ACTION PLAN OF THE PROJECT

Start Date 15-Apr-19


End Date 10-Oct-22
Overall Progress 15%

Day
Tasks Responsible Start End Status
s
Set kick-off meeting Project Manager 15-Apr-19 15-Apr-19 1 Complete
Formulate and Agree on objectives Project Team 16-Apr-19 18-Apr-19 3 Complete
Preparation of Project Proposal Business Manager 19-Apr-19 11-May-19 22 Complete
Submission of Project Proposal Business Manager 20-May-19 20-May-19 1 Overdue
Resource Plan Project Team 16-Apr-19 18-Apr-22 * In progress
Staffing Business Manager 16-Apr-22 10-May-22 25 In progress
Site Preparation Project Team 10-May-22 23-May-22 14 Not started
Building and Construction Works Project Team 23-May-22 12-Sep-22 * Not started
Equipment and Machinery Installation Project Team 12-Oct-22 13-Sep-22 31 Not started
Staff Training Project Team 13-Sep-22 28-Sep-22 15 Not started
Test Production Technical Team 28-Sep-22 7-Oct-22 10 Not started
Launch 10-Oct-22 10-Oct-22 *