Professional Documents
Culture Documents
“FLOATEL TRIUMPH”
AT KEMAMAN PORT – MALAYSIA
April 2022
DOCUMENT ISSUE RECORD
Rev. No. Date Status Author Checked Approved
0 29/04/22 Issued for Review Yifei Pradeep Pradeep
InterMoor Pte Ltd. assert the right to be identified as author of this document. The Copyright of this document and any
drawings and specifications contained within are the property of InterMoor Pte Ltd. This document must not be copied or
reproduced, in whole or in part by any means, must not be divulged to any unauthorised third party and must not be used for
any project other than that for which it is intended without the prior written consent of InterMoor Pte Ltd. The receipt of this
document implies that the conditions contained herein are accepted.
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
REVISION HISTORY
Pages/
Revision Appen Description
dix
0 - -
________________________________________________________________________
Page 2
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
ABBREVIATIONS
ACD = Above Chart Datum
AFT = After End of the vessel
API = American Petroleum Institute
ASB = Above Seabed
AWL = Above Waterline
CL = Centreline
DNV = Det Norske Veritas
DOF = Degrees of Freedom
FWD = Forward End of the vessel
GA = General Arrangement
HS = Significant wave height
HT = High Tide
KG = Distance from the Keel to the Vessel Centre of Gravity
KN = Kilonewton
kts = Knots
LT = Low Tide
LAT = Lowest Astronomical Tide
M = Displacement
m = Meter
MBL = Minimum Breaking Load
min = Minute
mt = Metric Ton Unit
PORT = Portside of the vessel
PP = Polypropylene
QTFs = Quadratic Transfer Function
RAOs = Response Amplitude Operator
s = Second
SLF = Single Line Failure
STBD = Starboard side of the vessel
SWL = Safe Working Load
TZ = Zero up-crossing Period
________________________________________________________________________
Page 3
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
EXECUTIVE SUMMARY
Quayside mooring analyses has been carried out for the vessel “Floatel Triumph”, for
quayside mooring at Kemaman Port, Malaysia. Six lines of 85mm (106mt MBL)
polypropylene ropes were used connecting the Floatel Triumph to the Jetty. Client advised
two Yokohama fenders (3.3m Dia and 6.5m Length) will be attached to the quay fenders. All
eight (8) units of polypropylene ropes, which were previously used for Floatel Triumph
quayside mooring at Kaohsiung port in Taiwan, are available for quayside mooring at
Kemaman Port. Current mooring design is carried out with the use of these available ropes.
Refer to Appendix A for the mooring arrangement.
The Floatel Triumph will be moored with transit draft of 7.47m around one month in May
2022. During this period, the rig is to be disconnected and standby with rig propellers if the
wind speed at the quayside exceeds the limiting design 1-minute average wind speed of
27knots at any direction. The Floatel Triumph can be safely moored for one month period
with 6 lines of 85mm (106mt MBL) polypropylene ropes if the 1-minute average wind speed
is 27knots or less. In months from May to July, wind speed at the mooring location is
expected to be less than 27 knots.
The mooring analysis (dynamic analysis for critical cases) results are presented in this
report based on the mooring arrangement shown in Appendix A. Three (3) of the mooring
lines are directly connected between the starboard side vessel bollards and the quayside
bollards. The other three (3) mooring lines are passing through the fairleads and are
connected between the vessel bollards and the quayside or land bollards. The vessel
bollards and fairleads are on the vessel pontoon deck. For this configuration, mooring
loading requirements are satisfying with considerable margin as summarised in Table 1
below.
As the jetty and land bollards are at higher elevation than vessel connection points, it is
recommended to provide rubber or rope protection to the mooring line at the contact points
at edge of jetty.
________________________________________________________________________
Page 4
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
Dimensions and exact location of concrete wall structure presence near the land bollard is
not available/ provided by the client after the InterMoor request. Hence, the location and
dimensions of this structure assumed with provided photos for the analysis to check the
mooring line #5 clashing with this structure. If the contact occurs between mooring line and
the concrete wall, it is recommended to provide rubber or rope protection to the mooring
line at the contact point.
Table 1: Dynamic analysis Critical Mooring Results for Both Low & High Tide Cases
Note: Jetty (Tee Head) Bollard SWL = 150mt, Land (Double Bitt) Bollard SWL = 50mt, Vessel
Bollard SWL = 95mt, Mooring Rope MBL = 106mt. Required minimum safety factor for
connecting components (bollard, towing bracket etc) are from Reference 5. Mooring rope
safety factor requirements are from Reference 3. Expected Maximum dynamic loading on
the Fender is 289KN.
________________________________________________________________________
Page 5
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
1 37.2 63
2 58.9 88
3 44.4 67
4 14.1 41
5 146.3 190 (95 + 95)
6 64.1 91
Spare 1 - 44
Note: Refer to Appendix A mooring arrangement drawing for line Numbers. For mooring
line no. 5, two 95m mooring ropes need to be joint together to meet the length requirement.
2m eye splice to be made at both ends of each pp rope.
________________________________________________________________________
Page 6
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
TABLE OF CONTENTS
ABBREVIATIONS ................................................................................................................................ 3
EXECUTIVE SUMMARY ...................................................................................................................... 4
1.0 INTRODUCTION .................................................................................................................... 8
1.1. BACKGROUND .................................................................................................................................................... 8
1.2. SCOPE OF WORK ............................................................................................................................................... 8
1.3. INFORMATION RECEIVED ............................................................................................................................... 9
1.4. ASSUMPTIONS.................................................................................................................................................... 9
2.0 ANALYSIS DATA .................................................................................................................. 10
2.1. QUAYSIDE LOCATION DETAILS .................................................................................................................. 10
2.2. ADVISED FLOTEL TRIUMPH MOORING POSITION................................................................................. 13
2.3. VESSEL CHARACTERISTICS.......................................................................................................................... 14
2.4. VESSEL CONNECTION POINTS .................................................................................................................... 17
2.5. ENVIRONMENTAL FORCES .......................................................................................................................... 18
3.0 DERIVATION OF MOORING SYSTEM .............................................................................. 20
3.1. MOORING SYSTEM ARRANGEMENT .......................................................................................................... 20
3.2. MOORING LINE PRETENSION ..................................................................................................................... 21
3.3. MOORING SYSTEM COMPONENT ............................................................................................................... 21
4.0 ANALYSIS METHODOLOGY .............................................................................................. 22
4.1. METHOD OF ANALYSIS ................................................................................................................................. 22
4.2. ANALYSIS CONSIDERATIONS....................................................................................................................... 22
4.3. MOORING GUIDELINES, CODES AND ACCEPTANCE CRITERIA............................................................ 23
4.4. ORCAFLEX MODELLING ............................................................................................................................... 23
4.5. METEOROLOGICAL (ENVIRONMENTAL) CRITERIA............................................................................... 26
5.0 STATIC ANALYSIS RESULTS – LOW TIDE & HIGH TIDE ............................................ 27
5.1. SUMMARY ........................................................................................................................................................ 27
5.2. MOORING LINE TENSIONS – INTACT CASE ............................................................................................. 27
5.3. JETTY / LAND BOLLARD LOAD – INTACT CASE..................................................................................... 28
5.4. ESSEL TOWING BRACKET LOAD – INTACT CASE ................................................................................... 29
5.5. CRITICAL MOORING COMPONENT RESULTS – CRITICAL SINGLE LINE FAIL CASE....................... 30
5.6. FENDER LOAD ................................................................................................................................................. 30
6.0 DYNAMIC ANALYSIS RESULTS – LOW TIDE & HIGH TIDE ........................................ 31
6.1. SUMMARY ........................................................................................................................................................ 31
6.2. CRITICAL MOORING COMPONENT RESULTS – CRITICAL INTACT CASE .......................................... 31
6.3. CRITICAL MOORING COMPONENT RESULTS – CRITICAL SINGLE LINE FAIL CASE....................... 31
6.4. FENDER LOAD ................................................................................................................................................. 32
7.0 REFERENCES ........................................................................................................................ 33
________________________________________________________________________
Page 7
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
1.0 INTRODUCTION
1.1. Background
1.1.2. InterMoor Pte Ltd was requested by Flotatel International to carry out the
quayside mooring analysis to design the mooring line size and quantity
requirement for specified limiting wind.
1.1.3. The Floatel Triumph will be moored with transit draft of 7.47m for one month in
May. During this period, the rig is to be disconnected and standby with rig
propellers if the weather pick up than the mooring design limiting wind.
1.2.3. Prepare an OrcaFlex model of the Floatel Triumph with the proposed mooring
system implementing all relevant vessel data.
1.2.5. Perform a quayside analysis for the mooring system in its intact and damaged
conditions using the directional environmental conditions corresponding to the
limiting wind.
1.2.6. Identify the tensions applied to the line, vessel connection points, quayside
connection points, and fenders under the environmental conditions and ensure
that loads are maintained within their specified safe working loads and minimum
breaking loads.
________________________________________________________________________
Page 8
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
1.2.7. Carryout the quayside mooring analysis to cover tidal variation, effect of current
in shallow water depth, wave generation due to nearby passing vessel etc.
1.2.8. Determine the size and length requirement of polypropylene mooring rope and to
figure out the most suitable strong point / connection point at the vessel side to
be used for the mooring end connection. Determine the line pre-tension
requirement.
1.3.1. Mooring location information including water depth reference to low tide level,
maximum tidal variation, Jetty details, quayside Bollard SWL, fender size.
1.3.2. Foatel Triumph general arrangement drawings, mooring draft, wind & current
force coefficients for the mooring draft.
1.3.3. Flotel Triumph possible connection point for mooring and SWL of those points,
vessel set-up position.
1.3.4. Google map view of mooring location at the Kemaman Port. Jetty photos showing
bollards, fenders and land.
1.4. Assumptions
1.4.2. Weather forecast data is available for to determine the variation of wind speed.
1.4.3. Wave reflection is possible due to vertical jetty wall (for conservative
assessment).
1.4.4. No other vessel will be moored at close proximity to Flotel Triumph sharing the
same Jetty bollard for mooring.
________________________________________________________________________
Page 9
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
Mooring jetty is in Kemaman Port - Malaysia. The mooring location and the jetty
photos are shown below (the floating dock, bridge and handrails will be removed
from the jetty prior to arrival of the Floatel Triumph). As shown, three sides are
surrounded by land. Hence current flow is minimum, and current flow mostly will be
parallel to the jetty. Waves can be propagated into mooring location through
diffraction or waves can be generated perpendicular to jetty wall due to motion of
other vessels next to the moored vessel. Wind can be flowing from any direction and
hence the dominant environmental loading on the vessel is from wind flow.
The minimum water depth at the quayside is around 14m during minimum low tide
leave. The ground level of jetty is +5.5m from minimum low tide level. Maximum
tidal variation at the location is 3.79m.
________________________________________________________________________
Page 10
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
Figure 2-3: Available Land (Double Bitt) Bollard for Mooring Rope Connection
________________________________________________________________________
Page 11
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
Figure 2-4: Available Jetty (Tee Head) Bollard for Mooring Rope Connection
________________________________________________________________________
Page 12
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
Below figure provides the client advised vessel position at the quayside. At advised
position, Fwd (frame 0) is around 1.2m from Jetty bollard #410 (refer to Appendix
A). Client advised Yokohama fender positions are also shown in below figure (two
blue colour boxes). Advised fender sizing is 3.3m diameter and 6.5m length.
Figure 2-5: Client Advised Vessel Mooring Position and Advised Fender Positions
(Two Blue Colour Boxes)
________________________________________________________________________
Page 13
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
________________________________________________________________________
Page 14
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
________________________________________________________________________
Page 15
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
________________________________________________________________________
Page 16
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
Below figure shows the vessel available rope end connection points (shown in red
circles) for mooring. All connection points are on vessel pontoon deck. There are in
total 12 vessel bollards on both pontoons. SWL of these bollards is 95mt. There are
in total 4 sets of vessel towing brackets and fairleads on both pontoons. SWL of these
towing brackets and fairleads is 200mt. Due to elevation difference between these
vessel connection points and jetty bollards (jetty bollards on higher elevation), it is
recommended to have the mooring ropes pass through the fairleads on the pontoon
deck, if possible, as these fairleads are capable of withstanding the vertical uplift
loads. Final designed vessel side connection points are detailed in Appendix A.
At mooring transit draft, the vessel pontoon deck is just above the water level.
Figure 2-9: Possible Rope Connection Points at Vessel Side – All Connection Points are
on Two Pontoon Decks
________________________________________________________________________
Page 17
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
The Vessel hydrodynamic data for the “Floatel Triumph” were taken from
hydrodynamic analysis carried out for transit draft of 7.47m.
Client advised wind and current coefficients for 7.47m tabulated below.
Figure 2-10: Axis System for Wind & Current Load Coefficient
Fx
Lpp/2 Fy
Nz
Current
Wave
Wind
________________________________________________________________________
Page 18
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
________________________________________________________________________
Page 19
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
Below figure shows the mooring system arrangement. Refer to Appendix A for the
details. Jetty bollard #380 are connected with two ropes.
Six lines of PP ropes are used for the quayside mooring. Three (3) of the mooring
lines are directly connected between the starboard side vessel bollards and the jetty
bollards. The other three (3) mooring lines are passing through the fairleads and are
connected between the vessel bollards and the jetty or land bollards.
As shown in the figure below, the vessel Fwd (frame 0) is set-up at 1.2m from Jetty
bollard #410.
________________________________________________________________________
Page 20
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
Below table provides the approximate mooring line pretension without applied
environment at different tide levels. The mooring system arrangement needs to be
set up at high tide level.
Table 3-1: Approximate Mooring Line Pretension without Environment
85mm Dia PP
Pretension at Low Tide Level Pretension at High Tide Level
Rope Mooring
(KN) (KN)
Line #
1 6.4 0.3
2 12.4 0.8
3 46.9 0.9
4 51.1 0.1
5 12.9 1.5
6 10.6 0.7
Mooring Rope: 85mm dia polypropylene mooring rope with MBL of 106mt.
Minimum line length requirement (eye to eye) given in Appendix A. Both rope end to
be 2m eye splice. The rope weight in air is 3.2kg/m. For conservative assessment,
axial stiffness of rope taken as 30 x MBL of the rope.
Quayside Bollard: There are jetty (Tee head) bollards with 150mt SWL and land
(double bitt) bollards with 50mt SWL available at quayside. No other vessels
expected to be moored with these bollards.
Vessel Towing Bracket: There are in total 4 sets of vessel towing brackets and
fairleads on both pontoons. SWL of these towing brackets and fairleads is 200mt.
Vessel Bollard: There are 12 vessel bollards on both pontoon decks (Figure 2-9).
SWL of vessel bollards is 95mt.
Fenders: There are 2 Yokohama fenders advised by client to be used. The diameter
is 3.3m and length is 6.5m on each fender. Fenders to be attached to jetty fenders as
advised by Client.
________________________________________________________________________
Page 21
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
4.1.1. The mooring system is analysed in the ultimate limit state (ULS) or for all
mooring line intact condition and accidental limit state (ALS) or single mooring
line fail conditions.
4.1.3. The worst results identified from the static analyses have been further
investigated using a time domain dynamic analysis.
• Six (6) dynamic simulation cases with random seeds are analysed.
• The results are based on the average of the maximum tensions from the 6
simulations.
4.2.1. Tidal variation and its effect on mooring line tension considered.
4.2.2. 5% to 10% MBL reduction was made due to pp rope end splicing.
4.2.4. Wave generation due to other vessels passing at mooring location considered.
4.2.5. Current force effect due to shallow depth incorporated in the analysis.
4.2.6. Wave & wind & current forces considered acting colinearly, some components
are neglected due to land covering of the quayside area (ex: no current
perpendicular to the Jetty etc).
4.2.7. Mooring guidelines, codes and acceptance criteria used in determining factor of
safety for each mooring component like ropes, vessel side towing bracket or
bollard connection and quayside bollard connection.
4.2.8. For static analysis all static wind, current, wave drift load considered. For
dynamic analysis 6 degree of motion incorporated.
________________________________________________________________________
Page 22
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
4.2.9. Range of zero up crossing wave period considered for the analysis to identify
critical Tz.
Note: For Rope, OCIMF-MEG3, Mooring Equipment Guidelines, 3rd Edition, 2008
specify more stringer requirements with maximum rope tension to be less than 50% of
MBL in both intact and single line fail condition.
The following details the modelling of the mooring system at the proposed location
using OrcaFlex (Reference 6).
4.4.1. Hydrodynamic analysis was carried out in Orcawave and imported to Orcaflex.
________________________________________________________________________
Page 23
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
4.4.2. “Flotel Triumph” is modelled as a rigid element having 3 DOF (Surge, Sway and
Yaw) in static analysis. In order to prevent the vessel from penetrating the
quayside, a contact element in the form of elastic solid is attached to the vessel
which acts as the hull of the vessel.
4.4.3. The quayside is modelled as an elastic solid contact element with dimensions
which are based on the supplied quayside information.
4.4.4. Fenders are modelled using constraint objects with lumped mass 6D buoy objects
representing the contact faces. Non-linear stiffness is assigned on the constraint
object. In the model, constraint object is limited to only one degree of freedom
which ensures that it only moves forward and backward, all other degrees of
freedom are not permitted.
4.4.6. Current is modelled with surface current speed having a uniform speed along
water depth.
4.4.7. The water depth varies at the advised vessel position. As the vessel is not moored
to the seabed, the effect of water depth is mainly on the wave loads, and
shallower water depth will be more critical. Therefore, the minimum water depth
at the advised vessel position (around 14m) is considered in the analysis for low
tide condition. The seabed is modelled as flat surface at water depth of 14m for
low tide and 17.35m for high tide. Two OrcaFlex models were generated for low
tide and high tide simulation with same mooring line point to point connection
length.
4.4.8. Dynamic analyses were conducted for the critical cases identified in static
screening. As critical wave generation is expected when only other vessels are
passing by, simulations were carried out for 30minites time.
________________________________________________________________________
Page 24
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
________________________________________________________________________
Page 25
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
As the vessel to be moored only for one month with thrusters available, the purpose
of the mooring analysis is to determine a reasonable liming wind speed so that
thrusters support is not required for one month mooring. Considering the geometry
of the location following wave, current and wind condition used for the analysis.
Here, the significant wave height of 0.6m includes wave generated due to nearby
passing other vessels. Wind generated surface current included in 1knot magnitude.
________________________________________________________________________
Page 26
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
5.1. Summary
Below Sections provides the static quayside mooring analysis critical results in both
minimum low tide and maximum high tide conditions. All the mooring requirements on
rope tension and connecting point loads on both quayside and vessel side are meeting
with a good margin for all environmental directions analysed.
Table 5-1: Critical Rope Tension – Low Tide & High Tide – Static Analysis –
Intact Case
0 deg 277 4
45 deg 363 4
90 deg 304 4
135 deg 188 6 468
180 deg 189 3 PASS
225 deg 211 3
270 deg 18 3
315 deg 228 2
________________________________________________________________________
Page 27
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
Table 5-2: Critical Jetty Bollard Load (Single Line Connection) – Low Tide &
High Tide – Static Analysis – Intact Case
Allowable Load (KN) as
Environment Critical Jetty Bollard Critical Jetty
per Reference 5, and
Direction Maximum Load (KN) Bollard #
meeting Requirements
Table 5-3: Critical Jetty Bollard Load (Multiple Lines Connection) – Low Tide &
High Tide – Static Analysis – Intact Case
Allowable Load (KN) as
Environment Critical Jetty Bollard Critical Jetty
per Reference 5, and
Direction Maximum Load (KN) Bollard #
meeting Requirements
0 deg 8
45 deg 82
90 deg 224
135 deg 287 1226
380
180 deg 145 PASS
225 deg 89
270 deg 8
315 deg 5
Note: For environment direction refer Figure 4-3
For Jetty Bollard numbering refer to Appendix A
________________________________________________________________________
Page 28
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
Table 5-4: Critical Land Bollard Load – Low Tide & High Tide – Static Analysis –
Intact Case
Allowable Load (KN) as
Environment Critica Land Bollard Critical Land
per Reference 5, and
Direction Maximum Load (KN) Bollard #
meeting Requirements
0 deg 67
45 deg 187
90 deg 185
135 deg 93 491
LBL 1
180 deg 12 PASS
225 deg 4
270 deg 8
315 deg 23
Note: For environment direction refer Figure 4-3
For Land Bollard numbering refer to Appendix A
Table 5-3: Critical Vessel Bollard Load – Low Tide & High Tide – Static Analysis
– Intact Case
________________________________________________________________________
Page 29
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
5.5. Critical Mooring Component Results – Critical Single Line Fail Case
Table 5-4: Critical Mooring Component Results – Low Tide & High Tide – Static
Analysis – Critical Single Line Fail Case
Maximum load Allowable load Meeting the
Load Bearing Component
(KN) (KN) requirements
________________________________________________________________________
Page 30
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
6.1. Summary
Below Sections provides the dynamic quayside mooring analysis critical results in both
minimum low tide and maximum high tide conditions. All the mooring requirements on
rope tension and connecting point loads on both quayside and vessel side are meeting for
critical environmental direction and critical line fail case analysed.
Table 6-1: Critical Mooring Component Results – Low Tide & High Tide – Dynamic
Analysis – Intact Case
Dynamic Simulation Seed # and Global Maximum
Averaged
Dynamic Load (KN)
Maximum Allowable Meeting the
Load Bearing Component
Design Load Load (KN) Requirements
1 2 3 4 5 6
(KN)
Critical Mooring Rope Tension 448 472 461 465 465 434 458 514 PASS
Critical Land Bollard 225 223 225 230 220 234 226 491 PASS
Critical Vessel Bollard 448 472 461 465 465 434 457 1398 PASS
6.3. Critical Mooring Component Results – Critical Single Line Fail Case
Table 6-2: Critical Mooring Component Results – Low Tide & High Tide – Dynamic
Analysis – Single Line Fail Case
Dynamic Simulation Seed # and Global Maximum
Averaged
Dynamic Load (KN)
Maximum Allowable Meeting the
Load Bearing Component
Design Load Load (KN) Requirements
1 2 3 4 5 6
(KN)
Critical Mooring Rope Tension 520 531 508 520 560 590 538 654 PASS
Critical Jetty Bollard 517 531 508 520 558 588 537 2207 PASS
Critical Land Bollard 232 234 229 258 223 241 236 736 PASS
Critical Vessel Bollard 520 531 508 520 559 590 538 1398 PASS
________________________________________________________________________
Page 31
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
The Yokohama Pneumatic Rubber Fender P-50 Size: 3.3m Dia x 6.5m has a standard
reaction of 3015KN. The quay fender, which the Yokohama fender is tied to, has a
standard reaction of 2107KN. Hence the capacities of fenders are adequate for the
maximum calculated loads of 289KN.
________________________________________________________________________
Page 32
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
7.0 REFERENCES
1 API-RP-2SK, Design and Analysis of Station keeping Systems for Floating Structures,
American Petroleum Institute, 3rd Edition, 2005
________________________________________________________________________
Page 33
Quayside Mooring Analysis report
Floatel Triumph
at Kemaman Port - Malaysia
P30049-MA-Rev 0
APPENDIX A
________________________________________________________________________
Appendix
5513
3641
NOTES:
380 YOKOHAMA FENDER (1) All mooring lines are 85mm dia polypropylene
410 Ø3.3m, L = 6.5m rope (106mt MBL). Propose available PP rope
435
465 BOLLARD lengths to be used are given in Table 1 last column.
490 QUAY FENDER
510 All ropes, both ends to be 2m eye splice.
LL ARD
LAN D BO NOTES:
(1) Mooring line #1, #5, #6 pass through fairleads before connecting to vessel bollards at the vessel
THIS DOCUMENT CONTAINS CONFIDENTIAL AND TRADE SECRET INFORMATION WHICH IS
side. THE PROPERTY OF INTERMOOR . AND RECEIPT OR POSSESSION DOES NOT CONVEY ANY
RIGHTS TO LOAN, SELL OR OTHERWISE DISCLOSE SAID INFORMATION. REPRODUCTION OR
USE OF SAID INFORMATION FOR ANY PURPOSE OTHER THAN THAT IN CONNECTION WITH
(2) Two ropes are to be joined together to make up longest mooring line #5. WHICH SAID INFORMATION WAS SUPPLIED MAY NOT BE MADE WITHOUT EXPRESS
WRITTEN PERMISSION OF INTERMOOR. THIS DOCUMENT IS TO BE RETURNED TO
INTERMOOR. UPON REQUEST AND IN ALL EVENTS UPON COMPLETION OF THE PURPOSE
FOR WHICH IT IS LOANED.
(3) All vessel side connection points including fairleads are at the pontoon deck level. Pontoon deck CLIENT:
PROJECT TITLE:
REFERENCE DRAWINGS REV DATE DRAWN DESIGN CHK'D APPD REVISION P30008 N.T.S P30049-IM-MR-2002 1 OF 1 A