Professional Documents
Culture Documents
Boq TB1
Boq TB1
i. PEKERJAAN PERSIAPAN
a. Pembuatan Direksi Keet dan Kantor Pelaksana m2 120 1,900,000 228,000,000
b. Pembuatan Gudang Material dan Barak Pekerja m2 240 1,600,000 384,000,000
c. Papan Nama Proyek buah 1 15,000,000 15,000,000
d. Dokumentasi Proyek bulan 7 714,286 5,000,000
e. Biaya Penyambungan Air Kerja ls 1 3,000,000 3,000,000
f. Biaya Penyambungan Listrik Kerja ls 1 100,000,000 100,000,000
g. Pengadaan Perlengkapan K3 dan Penanggulangan Ls 1 367,000,000 367,000,000
h. Pagar Sementara Proyek m 376 315,000 118,440,000
i. Pengukuran dan Pemasangan Bouwplank m 376 75,000 28,200,000
- Tower Crane (pondasi,mob demob,dsb) bulan 7 71,262,762 498,839,331
- Material Hoist (pondasi,mob demob,dsb) bulan 7 57,214,286 400,500,000
SUBTOTAL PERSIAPAN 2,464,429,331
-
II. PEKERJAAN PONDASI
Tower B 1,855,594,895
- Mob Demob Peralaatan Pancang Ls 1 81,368,303 40,684,151
- Pengadaan tiang pancang termasuk handling ke lo m 1,760 818,004 1,439,687,473
- Install tiang pancang m 1,760 358,021 630,116,137
- Bobok Tiang Pancang titik 88 118,354 10,415,143
- PDA Test titik 2 9,616,254 19,232,508
- Loading Test Axial titik 1 81,368,303 81,368,303
- Loading Test Lateral titik 1 19,972,220 19,972,220
SUBTOTAL PONDASI 2,241,475,934
LANTAI 2 1,038,000,427
a Pekerjaan Kolom 310,236,516
- Beton Readymix fc'30 Mpa m3 46 1,149,095 52,453,262
- Bekisting m2 319 174,496 55,661,991
- Tulangan besi beton kg 9,459 21,367 202,121,263
b Pekerjaan Balok 376,623,226
- Beton Readymix fc'30 Mpa m3 44 1,149,095 50,866,124
- Bekisting m2 337 174,496 58,755,463
- Tulangan besi beton kg 12,496 21,367 267,001,639
c Pekerjaan Pelat 323,509,196
- Beton Readymix fc'30 Mpa m3 0.719 1,149,095 826,622
- Bekisting m2 718 174,496 125,202,410
- Tulangan besi beton kg 9,242 21,367 197,480,164
d Pekerjaan Tangga 27,631,490
- Beton Readymix fc'30 Mpa m3 4 1,149,095 5,066,784
- Bekisting m2 34 174,496 5,943,033
- Tulangan besi beton kg 778 21,367 16,621,672
LANTAI 3 1,149,006,124
a Pekerjaan Kolom 310,236,516
- Beton Readymix fc'30 Mpa m3 46 1,149,095 52,453,262
- Bekisting m2 319 174,496 55,661,991
- Tulangan besi beton kg 9,459 21,367 202,121,263
b Pekerjaan Balok 376,623,226
- Beton Readymix fc'30 Mpa m3 44 1,149,095 50,866,124
- Bekisting m2 337 174,496 58,755,463
- Tulangan besi beton kg 12,496 21,367 267,001,639
c Pekerjaan Pelat 434,514,892
- Beton Readymix fc'30 Mpa m3 97 1,149,095 111,832,318
- Bekisting m2 718 174,496 125,202,410
- Tulangan besi beton kg 9,242 21,367 197,480,164
d Pekerjaan Tangga 27,631,490
- Beton Readymix fc'30 Mpa m3 4 1,149,095 5,066,784
- Bekisting m2 34 174,496 5,943,033
- Tulangan besi beton kg 778 21,367 16,621,672
LANTAI 4 1,179,516,723
a Pekerjaan Kolom 304,413,988
- Beton Readymix fc'30 Mpa m3 45 1,149,095 51,479,453
- Bekisting m2 291 174,496 50,813,272
- Tulangan besi beton kg 9,459 21,367 202,121,263
b Pekerjaan Balok 454,298,906
- Beton Readymix fc'30 Mpa m3 47 1,149,095 54,099,487
- Bekisting m2 299 174,496 52,220,252
- Tulangan besi beton kg 16,285 21,367 347,979,167
c Pekerjaan Pelat 389,432,134
- Beton Readymix fc'30 Mpa m3 83 1,149,095 95,853,414
- Bekisting m2 705 174,496 123,017,982
- Tulangan besi beton kg 7,982 21,367 170,560,738
d Pekerjaan Tangga 31,371,695
- Beton Readymix fc'30 Mpa m3 4 1,149,095 5,066,784
- Bekisting m2 34 174,496 5,943,033
- Tulangan besi beton kg 953 21,367 20,361,878
LANTAI 5 1,182,104,699
a Pekerjaan Kolom 281,152,726
- Beton Readymix fc'30 Mpa m3 31 1,149,095 36,035,617
- Bekisting m2 246 174,496 42,995,846
- Tulangan besi beton kg 9,459 21,367 202,121,263
b Pekerjaan Balok 475,415,215
- Beton Readymix fc'30 Mpa m3 47 1,149,095 54,244,043
- Bekisting m2 300 174,496 52,362,292
- Tulangan besi beton kg 17,260 21,367 368,808,880
c Pekerjaan Pelat 394,165,062
- Beton Readymix fc'30 Mpa m3 85 1,149,095 97,949,537
- Bekisting m2 720 174,496 125,654,787
- Tulangan besi beton kg 7,982 21,367 170,560,738
d Pekerjaan Tangga 31,371,695
- Beton Readymix fc'30 Mpa m3 4 1,149,095 5,066,784
- Bekisting m2 34 174,496 5,943,033
- Tulangan besi beton kg 953 21,367 20,361,878
LANTAI 6 1,127,476,190
a Pekerjaan Kolom 281,152,726
- Beton Readymix fc'30 Mpa m3 31 1,149,095 36,035,617
- Bekisting m2 246 174,496 42,995,846
- Tulangan besi beton kg 9,459 21,367 202,121,263
b Pekerjaan Balok 420,786,707
- Beton Readymix fc'30 Mpa m3 48 1,149,095 54,774,580
- Bekisting m2 300 174,496 52,362,292
- Tulangan besi beton kg 14,679 21,367 313,649,835
c Pekerjaan Pelat 394,165,062
- Beton Readymix fc'30 Mpa m3 85 1,149,095 97,949,537
- Bekisting m2 720 174,496 125,654,787
- Tulangan besi beton kg 7,982 21,367 170,560,738
d Pekerjaan Tangga 31,371,695
- Beton Readymix fc'30 Mpa m3 4 1,149,095 5,066,784
- Bekisting m2 34 174,496 5,943,033
- Tulangan besi beton kg 953 21,367 20,361,878
LANTAI 7 1,152,173,522
a Pekerjaan Kolom 305,850,058
- Beton Read#DIV/0! m3 41 1,149,095 47,296,747
- Bekisting #DIV/0! m2 323 174,496 56,432,048
- Tulangan be#DIV/0! kg 9,459 21,367 202,121,263
b Pekerjaan Balok 420,786,707
- Beton Readymix fc'30 Mpa m3 48 1,149,095 54,774,580
- Bekisting m2 300 174,496 52,362,292
- Tulangan besi beton kg 14,679 21,367 313,649,835
c Pekerjaan Pelat 394,165,062
- Beton Readymix fc'30 Mpa m3 85 1,149,095 97,949,537
- Bekisting m2 720 174,496 125,654,787
- Tulangan besi beton kg 7,982 21,367 170,560,738
d Pekerjaan Tangga 31,371,695
- Beton Readymix fc'30 Mpa m3 4 1,149,095 5,066,784
- Bekisting m2 34 174,496 5,943,033
- Tulangan besi beton kg 953 21,367 20,361,878