You are on page 1of 1

INTERIM PAYMENT CERTIFICATE

IPC~08
Month: August-2021
Project: GODE TOWN HOT MIX ASPHALT ROAD PROJECT 1 Main Contract 259,451,675.89
Location: Somali Regional State 2 Variation Orders
Employer: Somali Region Urban Development Bureau 3 Others
Contractor: Amal General Contractor 4 VAT 15% 38,917,751.38
Consultant: Tigraar Architect and Engineering Consultancy 5 Total Sum 298,369,427.27

As per the attached measurements value of the works executed and/or materials supplied to date is Eth. Birr:
A)Total Sum Before deductions 222,640,015.38
B) Material Advance (MA) 65,021,607.74
PREVIOUS CONSECUTIVE PAYMENTS C) Price Adjustment 48,308,115.33
D) Total with Material Advance & Price Escalation(WT) 335,969,738.45
VAT Amount
No. Net Pay (Birr)
(Birr)
Amount (Birr)

Advance 77,835,502.77 11,675,325.41 1. Previous Payment 172,876,101.33


IPC-1 47,192,215.23 7,078,832.29 3. Retention (Rt) 6,974,149.28

IPC-2 21,851,376.71 1,327,069.75 4. Penalty (P)

IPC-3 7,826,709.29 2,082,123.13 5. Advance Repayment 66,792,004.61

IPC-4 39,695,914.89 3,074,238.44 6. Others

IPC-5 29,546,154.22 2,095,882.93 7.Material Recovery 41,019,367.90

IPC-6 18,068,079.15 2,710,211.87 8. Total 287,661,623.12

IPC-7 8,695,651.84 1,304,347.78 Net Sum due to the Contractor (N) = 48,308,115.33

VAT15%= 7,246,217.30

Sum with 15% VAT due to the Contractor = 55,554,332.63

Total previous
172,876,101.33 31,348,031.61
payments

We certify that the Contractor is now entitled to the sum of Birr(Including VAT):
Fifty Five Million Five Hundred Fifty Four Thousand Three Hundred Thirty Two Birr and Sixty Three Cents

Contractor Consultant Client


Prepared By Certified By Approved by:

_________________________ __________________________________ _______________________________________