPa (100psig) for four hours.

D The Contractor shall provide certified and calibrated temperature and pressure instruments
and chart recorders and a deadweight tester to provide continuous calibration and direct
readings of time, temperature, and pressure on the same scale and chart during the tests.
Test Certifications and recorder charts shall be submitted to the COTR for approval prior to
final acceptance of the piping. Calibrated thermocouples may be surface applied.

E Repair any leaks detected. Retest at 4 hour pressure cycles, as described above after all
leaks have been repaired. Repeat repair and testing cycles until the system is acceptable to
COTR.

F Equipment, which is not rated by the manufacturer for the test pressure, shall be removed
or isolated prior to testing. Install temporary connections as necessary. All permanent
butterfly and plug valves and equipment, which are rated at the test pressure or greater,
shall be in place during the pneumatic tests.

G The 4 hour recordings shall be made after temperature and pressure has stabilized and
shall be conducted in accordance with NFPA Codes and API RP1110 and this specification.

H The pneumatic test shall be finalized before paving is started.

I Pneumatic testing shall be completed in segments as Phasing construction is completed.

3.8 HYDROSTATIC PRESSURE TESTING OF FUEL PIPING

Hamad International Airport


Terminal Building Expansion Project 33 52 43.13 / 14. Rev. 1

Page 97 of 154
A After a successful pneumatic test has been completed, the Contractor shall begin preparation
for hydrostatic testing.

B The Contractor shall remove all control valves, meters, and other equipment, which are not
rated by the manufacturer for the test pressure of 1,896kPa (275psig). Piping spools and
blind flanges shall be provided and installed by the Contractor.

C Prior to hydrostatic testing the Contractor shall carefully fill the fuel system piping with the
proper grade of fuel. During the filling process care should be taken to properly vent all high
points to disperse all air pockets.

D The Fuel System Operator will provide the required amount of fuel for the initial line fill and
hydrostatic testing. Contractor shall assist in confirming the line fill volume.

E The hydrostatic testing shall be in accordance with ASME B31.3 and shall include a two
step process. The initial step will be to gradually bring system pressure up to 689kPa
(100psig) and inspect all joints, components and connections. The second step will be to
gradually bring system pressure up to 1,896kPa (275psig) and recheck all joints,
components, and connections.

F The actual test shall be to hold pressure at 1,896kPa (275psig) for eight hours.

G During the testing period, if a leak develops, the Contractor shall abort the test, repair the
defect and restart the test from the beginning.

H The Contractor shall provide certified and calibrated temperature and pressure instruments
and chart recorders and a deadweight tester to provide continuous calibration and direct
readings of time, temperature, and pressure on the same scale and chart during the tests.
Test Certifications and recorder charts shall be submitted to the COTR for approval prior to
final acceptance of the piping. Calibrated thermocouples may be surface applied.

3.9 PIPE HANGERS AND SUPPORTS

A Pipe hangers and supports shall meet the requirements of ASME B31.3 and shall be as
detailed.

B Where changes in direction occur, reduce the spacing allowed in ASME B31.3 by three-
quarters.

C Not all supports are shown. Furnish and install all rigid supports, whether or not they are
shown and detailed, but are required to adequately support the piping systems. Include all
necessary structural steel, brackets, concrete inserts, etc., which are required to properly
support the piping systems.

D Install piping and provide necessary support and anchors to prevent forces from being
imposed on equipment that would exceed the limits specified by the equipment
manufacturer.

E Provide complete assemblies that are rated for a minimum of 200% of the applied load.

F Provide galvanized concrete inserts and shop- or field- fabricated galvanized brackets or
structural steel shapes where necessary to meet field conditions.

Hamad International Airport


Terminal Building Expansion Project 33 52 43.13 / 15. Rev. 1

Page 98 of 154
G Observe the flushing system in operation and make adjustments as necessary to support
the system under dynamic loads.

H Expansion bolts shall be self-drilling anchors, or insert type. Powder driven fasteners shall
not be used.

I Fabricate anchors welded to the pressure barrier from the same materials as the pipe and
fasten securely to structure at points of adequate structural strength.

J Support locations configuration and orientation shall be identified and submitted to the
COTR prior to beginning installation.

3.10 SAFETY PRECAUTIONS AND FUEL SYSTEM MODIFICATIONS

A Safety procedures are the responsibility of the Contractor. All operations in the construction
area that involve open flames or the possibility of arcing or sparking shall be conducted in a
"Gas-Free" condition.

B It shall be the responsibility of the Contractor to monitor the use and suitability of the
equipment and procedures on the job and maintain a safe "Gas-free" condition when
necessary during construction.

C Prior to commencing any phase of the work requiring a gas-free condition, the Contractor
shall make the following minimum provisions:

1. Empty pipes containing fuel and purge all vapors.


2. Isolate, blank off, and adequately ventilate open piping sections so that no part of the
pipe containing fuel or vapors is exposed.
3. Inspect for, and confirm that there are no open pools of fuel, or soil contaminated to a
combustible limit, in the area of the work.
4. Drain and ventilate storage tanks prior to working on the tanks or tank connections.

D Utilize a combustible gas analyzer or similar device to make certain that concentrations of
combustible gas do not exist in the construction area when performing these operations.

E Perform all safety precautions as required to assure that the work is conducted in a safe
manner and to conform to applicable codes.

3.11 FIELD QUALITY CONTROL

A Be responsible for periodic inspections for conformance with the approved SPPP. The
results of the periodic inspections shall be submitted to the COTR upon completion.

END OF SECTION

Hamad International Airport


Terminal Building Expansion Project 33 52 43.13 / 16. Rev. 1

Page 99 of 154
5. Drawing

Document No. ME-00065-A7110-CN-MCC-P-00-MAR-00001-00

Current version of this document is available online on the local intranet in electronic format. Page 100 of 154
Page 101 of 154
Page 102 of 154
6. Compliance Statement

Document No. ME-00065-A7110-CN-MCC-P-00-MAR-00001-00

Current version of this document is available online on the local intranet in electronic format. Page 103 of 154
HAMAD INTERNATIONAL AIRPORT
A7111 CENTRAL CONCOURSE APRON

The compliance statement as given below has the following meaning:


A7111 CENTRAL CONCOURSE APRON
Project Specification: SECTION 33 52 43.10 - FUEL SYSTEM GENERAL PROVISION

ITEM DESCRIPTION Comply REMARKS


1 PART 1 - GENERAL
PART 1 - GENERAL

1.1 SUMMARY

A Work in this section includes furnishing all materials, labor and supervision necessary for
the construction of miscellaneous fuel system modifications. The work shall include all pipe,
This submittal is applicable
1.1 fittings, valves, appurtenances and activities as specified herein and shown on the Noted and will be complied
for CS pipes & fittings.
drawings. All testing, inspection and flushing shall be provided as specified to provide a
complete and operational system.

B All permits and licenses that are required by governing authorities for the performance of
work shall be procured and paid for by the Contractor.

1.2 QUALIFICATION OF BIDDERS

A The Aviation Fuel Distribution System work shall be completed by a Contractor who
conforms to the following requirements:
1. Contractor must have been involved in the construction of commercial aviation fueling
industry projects for a minimum of ten (10) years.
Complied
2. Contactor must have successfully completed three (3) projects similar in complexity
and scope within the last five (5) years. The projects shall include installing internally
coated steel piping above and belowground, the installation of isolation valve vaults,
installation of horizontal fuel tanks, and construction of concrete vaults. The
Contractor shall provide a description of the referenced projects and client references
to include contact name, phone number and organization.

1.2 3. Contractor must have developed and implemented an aviation fuel system flushing
plan, using a method that utilizes flushing into mobile tankage. The flushing plan must
have incorporated the fuel quality requirements of ATA 103. Provide a list of projects
with appropriate descriptions where flushing plans have been developed and
implemented by the Contractor.

4. Contractor has as a member of his team, a tunneling subcontractor who has successfully completed a minimum of
three tunneling projects of similar length and diameter in the past ten (10) years. The tunneling subcontractor shall Tunneling is not part of the
Noted and complied
provide a description of the referenced projects and client references to include contact name, phone number and scope of works
organization.

5. Contractor has as a member of his team, a controls subcontractor who has successfully completed three (3) PLC
based Emergency Fuel Shutoff Systems (EFSO) projects requiring the integration and transmission of data for viewing
at a remote location (e.g. Tank Farm) for airport terminals with hydrant fueling systems. The controls subcontractor
shall provide a description of the referenced projects and client references to include contact name, phone number
and organization.

1.3 REFERENCES
A Refer to each individual section in this division for a list of applicable references from each
of the following organizations:
1. Air Transport Association (ATA)
2. American Petroleum Institute (API)
3. National Fire Protection Association (NFPA)
4. Underwriters Laboratories (UL)
5. American Society of Mechanical Engineers (ASME)
Noted and
1.3 6. American Society for Testing and Materials (ASTM)
complied
7. Environmental Protection Agency (EPA)
8. Factory Mutual Engineering Division (FM)
9. Industrial Risk Insurance (IRI)
10. Military Specifications (Mil)
11. Occupational Safety & Health Administration (OSHA)
12. Petroleum Equipment Industry (PEI)
13. Federal Aviation Administration (FAA)
14. Joint Inspection Group (JIG)

1.4 DEFINITIONS

Noted
A “Piping” includes in addition to pipe, all fittings, valves, sleeves, hangers, and other supports
and accessories related to such piping.

Page 104 of 154


1.4
B The words “furnish and install”, “provide”, “furnish”, and “install” are used to mean the
Contractor shall furnish and completely install the system, service, equipment, or material
named along with other associated devices, equipment, material, wiring, piping, etc. as Noted
required. System shall be a complete operating installation, and shall conform to the codes,
1.4 standards and guidelines applicable to this type of project.

C It is the intent of the specifications and drawings to call for finished work, tested and ready
for operation.
1. All apparatus, appliances, materials, or work not shown on drawings but mentioned in
specifications, or vice versa, and/or all incidental accessories necessary to make
work complete and ready for operation, even though not specified or shown on Noted
drawings, shall be furnished and installed without increase in contract price.
2. Should there be discrepancies or questions of intent, refer matter to the Contracting
Officer’s Technical Representative (COTR) in writing for a decision before ordering
any equipment or materials or before starting any related work.

1.5 COMPLIANCE SUBMITTALS

A Submittals are required for all material specified in Divisions XX XX XX.XX. If material or equipment is shown on the
drawings to be included in this project but is not specified, the Contractor shall bring this to the immediate attention
of the COTR. Submittals are required for all material and equipment incorporated into this project whether specified
or not.

B Submittals are required for the proposed subcontractors primarily responsible for tunneling/micro-tunneling, fuel
Noted and will be complied
pipe installation, EFSO controls and leak detection.

C The Contractor’s attention is called to the COTR’s review of Compliance Submittals. This review shall be completed
and the submittal returned to the Contractor before starting procurement, installation or fabrication.

D The Contractor’s submission of a compliance submittal constitutes that he has both verified and coordinated all
dimensional data, quantities, field conditions, catalog data, and compliance with the specification or he assumes full
responsibility for doing so.

E Compliance Submittals shall include all components and units associated with decommissioning the existing fuel
hydrant system and fabrication of the new hydrant fueling system as specified in the following Fuel System Work
sections:
1. Fuel System Inspection, Testing and Flushing 330850.10
2. Fuel System Emergency Fuel Shutoff System 330950.11
3. Fuel System General Provisions 335243.10 Compliance statement will
4. Fuel System Piping Specialties 335243.11 be provided for all
5. Fuel System Pipe, Fittings and Installation 335243.13 Noted applicable materials in
6. Fuel System General Valves 335243.15 respective material
7. Fuel System Service Pits and Valve Vault Covers 335243.20 submittals.
1.5 8. Fuel System Coating 335280.10
9. Fuel System Cathodic Protection System 335343.91
10. Fuel System Cathodic Protection System Testing 335343.92
11. Fuel System Pumps 335243.23
12. Fuel System Excavation, bedding and backfill 312323.13

F Submittal Formats are as follows:


1. Product Information: Submit manufacturer’s data sheets identifying equipment
size, descriptions, materials, ratings, etc.
2. Drawings: Submit drawings which graphically show relationship of various components of the work, schematic
Noted and complied
diagrams of systems, details of fabrication, layouts of particular elements, connections and other relational aspects
of the work.
3. Instructions: Preprinted material describing installation of a product, system or material, including special notices
and material safety data sheet, if any, concerning impedance, hazards and safety precautions.

4. Statements: A document required of the Contractor, or through the Contractor, from a supplier, installer,
manufacture, or other lower tier Contractor. The purpose of which is to confirm the quality or orderly progression of
a portion of the work by documenting procedures, acceptability of methods or personnel, qualifications or other
Noted and complied
verifications of quality.
5. Reports: Reports of inspections or tests, including analysis and interpretation of test results. Each report shall be
properly identified. Test methods used shall be identified and test results shall be recorded.

6. Certificates: Statement signed by an official authorized to certify on behalf of the manufacturer of a product,
system or material, attesting that the product, system or material meets specified requirements. The statement must
be dated after the award of this contract, must state the Contractor’s name and address, must name the project and Noted and complied
location, and must list the specific requirements that are being certified.
7. Records: Documentation to record compliance with technical or administrative requirements.

Page 105 of 154


8. Submittal Review Action:
a. Approved: Indicates information is sufficient in detail and adequately organized for performance of the review.
Material conforms to the intended functional requirements of the contract documents and is approved for
fabrication, procurement and incorporation into the project as submitted.
b. Approved as Noted/No Resubmittal Required: Indicates information submitted is sufficient in detail and
Noted
adequately organized for performance of the review. Material conforms to the intended functional requirements of
the contract documents and is approved for fabrication, procurement and incorporation into the project as noted.
Submitted item is not considered by the reviewer to be a critical element of the project and/or noted comments are
minimal in quantity and complexity so that no additional review is necessary. Copies with limited marks are
acceptable to all parties as permanent record documents.

c. Approved as Noted/Resubmit: Indicates information submitted is sufficient in detail and adequately organized for
performance of the review. Item generally conforms to the intended functional requirements of the contract
documents and is approved for fabrication, procurement and incorporation into the project as noted. Submitted item
is not considered by the reviewer to be a critical element of the project but noted comments are sufficient in Noted
quantity or complexity so that resubmission is appropriate to assure responsive action, or copies with marks are not
acceptable to all parties as permanent record documents. Item must be resubmitted responsive to the reviewers’
comments.
1.5
d. Revise/Resubmit: Indicates information submitted may not be sufficient in detail or adequately organized for
performance of the review. Item may appear to conform to the intended functional requirements of the contract
documents but certain elements do not or lack sufficient information to be evaluated. Item is not approved for
fabrication, procurement or incorporation into the project. Submitted Noted
item is considered by the reviewer to be a critical element of the project and/or noted comments are sufficient in
quantity or complexity so that resubmission is necessary to assure acceptable responsive action and conformance
with the contract documents. Item must be resubmitted responsive to the reviewers’ comments

e. Rejected/Resubmit: Indicates information submitted is not sufficient in detail, is not adequately organized for
performance of the review, or does not conform to the intended functional requirements of the contract documents.
Noted
Item is not approved for fabrication, procurement or incorporation into the project. Item must be resubmitted
responsive to the contract documents and reviewers comments.

f. No Action Required: Indicates item has been submitted for informational purposes only and no action response or
comments are needed by the reviewer. Item should be retained in project files.
Noted
g. Not Subject to Review: Indicates submission of item was not required by the contract documents and is not part of
the reviewers’ contractual project scope. Item is being returned without review or comment.

1.6 QUALITY ASSURANCE


A Materials and equipment shall be new, unused, and shall bear manufacture’s name, model number, and other
identification marking.
B Materials and equipment shall be standard product of manufacturer regularly engaged in the production of
Complied
required type of material or equipment for at least 5 years (unless specifically exempted by COTR) and shall be
manufacturer’s latest design having published properties.
C If more than one unit of the same type of equipment is required, (i.e., control valves, manual valves, etc.) they shall
be products of a single manufacturer.

D All equipment, materials, components, coatings, and accessories provided shall be suitable
for use with the specific product. The following table is provided to indicate the basic design
conditions of the components:

Complied

1.6

E The Contractor is responsible for protecting all equipment and material from loss or damage until the system is
completed and accepted by the COTR.
F The Contractor shall be responsible for coordinating with the manufacturer for installation of the equipment
furnished. The Contractor shall be responsible for warranty work required and shall coordinate with the
Noted and will be complied
manufacturer of the equipment to accomplish warranty work including any labor and additional cost for such
warranty work. The equipment manufacturer shall provide the Contractor with installation manuals and instructions.
The Contractor shall receive and install this equipment for a complete furnished and installed installation including all
accessories as specified within these specifications and as shown on drawings.

G The Contractor shall check equipment delivered to job site by the equipment supplier against approved Compliance
Submittals or other required documentation. The Contractor shall report all discrepancies, shortages, or lack of data
Noted and will be complied
to the COTR and equipment supplier for adjustments within one week after equipment is received. If such report is
not made within one week, it shall be assumed no discrepancies, shortages or lack of data has been found.

Page 106 of 154


H Contractor shall provide the following for all equipment furnished:
1. All rough-ins for equipment and accessories
2. Installation of loose trim provided with equipment by the equipment supplier Noted and will be complied
3. Furnish and install all piping connections, valves, unions, control valves, drains and other accessories as indicated
on the plans and as specified here within these documents.

I The products of specific manufacturers have been used as the basis of design. Any changes to the structure, piping,
controls and electrical connections that result from the use of other manufacturers shall be coordinated with all
1.6 other trades by the Contractor and approved in writing on letterhead by the COTR before the ordering of the
equipment from the manufacturer. Any resultant modifications required shall be performed without incurring
additions to the contract price.
J The bid shall be based only on products specified. The Contractor shall verify delivery dates
Noted and will be complied
for timeliness before submitting his bid. Desired product substitutions shall be brought to the
COTR’s attention prior to bidding. No consideration shall be given to substitutions after bids
are received.
K Unless this Contractor states in writing at the time of pricing any and all exclusions to these specifications or
drawings in his bid proposal, this Contractor shall furnish and install at the job site the equipment, material, labor and
services as specified herein and shown on the drawings for the amount of his bid.

1.7 DRAWINGS
A Drawings are diagrammatic and indicate the general arrangement of systems and work included in the contract.
Drawings are not to be scaled. All drawings and details shall be examined and coordinated by the Contractor to
All Drawings are
1.7 establish exact location of piping and equipment. Where conflicts occur, the Contractor shall inform the COTR Noted and will be complied
immediately. separate submittals
B The Contractor shall follow all contract drawings in laying out work and shall check shop drawings of other trades
to verify spaces in which work will be installed.

1.8 MAINTENANCE MANUALS


A In addition to the requirements specified in the General Conditions, at the project’s completion, the Contractor
shall submit a complete system Operating and Maintenance Manual (O&M). The manual at a minimum shall include
the following:
1. The manual shall be composed of typed instruction sheets with large drawing sheets (not reduced) folded in with
reinforced margin. It shall have a post binder system so that the sheets can be easily substituted and shall have a
hard cover.
2. The manual shall be organized into systems and shall contain the manufacturer’s complete detailed operating and Not applicable for
maintenance instructions with data sheets for each piece of equipment furnished under this project.
1.8 3. Include a spare parts list for each major piece of equipment furnished for the project
Noted and will be complied this submittal (CS
including but not limited to: pipes and Fittings)
4. Manual Valves
5. Leak detection system
6. Service pits
7. EFSO system
8. Hydrant Cart Test Stand
9. Provide a comprehensive list of maintenance procedures for preventative maintenance and troubleshooting;
repair and reassembly, aligning and adjusting, and disassembly.

1.9 NAME PLATES


A All major equipment items shall have a permanent, stamped metal, nameplate. The nameplate shall be
permanently attached to the equipment in a manner such that it does not hinder the operation of the equipment. All
nameplates shall be protected from overspray during field painting operations. Nameplates shall generally include
the applicable items in the following list: Not applicable for
1.9 1. Manufacturer’s Size and Type Noted and will be complied this submittal (CS
2. Serial Number pipes and Fittings)
3. Design Capacity
4. Design Pressure
5. Design Temperature
6. Code Conformance

1.10 CODE REQUIREMENTS AND PERMITS


A All work indicated on the contract drawings and herein specified shall conform with all
applicable codes or laws of QATAR and any other governmental bodies having
jurisdiction and shall be installed to the satisfaction of the inspecting authority.
B Any deviations from the contract documents or specifications required for conformance with
the applicable codes or laws shall be made without change in contract price, but not until
Noted and will be complied
such deviations have been brought to the attention of, and approved in writing, by the
COTR.
C The applicable codes and laws shall govern the minimum requirements only. Where the
drawings or specifications call for materials, construction limitations, or other similar
requirements in excess of the code requirements, the drawings and specifications shall be
followed.

Page 107 of 154


D The Contractor shall obtain and pay for permits and licenses, and shall pay all fees and taxes and give all notices
bearing on the conduct of the work as drawn and specified. Certificates of compliance, approval, or acceptance from
all authorities having jurisdiction
over the work shall be obtained and delivered to the COTR.
E All work indicated on the drawings and herein specified shall conform with all applicable standards of the National
Fire Protection Association, American Petroleum Institute,
Noted and will be complied
American National Standards Institute and American Society for Testing and Materials.
F All work indicated on the drawings, and herein specified, or tasks required in the performance of the work but not
specifically indicated in the drawing or specifications, shall conform to the applicable requirements of the
Occupational Safety and Health Administration (OSHA) as provided in 29 CFR. Applicable requirements include, but
are not limited to, Part 1910 – Occupational Safety and Health Standards and Part 1926 – Safety and Health
Regulations for Construction.

G All equipment, materials, and specialties shall be installed and connected in accordance with the best engineering
practice and standards for this type of work. Unless otherwise specified or shown on the drawings, the
recommendations and instructions of the manufacturer shall be followed for installing the work. H The Contractor
shall promptly notify the COTR in writing, of any instances in the specifications or on the drawings that are in conflict Noted and will be complied
with any of the aforementioned authorities so that any required changes shall be adjusted before the contract is
awarded. If the Contractor performs any work contrary to such laws, rules, regulations or recommendations, without
notice, he shall bear all cost arising therefrom.

PART 2 - PRODUCTS
2 Not Applicable

PART 3 - EXECUTIONS
3.1 GENERAL INSTALLATION
A Contractor shall be responsible for the safety and protection from loss or damage of all equipment and material
received until all the work under this contract is complete and the Contractor has received final acceptance. Protect
all equipment and material during storage and prior to start-up, which shall include the coverings of all openings,
protection against water intrusion or accumulation, protection against rust and other damage, etc.
3.1 B Contractor shall ensure that all equipment installed as part of this contract shall be properly aligned, adjusted and Noted and will be complied
lubricated before final acceptance.
C Contractor shall spot paint all equipment where the shop paint has been damaged or flaked
off.
D Furnish all bolts, studs, nuts and gaskets for makeup of all connections to the equipment and replace all gaskets,
bolts and fasteners damaged or as directed during the flushing process.
E All connections to equipment shall be made with socket welds, unions or flanges.

3.2 REQUIREMENTS
A Mechanical and electrical designs are based on the requirements for the specified manufacturers listed in the
equipment specification. Conduit sizes are selected on the basis of specified equipment. Increased manufacturers
requirements necessitating piping changes, additional power conductors, controls, foundations, etc., or any changes
required to accommodate any alternate or substitute manufacturer’s equipment, other than as shown on drawings
shall be provided without any increase in contract price by Contractor. Noted and will be complied
B Manufacturers, where specifically called for, must provide factory tests, unit installation observations, unit start-up
and tests, etc., as specified. Signed reports shall be submitted to the COTR upon completion of these services.
Subletting of these services will not be permitted. Compliance Submittals shall be accompanied with a letter of
certification by the manufacturer that the specified services shall be provided. Failure to do so shall be cause to
reject the Compliance Submittals.

C The contract drawings are in part schematic, intended to convey the scope of work and indicate the general layout,
design, and arrangement. The Contractor shall follow these drawings in the layout of his work and shall consult
3.2 general construction drawings, electrical drawings, and all other drawings for this project. Contractor shall verify all
existing site conditions to determine all conditions affecting the work shown or specified. The contract drawings are
Noted and will be complied
not to be scaled and the Contractor shall verify areas in which the work is to be installed.
D Follow drawings in laying out work, check drawings of other trades to verify spaces in which work will be installed,
and maintain maximum space conditions at all points. Where space conditions appear inadequate, COTR shall be
notified before proceeding with installation.

E All work shall be performed by trained personnel of the particular trade involved and shall be done in neat and
workmanlike manner as approved by the COTR.
1. Work shall be performed in cooperation with other trades and scheduled to allow timely and efficient completion
of project.
2. Furnish other trades advance information on locations and sizes of frames, boxes, sleeves and openings needed Noted and will be complied
for work. Also furnish information and shop drawings necessary to permit other trades affected to install their work
properly without delay.
3. Where there is evidence that work of one trade will interfere with work of other trades, all trades shall assist in
working out space conditions to make satisfactory adjustments.

Page 108 of 154


F Work installed before coordinating with other trades causing interference with work of such other trades shall be
changed to correct such condition without increase in contract price and as directed by COTR.
G Where specific details and dimensions are not shown on the drawings, the Contractor shall take measurements
and make layouts as required for the proper installation of the work and for coordination with all other work on the
Noted and will be complied
project. In case of any discrepancies between the drawings and the specifications, it shall be assumed by the signing
of the Contract that the higher cost (if any difference in costs) is included in the contract price. The Contractor shall
perform the work in accordance with the drawings or with the specifications, as determined and approved by the
COTR.

H The Contractor shall be responsible for a scheduled sequence in performing the work so that it will not interfere
with the Authority’s operation. Before any work is started, the Contractor shall consult with the COTR and arrange a
satisfactory schedule.
1. Make temporary alterations as required to execute work so that all operations and services are maintained with
the minimum possible interruption. Noted and will be complied
2. Temporary shut-downs shall be segregated and shall be of the shortest possible duration. All facilities shall be kept
in continuous operation unless Authority grants specific written permission to the contrary.
I It is the responsibility of the Contractor to monitor the construction area for the presence of flammable vapors and
to assure the proper construction methods and equipment is used if hazardous conditions exist.

3.3 EXISTING CONDITIONS


A Each bidder shall inspect the site as required for knowledge of existing conditions. Failure to obtain such knowledge
shall not relieve the successful bidder of the responsibility to meet existing conditions in performing the work under
the contract.
Noted
B Where new work cannot be installed without changes in existing plant, facility, or systems or where it is indicated
on drawings to re-work an existing installation, this contract shall include alterations to existing work as required to
install new work. Additions to the contract cost will not be allowed because of the Contractor’s failure to inspect
existing conditions.

3.3 C Existing conditions indicated on the drawings are taken from the best information available on previous contract
drawings and from visual site inspection. They are not to be construed as “As Built” conditions, but are to indicate the
intent of this work. It shall be the responsibility of the Contractor to verify all existing conditions at the project site
and to perform the work as required to meet the existing conditions and the intent of this work indicated.
D Unless specified otherwise, all existing material and equipment shown or required to be removed from existing
Noted
construction and not shown to be reused or turned over to the Authority shall become the property of the
Contractor and shall be promptly removed from the site.
E Any existing material or equipment which is to be reused or is to remain in place and which is damaged by this
Contractor in performing the contract work shall be repaired to the satisfaction of the Authority or shall be replaced
with new equipment and material.

3.4 STORING MATERIALS


A Unless otherwise arranged for by the Contractor, buildings of the Authority shall not be used for Contractor storage
3.4 or job office purposes. Open or exposed space for storage of material and location of temporary job facilities will be Noted and will be complied
allocated to the Contractor. The Contractor, at his own expense, shall provide any temporary structures such as
trailers and sheds, as may be required for this purpose.

3.5 CUTTING AND PATCHING


A The responsibility for the cutting of existing masonry and concrete which is required for the installation of new
work shall be by the Contractor. The Contractor shall coordinate with the Authority before any cutting and obtain
Not relevant to this Material
approval from the Contracting Officer’s Technical Representative (COTR) prior to any cutting.
submittal
B Cutting shall be done with extreme care and in such a manner that the strength of the structure will not be
endangered. Wherever possible, openings in concrete or masonry construction shall be by concrete saw or rotary
core drill. Openings in any construction shall be cut the minimum size required for the installation of the work.

3.5

C Where openings or holes are cut in existing construction and the cutting breaks existing electrical circuitry, control
circuitry, communications, conduit, or wiring, then it shall be the responsibility of the Contractor to have the circuitry,
conduit, and rewiring re-routed as required and as approved by the COTR. Temporary completion shall be provided
where necessary before the permanent re-routing and completion work is finished. All costs for this work shall be the Not relevant to Material submittal
responsibility of the Contractor and no additions will be allowed to the contract price.
D Where existing work is removed from openings in existing construction and the opening is not to be reused for new
work, the opening shall be filled and patched to match existing adjacent construction.

Page 109 of 154


3.6 BASES, FOUNDATIONS, SUPPORTS AND ATTACHMENTS
A The Contractor shall provide all structural steel, concrete, and materials necessary to properly support and anchor
equipment and lines provided under this contract.

B All equipment and materials shall be securely attached in an approved manner. Attachments shall be of a strong
and durable nature and suitable for the service required. Not relevant to this Material
3.6 submittal
C Concrete bases shall be provided where shown on the drawings. Equipment which is to be grouted in place shall be
grouted with non-shrink grout.

D All equipment shall be mounted, aligned, adjusted, and serviced in accordance with
manufacturer’s recommendations before system testing and final acceptance of the system.

3.7 ELECTRICAL COORDINATION


A All electrical products and their installation shall conform unless otherwise specifically noted,
Not relevant to this Material
3.7 to applicable standards of the National Electrical Manufacturers Association, NFPA 70,
submittal
Division 33 of these specifications, and shall also be listed by Underwriter’s Laboratories,
Inc. and/or other agencies, as required.

3.8 TESTING LABORATORY SERVICES


A The Contractor shall secure the services of an independent testing laboratory approved by
the COTR to perform all testing, witnessing and certification of materials. This applies to Noted and will be complied
coating integrity, fuel acceptability, pressure tests and weld examinations.
B The cost for all laboratory services will be the responsibility of the Contractor.

C The laboratory shall:


1. Cooperate with the Contracting Officer’s Technical Representative (COTR), Authority and Contractor; and provide
qualified personnel promptly on notice.
2. Perform specified inspections, sampling and testing of materials and methods of construction:
a. Comply with specified standards; ASTM, other recognized authorities and as specified. Noted and will be complied
b. Ascertain compliance with requirements of contract documents.

3. Promptly notify the Contracting Officer’s Technical Representative (COTR), Authority and Contractor of
irregularities or deficiencies of work, which are observed during performance of services.

4. Promptly submit 2 copies of reports of inspections and test to the COTR including:
a. Date Issued
b. Project Title and Number
c. Testing Laboratory Name and Address
d. Name and Signature of Inspector
e. Date of Inspection or Sampling
Noted and will be complied
f. Record of Temperature and Weather
g. Date of Test
h. Identification of Product and Specification Section
i. Location in Project
j. Type of Inspection or Test
k. Observations Regarding Compliance with Contract Documents

5. Perform additional pre-approved services as required by the Contracting Officer’s


Technical Representative (COTR), Authority and Contractor.
6. The laboratory is not authorized to:
Noted and will be complied
a. Release, revoke, alter, or enlarge on, requirements of contract documents
b. Approve or accept any portion of work
c. Perform any duties of the Contractor

D The Contractor shall:


1. Coordinate laboratory services, cooperate with laboratory personnel, provide access
to project and to manufacturer’s operations.
2. Furnish to laboratory preliminary representative samples of materials to be tested, in
required quantities.
3. Furnish labor and facilities:
a. To provide access to work to be tested
b. To obtain and handle samples at the site
Noted and will be complied
c. To facilitate inspections and tests
d. For laboratory’s use for storage of test samples
4. Arrange with laboratory and pay for pre-approved additional samples and tests
required for Contractor’s convenience.
5. The Authority shall reserve the right to request the Contractor to obtain the services of
a separate, equally qualified independent testing laboratory, to perform additional
inspections, sampling and testing required when initial test indicate work does not
comply with contract documents. The Contractor shall pay the costs of such retesting.

Page 110 of 154


3.9 WARRANTY BY CONTRACTOR
A Warrant all systems, equipment, materials and components installed under these specifications for a period of not comply
less than one (1) year from time of beneficial use of the facility and systems by the Authority.

3.10 FIELD QUALITY CONTROL


A Be responsible for periodic inspections for conformance with the approved SPPP. The results of the periodic Noted and will be complied
inspections shall be submitted to the COTR upon completion.

Page 111 of 154


HAMAD INTERNATIONAL AIRPORT
A7111 CENTRAL CONCOURSE APRON

The compliance statement as given below has the following meaning:


A7111 CENTRAL CONCOURSE APRON
Project Specification: SECTION 33 52 43.13 - FUEL SYSTEM PIPE, FITTING AND INSTALLATION

ITEM DESCRIPTION Comply REMARKS

1 PART 1 - GENERAL

PART 1 - GENERAL

1.1 1.1 SUMMARY Noted


A This Section of the specifications describes and provides for the furnishing, installing and
testing of pipe and piping components for the aviation fueling system.

1.2 PRODUCTS INSTALLED BUT NOT SUPPLIED UNDER THIS SECTION


1.2 Noted
A Not applicable

1.3 RELATED SECTIONS


A Section 33 52 80.10 – Fuel System Coatings
1.3 Noted
B Section 33 08 50.10 – Fuel System Inspection, Testing and Flushing
C Section 33 53 43.92 – Fuel System Cathodic Protection System
1.4 REFERENCES
A American Society for Testing and Materials (ASTM)
1. A53 - Pipe, Steel, Black, and Hot Dipped, Zinc Coated Welded and Seamless
2. A105 - Forging, Carbon Steel, for Piping Components
3. A193 – Alloy-Steel and Stainless Steel Bolting Materials for High-Temperature
Service
4. A194 - Carbon and Alloy Steel Nuts for Bolts for High Pressure and High
Temperature Service
5. A234 - Piping Fitting of Wrought Carbon Steel and Alloy Steel for Moderate and
Elevated Temperatures
6. D1655 - Standard Specification for Aviation Turbine Fuels
B American Society of Mechanical Engineers (ASME)
1. B1.20.1 – Pipe Threads, General Purpose
1.4 2. B16.5 - Pipe Flanges and Flanged Fittings Noted
3. B16.9 – Factory Made Wrought Steel Butt Welding Fittings
4. B16.9 - Factory Made Wrought Steel Butt Welding Fittings
5. B16.11 - Forged Steel Fittings, Socket Welding and Threaded
6. B16.25 - Buttwelding Ends
7. B31.1 - Power Piping
8. B31.3 - Chemical Plant and Petroleum Refinery Piping
C American Petroleum Institute (API):
1. RP 1110 – Pressure Testing of Liquid Petroleum Pipelines
2. Spec 5L - Line Pipe
3. Std. 601.21 - Metallic Gaskets for Piping, Double-Jacketed Corrugated and Spiral
Wound
D Federal Specifications (FS) QQ-P-416 - Plating, Cadmium
E National Electrical Manufacturer’s Association (NEMA)
1.5 DEFINITIONS

A Unless otherwise specified, the working pressure ratings as used in these specifications for
valves, fittings, unions, and other piping specialties refer to pressure ratings in pounds per
2.1 square inch above atmosphere (PSIG) in accordance with applicable ASME Standards. Noted
This document also provides the reference to the respective International Metric System.
B The use of the word "piping" shall be interpreted to include all pipe, valves, fittings, flanges,
supports, or accessories for any particular portion of the work, or system to which the word
"piping" is applied.

1.6 SUBMITTALS
A General: Compliance Submittals shall be in accordance with Section 33 52 43.10, Fuel Noted and complied
System General Provisions.

1.6

1 of 11 Page 112 of 154


HAMAD INTERNATIONAL AIRPORT
A7111 CENTRAL CONCOURSE APRON

The compliance statement as given below has the following meaning:


A7111 CENTRAL CONCOURSE APRON
Project Specification: SECTION 33 52 43.13 - FUEL SYSTEM PIPE, FITTING AND INSTALLATION

ITEM DESCRIPTION Comply REMARKS

B Product Information: Submit manufacturer’s data sheets identifying equipment size,


materials, pressure ratings, etc.
1. Piping
2. Fittings (include specialty hot tap and line plug)
Noted and will be complied
3. Flanges and Gaskets
4. Bolts, Nuts and Washers
C Reports
1.6 1. Radiograph Test Reports

D Certificates:
1. Pipe
2. Fittings (include specialty hot tap and line plug)
3. Flanges and Gaskets
4. Bolts, Nuts and Washers
5. Welder Performance Qualification (WPQ) Noted and will be complied
6. Welding Procedure Specifications (WPS)
7. Piping System Installation
8. Test Equipment and Results
E Records:
1. Procedure Qualification Records (PQR)
1.7 QUALITY ASSURANCE
A. All pipe and piping materials shall be provided by a manufacturer and fabricator approved by
the COTR.

B. Welding operations, qualification of welders and welding procedures shall comply with
ASME B31.3 and the ASME Boiler and Pressure Vessel Code, Section I and Section IX.
Certified copies of the welding procedure, the procedure qualification, and the welder,
qualification certification must be submitted prior to beginning any welding operations.

C. Welders must be qualified to position 6G of ASME B31.3, tested on the type of pipe used in Noted and will be complied
this project, and must have been qualified within the six months preceding this project or the
welder shall be re-qualified.

D. Contractor is responsible for all costs associated with procedure and welder qualifications.

E. Internal Coating shall comply with EI 1541 “Requirements for internal protective coating
systems used in aviation fuel handling systems”. Material warranty shall be 10 years.
Certified copies of the quality control procedures and results of the internal pipe coating
application shall be submitted.
F Certified copies of the quality control procedures and results of the internal pipe coating
1.7 application shall be submitted.
Noted and will be complied
G No foreign materials or components, supplied as part of this Section, shall be utilized. The
G. Make and country of origin for
use of the words “domestic materials” or “no foreign materials” shall mean all materials shall be
the pipes and fittings are
of U.S. origin. The Contractor shall certify this condition in the compliance submittals. If at any
highlighted in the summary sheet
time, the COTR determines that any flanges, fittings, bolts or nuts are not of U.S. origin, the
in line with project technical
Authority shall be entitled to replace the components without need for individual testing for
requirements. However, contract
conformance to technical specifications. Contractor shall be responsible for all costs
is not limited to US origin and all
associated with such replacement.
materials will be supplied as per
Qatar government country of
H The installation shall include all necessary materials, coating, supports, controls, valves and
origin regulation.
fittings, hereinafter described or called for on the Contract Drawings accompanying these
specifications, or as necessary to make the installation complete.
I The drawings and specifications shall be considered complementary, one to the other, so
that materials and labor indicated, or called for, or implied by the one and not the other,
shall be supplied and installed as though specifically called for by both.
J All materials and equipment provided under these specifications shall be new, unused Noted and will be complied
products of manufacturers regularly engaged in production of such equipment for a
minimum of 5 years. All products shall conform to the applicable code or standard for its
manufacturing, fabricating and installation.

2 of 11 Page 113 of 154


HAMAD INTERNATIONAL AIRPORT
A7111 CENTRAL CONCOURSE APRON

The compliance statement as given below has the following meaning:


A7111 CENTRAL CONCOURSE APRON
Project Specification: SECTION 33 52 43.13 - FUEL SYSTEM PIPE, FITTING AND INSTALLATION

ITEM DESCRIPTION Comply REMARKS

PART 2 - MATERIAL
As per Tender
2.1 PIPING MATERIALS
Clarification # HIAEP-
A The piping system is a combination of above ground and below ground piping. All above
0013_TC_No:08
ground piping shall be of single wall construction. Below ground piping is single wall construction; Not Applicable.
Item # 64, all the
however, a casing system is required for the two taxiway crossings. These two casings require wax fill
pipes will be direct
between the casing and carrier piping.
buried.

B All direct buried piping connections shall be welded. Welded joints shall conform to the
Noted and will be complied
standards set forth in the ASME B31.3 Code for Petroleum Refinery Piping.

C Threaded joints are only allowed for small bore piping that has no internal pressure such as
vent or atmospheric drain piping. Threaded joints shall be American Standard for Pipe
Threads, ASME B1.20.1. All burrs shall be removed. Pipe ends shall be reamed out to size Noted and will be complied
of bore and all chips shall be removed. Teflon pipe thread sealant shall be used on the male
threads only and shall not extend past the end of the pipe.

D Furnish and install flanges where shown and at connections to all equipment. Flanged
connections are only allowed above ground or within pits/vaults. Flanges shall not be direct Noted and will be complied
buried except at temporary line plug (stopple) connections.
E Unless otherwise specified herein or stipulated on the Drawings, all flanges shall be
2.1
matched on piping, valve or equipment as to size, and shall be constructed from materials Noted and will be complied
equivalent to the piping. Flanges shall be raised face.

F Pipe fittings shall be of standard manufacture of materials, weight, and quality


Noted and will be complied
corresponding to the pipe with which they are used.

G Fittings such as elbows, tees, reducers and caps shall be used for all changes in piping
direction, intersections, size changes and end closures unless otherwise stipulated on the Noted and will be complied
Drawings or specified herein.

H The manufacturer or supplier of the piping materials shall provide a certificate of the
inspection, stating origin of manufacture and that all material has been manufactured,
Noted and will be complied
sampled, tested and inspected in accordance with the specified ASTM, API and other
identified specification and has found to meet those requirements.

I All piping shall be stamped with specification and grade. Shop coated pipe shall have
Noted and will be complied
specification and grade stenciled on the coating.

J Galvanized piping is not allowed in the aircraft fueling system. Noted

2.2 PIPING SPECIFICATIONS


A The following table is provided to indicate the basic design conditions of the components Noted
within this section of the specification:

Noted

B The following table is provided to indicate the various materials of construction for the
Noted
design service required by this specification.

2.2

3 of 11 Page 114 of 154


HAMAD INTERNATIONAL AIRPORT
A7111 CENTRAL CONCOURSE APRON

The compliance statement as given below has the following meaning:


A7111 CENTRAL CONCOURSE APRON
Project Specification: SECTION 33 52 43.13 - FUEL SYSTEM PIPE, FITTING AND INSTALLATION

ITEM DESCRIPTION Comply REMARKS

6” CS Pipes API 5L GR.B


SMLS/ERW, PSL2,Sch STD, BE

2.2

Noted and will be complied

SEPARATE
SUBMITTAL

SEPARATE
Complied
SUBMITTAL

noted/complied separate submittal

noted/complied separate submittal

2.2

4 of 11 Page 115 of 154


HAMAD INTERNATIONAL AIRPORT
A7111 CENTRAL CONCOURSE APRON

The compliance statement as given below has the following meaning:


A7111 CENTRAL CONCOURSE APRON
Project Specification: SECTION 33 52 43.13 - FUEL SYSTEM PIPE, FITTING AND INSTALLATION

ITEM DESCRIPTION Comply REMARKS

2.2
noted/complied separate submittal

C The interior and exterior coating for all pipe and piping materials shall be as specified in Section 33 52
Noted and will be complied
80.10, Fuel System Coating.

D Welded elbows shall be long radius unless otherwise shown. Noted and will be complied

E Changes in direction of pipe of other than 45 degrees or 90 degrees shall be made as


follows:
1. With long radius welds cut to proper angle and shop beveled.
2. Or, at the option of the Contractor, with long radius pipe bends. Pipe roundness shall be maintained Noted and will be complied
to factory tolerance for straight pipe lengths. Submit shop drawings of all bends and bending procedures
for approval.
3. Bends of 10 degrees or less shall be miter joints.

F Tee Connections:
1. Branch connections may be used in lieu of butt welding tees for sizes below 3" only, and only above
ground or within pits/vaults. Branch connections shall not be used in direct buried piping unless
otherwise indicated by the Contract Drawings.
2. Branch connections shall be weldolets, sockolets, socket-welded nipolets, or socketwelded
elbolets, as manufactured by Bonney Forge or equal.
Noted and will be complied
3. Material shall be ASTM A105, Grade 2, standard weight steel, and shall conform to ASME B16.11.
4. Use for all vent and instrument connections.
5. If approved by the COTR, the Contractor may use fabricated branch connections in lieu of butt welded
tees for direct buried applications. Connections shall be sweepolets or insert-weldolets as manufactured
by Bonney Forge or equal. All welds on these connections shall be full penetration butt welds and shall
be radiographed.

G Vault Sump Piping:


1. To facilitate pumping out of vault sumps, a drop pipe and quick coupling shall be used. The quick
coupling assembly shall be Dixon Model DDA200ALMNPT or approved equal.
Noted and will be complied
2. The assembly shall be a dry break coupling adapter and protective dust cap of aluminum construction.
3. Use aluminum Schedule 40, 5cm (2 inches) threaded pipe and fittings for fabricating the drop pipe at
the vault sump.

H Fittings for Threaded Fuel Pipe:


1. Threads of threaded jointed piping shall be full, clean, sharp, and true.
Noted and will be complied
2. Bushings shall not be used except as noted on the drawings.
3. 3,000 pound forged steel conforming to ASME B16.11.

2.3 TESTING EQUIPMENT


A The Contractor shall provide all necessary devices to test the completed piping system. Items shall
include but, not be limited to the following:
1. Air compressors:
a. Air compressors shall be equipped with condensate dryer system and filter capable of generating oil-
free air at -29oC (-20 "F) dew point.
b. Air compressors shall have sufficient capacity to bring the system pressure in a maximum of 60
2.3 Noted and will be complied
minutes.
2. Pressure and temperature recorders:
a. Provide certified and calibrated test instruments capable of recording direct temperature, pressure
and time in the same scale and chart.
b. Submit data for test instruments and certificates of calibration.
3. Temporary piping:
a. Provide all piping, fittings, valves, gauges and equipment required for inspection and testing.

5 of 11 Page 116 of 154


HAMAD INTERNATIONAL AIRPORT
A7111 CENTRAL CONCOURSE APRON

The compliance statement as given below has the following meaning:


A7111 CENTRAL CONCOURSE APRON
Project Specification: SECTION 33 52 43.13 - FUEL SYSTEM PIPE, FITTING AND INSTALLATION

ITEM DESCRIPTION Comply REMARKS

2.4 FUELS
Separate procedure
A The Contractor shall perform hydrostatic testing of the new pipe. The Fuel System Operator
2.4 Noted and will be complied will be submitted for
will provide the Jet A fuel required for the hydrostatic testing. The fuel shall meet ASTM D1665, latest
approval
revision specification for Jet A Aviation Turbine Fuel.

PART 3 - EXECUTIONS
3.1 CLEAN PIPING REQUIREMENTS
A The importance of keeping the interior of all piping systems clean during construction is critical. The
Contractor is required to keep the interior of the carrier piping, and the annular space between carrier
pipe and casing pipe, clean from all visible dirt or foreign matter at all times and under all conditions. If
Noted and will be complied
for any reason the inside of the piping contains dirt or foreign matter, the Contractor shall correct this
condition to the COTR's satisfaction with all necessary material, labor and equipment for cleaning being
furnished at the Contractor's expense. The following measures shall be taken to assure cleanliness of the
system:
3.1
1. The pipe and fittings shall be delivered to the job site sealed. The seals are not to be removed until the
pipe is installed. After each day's work, the open ends of all pipe being installed shall be sealed closed
with an expansion type weatherproof and watertight seal manufactured for this purposes. At the
Contractors option, weld caps or plate steel may be welded into place on the end of the pipe.
Noted and will be complied
2. All fittings and valves shall be kept in a covered dry storage area until installation.
3. Pipe shall not be installed or stored in areas or ditches containing water or mud.
4. At openings for branches in piping, all material that falls into the pipe must be removed before
welding in the branch fittings.

3.2 HANDLING PIPE


A The shipment, delivery, and installation of all pipe and accessories shall be handled in such
manner as to ensure a sound undamaged condition. Particular care shall be taken not to damage pipe
coating when storing pipe. No other pipe or materials of any kind shall be placed inside a pipe or fitting
3.2 Noted and will be complied
after the coating has been applied.

B Perform the hauling of pipe and other materials in such a manner as to prevent damage to
pipe and material. If damage is sustained, Contractor shall be responsible for repair or replacement cost.

3.3 FABRICATION AND INSTALLATION


A All piping materials, fabrication, installation and application shall be in compliance with the
Noted and will be complied
latest requirements of the code for Petroleum Refinery Piping ASME B31.3, and all state and local
regulations when applicable.
3.3

B All temporary piping required for construction, testing, flushing and start-up shall be furnished by the
Contractor. Such piping shall remain the property of the Contractor; and it shall be his responsibility to Noted and will be complied
dismantle and remove it from the premises when no longer required.

C End Preparation: The base metals for all butt-welding pipe joints shall be prepared to provide for
proper "fit-up" in accordance with ASME B16.25. Ends shall be prepared by machining or flame cutting.
Hand flame cutting is only allowed subject to approval by the COTR and only where the use of machine
or automatic machine flame cutting is impractical. Hand flame cuttings shall be ground smooth. No
welded joint shall be made where either flame cut or machine cut ends provide a spacing between the
Noted and will be complied
pipe so large that more than one stringer bead is required to completely close the pipe. Where flame
cutting by hand is employed, the included angle or bevel at the end of the pipe shall be not less than
plus or minus 5 degrees from that which is required elsewhere in these specifications for machine cut
beveled ends. Pipe end for socket welding shall be reamed for the full inside diameter to remove all
burrs and obstructions.

D All pipe shall follow the rutes shown on the drawings and shall be placed accurately to measurements
indicated or established from the work. Pipe shall be placed clear of equipment, and other work.
Noted and will be complied
Changes in direction shall be made by use of fittings for standard angles and by trimmed fittings for
angles other than standard. Reference earlier paragraphs in this section.

E Any damage to the internal or external pipe coatings by bending or handling, including lineup of pipe
joints, shall be the responsibility of the Contractor and shall be repaired to equal the original coating. Noted and will be complied
Repair of the internal coating damaged by field welding of pipe joints is not required.

F Proper pipe joint alignment and separation shall be accomplished without the use of backing rings. Noted and will be complied

6 of 11 Page 117 of 154


HAMAD INTERNATIONAL AIRPORT
A7111 CENTRAL CONCOURSE APRON

The compliance statement as given below has the following meaning:


A7111 CENTRAL CONCOURSE APRON
Project Specification: SECTION 33 52 43.13 - FUEL SYSTEM PIPE, FITTING AND INSTALLATION

ITEM DESCRIPTION Comply REMARKS

G Weld spatter shall be removed around welds leaving a smooth clean surface. Noted and will be complied

H Pipe shall be fabricated to measurements established on the job and shall be carefully worked into
Noted and will be complied
place without springing or forcing.
3.3

I Flanges and unions shall not be placed in a location that will be inaccessible after completion of the
Noted and will be complied
work.

J All piping and equipment shall be properly supported and guided. Anchors shall be provided where
Noted and will be complied
shown and where required to absorb or transmit thrust and eliminate vibration or pulsation.

K Changes in pipe size shall be made with reducing fittings. The Contractor shall pay special
attention to the type of reducer, and its orientation, shown on the Contract Drawings. Bushings shall Noted and will be complied
not be used unless otherwise shown.

L Flanged joints shall be accurately centered and aligned prior to installation of bolts so as to
Noted and will be complied
prevent mechanical pre-stressing of the flanges, pipe and equipment.

M For Buried Piping refer Section 31 23 23.13 Fuel System Excavation, Bedding & Backfill for
Noted and will be complied
trench excavation, backfill and compaction requirements.

N Install pipe so as to be clear of contacts with other pipes, pipe sleeves, casings, reinforcing
steel, conduits, cables, or other metallic structures. Minimum separation from non-metallic
utilities is 30.5cm (12 inches) and from metallic utilities is 61cm (24 inches). Should uncovered field Noted and will be complied
conditions result in clearances less than this, bring to the attention of the COTR for resolution prior to
installing the new piping.
O Verify all measurements before commencing work. Submit discrepancies for clarification
Noted and will be complied
before proceeding.

P Arrange all piping with proper slopes, without sags, traps, or pockets. Noted and will be complied

Q Provide high point vents, pump outs, and low point drains as required and indicated on the
Noted and will be complied
drawings.

3.4 WELDING
A Qualifications of welders shall be done by Contractor in accordance with ASME B31.3, Petroleum
Refinery Piping, on the project site, witnessed by the COTR and before being allowed to make
construction welds. Certified test results for each welder employed by the Contractor shall be kept in the Noted and will be complied
contractor's field office for inspection by the COTR. Performance test records of welders issued by a
previous employer, in lieu of qualification tests conducted by the Contractor, will not be acceptable. The
Contractor shall assume the costs for all tests.

B. Welding and fabrication shall be accomplished in accordance with ASME B31.3 latest edition. Before
welding, the piping or other equipment shall be carefully lined up so that no part is offset; flanges and
branches shall be set square and true. This alignment must be preserved during the welding operation. If
tack welds are used, they must be of the same quality and made by the said procedure as the completed
weld. Backing rings shall not be used. No weld metal shall project within the pipe so as to restrict its area Noted and will be complied
or cause danger of its loosening and falling into the pipe. The piping shall not be split, bent, flattened or
otherwise injured before, during or after installation. During erection, care shall be taken to remove all
dirt, scale and other foreign matter from inside the piping before tying in sections, valves, equipment or
fittings.

C. All welded joints shall be made as recommended by the standards of the American Welding
Society and B31.3. The welding shall ensure complete penetration of the deposited metal with the base
Noted and will be complied
metal. The filler shall be suitable for use with the base metal. Mitered joints shall not be used except
where specifically allowed in this specification or on the Drawings.
D. All manual welds shall be made using downhill welding procedure. Shop welds utilizing machine-
welding procedures do not have to qualify to the downhill requirement. Machine welding Noted and will be complied
procedures must be qualified and submitted to the COTR.

3.4

7 of 11 Page 118 of 154


HAMAD INTERNATIONAL AIRPORT
A7111 CENTRAL CONCOURSE APRON

The compliance statement as given below has the following meaning:


A7111 CENTRAL CONCOURSE APRON
Project Specification: SECTION 33 52 43.13 - FUEL SYSTEM PIPE, FITTING AND INSTALLATION

ITEM DESCRIPTION Comply REMARKS

E Inspection and Repair:


3.4 1. All below ground welds (100%) shall be radiographed in accordance with these specifications. All
socket welds and fillet welds shall be inspected with magnetic particle testing. Noted and will be complied
2. Any weld that is determined to be defective by the testing laboratory shall be repaired in accordance
with ASME B31.3. The Contractor shall be responsible for all costs associated with the weld repair.

F Qualifications and Approval:


1. Welding procedures that are intended to be used on the job shall be submitted for approval. The
Contractor shall be responsible to assure that all welding procedures, welders, and welding operators
have been qualified in accordance with applicable code requirements before work is started. Shop and
field procedures shall be submitted to the COTR for approval. The procedure specifications shall be as
follows:
a. Include copies of the qualification test records as evidence that the procedures have been qualified in
accordance with the latest revisions of the following code: # ASME B31.3 - Chemical Plant and Petroleum
Refinery Piping Noted and will be complied
b. Developed for the conditions of this Contract and be complete and specific, and if necessary,
differentiate between shop and field welding.
c. Welder Performance Qualification Test Certificates:
# Furnish welder performance qualification test certificates prior to starting work for position 6G for the
pipe being installed as part of this project made in strict compliance with the above code.
2. Submit qualification test records for each welder on the project and keep record files.
3. Costs: Costs incident to procedure and welders qualification tests shall be the responsibility of the
Contractor.

G Each welder shall identify each of his welds with a specific code or identifier. The Contractor shall keep
an as built fabrication drawing on the site that identifies the location of each weld made and also
Noted and will be complied
indicates the welder who made the weld. The weld shall be made with a “low stress” steel stamp or
permanent ink marking.

H The Authority reserves the right to place welding inspectors (at the Authority’s cost) in the shop where
Noted and will be complied
off site welding is taking place.

3.5 CONNECTION TO ACTIVE PIPING


A Active piping shall not be cut, tapped or disturbed until the Contractor has obtained the Noted and will be complied
necessary written approvals from the COTR and the Fuel System Operator.

B Each active fuel line shall be substantially drained prior to cutting into the line. Fuel shall not
3.5 remain in the piping as it is cut. The contractor shall exercise extreme caution during the cutting of Noted and will be complied
existing piping and shall not use cutting torches and spark producing cutting tools and methods.

C The Contractor shall have the necessary number of drip pans and vacuum trucks on site during cutting
operations. Any and all fuel spilled during the cutting procedure shall be immediately cleaned up and Noted and will be complied
removed from the site by the Contractor at no additional cost to the Contract.

D The Contractor shall take adequate measures for fire protection during modifications to existing piping
and equipment. Such measures shall include, as a minimum but not limited to, the following
precautions:
1. Do not cut, bevel, weld, grind or otherwise generate sparks near open sources or spills of jet fuel.
2. Provide a fire extinguisher, 9.5L (2.5 gallons) Class AB Foam Type, at each welding operation.
Noted and will be complied
3. Protect adjacent services from weld splatter and sparks by use of welding blankets.
4. Obtain necessary hot work permits from the Airport.
5. Notify the Airport Fire Department at least 48 hours in advance of the intended operation. In the
event the Fire Department elects to have equipment present during the operation, the Contractor shall
coordinate the construction area with the Fire Chief to allow proper positioning of equipment.

3-Instead of Plidco
E Welding to existing piping: fittigns, the fuel line
1. Flow nitrogen through piping and weld area to eliminate all measurable oxygen. will be gas freed and
1 & 2 -Noted and will be complied
2. Weld piping in accordance with API, NFPA and 0SHA requirements. welding will be
3. Use Plidco fittings to eliminate welding directly within the vapor space of existing piping. carried out. Detailed
procedure will be
3.5

8 of 11 Page 119 of 154


HAMAD INTERNATIONAL AIRPORT
A7111 CENTRAL CONCOURSE APRON

The compliance statement as given below has the following meaning:


A7111 CENTRAL CONCOURSE APRON
Project Specification: SECTION 33 52 43.13 - FUEL SYSTEM PIPE, FITTING AND INSTALLATION

ITEM DESCRIPTION Comply REMARKS


3.5 F Plidco Fittings:
1. Plidco fittings (“weld + ends”) shall be employed at each saw cut into existing underground piping.
Each fuel line shall be substantially drained prior to cutting into the line.
2. Follow the manufacturer’s printed installation procedure. Flow fuel prior to weld-out.
3. Installing Plidco “weld +ends”:
a. The existing piping shall be cleaned of all old coating in the area where the Plidco is to be installed.
The pipe shall be cleaned of burrs and other surface irregularities that might damage the Plidco seals
during operation.
b. Slide Plidco “weld + ends” completely over one end of pipe. Mark off one-half of Plidco “weld + ends” Not part of this material
coupling length from middle of gap in pipe joints. Slide fitting back to mark to divide coupling equally submittal
over joint.
c. After coupling is positioned, torque clamping and thrust screws tight, following the manufacturers
installation instructions for torque values and sequence.
d. Pipeline shall be put in operation. Thrust screws shall be burned off flush. Ends of coupling shall be
fillet-welded around circumference, including seal welding of thrust screws. Clamping screws shall be cut
or burned off and seal-welded also.
e. For critical, limited schedule, tie-in operations the Contractor shall have an extra pair of seals on hand
for each size of Plidco coupling.
3.6 WELD INTEGRITY TESTING
A All butt welds for field and shop fabricated piping for belowground installation (including those welds
within a pit/vault) shall be 100 percent radiographed. All socket welds for field and shop fabricated
Noted and will be complied
piping for installation within a pit or vault, shall be 100 percent magnetic particle inspected. Ten percent
of the aboveground piping shall be randomly selected for radiographic and/or magnetic particle
inspection.

B All fillet welds on hot tap weldolets and on Plidco couplings shall be magnetic particle tested. Noted and will be complied

C Piping where factory welds have been performed, must also be radiographed or tested by an approved
testing laboratory with results provided to the Contractor upon delivery and receipt of the piping. Noted and will be complied
Forward results of the testing to the COTR.

D All weld integrity-testing costs, including test reports and interpretation, are the responsibility
of the Contractor. An independent testing laboratory employed by the Contractor, and subject to
Noted and will be complied
approval by the COTR, shall perform the weld integrity testing. All testing shall be performed in
accordance with ASME B31.3.
3.6
E One film negative of each radiograph shall be made. Each negative shall be identified as to
location. Negatives shall be turned over to the Authority at the end of the project. An expert
interpretation by a recognized testing laboratory shall be submitted in report form for every weld to the Noted and will be complied
COTR throughout the progress of the work. The report shall show date of test, location, area, film
number, weld number and other pertinent information.

F Permanent radiographic identification stamps shall be located on the piping near the welds. Noted and will be complied

G The Independent Laboratory making the tests shall interpret test results and any defects
found shall be repaired by the Contractor and a new radiograph taken of the repair. The cost for Noted and will be complied
inspection of defective welds shall be the responsibility of the Contractor at no cost to the Authority.

H The Contractor shall coordinate the weld integrity testing with the testing lab, making certain
Noted and will be complied
that adequate notices are given that the welds are available for testing.

I Backfilling of the piping shall not commence until tests have been approved by the COTR and pressure
Noted and will be complied
tests have been completed.

3.7 PNEUMATIC PRESSURE TESTING OF FUEL

A General: The entire newly installed, fuel distribution piping shall be pneumatically pressure tested
Noted and will be complied
after all joints are completed, in accordance with ASME B31.3 and API RP 1110. Sections of the system
may be tested and accepted in order to expedite the work or as required due to phasing requirements.
These sections shall be tagged by the Contractor to indicate compliance with the tests.

B Install temporary closures or other fittings, including plugs, weld caps, blind flanges, etc., as
Noted and will be complied
necessary to facilitate the testing process.

9 of 11 Page 120 of 154


HAMAD INTERNATIONAL AIRPORT
A7111 CENTRAL CONCOURSE APRON

The compliance statement as given below has the following meaning:


A7111 CENTRAL CONCOURSE APRON
Project Specification: SECTION 33 52 43.13 - FUEL SYSTEM PIPE, FITTING AND INSTALLATION

ITEM DESCRIPTION Comply REMARKS

C Test Procedure: Tests shall be made with clean dry-filtered and oil-free compressed air – negative
29oC (-20oF) pressure dew point – or compressed nitrogen gas and shall be made in accordance with all
applicable codes particularly with regard to safety precautions and the following:
1. A preliminary check of the fuel distribution piping at 172kPa (25psig) shall be made. Noted and will be complied
2. The pressure shall be increased gradually in steps, providing sufficient time to allow the piping to
equalize strains during the test, and to be checked for leaks. Final test pressure shall be 689kPa (100psig)
for four hours.

3.7 D The Contractor shall provide certified and calibrated temperature and pressure instruments
and chart recorders and a deadweight tester to provide continuous calibration and direct readings of
time, temperature, and pressure on the same scale and chart during the tests. Test Certifications and Noted and will be complied
recorder charts shall be submitted to the COTR for approval prior to final acceptance of the piping.
Calibrated thermocouples may be surface applied.

E Repair any leaks detected. Retest at 4 hour pressure cycles, as described above after all leaks have
Noted and will be complied
been repaired. Repeat repair and testing cycles until the system is acceptable to COTR.

F Equipment, which is not rated by the manufacturer for the test pressure, shall be removed or isolated
prior to testing. Install temporary connections as necessary. All permanent butterfly and plug valves and Noted and will be complied
equipment, which are rated at the test pressure or greater, shall be in place during the pneumatic tests.

G The 4 hour recordings shall be made after temperature and pressure has stabilized and shall be
Noted and will be complied
conducted in accordance with NFPA Codes and API RP1110 and this specification.

H The pneumatic test shall be finalized before paving is started. Noted and will be complied

I Pneumatic testing shall be completed in segments as Phasing construction is completed. Noted and will be complied

3.8 HYDROSTATIC PRESSURE TESTING OF FUEL PIPING


A After a successful pneumatic test has been completed, the Contractor shall begin preparation Noted and will be complied
for hydrostatic testing.

B The Contractor shall remove all control valves, meters, and other equipment, which are not rated by
the manufacturer for the test pressure of 1,896kPa (275psig). Piping spools and blind flanges shall be Noted and will be complied
provided and installed by the Contractor.

C Prior to hydrostatic testing the Contractor shall carefully fill the fuel system piping with the proper
grade of fuel. During the filling process care should be taken to properly vent all high Noted and will be complied
points to disperse all air pockets.

D The Fuel System Operator will provide the required amount of fuel for the initial line fill and
Noted and will be complied
hydrostatic testing. Contractor shall assist in confirming the line fill volume.

3.8
E The hydrostatic testing shall be in accordance with ASME B31.3 and shall include a two step process.
The initial step will be to gradually bring system pressure up to 689kPa (100psig) and inspect all joints,
Noted and will be complied
components and connections. The second step will be to gradually bring system pressure up to 1,896kPa
(275psig) and recheck all joints, components, and connections.

F The actual test shall be to hold pressure at 1,896kPa (275psig) for eight hours. Noted and will be complied

G During the testing period, if a leak develops, the Contractor shall abort the test, repair the defect and
Noted and will be complied
restart the test from the beginning.

H The Contractor shall provide certified and calibrated temperature and pressure instruments
and chart recorders and a deadweight tester to provide continuous calibration and direct readings of
time, temperature, and pressure on the same scale and chart during the tests. Test Certifications and Noted and will be complied
recorder charts shall be submitted to the COTR for approval prior to final acceptance of the piping.
Calibrated thermocouples may be surface applied.

10 of 11 Page 121 of 154


HAMAD INTERNATIONAL AIRPORT
A7111 CENTRAL CONCOURSE APRON

The compliance statement as given below has the following meaning:


A7111 CENTRAL CONCOURSE APRON
Project Specification: SECTION 33 52 43.13 - FUEL SYSTEM PIPE, FITTING AND INSTALLATION

ITEM DESCRIPTION Comply REMARKS

3.9 PIPE HANGERS AND SUPPORTS


A Pipe hangers and supports shall meet the requirements of ASME B31.3 and shall be as detailed.
B Where changes in direction occur, reduce the spacing allowed in ASME B31.3 by threequarters.
C Not all supports are shown. Furnish and install all rigid supports, whether or not they are shown and Not part of this material
detailed, but are required to adequately support the piping systems. Include all necessary structural submittal
steel, brackets, concrete inserts, etc., which are required to properly support the piping systems.
D Install piping and provide necessary support and anchors to prevent forces from being imposed on
equipment that would exceed the limits specified by the equipment manufacturer.

3.9
E Provide complete assemblies that are rated for a minimum of 200% of the applied load.
F Provide galvanized concrete inserts and shop- or field- fabricated galvanized brackets or
structural steel shapes where necessary to meet field conditions.
G Observe the flushing system in operation and make adjustments as necessary to support the system
under dynamic loads. Not part of this material
H Expansion bolts shall be self-drilling anchors, or insert type. Powder driven fasteners shal not be used. submittal
I Fabricate anchors welded to the pressure barrier from the same materials as the pipe and fasten
securely to structure at points of adequate structural strength.
J Support locations configuration and orientation shall be identified and submitted to the COTR prior to
beginning installation.

3.10 SAFETY PRECAUTIONS AND FUEL SYSTEM MODIFICATIONS


A Safety procedures are the responsibility of the Contractor. All operations in the construction
area that involve open flames or the possibility of arcing or sparking shall be conducted in a Not part of this material
"Gas-Free" condition. submittal
B It shall be the responsibility of the Contractor to monitor the use and suitability of the equipment and
procedures on the job and maintain a safe "Gas-free" condition when necessary during construction.

C Prior to commencing any phase of the work requiring a gas-free condition, the Contractor shall make
the following minimum provisions:
3.1 1. Empty pipes containing fuel and purge all vapors.
2. Isolate, blank off, and adequately ventilate open piping sections so that no part of the pipe containing Not part of this material
fuel or vapors is exposed. submittal
3. Inspect for, and confirm that there are no open pools of fuel, or soil contaminated to a combustible
limit, in the area of the work.
4. Drain and ventilate storage tanks prior to working on the tanks or tank connections.

D Utilize a combustible gas analyzer or similar device to make certain that concentrations of
combustible gas do not exist in the construction area when performing these operations. Not part of this material
E Perform all safety precautions as required to assure that the work is conducted in a safe manner and submittal
to conform to applicable codes.

3.11 FIELD QUALITY CONTROL


3.11 A Be responsible for periodic inspections for conformance with the approved SPPP. The results of the Noted and will be complied
periodic inspections shall be submitted to the COTR upon completion.

11 of 11 Page 122 of 154


7. Typical Material Test Report

Document No. ME-00065-A7110-CN-MCC-P-00-MAR-00001-00

Current version of this document is available online on the local intranet in electronic format. Page 123 of 154
Page 124 of 154
Page 125 of 154
Page 126 of 154
Page 127 of 154
Page 128 of 154
Page 129 of 154
Page 130 of 154
Page 131 of 154
Page 132 of 154
Page 133 of 154
Page 134 of 154
Page 135 of 154
Page 136 of 154
Page 137 of 154
Page 138 of 154
Page 139 of 154
Page 140 of 154
Page 141 of 154
Page 142 of 154
8. Bill of Quantity

Document No. ME-00065-A7110-CN-MCC-P-00-MAR-00001-00

Current version of this document is available online on the local intranet in electronic format. Page 143 of 154
Project : A7110 CONCOURSE D+E - EXPANSION
Employer : Hamad International Airport, Qatar
Engineer : Dar
Contractor : Midmac
Sub Contractor : AMANA
FUEL HYDRANT NETWORK - MECHANICAL BOQ FOR CONCOURSE D & E EXPANSION

Total
Sl No. Description Dia Unit Required Remarks
Qty

30 Deg Induction Bend (5xDia) API 5L GR.B, PSL2, ANSI B 16.49 Sch. XS, BE 20" Nos 6 TBC
1
90 Deg Elbow (Short Radius) ASTM A234, Grade B, SCH. XS, BE 20" Nos 2
2
Equal Tee ASTM A234 WPB, SCH. XS, BE 20" Nos 2
3
End Cap ASTM A234 WPB, ANSI B16.9, SCH XS, BE 20" Nos 6
4

Page 144 of 154


Page 1 of 4
9. Material Submittal Previous Approvals for HIA.

Document No. ME-00065-A7110-CN-MCC-P-00-MAR-00001-00

Current version of this document is available online on the local intranet in electronic format. Page 148 of 154
Page 149 of 154
Page 150 of 154
Page 151 of 154
10. Certificate of Origin (COO)

Document No. ME-00065-A7110-CN-MCC-P-00-MAR-00001-00

Current version of this document is available online on the local intranet in electronic format. Page 152 of 154
Page 153 of 154
Page 154 of 154

You might also like