Professional Documents
Culture Documents
Tabel Progress Per-Minggu - Revisi 1
Tabel Progress Per-Minggu - Revisi 1
PERIODE PROGRES
Deviasi Ket
Rencana (%) Realisasi (%)
(%)
Minggu
Bulan Tanggal s.d s.d
ke- Minggu Minggu
Minggu Minggu
Ini Ini
Ini Ini
13 - 19 1 0,008% 0,008% 0,039% 0,039% 0,032%
November 2019 20 - 26 2 0,008% 0,015% 0,016% 0,055% 0,040%
27 - 03 Des 3 0,008% 0,023% 0,016% 0,071% 0,048%
04 - 10 4 0,207% 0,230% 0,105% 0,176% -0,055%
11 - 17 5 0,207% 0,438% 0,015% 0,190% -0,247%
Desember 2019
18 - 24 6 0,207% 0,645% 0,132% 0,322% -0,322%
25 - 01 Jan 7 0,830% 1,475% 0,027% 0,349% -1,125%
02 - 08 8 0,830% 2,305% 0,019% 0,368% -1,937%
09 - 15 9 0,830% 3,135% 0,140% 0,508% -2,626%
Revisi Schedulle
Januari 2020 16 - 22 10 1,245% 4,380% 0,094% 0,602% -3,778%
MC-0
23 - 28 11 1,106% 5,486% 0,004% 0,606% -4,880%
29 - 04 Feb 12 0,765% 6,251% 0,458% 1,063% -5,188%
05 - 11 13 0,526% 6,777% 0,340% 1,403% -5,374%
12 - 18 14 0,526% 7,303% 0,243% 1,646% -5,657%
Februari 2020
19 - 25 15 0,526% 7,829% 0,355% 2,001% -5,828%
26 - 03 Mar 16 0,526% 8,355% 0,463% 2,464% -5,891%
04 - 10 17 0,526% 8,882% 2,590% 5,054% -3,828% Termin 1
11 - 17 18 1,262% 10,144% 0,380% 5,434% -4,710%
Maret 2020
18 - 24 19 1,262% 11,406% 0,421% 5,855% -5,551% Add-1
25 - 31 20 1,276% 12,682% 0,095% 5,951% -6,731%
01 - 07 21 1,276% 13,958% 0,029% 5,980% -7,978%
08 - 14 22 1,076% 15,034% 0,155% 6,135% -8,899%
April 2020
15 - 21 23 0,776% 15,810% 0,521% 6,656% -9,154%
22 - 28 24 0,276% 16,086% 0,675% 7,331% -8,755%
29 - 05 Mei 25 1,276% 17,362% 1,062% 8,393% -8,969%
06 - 12 26 1,776% 19,138% 1,657% 10,050% -9,089%
Mei 2020 13 - 19 27 0,990% 20,129% 0,000% 10,050% -10,079% Termin 2
20 - 26 28
LIBUR IDUL FITRI 1442 H
27 - 02 Juni 29
03 - 09 30 0,253% 20,382% 0,283% 10,333% -10,049% SCM-1
10 - 16 31 0,279% 20,661% 0,410% 10,743% -9,918%
Juni 2020
17 - 23 32 0,065% 20,726% 0,140% 10,883% -9,843%
24 - 30 33 0,273% 20,999% 0,148% 11,030% -9,968% Add-2
01 - 07 34 1,123% 22,122% 1,242% 12,272% -9,849%
08 - 14 35 0,313% 22,435% 0,165% 12,438% -9,997%
Juli 2020 15 - 21 36 0,123% 22,558% 0,152% 12,590% -9,968%
22 - 28 37 2,123% 24,681% 2,214% 14,804% -9,877%
29-04 Agust 38 4,423% 29,104% 0,193% 14,997% -14,106%
05 - 11 39 7,423% 36,527% 10,756% 25,753% -10,773% SCM-2
12 - 18 40 3,583% 40,109% 1,555% 27,308% -12,801% Termin 3
Agustus 2020
19 - 25 41 2,164% 42,273% 2,360% 29,668% -12,605%
26-01 Sept 42 2,964% 45,237% 1,813% 31,481% -13,756%
02 - 08 43 3,564% 48,801% 0,542% 32,023% -16,778%
09 - 15 44 6,674% 55,476% 6,552% 38,575% -16,901% SCM-3
September 2020
16 - 22 45 2,954% 58,430% 7,060% 45,635% -12,795% Termin 4
23 - 29 46 3,017% 61,447% 4,655% 50,290% -11,157%
30-06 Okt 47 3,017% 64,464% 3,863% 54,153% -10,311%
07 - 13 48 3,017% 67,482% 2,749% 56,902% -10,580%
Oktober 2020 14 - 20 49 3,288% 70,770% 4,008% 60,910% -9,860% Termin 5
21 - 27 50 0,993% 71,763% 1,098% 62,008% -9,755% Add-3
28-03 Nov 51 3,053% 74,816% 3,561% 65,570% -9,246%
04 - 10 52 5,299% 80,115% 6,773% 72,343% -7,773%
11 - 17 53 3,093% 83,209% 3,663% 76,006% -7,203%
November 2020
18 - 24 54 3,595% 86,804% 4,348% 80,354% -6,451% Termin 6
25-01 Des 55 4,167% 90,972% 4,555% 84,909% -6,063%
02 - 08 56 4,252% 95,224% 4,614% 89,523% -5,701%
Desember 2020 09 - 15 57 3,493% 98,717% 3,597% 93,120% -5,597% Termin 7
16 - 24 58 1,275% 100% 5,030% 98,150% -1,842%
1. Pekerjaan Menara & Bangunan Penunjang, belum bisa dikerjakan (revisi disain oleh
-1,245%
Perencana);
2. RTH & Panggung bekum bisa dikerjakan karena Lahan kerja belum bebas
3. Pekerjaan MEP Kawasan belum bisa dikerjakan, karena menunggu persetujuan revisi Disain dari
Perencana
5,054% Termin 1
Addendum 1 dilakukan tanggal 20 Maret 2020 terkait dengan adanya perubahan disain pondasi
pancang menjadi pondasi tapak.
10,050% Termin 2
45,635% Termin 4
60,910% Termin 5
Addendum 3, ada penyesuian bobot pekerjaan, sehingga berpengaruh terhadap bobot kumulatif
rencana
80,354% Termin 6
93,120% Termin 7