TASK START DATE END DATE DURATION

project jump start 2/2/2019 2/20/2019 18


final brain storm 6/2/2019 6/19/2019 17
develop database 4/2/2020 4/30/2020 28
testing 1/2/2020 1/25/2020 23
Implementation 4/2/2021 5/10/2021 38
Customer Acceptance 9/2/2022 10/6/2022 34
Maintenance 11/3/2022 11/5/2022 2

TASKS A

02/02/2019 21/08/2019 08/03/2020 24/09/2020 12/04/2021 29/10/2021 17/05/2022

project jump start

final brain storm

develop database

testing

Implementation

Customer Acceptance

Maintenance
43498 44870

1 29/10/2021 17/05/2022

START DATE
DURATION