Professional Documents
Culture Documents
Geo Bags Countermeasure
Geo Bags Countermeasure
net/publication/245297469
CITATIONS READS
27 2,974
5 authors, including:
Brian Barkdoll
Michigan Technological University
129 PUBLICATIONS 1,852 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Robert Ettema on 21 June 2017.
Abstract: This paper presents observations and data from a sequence of laboratory experiments conducted to evaluate geobags as a
countermeasure to protect bridge-abutment foundations from failure attributable to scour of the alluvial-river channel in which they are
placed. Geobags comprise geotextile cloth bags filled with local sediment or concrete. The experiments focused on the performance of
geobags placed as an apron around pile-supported wing-wall abutments retaining erodible embankments, and subject to live-bed and
clear-water flow conditions. Though an apron of geobags is shown to substantially reduce or eliminate scour immediately at the abutment,
the apron must be formed flexibly of linked geobags. Moreover, a performance concern is that the apron may shift scour to a location
flanking or downstream of the apron, and in so doing imperil a nearby pier or riverbank. The experiments indicate the importance of
protecting the embankment region beneath and immediately behind the abutment’s pile cap. Live-bed conditions proved to be the more
critical for abutment protection, owing to the capacity of dunes to destabilize geobags around the edges of the apron. Design guidelines
are given and include using current riprap configurations for sizing and placing geobags.
DOI: 10.1061/共ASCE兲0733-9429共2007兲133:4共431兲
CE Database subject headings: Scour; Measurement; Bridge abutments.
Ksl = 冑 冋 册
1−
sin2 ␣
sin2
共2兲
Riprap Sizing
The diameter of riprap stone used was estimated using the rela- Fig. 4. Location of deepest scour: 共A兲 no protective apron; 共B兲 loose
tionship proposed by Richardson and Davis 共1995兲 protective apron; and 共C兲 protective apron as mat tied to abutment
pile-cap base. Use of scour protection immediately behind the toe, and resulted in large parts of the entire riprap apron sliding
pile cap, or use of a lowered pile cap, therefore enables a wing- into the scour hole forming around the apron. As the riprap apron
wall abutment and its approach embankment to better withstand slid, it exposed the pile cap so that embankment sediment was
scour. winnowed from beneath the pile cap. The embankment then failed
due to winnowing of sediment from beneath the pile cap. Addi-
tionally, the deepening scour hole caused the embankment side-
Scour at Abutment with Riprap Apron
slope to become unstable. Fig. 7共b兲 shows the resultant scour
Series of experiments were conducted to determine how scour hole, whose maximum scour depth occurred at the upstream cor-
develops when an apron of riprap stone is placed around the ner of the abutment, and was 85 mm. The manner of riprap apron
abutment in a similar manner to that shown in Fig. 1. The riprap failure essentially was the same as observed by Chiew and Lim
apron comprised a layer of riprap about two stones thick, with a 共2000兲 and Parker et al. 共1998兲 for riprap aprons placed around
toe three to four stones thick. The riprap stones simulated were model bridge piers. It is evident from the experiment that riprap
scaled down to uniform-sized riprap of d50 of 22 mm. Fig. 7共a兲 aprons placed locally around an abutment may not work in dune-
illustrates the initial arrangement of the riprap apron used in the bed channels, unless the apron toe extends sufficiently deep so as
flume experiments. The experiments showed that edge failure of to be below the trough elevation of dunes moving through the
the riprap apron led to apron failure, and scour progression be- bridge opening.
neath and around the abutment, including the abutment pile cap.
The failure started at the apron’s upstream edge, where acceler-
ated flow and the passage of dunes destabilized the apron’s riprap Scour at Abutment Fitted with Single Large Geobag
To address the question posed for this study, a series of trial-and-
error experiments were conducted to determine whether, and how,
scour would be prevented by one or more large geobags fitted as
an apron around the perimeter of the test wing-wall abutment. All
of these experiments essentially showed that for large geobags to
be effective at preventing scour depth at abutments, the geobags
must be tied to the abutment, otherwise they would slide away
from the abutment, expose the abutment footing, and cause scour
of sediment from beneath the footing. However, even though the
large tied geobag eliminated scour at the abutment, it caused the
location of deepest scour to shift downstream of the abutment;
maximum scour depth dSmax was 110 mm, about the flow depth.
Fig. 8 illustrates a typical result from the experiments. The loca-
tion of maximum scour depth moved from Location A to C
共Fig. 4兲.
It was found that, as additional geobags were placed around
the abutment, the scour shifted further downstream of the abut-
ment. Therefore, to be effective, the geobags have to extend out a
substantial distance from the abutment. As shown by the subse-
Fig. 5. Scour development at the abutment and embankment when quent experiments, this finding indicates that, for single- or
unprotected: A = location of deepest scour double-span bridges, the geobag 共or riprap兲 protection should ex-
two bags thick, with a toe three to four bags thick, and generally
conformed with the layout of the riprap apron shown in Fig. 4.
Early experiments revealed that, though the geobags loosely
placed reduced scour depth, they might not fully protect the abut-
ment pile cap. Figs. 9共a and b兲 illustrate the results of one typical
test finding in which sand was winnowed from between gaps in a
single layer of geobags, causing the bags to settle in a scour
region around the abutment.
Fig. 6. As scour exposes piles 共a兲 and 共b兲, embankment soil may be
The experiments showed that an apron of suitably positioned
sucked under pile cap, forming a cavity behind the pile cap 共c兲
and connected geobags 共acting like cable-tied blocks兲, such as
generally conforming to the apron in Fig. 4, can reduce the scour
depth at an abutment. However, as with a riprap apron, scour may
tend across the full width of the bridge waterway. Also, if the occur at Position B, the perimeter of the geobag apron, if the
additional geobags were not secured to the abutment, they would geobags were loosely placed, or at Position C downstream from
slide into the scour hole. To be kept in mind in sizing bag the apron, if the geobags were aligned together as a mattress.
thickness using Eqs. 共1兲 and 共2兲 is that the slope angle may in- Once edge scour occurred, at either Position B or C, the edge
crease substantially as scour develops, and that bag thickness geobags 共as with riprap兲 were dislodged into the scour hole.
should be based on the anticipated slope associated with scour- The experiments showed that the edge failure is the principal
hole formation. factor that results in the failure of the geobag apron, as in Fig. 10.
Such failure can be eliminated or substantially reduced by fully
linking the geobags so as to form a flexible apron, by then sloping
Scour at Abutment with Apron of Small Geobags
the apron into the bed, and by forming a suitably deep toe of
Series of experiments were conducted to determine how an apron geobags 共as for riprap兲 around the apron’s perimeter. It was found
of relatively small geobags would perform as an alternative to a that geobag size did not affect the performance of a tied apron of
riprap apron. The experiments involved an apron of geobags geobags, for the experiment conditions tested. Of greater impor-
placed in the design layout essentially the same as for the riprap tance was that the geobag elements be linked to form a flexible
apron described earlier. The apron comprised a layer of geobags, apron of sufficient coverage around the abutment.
Conclusions