Professional Documents
Culture Documents
1 Agenda
2 About Fenwick Elliott
3 Nicholas Gould Biography
4 Jeremy Glover Biography
5 Presentation slides
Agenda
Topic Speaker Time
Risk Allocation, Design & BIM Nicholas Gould & Jeremy Glover 3.20 - 4.00pm
Claims Management, Time and Money Nicholas Gould & Jeremy Glover 4.15 - 5.10pm
Suspension and Termination Nicholas Gould & Jeremy Glover 5.10 - 5.30pm
For more than three decades Fenwick Elliott has been delivering first class service to
clients around the world in the building, engineering and energy sectors.
Fenwick Elliott is the UK’s largest specialist construction and energy law firm and provides
commercially driven solutions through a pragmatic and professional approach.
Areas of practice
Dispute avoidance and dispute resolution: Fenwick Elliott is highly experienced in this
field and is a leader in the use of alternative dispute resolution. Whilst the firm takes
whatever steps are necessary to resolve disputes, its primary focus is to avoid disputes
and much of its work is in the form of day to day project support, including strategic
advice and review of project correspondence/notices to enable its clients to manage
and effectively address problems as they arise, thereby avoiding formal proceedings.
The firm regularly advises upon and conducts complex international arbitrations. It has
experience of arbitrations under the DIAC, DIFC/LCIA, ADCCAC, QICCA, ICC, LCIA, SIAC,
UNCITRAL and ICSID arbitration rules, as well as under ad hoc and bespoke arbitration
rules. The firm is used to working closely with in-house counsel and local counsel. The
team is also well versed in FIDIC and other dispute resolution boards’ procedures.
The majority of the firm’s work in this field concerns disputes up to $2bn arising out of
major international construction, infrastructure and energy projects. The geographical
spread of the firm’s work is worldwide. It has developed a close relationship with a
number of major international contractors whom it is advising on a number of disputes
and strategic matters throughout the Middle East, Africa and the Caribbean. The firm
also traces assets and seeks enforcement around the world in respect of international
arbitration awards and makes calls on bonds or guarantees in many jurisdictions.
Nicholas is a Visiting Professor at King’s College London and Vice President of the
ICC’s Arbitration Commission. He is past Chairman of the Society of Construction Law,
Adjudication Society and the DRBF (Region 2). He has published widely in the area of
construction law and international arbitration, and speaks regularly on construction law
and dispute resolution. Nicholas is lead author of the report “Mediating Construction
Disputes: An Evaluation of Existing Practice” published in February 2010, it received a
finalists CEDR Award for Excellence in 2010. Nicholas features as one of only 5 practitioners
in Europe in the inaugural edition 2017 of Who’s Who Legal: Thought Leaders.
Jeremy Glover, Partner
Jeremy has specialised in construction energy and engineering law and related matters
for most of his career. He advises on all aspects of projects both at home and abroad, from
initial procurement and strategic project advice to dispute avoidance and resolution. He
acts across a wide range of construction sectors in the UK and internationally, including
general construction, transport, communications, process plant, oil, gas, nuclear and
renewables.
Jeremy also has extensive experience of all principal main contracts including JCT,
ICE, FIDIC, NEC, GC/Works, I CHEM E, subcontracts including DOM/1 and DOM/2, and
numerous bespoke forms used in international and domestic construction, energy and
infrastructure projects.
The New 2017 FIDIC Red,
Yellow and Silver Books
Introduction
FIDIC Sub-Contract
* In the 2017 Second edition there are now 21 clauses, with clause 20
dealing with claims and clause 21 dealing with disputes
• Foreword:
“In the preparation of these Conditions of contract for
Construction it was recognised that, while there are many
sub-clauses which will be generally applicable, there are
some sub-clauses which must necessarily vary to take
account of the circumstances relevant to the particular
contract. The sub-clauses which were considered to be
applicable to many (but not all) contracts have been included
in the General Conditions.”
• Particular Conditions take priority over the General Conditions
• Particular Conditions + General Conditions = Conditions of
Contract
General provisions
Priority of Documents (Clause 1.5)
• Important to check for inconsistencies and conflicts within the documents and address them prior
to entering into Contract
FIDIC
• FIDIC Values:
• Quality
• Integrity
• Sustainability
• FIDIC Objectives:
• Promote and enhance the leading position of FIDIC’s
Forms of Contract.
• The 63 page 1999 Yellow Book is now 119 pages (69 to now 126 with
Appendices including the DAAB rules).
• Prescriptive.
• Particular Conditions, Contract Data and Special Conditions.
• Definitions:
• “Claim” – request or assertion
• “Dispute” – claim made, and rejected, and first party does not
acquiesce (submit or comply silently or eg by serving a NOD);
• “Cost Plus Profit” default is 5%;
• Interpretation:
• “shall” is mandatory
• “may” is optional
• “include” is a non-exhaustive list.
Dispute Avoidance
Reciprocal Rights
• Confidentiality.
• Employer’s Agent
• Supervisor
• Resident Engineer?
• Certifier
• Dispute Resolution?
• The Sub-Clause 2.4 notice might have lapsed by the time the
contract was terminated (noted by the courts but not argued by the
parties).
Ramifications of NH International
NH International
Contractor’s Obligations
2017 Contractor’s Obligations - Clause 4
• Be responsible for all power, water and other services for the works
(Sub-Clause 4.19).
Defects Liability
• FIDIC forms do not define ‘defects’ – general view is any works or materials not in
accordance with the contract
• Clause 4.1 – Contractor must complete Works and ‘remedy any defects in the
Works’
• Clause 11.1 - Contains an obligation for remedying defects or damage after Taking
Over and throughout the Defects Notification Period on notice by the Employer
• Clause 11.2 - all defects or damage shall be executed ‘at the risk and cost of the
Contractor’ save for items not the Contractor’s fault which shall be dealt with under
the Variation Procedure (Clause 13.3)
• Clause 11.3 – Defects Notification Period shall extended (but not beyond 2 years) if
Works cannot be used as a result of a defect or damage under Clause 2.5
[Employer’s Claims]
• Clause 11.4 – Failure to remedy defects within a reasonable time entitles the
Employer to get (i) others to carry out remedial works at the Contractor’s
reasonable cost (ii) an Engineers Determination for a reasonable deduction or (iiii)
if the
Risk Allocation
Risk Allocation
Employer’s Responsibilities
• Setting out;
Unforeseeable Physical
Conditions
• FIDIC Red Book Sub-Clause 4.12 (Yellow Book is the same):
“Physical Conditions means natural Physical Conditions and man made and
other physical obstructions and pollutants, which the Contractor encounters
at the Site when executing the Works, including sub-surface and
hydrological conditions but excluding climatic conditions”.
• The Contractor gives notice to the Engineer as soon as practicable.
• The Contractor must also issue a Sub-Clause 20.1 Notice in so far as an EoT
and/or additional costs are claimed.
• The Contractor is to proceed in accordance with the Sub-Clause 3.5
[Determinations].
• The Engineer may consider and review whether the physical conditions are
similar or more favourable than could reasonably have been foreseen when the
Contractor submitted the Tender. If so a reduction could be determined.
However, there should be no net reduction in the Contract Price.
“The Contractor shall set out the Works in relation to the original
points, lines and levels of reference specified in the Contract. The
Contractor shall be responsible for the correct positioning of all parts
of the Works, and shall rectify any error in the positions, levels,
dimensions or alignment of the Works”.
Design Liability
Employer’s Requirements
• Clauses 1.9 and 5.1 are often amended to relieve the Employer from
any responsibility for documents or design provided by it and to place
a full design and ER risk on the Contractor
(a) Portions, data and information which are stated in the Contract as
being immutable or the responsibility of the Employer;
(b) Definitions of intended purposes of the Works or any part thereof;
(c) Criteria for the testing and performance of the Completed Works;
and
(d) Portions, data and information which cannot be verified by the
Contractor, except as otherwise stated in the Contract”.
Design Liability
• Design Clause 5:
• Contractor to design the Works using designers that “are engineers or
other professionals, qualified, experienced and competent in the
discipline of the design for which they are responsible.”
• Promptly after Commencement to scrutinise the ERs.
• Errors in ERs Sub-Clause 1.9:
• Scrutinise and report within 42 days (and after) from the
Commencement date;
• Engineer proceeds under Sub-Clause 3.7 to agree or determine if
there is an error and its cost and time implications;
• If an experienced contractor would not have discovered the error then
a Variation shall apply; and
• Money and time claims will require a Sub-Clause 20.2 Notice.
Design Obligations: NEC & FIDIC
UAE:
“the two obligations are not mutually incompatible and therefore can
co-exist side by side.”
Mr Justice Stuart-Smith
“too slender a thread upon which to hang a finding that MTH gave a
warranty of 20 years life for the foundations”.
Per Lord Justice Jackson
MT Højgaard A/S v E.ON Climate and
Renewables UK Robin Rigg East Ltd & Anr
“While each case must turn on its own facts, the message from
decisions and observations of judges in the United Kingdom
and Canada is that the courts are generally inclined to give full
effect to the requirement that the item as produced complies
with the prescribed criteria, on the basis that, even if the
customer or Employer has specified or approved the design, it
is the Contractor who can be expected to take the risk if he
agreed to work to a design which would render the item
incapable of meeting the criteria to which he has agreed.”
Lord Neuberger
Decennial Liability
Article 880 of the UAE Civil Code:
“If the subject of the construction contract is the erection of buildings or other
fixed structures the plans for which have been made by an architect [engineer]
with the intention that the contractor shall carry them out under his supervision;
they shall be jointly liable to pay compensation to the employer for any total or
partial destruction occurring within 10 years to the buildings they have
constructed or the installations they have erected, unless the contract provides for
a longer period of time, or unless it was the intention of the parties that such
installations should remain for a period shorter than ten years. The liability to pay
compensation as aforesaid shall endure notwithstanding that the defect or
collapse arises out of a fault in the land itself or that the employer consented to
the erection of defective buildings or installations.”
But the liability of the architect will be limited to design defects if he has no role in
supervising the construction performance (Article 881)
www.nbs.com
BIM
• 2013 the Dubai Municipality issued circular (196), mandating the
use of BIM for architectural and MEP work on certain projects. This
was subsequently widened by circular (207) in 2015 to include
architectural and mechanical works for:
• buildings higher than 20 floors;
• buildings and facilities with areas larger than 200 thousand
square foot;
• special facilities like hospitals and universities;
• government projects; and
• projects by foreign offices.
• The Opera House, Downtown Dubai, the Midfield Terminal
Complex Development at Abu Dhabi Airport and the Louvre
Museum in Abu Dhabi.
• FIDIC has identified the key risk areas on any BIM-enabled project:
• Misunderstanding of scope of services.
• Use of data for an inappropriate purpose and reliance on
inappropriate data.
• Ineffective information, document or data management.
• Cyber security and responsibility for “holding” the models or data.
• Definition of deliverables, approval and delivery.
• The Winfield Rock Report
• http://www.ukbimalliance.org/resources/request-a-copy-of-the-
winfield-rock-report/
• Definitions;
• Establishes priority of the contract documents;
• Obligations of the Employer:
• Put a Protocol in place for everyone;
• Appoint the Information Manager.
• Obligations of project team members:
• Produce the specified models as agreed;
• Collaborative working practice.
Key features of the BIM protocol
Time Management
2017 Management Meetings
Concurrent Delay
Sub-Clause 8.5:
• The Contractor may apply for a Taking Over Certificate not earlier
than 14 days before the Works will in the Contractor’s opinion be
complete (Sub-Clause 10.1).
• The Engineer has 28 days to issue a Taking Over Certificate
stating the date on which the Works or section were completed
(save any minor defects) or reject the application giving reasons.
• If the Engineer fails to respond within 28 days a Taking Over
Certificate is deemed to have been issued on the last day of that
period.
• The Engineer may at the sole discretion of the Employer issue a
Taking Over Certificate for any part of the permanent works (Sub-
Clause 10.2).
On completion
• Statement at completion – 84 days after taking over the Contractor
submits a statement at completion and all supporting documents (Sub-
Clause 14.10).
• Application for Final Payment Certificate – 56 days after receiving a
performance certificate the Contractor submits a draft final statement
with supporting documents. (Sub-Clause 14.11)
• Discharge – the Contractor confirms the total final statement represents
the full and final settlement (Sub-Clause 14.12).
• Issue of Final Payment Certificate – 28 days after receiving the final
statement and written discharge the Engineer issues the final payment
certificate (Sub-Clause 14.13).
Payment on Delivery
General Contract
Administration and Claims
Management under the
New FIDIC Form
General contract administration: the
problem
Rank Cause
Avoiding claims
• Record progress;
• Do not exaggerate;
Early Warning
Importance of records
• Progress;
• Access issues;
• Delays;
• Costs.
Claim No.CV2008-04881/CV2008-04998
“one of the fundamental difficulties with the insurance claim was the
absence of any record of the works actually carried out. There was no
specification or schedule of works, or even a basic inventory. It is
therefore impossible to say with certainty, even now, precisely what was
done and, perhaps more importantly, what was not done. The absence
of any clear fixed scope of work has now rebounded on the insurers as
they struggle to prove the subrogated claim against the defendants.”
Mr Justice Coulson
Brit Inns Ltd & Ors v BDW Trading Ltd [2012] EWHC 214
Brit Inns Ltd & Ors v BDW Trading Ltd [2012] EWHC 214
• The ultimate answer to the question is “no”. You must retain sufficient
records to substantiate your claim;
• The more time that passes, the more memories fade, the more you
have to rely on documents.
Documents v memory?
“Having listened carefully to Mr Conlon and observed him in the witness
box my overall impression is that he is a well-meaning man. However, he
was placed in a very difficult position as he did not have the detail of
events which occurred some time ago close at hand. He was being
asked to confirm a case which did not originate with him and which was
drafted by lawyers.
...
He was asked to speak to detailed witnesses statements which were
prepared by lawyers and understandably he faltered in that exercise. He
was also asked to remember events long ago and to remember a letter
that he had not volunteered himself.”
Keegan J, Glen Water Ltd v Northern Ireland Water Ltd
[2017] NIQB 20
Result:
• An increased likelihood that if you fail to follow the rules, you lose the
right to make a claim.
Solutions: remember the following
• Record keeping;
• Manage claims
Conclusions
Max Abrahamson
Engineering Law and the ICE contracts, 1979
Suspension and
Termination
Contract Annulment
• UAE Civil Code Article 275: parties are required to return any
performance received;
Termination by Employer
“the Employer shall have made available to the Contractor for his information,
prior to the Base Date, all relevant data in the Employer’s position on the
sub-surface and hydrological conditions at the Site, including environmental
aspects. The Employer shall similarly make available to the Contractor all
such data which come into the Employers position after the Base Date. The
Contractor shall be responsible for interpreting all such data.
To the extent which was practicable (taking account of cost and time), the
Contractor shall be deemed to have obtained all necessary information as to
risks, contingences and other circumstances which may influence or effect
Tender or Works. To the same extent, the Contractor shall be deemed to
have inspected and examined the Site, it’s surroundings, the above data and
other available information, and to have been satisfied before submitting the
Tender as to all relevant matters, including (without limitation):
• The form and nature of the Site, including sub-surface conditions”.
Obrascon – Site Data and
Unforeseeable Conditions
• CA held the contractor cannot just rely on the site data. It must make its
own assessment.
• CA stated that the Contractor should make provision for a “possible worse
case scenario”. (Paragraph 223 of TTC decision confirmed by CA).
Obrascon – Termination by
Employer
• A Notice to Correct (Sub-Clause 15.1) should only be issued for “more than
significant contractor failures”.
• So for a trivial breach a Notice to Correct should not be issued. This is a
question of fact.
• However, a breach need not amount to a repudiatory breach in order to
trigger termination.
• A Notice to Correct can only be issued in relation to actual failures (not
estimated or potential future failures).
• The time for correcting the works must be reasonable in all the
circumstances prevailing time at which the notice was issued. It should take
into account problems that are solely at the Contractor’s risk.
• It can also take into account the circumstances leading up to the Notice to
Correct. If the Contractor has ignored requests then less time might be
reasonable, but if the notice were issued immediately without any prior
warning.
Actions on termination
Freedom of Contract:
Article 243 (2) of the UAE Civil Code states:
“With regard to the rights (obligations) arising our of the contract,
each of the contracting parties must perform that which the contract
obliges him to do .”
Article 106 of the UAE Civil Code provides that the exercise of a right
shall be unlawful if it is disproportionate to the harm suffered by the
other party:
Unjust enrichment:
Article 319 (1): “Any person who acquires the property of other
person without any disposition vesting ownership must return it if that
property still exists, or its like or the value thereof if it no longer exists,
unless the law otherwise provides.”
Dispute Events (Clause 20)
• Sub-Clause 21.4.4.
• Either party can serve a NOD:
• stating clearly that it is a NOD:
• with reason(s);
• within 28 days after receiving the DAAB Decision; and
• may dispute all or part.
• After 28 days the DAAB Decision “… shall become final and
binding on both Parties.”
• Note that “… neither party shall be entitled to commence
arbitration of a Dispute unless a NOD in respect of that Dispute
has been given …”
• There are some exceptions.
Arbitration
• If a NOD has been served [Sub-Clause 21.5]:
• amicable settlement for 28 days after the date on which the NOD was
given; but
• no attempt to amicably settle need be made;
• ICC Arbitration [Sub-Clause 21.6]:
• one or three arbitrators;
• language of the Contract applies;
• may open up review, revise etc.;
• costs; tribunal may take account a Party’s failure to cooperate with
the other in constituting a DAAB;
• not limited to evidence put before the DAAB;
• may commence before or after completion of the Works; and
• if award requires payment then this is immediately due (no need for a
certificate etc).
No DAAB in Place
• Sub-Clause 21.8.
Questions?
Nicholas Gould & Jeremy Glover
Partners, Fenwick Elliott LLP Dubai
ngould@fenwickelliott.com
Visiting Professor, Kings College London
M UAE +971 56 971 5993
jglover@fenwickelliott.com
M UK +44 7760 175 672
www.fenwickelliott.com