Professional Documents
Culture Documents
Fidic Contracts A Contractors View Ben Edwards
Fidic Contracts A Contractors View Ben Edwards
FIDIC Contracts
in use in
International
Projects
Ben Edwards
Kier Construction
FIDIC Contracts
in use in The “Rainbow Suite”
International
Projects
Red
Yellow
Silver
Green
n
Gold
Blue
White
The standard
standard form isis a starting
starting point
point – it is importa
important
nt to
draft the appendix to tender and particular conditions
conditions to
reflect the full agreement between the parties.
• Clau
Clause
sess ar
aree ge
gene
nera
rall in nat
natur
ure
e
• Thi
Thiss all
allows
ows con
contra
tracts
cts to be
be agre
agreed
ed quic
quickl
kly
y but
but part
parties
ies
have to be diligent that all issues are considered in
order to avoid potential for disputes
• Fro
Front
nt end inv
invest
estmen
mentt can
can avo
avoid
id back
back end didispu
spute
te cost
costs s
• Ge
Gett the
the righ
rightt bala
balance
nce Emp
Emploloyer
yer Bi
Bias
as v Con
Contra
tracto
ctorr Bi
Bias
as
• Se
Sellect th
thee App
Appro
ropr
priiate Fo
Form
rm
• Un
Unde
ders
rsta
tand
nd ththe
e diff
differ
eren
ence
cess betw
betwee
een
n the
the form
formss
• Follow ththe Co
Contract
FIDIC Contracts
in use in
International
Projects
• - The 19
1999 Re
Red Bo
Book (f
(firs
rstt edi
edittion)
• - Th
Thee 19
1999 Yel
Yello
low
w Boo
Book
k (fi
(firs
rstt edi
editi
tion
on))
• - Silver Book
• - Green Book
• FIDIC
FIDIC ha
has
s redu
reduced
ced th
the
e numbe
numberr of cla
claus
uses
es in
in all
all
of the recent contracts. The Orange Book
contained 20 clauses, as now do the Red,
Yellow and Silver Books. Previously, the Red
Book had 72 clauses.
• FI
FIDIC
DIC ha
hass also
also sta
stand
ndard
ardis
ised
ed the
the ter
terms
ms acr
acros
osss
- “Co
“Condit
ndition
ions
s of Contract
Contract for
for Constr
Constructi
uction
on for
Building and Engineering Works Designed by
the Employer”
- Tr
Tradi
aditi
tion
onal
al co
contr
ntrac
actt
- -
- “Co
“Condit
ndition
ions
s of Contrac
Contractt for Plant
Plant and
and Design
Design
e reen oo
Short Form of Contract
Recommended for engineering and building work
of:
- sma
small ll capi
capita
tall valu
valuee and/o
and/orr
- sim
simple
ple or repet
repetiti
itive
ve wor
work
k and
and //or
or
- sh
shor
ortt dur
durat
atio
ion
n
Pink Book
The “Multilateral Development Bank Construction Contract”
(The “Red Book” For Development Bank financed projects)
Features provisions on:
- Corruption
- Social utility
- Loan facility
- Dr gin
Dred
edg ing
g and
and Re
Recl
clam
amat
atio
ion
n Wo
Worrks
White Book
- Consultancy Ag
Agreement
Gold Book
- Design, Buil
ild
d, Operate
FIDIC Contracts
currently in use
by Kier in
Jamaica
Yellow
formsand Silver Books are Lump Sum Design & Build
of contract
- Little
Little or no risk to the Employ
Employer
er of price
price increase
increase if there
there
are unforeseen risks
- “Tu
“Turn
rnk
key
ey”
”
- Contr
Contractor
actor under
under much
much greater
greater design
design risk and
and burden
burden of
ground conditions risk under Silver Book
- Desi
Design
gn Re
Resp
spon
onsi
sibi
billit
itie
iess
- Si
Site
te C
Cond
onditi
itions
ons & Adver
Adverse se Phy
Physic
sical
al Con
Condit
ditio
ions
ns
- Ta
Taki
king
ng Ove
verr Part
Partss of
of the
the Wo
Work
rkss
Design Risk
purpose”
“Fitness for purpose”
Under Red Book, the Contractor is responsible for any
part he designs being fit for purpose
Under Silver Book, risk of the adequacy of the Employer’s
Employer’s
FIDIC Contracts
in use in
International
Projects
• In al
alll FIDI
FIDIC
C Form
Forms
s the
the givi
giving
ng of
of Noti
Notice
ces
s and
and
further updates by the Contractor is extremely
important
• Time-bar issues
• a ms
ms s ou no e gnore – nanc a an
/or time
• Pr
Pres
escr
crib
ibed
ed tim
time
e in Co
Cont
ntra
ract
ct for
for respo
respondi
nding
ng to
claims
Express Provisions
Provisions for Additional Cost (+ Profit)
Fossils 4.24 Y Y Y
Testing 7.4 Y+ Y+ Y+
Variations 13.3 Y Y+ Y+
Unforseeable
shortages in
personnel or
goods due to
the
Government 8.4 (d) N N N
Delay,
prevention due
to Employer 8.4 (e) r&Y N N N
Delay by
Authorities 8.5 N N N
Suspension
instructed by
CA 8.9 Y Y Y
Suspension by
Contractor 16.1 Y+ Y+ Y+
Limitations of Liability
Clause 17.6 of the Red, Yellow and Silver Books (similar
(similar
obligations):
Employer Bias
Removal of standard Clause and replacement with only
a full exclusion of liability
liability for the Employer for
consequential loss
Contractor Bias
Widening of joint exclusion of loss of profits,
consequential loss etc
Widening of the Contract Sum cap to include
indemnities
indemnitie s and a cap on delay damages
Introduction of a time limitation limiting the
t he number of
years after the Taking Over Certificate that the
Contractor is liable
This requires:
Passing the Tests on Completion
EOT Claims
Clause 20.1 – EOT clai
Clause claims
ms by Contr
Contractor
actor
Notice to be given by the Contractor within 28 days of
the Contractor becoming aware or when it should have
become aware of the event
Condition precedent to entitlement to an extension of
time:
e on rac or a s o g ve no ce o a c a m w n
such period of 28 days, the Time for Completion shall
not be extended, and the Contractor shall not be
entitled to additional payment, and the Employer shall
Co-operation 4.6/8.4(a) Y Y Y
Fossils 4.24 Y Y Y
Testing 7.4 Y Y Y
Variations 8.4(a) Y Y Y
Li
Liqu
quid
idat
ated
ed Da
Damag
mages
es
Clause 8.7 “Delay Damages”
Amount stated in Contract Particulars / Appendix to
Tender
Delay Damages apply per day from the Time for
Completion (as may be extended) until the date stated
in the Taking Over Certificate
oss e or par es o cap e amoun o e ay
Damages
Exclusive remedy for the Employer for Contractor
delay, except:
- in the event
event of terminati
termination,
on, where
where the Employ
Employerer may
be able to recover additional costs
- where the Contract
Contractor
or is requir
required
ed to accelera
accelerate
te the
Works under clause 8.6 for being “too slow” or having
failed to comply with the Programme
Claims
Red and Yellow Books have the same claims
provisions.
Silver Book is slightly different, with the only
real difference being the involvement or not of
the Engineer
For all claims, notices must follow the required
.
• In writing
• De
Deli
live
vere
red
d by
by ha
hand
nd,, se
sent
nt by ma
mail
il or co
cour
urie
ierr or
or
Claims
Clause 2.5
Contractor bias amendment:
“If the Employer
Employer fails to give
give notice of a claim within
such period of 15 Business Days after the Employer
became aware, or ought reasonably to suspect, or
oug t reasona y to ave ecome aware, or s ou
have become aware of the event or circumstance giving
giving
rise to the claim, then the Employer shall not be entitled
to any amount, payment or extension whatsoever from
the Contractor in respect of such claim and the
Contractor shall be discharged from all liabili
liability
ty in
connection with such claim”
Golden Rules
- Bewar
Bewaree – ent
enter
er in ha
hast
ste,
e, re
repen
pentt at le
leis
isur
ure……
e……
- Be sure
sure you
you are
are in agre
agreemen
ementt befor
before e you
enter the Agreement
- The Cont
Contract
ract requi
requires
res the
the Contra
Contracto
ctorr to issue
issue
o ces or me- ars m – on e emo ons
clou
cloud
d the
the need
need to
to issu
issue
e or rec
recei
eive
ve No
Notitice
ces.
s.
END OF PRESENTATION