Linda& Jason International Co., Ltd.

Title:Rubber Mould Testing Procedure


Start:Mould finished with cavity No. Date:2008/6/16
End:Shipment Process
Remark of the Operation Mould Maker Manufacturing Unit L&J Customer

Moulds finished Doing mould test


with cavity No. to produce

Each samples for Sample Delivery


each mould has to Separately group
be distinguished by
the samples by Cp& Cpk study
the its code
cavity No. report

Dimensions
measured by 2.5D Critical dimension
projector measurement Cp& Cpk study
report
Process of
The result of mould Approval
test including Mould Test Double Check
production Report
parameter

Cp& Cpk Yes


Statistic Analysis
calculation(,if need) Shipment Approval
Process Judgement

Cp& Cpk study


report(,if need) No

Discussion&
Communication
Mould Yes
Capability

No

Exam& Revise

*To 100% simulate the operating environment of customer, we must:


1.The rubber material and metal insert(if have) have to be provided from customer.
2.Sometimes customer needs to provide their manufacturing parameter of the compound rubber like, molding temperature,
pressure and curing time.
3.The manufacturing unit has to obey the parameter competely, or provide the suggestion of best parameter after test.