Professional Documents
Culture Documents
Pubhealthreporig00041 0061
Pubhealthreporig00041 0061
program aspects will require more effort to have been allotted to each activity, it is possible
meet the program's planned completion date to determine the critical path and slack. The
Blood pressure
measuring device
PRIVATE PHYSICIANS
Clinitron
STATE HEALTH
DEPARTMENT
Papanicolaou kits
CANCER SOCIETY
Health and welfare Physicians and Staffing at program Type of followup Function of public
planning council other health letter health nurse
Tuberculosis
professionals Financial arrange¬ Financial arrange¬
association Public health nurses ments for indigents, ments for indigents,
for followup medical indigents medical indigents
Diabetes association
Society for the
prevention of
blindness
Cancer society
Heart association
critical path is the series of activities and events 13.8 weeks, and the Clinitron must be at the
that require the most time (fig. 2). By period¬ multiple screening site 0.4 week before the com¬
ically comparing actual progress of events on pletion date. Therefore, the latest allowable
the critical path with their estimated completion date is 13.8 minus 0.4, or 13.4 weeks. The
dates, it is possible to determine if the end- earliest expected date when the Clinitron will be
event completion date can be met as planned. at the screening site is obtained by totaling esti¬
If progress is slower than estimated, the ad¬ mated activity times back from the event
ministrator can set the end-event completion through the longest path of the network to the
date ahead, or channel more effort into activities beginning event. In the case of the Clinitron,
along the critical path. When progress is ahead the earliest expected time is 12.6 weeks. Slack
of schedule, he can proceed as originally planned at this event is, therefore, 13.4 minus 12.6 or 0.8
and meet an earlier end-event completion date or weeks. Slack can be determined for each event
increase the time estimates for uncompleted ac¬ in this manner.
tivities on the critical path. Slack is the differ¬ When the network has been developed to this
ence between the latest allowable date (TL) and point, including slack times for key events, its
theearliest expected date (TE) for the occurrence value as a management tool becomes more ob¬
of an event. vious. The administrator should view the net¬
Slack indicates the time cushion available at work critically to determine obvious duplica-
each event, which can be used, as necessary, tions of effort, how the critical path might be
without affecting the timing of the total pro¬ reduced by rearranging activities, how much
gram. The latest allowable date for each event slack is available for events not on the critical
is determined by working back through the path, and how resources could be scheduled
longest path of the network from the end event most effectively.
to the event for which the TL is desired. For After the network is modified to include any
example, in the illustration the critical path is changes suggested through this panoramic view
Vol. 81, No. 5, May 1966 451
Figure 2, Network diagram
TL =6.6
TE 2.1
=
Slock=4.5
Right physical
facility
Event
¦^Critical path
'-*¦
Activity
te Estimated time for
an activity (weeks)
TL Latest allowable date for an event
Tg -
Earliest expected date for an event
Slack TL minus TE
te^0.4
te^0.2
»e-0,2