Professional Documents
Culture Documents
CE1.1) Introduction
Bajra Guru Construction Company Pvt Ltd, Nepal was awarded the tender to construct
the civil works at Sanjen (Upper) Hydroelectric Project (SUHP). This run of rover
scheme project generates 14.8MW during peak discharge from Sanjen and Chilime River
Basin, which falls under Rasuwa district, 161 km north of the capital of Nepal. The civil
works is located approximately 6km upstream of the headworks of the Chilime station.
The powerhouse and the headwork of the project are almost 29kms and 25kms from
Syaphrubesi. The designed location of headwork site is Tiloche which is 1.5km upstream
from the confluence of Chhuphcung Khola and Sanjen River. The water from sanjen river
is diverted in to the powerhouse from a 1.4kms long headrace channel. My Tenure as
civil engineer at Bajra Guru Construction Company started on 1st May 2013 and I worked
till 30th June 2014
CE1.2) Background:
Bajraguru Construction Company Pvt Ltd is one of the leading construction companies in
Nepal and is registered with Ministry of physical planning and works, Government of
Nepal. Bajraguru has a massive experience in delivery of infrastructural projects such
road, bridges, irrigation, transmission lines and hydropower. Bajraguru has successfully
completed numerous civil projects and specializes in construction of civil and mechanical
works of hydroelectric projects.
1
Tak Bahadur Pun
Narrative I
Organizational Structure and chart
“Construction of Inlet Portal of Sanjen (Upper) Hydroelectric Project”
Sanjen Jalavidyut Company Ltd
Ministry of Energy, Water Resources and Irrigation
Nepal Electricity Authority
(Client)
Mechanical Engineer Geotechnical Engineer Civil/ Site Engineer Electrical Engineer Geologist
Civil Overseer
Surveyor/Sub overseer/Supervisors/Staffs
3
Tak Bahadur Pun
Narrative I
My technical and project management skills helped me get appointed as the site engineer
and tunneling works in charge of the hydropower project. The site location being very
remote and limited access to resources was one of the major challenges I felt. Luckily my
project manager was a very experienced and helping personality. Geologists,
geotechnical engineers, contract documents, drawings and codes helped me understand
the dynamics of the tunnels.
4
Tak Bahadur Pun
Narrative I
CE 1.9) Construction, Monitoring and Supervision of Blasting, Excavation and Rock
Supporting Works:
After surveying works my next job was site clearance, excavation and rock supporting
works. There were many trees and stumps in the alignment of the inlet portal. As per the
EIA report for the trees clearing works, I had to co-ordinate with the clearing
subcontractor and ecologist. During blasting works I had to co-ordinate with Nepal army
and the blasting team for a schedule. After the confirmation of blasting date, I had to
stake out the central, bottom and side RLs of the channel (3.75m x 3.5m) with the help of
Total Station within a tolerance of 5mm. After the controlled blasting of the tunnel I had
to inspect the blasted materials and use rock mass classification system to classify the
type of the rock and record the quantity of rock. The rock mass classification would
automatically recommend the rock support system. During the supervision works I
referred codes such as IS 15026 Tunneling Methods in Rock Masses, IS 5878 Code of
Practice for Construction of Tunnels and IS 4756 Safety Code of Tunneling Works. I
prepared rebar schedule and shop drawings of the tunnel. I used NBC 111: 1994, IS 800:
2007 for Steel, NBC 110: 1994 and IS 456: 2000 for Plain and Reinforced Concrete. I
frequently used Ms-Excel and Auto CAD for drafting and calculation purposes. While
placing the rock bolts, steel ribs and shotcrete I had to refer my course books and IS
codes regarding drainage system in tunnels within water charged rock, identification of
weak zone, strength and strength of shotcrete mix, type, spacing and capacity of roof
bolts, steel ribs and plates in different types of joints. I developed casting schedule for
installation of A-continuous steel ribs (3.75m x 3.5m) and D rib wall and post and
shotcreting schedules. During the tunnel construction works I also consulted with geo
technical engineers, geologists and my project managers.
5
Tak Bahadur Pun
Narrative I
three-stage solution using IS 4756, IS 5878, IS 15026 and Building codes and excel
sheets:
a) Calculation sheet of Q Method of rock mass classification to record mass quality with
the help of joint sets, roughness, alternation and rock mass stress situation
A 1 = Very Good Q>40: Massive to low joint frequency, Jv< 5/m3. Tight joints,
unaltered strong rock and insignificant stress slabbing.
A 2 = Good 10<Q<40: Low to moderate joint frequency, 5<Jv< 10. Strong rock with
none or insignificant alteration and with coating on some joints. Low to moderate
stress slabbing.
A 3 = Fair 4<Q<10: Moderate to high joint frequency, 10<Jv< 20. Moderately strong
to strong rock generally with coated joints
A 4 = Poor1<Q<4: High joint frequency, Jv> 20, clay seams (fault zones, swelling
clays) in moderately strong rock.
A 5 = Extremely PoorQ<1: Completely crushed rock containing a significant amount
of secondary clay minerals as in major fault zones.
b) Stockpiling excavated rocks as per the Q System. Doing survey pick up of the
stockpiles. Maintaining tip sheets and run sheets of the dump trucks to calculate the
approximate volume and match it with the stock pile volume.
c) Rock Support (RS) used for each rock class (A) to be as per follows:
6
Tak Bahadur Pun
Narrative I
CE 1.12) Preparation and approval of Progress Report:
I prepared monthly progress report with the help of grant chart and s-curve which
recorded the ongoing activity progress, achieved milestones within the month and task
planned for the coming month. My monthly progress report also recorded the technical
and nontechnical delays in the month, reasons and lessons learnt from the delays and
extension of time claimed for the month. I used project management tools like Primavera
and Ms-project.
Inventory management and quality control was one my major duties. Inventory of
explosives and chemicals was a very risky task assigned to me. Stock of the explosive
and right handling was essential to achieve project milestones. Inspection of rock
surfaces, establishing chainages, recommendation of type of rock support system and
scaling works was my everyday task. Analysis and recording of rock mass and required
support system, rock scaling, rock bolting and grouting, shotcrete, hydraulic pull testing
were my quality control methods to record consistency, strength, porosity, expansion,
permeability and tensioning of the support system. Regular sampling including sieve
analysis of aggregate, cements, tensile strength of steel and compressive strength and
slump value of concrete were other methods of quality control. I drafted a whole set of
ITPs and checklist to make sure that all the hold points and witness points were recorded.
7
Tak Bahadur Pun
Narrative I
I referred International Standard ISO 2859-1 “Sampling procedures and tables for
inspection by attributes” for determining sampling requirement and test frequencies.
Summary:
This site engineer role was a game changing position in my career which helped me
understand the basics of surveying, foundation engineering, soil mechanics, rock
slope engineering and dynamics of tunnelling. I also acquired the knowledge of
project formulation, planning, implementation and management. Moreover, quality
assurance and control, compliance to safety standards, effective communicating
skills, report writing, and presentations, team leading skills were other skills that
helped to logically reason and critically think to excel in my professional career. I
also learnt the effective use of computer aided software such as Civil CAD 3D,
primavera and SW-DTM.
.
8
Tak Bahadur Pun
Narrative I
Site Meeting after the excavation of Inlet Portal Access
9
Tak Bahadur Pun
Narrative I