INDIVIDUAL WORK SCHEDULE FROM 28.10.

2022
JUSTIFICATION FOR COS CULVERT
SR. NO. NAME JOB FINISHING DATE Project Name SUBMISSION DATE
JOB STATUS MAN DAYS REASON OF DELAY
1 Ashish/ Jaipal 03-11-2022 Viaduct-3 Km-85+218- km 85+538 (320m) 07.11.2022 Design of super str 4 girder system straight Pending 3
2 Ashish/Jaipal 05-11-2022 Viaduct-3 Km-85+218- km 85+538 (320m) 07.11.2022 Design of Pier cap Design and dwg pending 2
3 Ashish 07-11-2022 Viaduct-4 Km-87+048- km 87+168 (120m) 11.11.2022 Design of Pier cap Design and dwg pending 2
4 Ashish 09-11-2022 Viaduct-4 Km-87+048- km 87+168 (120m) 11.11.2022 Design OF Abutment (RCC box) Pending 2
5 Ashish 11-11-2022 Viaduct-5 Km-88+086- km 88+226 (140m) 14.11.2022 Design of Pier cap Pending 2
6 Ashish 15-11-2022 (NH-319A) Design and drawing of Super str Pending 4
7 Jaipal 12-11-2022 Viaduct-5 Km-88+086- km 88+226 (140m) 14.11.2022 Dimensional and Reinforcement dwg of super structure for curved Pending 7
8 Pushpesh/ Jaipal 29-10-2022 Viaduct-1 Km-82+954- km 83+174 (220m) 18.11.2022 Submission of GAD GAD is complete , submission pending
9 Pushpesh 04-11-2022 Viaduct-3 Km-85+218- km 85+538 (320m) 07.11.2022 Design OF Abutment Pending 4
10 Pushpesh 07-11-2022 Viaduct-4 Km-87+048- km 87+168 (120m) 11.11.2022 Design OF Abutment Pending 3
11 Pushpesh 09-11-2022 Viaduct-5 Km-88+086- km 88+226 (140m) 14.11.2022 Design OF Abutment Pending 2
12 Pushpesh 11-11-2022 Viaduct-1 Km-82+954- km 83+174 (220m) 18.11.2022 Design and dwg of Pier Pending 2
13 Pushpesh 12-11-2022 Viaduct-1 Km-82+954- km 83+174 (220m) 18.11.2022 Design OF Abutment Pending
1
14 Pushpesh 12-11-2022 Viaduct-1 Km-82+954- km 83+174 (220m) 18.11.2022 Design of super str 4 girder system straight apply similar already designed
15 Pushpesh 16-11-2022 Viaduct-1 Km-82+954- km 83+174 (220m) 18.11.2022 Design of Pier cap pending 4
16 Pushpesh/ Jaipal Viaduct-2 Km-84+282- km 85+048 (220m) 26.11.2022 Design of Pier cap Design and dwg pending
26.11.2022 10
17 Pushpesh/ Jaipal Viaduct-2 Km-84+282- km 85+048 (220m) 26.11.2022 Design OF Abutment Pending
18 Aayush 31.10.2022 TOPSI BOW String PENDING
19 Aayush 01.11.2022 PANDABESWAR Submission of A2 Pier Cap PENDING 1
20 Aayush 03.11.2022 SURI DBR of Suri PENDING 2
21 Aayush 05.11.2022 NH-319A Design and drawing of sub str foundation bridge at km 11+607 PENDING 2
22 Aayush 08.11.2022 NH-319A Design and drawing of sub str foundation bridge at km 30+307 PENDING 3
23 Karan 14.11.2022 NH-319A Design and DWG of Bus shelter / Plan PENDING 9
24 Karan 02.11.2022 NH-319A Design of Box Bridge (Straight) MODIFICATION REQUIRED 2
25 Karan 05.11.2022 NH-319A Design of Box Bridge (Skew) PENDING 3
26 Karan 10.11.2022 NH-319A Design of BOX culvert Cast in situ PENDING 5
27 Kunti 28.10.2022 TOPSI Road furniture and sinages dwg PENDING
28 Kunti 29.10.2022 PANDABESWAR Road furniture and sinages dwg KUNTI
29 Shadab/Kunti 03.11.2022 NH-319A Submission of Plan and Profile, TCS MODIFICAITON REQUIRED 3
30 Kunti 30.11.2022 SURI Submission of Junction Dwg PENDING 27
31 Jaiki/Shadab 03.11.2022 ADDITIONAL BLACK SPOT Submission of final DPR as per revised design 3
32 Jaiki/Shadab 18.11.2022 ADDITIONAL BLACK SPOT Submission of Final DPR Gulab bagh 15