REVISI PROGRES PEKERJAAN SRG

PERIODE PROGRES
Deviasi Ket
Rencana (%) Realisasi (%)
(%)
Minggu
Bulan Tanggal s.d s.d
ke- Minggu Minggu
Minggu Minggu
Ini Ini
Ini Ini
13 - 19 1 0,008% 0,008% 0,039% 0,039% 0,032%
November 2019 20 - 26 2 0,008% 0,015% 0,016% 0,055% 0,040%
27 - 03 Des 3 0,008% 0,023% 0,016% 0,071% 0,048%
04 - 10 4 0,207% 0,230% 0,105% 0,176% -0,055%
11 - 17 5 0,207% 0,438% 0,015% 0,190% -0,247%
Desember 2019
18 - 24 6 0,207% 0,645% 0,132% 0,322% -0,322%
25 - 01 Jan 7 0,830% 1,475% 0,027% 0,349% -1,125%
02 - 08 8 0,830% 2,305% 0,019% 0,368% -1,937%
09 - 15 9 0,830% 3,135% 0,140% 0,508% -2,626%
Revisi Schedulle
Januari 2020 16 - 22 10 1,245% 4,380% 0,094% 0,602% -3,778%
MC-0
23 - 28 11 1,106% 5,486% 0,004% 0,606% -4,880%
29 - 04 Feb 12 0,765% 6,251% 0,458% 1,063% -5,188%
05 - 11 13 0,526% 6,777% 0,340% 1,403% -5,374%
12 - 18 14 0,526% 7,303% 0,243% 1,646% -5,657%
Februari 2020
19 - 25 15 0,526% 7,829% 0,355% 2,001% -5,828%
26 - 03 Mar 16 0,526% 8,355% 0,463% 2,464% -5,891%
04 - 10 17 0,526% 8,882% 2,590% 5,054% -3,828% Termin 1
11 - 17 18 1,262% 10,144% 0,380% 5,434% -4,710%
Maret 2020
18 - 24 19 1,262% 11,406% 0,421% 5,855% -5,551% Add-1
25 - 31 20 1,276% 12,682% 0,095% 5,951% -6,731%
01 - 07 21 1,276% 13,958% 0,029% 5,980% -7,978%
08 - 14 22 1,076% 15,034% 0,155% 6,135% -8,899%
April 2020
15 - 21 23 0,776% 15,810% 0,521% 6,656% -9,154%
22 - 28 24 0,276% 16,086% 0,675% 7,331% -8,755%
29 - 05 Mei 25 1,276% 17,362% 1,062% 8,393% -8,969%
06 - 12 26 1,776% 19,138% 1,657% 10,050% -9,089%
Mei 2020 13 - 19 27 0,990% 20,129% 0,000% 10,050% -10,079% Termin 2
20 - 26 28
LIBUR IDUL FITRI 1442 H
27 - 02 Juni 29
03 - 09 30 0,253% 20,382% 0,283% 10,333% -10,049% SCM-1
10 - 16 31 0,279% 20,661% 0,410% 10,743% -9,918%
Juni 2020
17 - 23 32 0,065% 20,726% 0,140% 10,883% -9,843%
24 - 30 33 0,273% 20,999% 0,148% 11,030% -9,968% Add-2
01 - 07 34 1,123% 22,122% 1,242% 12,272% -9,849%
08 - 14 35 0,313% 22,435% 0,165% 12,438% -9,997%
Juli 2020 15 - 21 36 0,123% 22,558% 0,152% 12,590% -9,968%
22 - 28 37 2,123% 24,681% 2,214% 14,804% -9,877%
29-04 Agust 38 4,423% 29,104% 0,193% 14,997% -14,106%
05 - 11 39 7,423% 36,527% 10,756% 25,753% -10,773% SCM-2
12 - 18 40 3,583% 40,109% 1,555% 27,308% -12,801% Termin 3
Agustus 2020
19 - 25 41 2,164% 42,273% 2,360% 29,668% -12,605%
26-01 Sept 42 2,964% 45,237% 1,813% 31,481% -13,756%
02 - 08 43 3,564% 48,801% 0,542% 32,023% -16,778%
09 - 15 44 6,674% 55,476% 6,552% 38,575% -16,901% SCM-3
September 2020
16 - 22 45 2,954% 58,430% 7,060% 45,635% -12,795% Termin 4
23 - 29 46 3,017% 61,447% 4,655% 50,290% -11,157%
30-06 Okt 47 3,017% 64,464% 3,863% 54,153% -10,311%
07 - 13 48 3,017% 67,482% 2,749% 56,902% -10,580%
Oktober 2020 14 - 20 49 3,288% 70,770% 4,008% 60,910% -9,860% Termin 5
21 - 27 50 0,993% 71,763% 1,098% 62,008% -9,755% Add-3
28-03 Nov 51 3,053% 74,816% 3,561% 65,570% -9,246%
04 - 10 52 5,299% 80,115% 6,773% 72,343% -7,773%
11 - 17 53 3,093% 83,209% 3,663% 76,006% -7,203%
November 2020
18 - 24 54 3,595% 86,804% 4,348% 80,354% -6,451% Termin 6
25-01 Des 55 4,167% 90,972% 4,555% 84,909% -6,063%
02 - 08 56 4,252% 95,224% 4,614% 89,523% -5,701%
Desember 2020 09 - 15 57 3,493% 98,717% 3,597% 93,120% -5,597% Termin 7
16 - 24 58 1,275% 100% 5,030% 98,150% -1,842%
1. Pekerjaan Menara & Bangunan Penunjang, belum bisa dikerjakan (revisi disain oleh
-1,245%
Perencana);
2. RTH & Panggung bekum bisa dikerjakan karena Lahan kerja belum bebas
3. Pekerjaan MEP Kawasan belum bisa dikerjakan, karena menunggu persetujuan revisi Disain dari
Perencana

5,054% Termin 1

Addendum 1 dilakukan tanggal 20 Maret 2020 terkait dengan adanya perubahan disain pondasi
pancang menjadi pondasi tapak.

10,050% Termin 2

-0,253% Ada perubahan Master Schedule, hal ini disebabkan oleh :


1. Pekerjaan Menara dan Bangunan Penunjang belum bisa dikerjakan karena menunggu revisi Disain
dari Perencana
2. Pekerjaan RTH dan Panggung belum bisa dikerjakan, karena lahan kerja belum bebas
3. Pekerjaan MEP Kawasan belum bisa dikerjakan, karena menunggu persetujuan revisi Disain dari
Perencana
27,308% Termin 3

45,635% Termin 4

60,910% Termin 5
Addendum 3, ada penyesuian bobot pekerjaan, sehingga berpengaruh terhadap bobot kumulatif
rencana

80,354% Termin 6

93,120% Termin 7