Pouring Concrete Work Procedure
Pouring Concrete Work Procedure
005/GMT/WP/SOP/VII/19
Page Page 1 of 9
PT. GAMMA MANDIRI TEKNIK
@gmt.copyright.jul.2019
Document. No. 005/GMT/WP/SOP/VII/19
Page Page 2 of 9
PT. GAMMA MANDIRI TEKNIK
1. Tujuan (Purpose)....................................................................................................................................
2. Ruang Lingkup Aplikasi (Scope of Application)....................................................................................
a. Ruang Lingkup (Scope).....................................................................................................................
b. Responsibilitas (Responsibilities).......................................................................................................
3. Referensi (Reference)..............................................................................................................................
4. Resiko Keselamatan dan Peralatan Kerja (Safety Risk and Working Equipment)...................................
a. Resiko Keselamatan (Safety Risk).....................................................................................................
b. Peralatan Kerja (Working Equipment)..................................................................................................
5. Prosedur Kerja Pengecoran Beton (Pouring Concrete Work Procedure)................................................
a. Pekerjaan Persiapan (Work Preparation)..........................................................................................
b. Pelaksanaan Pekerjaan Pengecoran (Pouring Work Implementation).....................................................
c. Pekerjaan Perawatan Hasil Pengecoran (Maintenance Work for Result of Pouring)................................
d. Akhir Pekerjaan (End of Work)............................................................................................................
6. Kebijakan Pekerjaan (Work Policy).......................................................................................................
a. Peralatan Keselamatan Kerja (Work Protective Equipment)..............................................................
@gmt.copyright.jul.2019
Document. No. 005/GMT/WP/SOP/VII/19
Page Page 3 of 9
PT. GAMMA MANDIRI TEKNIK
1. TUJUAN
(PURPOSE)
a. Untuk memberikan pedoman mendasar dalam pekerjaan pengecoran beton sehingga pekerja
dapat bekerja efisien dan aman.
(To provide fundamental guidance in construction work for pouring concrete so that workers
can work efficiently and safely.).
b. Untuk memberikan pemahaman yang sama dalam menyelesaikan permasalahan yang muncul
selama proses pekerjaan pengecoran beton berlangsung.
(To provide the same understanding in solving the problems that arise during the process of
construction work for pouring concrete takes place).
c. Untuk memastikan pekerjaan berjalan sesuai dengan rencana kerja, selesai tepat waktu,
berkualitas dan tetap memperhatikan item-item dalam keselamatan kerja.
(To ensure the work goes according to the work plan, finish on time, quality, and keep the items
in occupational safety.)
@gmt.copyright.jul.2019
Document. No. 005/GMT/WP/SOP/VII/19
Page Page 4 of 9
PT. GAMMA MANDIRI TEKNIK
Manajemen PT. Gamma Mandiri Teknik dan rekanan akan memastikan bahwa para pekerja,
dimana mereka memiliki control langsung, mematuhi pedoman ini dan bahwa subkontraktor
dikelola dengan sesuai.
(Management of PT. Gamma Mandiri Teknik and its Partners will ensure that the workers,
over whom they have direct control, comply with this guideline and that subcontractors are
managed accordingly).
Semua personel pengawas lapangan harus memantau dan melaporkan setiap pelaggaran
terhadap pedoman apa pun kepada manajer terkait.
(All Site Supervisory Personnel shall monitor compliance and report any breach of any
guideline to the appropriate manager).
3. REFERENSI
(REFERENCE)
a. Gambar teknik untuk pengecoran beton.
(Technical drawing for pouring concrete).
b. SNI 2847 : 2013, untuk standar persyaratan beton structural untuk bangunan gedung.
(SNI 03-2914 - 1992, for standard structural concrete requirements for buildings).
c. SNI 03 – 2914 - 1992, untuk standar spesifikasi beton bertulang kedap air.
(SNI 03-2914 - 1992, for waterproof reinforced concrete specification standards).
d. ISO 9001, 2008 untuk kualitas hasil pekerjaan.
(ISO 9001, 2008 for quality of work).
e. ISO 14001, 2004 tentang dampak pekerjaan terhadap lingkungan.
(ISO 14001, 2004 about the impact of work on the environment).
f. OHSAS 18001, 2007 tentang keselamatan kerja.
(OSHAS 18001, 2007 about work safety).
@gmt.copyright.jul.2019
Document. No. 005/GMT/WP/SOP/VII/19
Page Page 5 of 9
PT. GAMMA MANDIRI TEKNIK
@gmt.copyright.jul.2019
Document. No. 005/GMT/WP/SOP/VII/19
Page Page 6 of 9
PT. GAMMA MANDIRI TEKNIK
xi. Pemukaan sebelah dalam dari bekisting yang nantinya menempel dengan beton harus
dibasahi dengan air atau diolesi minyak yang tidak meninggalkan bekas.
(The inner surface of the formwork that later attaches to the concrete must be
moistened with water or smeared with oil that does not leave marks).
@gmt.copyright.jul.2019
Document. No. 005/GMT/WP/SOP/VII/19
Page Page 7 of 9
PT. GAMMA MANDIRI TEKNIK
paling sedikitnya 3 hari. Perawatan beton juga dapat dilakukan dengan uap ataupun
dengan chemical.
(Perform maintenance after the concrete begins to harden by covering it with material
that can absorb water. Material sheets must be saturated within at least 3 days.
Concrete treatment can also be done with steam or with chemical).
viii. Apabila menggunakan bekisting kayu, bekisting tersebut harus dipertahankan basah
setiap saat sampai dibongkar.
(When using wood formwork, the formwork must be kept wet at all times until it is
dismantled).
ix. Lalu lintas ataupun penambahan beban selain beban sendiri tidak diperkenankan
sampai beton tersebut berumur 7 hari setelah pelaksanaan pengecoran.
(Traffic or additional expenses other than the load itself are not permitted until the
concrete is 7 days after casting).
x. Pada lantai beton yang difungsikan sebagai lantai aus harus dirawat setelah
permukaaannya mulai mengeras dengan cara ditutup oleh lapisan lembab paling sedikit
selama 21 hari.
(On concrete floors that function as worn floors must be treated after the surface
begins to harden by being covered by a moist layer for at least 21 days).
@gmt.copyright.jul.2019
Document. No. 005/GMT/WP/SOP/VII/19
Page Page 8 of 9
PT. GAMMA MANDIRI TEKNIK
(Check the construction joints to make sure the connection does not leak and
discontinuity. Inspection can be carried out by spraying water or inundating water at
the location of the construction connection, if there is seepage, the construction
connection must be repaired).
6. KEBIJAKAN PEKERJAAN
(WORK POLICY)
PT. Gamma Mandiri Teknik akan menyediakan supervisor sipil untuk mengendalikan kegiatan
pengecoran beton di lokasi proyek PT. PLN (Persero) Unit Pembangkitan Sebalang.
(PT. Garuda Teknik Persada will provide civilian supervisors to control the pouring concrete activities
at the project location of PT. PLN (Persero) Unit Pembangkitan Sebalang).
Pengawas ini akan memeriksa pekerjaan sbenarnya dan membandingkan dengan spesifikasi klien untuk
pekerjaan ini sebelum melanjutkan ke perkerjaan berikutnya.
(This supervisor will checking actual work and compare with Client specification for this works before
go to the next work).
@gmt.copyright.jul.2019
Document. No. 005/GMT/WP/SOP/VII/19
Page Page 9 of 9
PT. GAMMA MANDIRI TEKNIK
@gmt.copyright.jul.2019