Professional Documents
Culture Documents
2022 New Safety
2022 New Safety
Php0.00
CHECKLIST
(Program of Works / Approved Budget for the Contract)
TEOFILA U. TAN
Chief, Planning and Design Division
Reference No. ______
November 26, 2022
Republic of the Philippines
Department of Public Works and Highways
OFFICE OF THE REGIONAL DIRECTOR
Region XI, Davao City
EXECUTIVE SUMMARY
(Program of Works / Approved Budget for the Contract)
2. Contract ID :
3. Implementing Office : DPWH Region XI ,Regional Office
4. Reviewing Office : Planning and Design Division
5. Mode of Contracting : Public Bidding
6. Source of Fund : FY 2021 Regular Infrastructure program
6. Allocation : Php0.00
7. Approved Budget for : Php98,393,454.04
the Contract (ABC)
8. Action Recommended : For Approval
9. Remarks : This Office after review found the proposed Program of Works
(POW) and Approved Budget for the Contract (ABC) reasonable as
corrected
Attached herewith are the following:
1. Construction Drawing prepared by DPWH Region XI ,Regional
Office and reviewed by this Office.
Project : ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO
OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
SCOPE OF WORK
AMOUNT PERCENT
ITEM NO. DESCRIPTION (TOTAL COST) WEIGHT
#NAME?
Concreting = = #NAME?
3.360 km
TEOFILA U. TAN
Chief, Planning and Design Division
98,393,454.04 #NAME?
3.412
Department of Public Works and Highways (DPWH)
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO
OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
Project Name : Net Length : (a) Road
Scope of Works : Widening (2 into 4 lanes), 280mm THK, PCCP (b) Bridge
Project ID : : Construction of manhholes, box culverts, concrete and CHB lined (c ) Others
canal, cross drains and other minor drainage structures
Location : DAVAO ORIENTAL Target Start Date :
: : Removal of guardrails Total Project Duration : 280 Calendar days
Station Limits (As
per RBIA) : Installation of chevron and warning signs No. of Pre-determined :
Unworkable Days
64 Calendar days
: Removal, Furnishing and transplanting of trees
: Application of reflectorized thermoplastic pavement markings No. of Working Days : 216 Calendar days
Appropriation : Php0.00
Source of Fund : CY 2022 DPWH REGULAR INFRASTRUCTURE PROGRAM : Installation of metal guardrails
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part A: FACILITIES FOR THE ENGINEER PLS SEE FORM POW 0.40% 316,901.36 0.40% 316,901.36
B: OTHER GENERAL REQUIREMENTS 3.17% 2,521,377.78 3.17% 2,521,377.78
C: EARTHWORK 24.06% 19,163,554.59 24.06% 19,163,554.59
D: SUBBASE AND BASE COURSE 12.87% 10,248,796.67 12.87% 10,248,796.67
E: SURFACE COURSE 45.82% 36,494,811.53 45.82% 36,494,811.53
F: DRAINGE CONSTRUCTION 2.77% 2,208,983.43 2.77% 2,208,983.43
G: DRAINAGE AND SLOPE PROTECTION STRUCTURES 7.08% 5,643,285.56 7.08% 5,643,285.56
H: MISCELLANEOUS STRUCTURE 3.84% 3,055,770.61 3.84% 3,055,770.61
Prepared By: Checked/Submitted By: Reviewed as to Unit Cost: Recommending Approval: Approved:
JESSICA B. APOSTOL JUDY ANN T. BERNARDINO TEOFILA U. TAN ARTURO P. LONGYAPON REY PETER B. GILLE, DM
Engineer II Engineer IV Chief, Planning & Design Division Assistant Regional Director OIC - Regional Director
PROJECT COST
RROW
CIVIL WORKS -
(34,360.92)
79,619,120.61
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED
A.1.1(3) Construction of Field Office for the Engineer 1.00 1.00 ls 198,192.64 198,192.64 198,192.64 198,192.64 245,560.68 245,560.68
A.1.1(16) Operation & Maintenance of Field Office for the Engineer 8.00 8.00 mo 118,708.72 118,708.72 14,838.59 14,838.59 16,826.96 16,826.96
B.4(1) Construction survey and staking 3.36 3.36 km 70,491.46 70,491.46 20,979.60 20,979.60 25,993.72 25,993.72
B.5 Project Billboard / Signboard 2.00 2.00 each 8,928.37 8,928.37 4,464.18 4,464.18 5,531.12 5,531.12
B.7(2) Occupational Safety and Health Program 1.00 1.00 ls 1,193,412.98 1,193,412.98 1,193,412.98 1,193,412.98 1,353,330.32 1,353,330.32
B.8(2) Traffic Management 1.00 1.00 ls 911,168.98 911,168.98 911,168.98 911,168.98 1,033,265.62 1,033,265.62
B.9 Mobilization / Demobilization 1.00 1.00 ls 337,376.00 337,376.00 337,376.00 337,376.00 354,244.80 354,244.80
PART C EARTHWORK
100(1) Clearing and Grubbing 0.24 0.24 ha 39,281.18 39,281.18 163,671.60 163,671.60 202,789.11 202,789.11
100(3)a3 Individual Removal of Trees, 501-750 mm dia. (Small) 1,680.00 1,680.00 each 12,593,764.81 12,593,764.81 7,496.29 7,496.29 9,287.90 9,287.90
101(1) Removal of Structures and Obstruction 1.00 1.00 ls 721,344.68 721,344.68 721,344.68 721,344.68 893,746.06 893,746.06
101(2) Removal of Actual Structures/Obstruction 28.00 28.00 each 72,092.66 72,092.66 2,574.74 2,574.74 3,190.10 3,190.10
11 of 3
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED
101(10) Removal of Existing Road Signs 20.00 20.00 each 19,548.12 19,548.12 977.41 977.41 1,211.01 1,211.01
102(2) Surplus Common Excavation 14,097.00 14,097.00 cu m 2,805,387.58 2,805,387.58 199.01 199.01 246.57 246.57
103(1)a Structure Excavation (Common soil) 383.60 383.60 cu m 90,125.19 90,125.19 234.95 234.95 291.10 291.10
103(3) Foundation Fill 39.10 39.10 cu m 50,545.22 50,545.22 1,292.72 1,292.72 1,601.68 1,601.68
103(6)a Pipe Culverts and Drain Excavation (Common soil) 194.30 194.30 cu m 45,649.96 45,649.96 234.95 234.95 291.10 291.10
104(1)a Embankment from Roadway Excavation (Common Soil) 8,916.00 8,916.00 cu m 2,078,400.09 2,078,400.09 233.11 233.11 288.82 288.82
105(1)a Subgrade Preparation (Common Material) 32,774.00 32,774.00 sq m 531,275.28 531,275.28 16.21 16.21 20.08 20.08
200(1) Aggregate Subbase Course 10,668.00 10,668.00 cu m 10,248,796.67 10,248,796.67 960.70 960.70 1,190.31 1,190.31
300(1) Gravel Surface Course 2,157.00 2,157.00 cu m 2,729,585.57 2,729,585.57 1,265.45 1,265.45 1,567.90 1,567.90
12 of 3
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED
404(1)a Reinforcing Steel , Grade 40 18,537.14 18,537.14 kg 963,953.42 963,953.42 52.00 52.00 64.43 64.43
405(1)a3 Structural Concrete, 20.68 MPa, Class "A", 28 days 192.10 192.10 cu m 1,245,030.01 1,245,030.01 6,481.16 6,481.16 8,030.15 8,030.15
500(1)b3 Pipe Culverts, 910 mm dia. Class IV RCPC 63.00 63.00 ln m 404,418.65 404,418.65 6,419.34 6,419.34 7,953.57 7,953.57
500(1)b5 Pipe Culverts, 1220 mm dia. Class IV RCPC 6.00 6.00 ln m 62,409.85 62,409.85 10,401.64 10,401.64 12,887.63 12,887.63
505(2)a Grouted Riprap, Class A 1,650.80 1,650.80 cu m 4,862,135.02 4,862,135.02 2,945.32 2,945.32 3,649.25 3,649.25
506(1) Stone Masonry 47.80 47.80 cu m 176,957.14 176,957.14 3,702.03 3,702.03 4,586.82 4,586.82
508 (1) Hand Laid Rock Embankment 8.00 8.00 cu m 11,250.74 11,250.74 1,406.34 1,406.34 1,742.46 1,742.46
511(1)a3 Gabions,1m x 1m x 2m, Metallic Coated 44.00 44.00 cu m 118,476.47 118,476.47 2,692.65 2,692.65 3,336.19 3,336.19
511(3) Filter Cloth 39.30 39.30 sq m 7,637.70 7,637.70 194.34 194.34 240.79 240.79
603(3)a1 Metal Guardrails (Metal Beam) Including Post, Single (W-Beam) 190.50 190.50 ln m 563,130.93 563,130.93 2,956.07 2,956.07 3,662.57 3,662.57
603(4)b Metal Beam End Piece (Bull Nose) 18.00 18.00 each 403,044.86 403,044.86 22,391.38 22,391.38 27,742.92 27,742.92
13 of 3
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED
605(2)a3 Regulatory Signs, 750mm x 750mm, R1-1C, Priority Signs Stop 1.00 1.00 each 6,502.43 6,502.43 6,502.43 6,502.43 8,056.51 8,056.51
605(6)e1 Hazard Markers, 450x600mm, Chevron Signs 18.00 18.00 each 176,759.55 176,759.55 9,819.98 9,819.98 12,166.95 12,166.95
611(1) Trees Furnishing and Transplanting 5,040.00 5,040.00 each 115,009.44 115,009.44 22.82 22.82 28.27 28.27
612(1) Reflectorized Thermoplastic Pavement Markings (White) 1,079.74 1,079.74 sq m 782,145.62 782,145.62 724.38 724.38 897.51 897.51
612(2) Reflectorized Thermoplastic Pavement Markings (Yellow) 1,008.24 1,008.24 sq m 737,085.25 737,085.25 731.06 731.06 905.78 905.78
622(2)c Cocologs/Fascine, CN300 128.40 128.40 ln m 73,284.79 73,284.79 570.75 570.75 707.16 707.16
622(3)b Vegetation, Vetiver Grass System 756.80 756.80 sq m 102,256.38 102,256.38 135.12 135.12 167.41 167.41
79,653,481.53
-
14 of 3
245,560.68
134,615.69 380,176.36
87,338.91
11,062.25
1,353,330.32
1,033,265.62
354,244.80 2,839,241.90
48,669.39
15,603,674.59
893,746.06
89,322.81
15 of 3
143,897.23
24,220.12
3,475,875.21
111,665.11
62,625.53
56,560.30
2,575,137.72
658,250.07 23,743,644.14
12,698,259.08 12,698,259.08
3,381,956.52
41,835,114.97 45,217,071.49
16 of 3
-
1,194,338.29
1,542,592.19 2,736,930.48
501,074.70
77,325.80
6,024,185.29
219,249.89
13,939.67 6,835,775.36
146,792.34
9,463.10
697,719.22
499,372.58
7,498.96
49,906.29
17 of 3
16,113.02
16,113.02
8,056.51
14,997.92
14,997.92
219,005.09
142,496.70
969,078.43
913,248.62
90,799.86
126,695.66
#REF!
98,391,735.99
#REF!
18 of 3
Department of Public Works and Highways (DPWH)
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
PART C EARTHWORK
Page 19 OF 4
QTY UNIT TOTAL DIRECT TOTAL MARK-UP 5% VAT TOTAL INDIRECT
ITEM NO. DESCRIPTION TOTAL COST UNIT COST
COST % VALUE COST
Page 20 OF 4
QTY UNIT TOTAL DIRECT TOTAL MARK-UP 5% VAT TOTAL INDIRECT
ITEM NO. DESCRIPTION TOTAL COST UNIT COST
COST % VALUE COST
Page 21 OF 4
QTY UNIT TOTAL DIRECT TOTAL MARK-UP 5% VAT TOTAL INDIRECT
ITEM NO. DESCRIPTION TOTAL COST UNIT COST
COST % VALUE COST
Page 22 OF 4
QTY UNIT TOTAL DIRECT TOTAL MARK-UP 5% VAT TOTAL INDIRECT
ITEM NO. DESCRIPTION TOTAL COST UNIT COST
COST % VALUE COST
Warning Signs 450 x 700 mm, W4-2PA, Road Width Sign Road AS EVALUATED 6.00 each 40,279.49 18 7,250.31 2,376.49 9,626.80 49,906.29 8,317.72
605 (1)u4 Narrows
AS SUBMITTED 6.00 each 40,279.49 18 7,250.31 2,376.49 9,626.80 49,906.29 8,317.72
Page 23 OF 4
QTY UNIT TOTAL DIRECT TOTAL MARK-UP 5% VAT TOTAL INDIRECT
ITEM NO. DESCRIPTION TOTAL COST UNIT COST
COST % VALUE COST
Page 24 OF 4
245,560.68
16,826.96
262,387.64
25,993.73
5,531.12
1,353,330.31
1,033,265.62
354,244.80
2,772,365.58
202,789.11
9,287.90
Page 25 OF 4
893,746.06
3,190.10
1,211.01
246.57
291.10
1,601.68
291.10
288.82
20.08
1,112,963.53
1,190.31
Page 26 OF 4
1,567.90
1,857.91
3,425.81
64.43
8,030.15
8,094.58
7,953.57
12,887.63
3,649.25
4,586.82
1,742.46
3,336.19
240.79
Page 27 OF 4
30,819.73
3,662.57
Page 28 OF 4
27,742.92
7,498.96
8,317.72
8,056.51
8,056.51
8,056.51
7,498.96
7,498.96
12,166.95
28.27
897.51
905.78
707.16
167.41
Page 29 OF 4
- 61,483.68
98,391,735.99
- 79,653,481.53
- 14,054,569.93 1190
1,718.05 4,683,684.53
98,357,375.07
Page 30 OF 4
Department of Public Works and Highways (DPWH)
FORM ABC-2015-02-00
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
Summary of ABC
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART A FACILITIES FOR THE ENGINEER
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 8.00% - - -
AS EVALUATED - - - - - - 8.00% - - -
AS SUBMITTED - 8.00% - - -
AS EVALUATED - - - - - - 8.00% - - -
AS SUBMITTED - 0.00% - - -
AS EVALUATED - - - - - - 0.00% - - -
AS SUBMITTED - - - - 18.00% - - -
TOTAL OF PART B
AS EVALUATED - - - - 18.00% - - -
PART C EARTHWORKS
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
32 of 218
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
AS EVALUATED - - - - - - 18.00% - - -
33 of 218
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - - - - 18.00% - - -
TOTAL OF PART C
AS EVALUATED - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - - - - 18.00% - - -
TOTAL OF PART D
AS EVALUATED - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - - - - 18.00% - - -
TOTAL OF PART E
AS EVALUATED - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - - - - 18.00% - - -
TOTAL OF PART F
34 of 218
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
TOTAL OF PART F
AS EVALUATED - - - - 18.00% - - -
35 of 218
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
AS SUBMITTED - 18.00% - - -
AS EVALUATED - 0 - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - 0 - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - 0 - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - 0 - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - 0 - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - 0 - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - 0 - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - 0 - - - - 18.00% - - -
AS SUBMITTED - - - - 18.00% - - -
TOTAL OF PART G
AS EVALUATED - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
36 of 218
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - 18.00% - - -
AS EVALUATED - - - - - - 18.00% - - -
AS SUBMITTED - - - - 18.00% - - -
TOTAL OF PART H
AS EVALUATED - - - - 18.00% - - -
37 of 218
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No. / Description : A.1.1(3) Construction of Field Office for the Engineer
Unit of Measurement : ls
Output per hour - As Submitted :
Output per hour - As Evaluated :
Quantity : 1.0 ls
Labor
A.1
Labor 1 ls 45,736.76 45,736.76
B.1 Equipment
Item No. / Description : A.1.1(16) Operation & Maintenance of Field Office for the Engineer
Unit of Measurement : mo
Output per hour - As Submitted :
Output per hour - As Evaluated :
Quantity : 8.0 mo
Labor
A.1
Utility man 1 1 9,702.00 9,702.00
B.1 Equipment
45,736.76
152,455.88
77,616.00
41,092.72
123,352.76 193,548.60 -
LABOR MATERIAL EQUIPMENT
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
DETAILED UNIT PRICE ANALYSIS (DUPA)
Unit of Measurement : km
Output per hour - As Submitted :
Output per hour - As Evaluated :
Quantity : 3.360 km
Labor
Instrumentman 2 2 875.52 3,502.08
A.1
surveyman 4 2 875.52 7,004.16
laborer 3 2 488.56 2,931.36
Materials
2 x 2 x 8 coco lumber=70 pcs bd dt 300 12.00 3,600.00
F.1
paint gal 6 614.00 3,684.00
Field books pcs 6 43.00 258.00
Labor
A.1 a. Safety Practitioner/Officer (Full time) 1 280 875.52 245,460.79
b. Health Personnel (Full time First Aider) 1 280 633.36 177,568.81
c. Sanitation aide 2 280 488.56 273,945.36
Sub - Total for A.1 - As Submitted 696,974.96
Labor
a. Safety Practitioner/Officer (Full time) 1 280 875.52 245,460.79
A.2 b. Health Personnel (Full time First Aider) 1 280 633.36 177,568.81
c. Sanitation aide 2 280 488.56 273,945.36
Sub - Total for A.2 - As Evaluated 696,974.96
Name and Capacity No. of Unit/s No. of hrs Monthly Rate Amount (Php)
Equipment
a. Portable Mist-Based Sanitation Tent 1 2242.88 9.79 21,957.80
B.1 b. Thermal Scanner (w/ rechargeable battery) 2 2242.88 1.03 4,620.33
c. Power Sprayer with complete accessories 1 2242.88 3.47 7,782.79
Unit of Measurement : ls
Output per hour - As Submitted :
Output per hour - As Evaluated :
Quantity : 1.00 ls
Materials
LAY OUT 5
Roadwork ahead(T1-1) ea 8 3285.00 26,280.00
Workmen Ahead(T1-5) ea 8 1692.00 13,536.00
Lane Status (T2-6-1) ea 8 2658.00 21,264.00
F.1
Temporary hazard Marker (chevron T5-5) ea 10 2403.00 24,030.00
Traffic Cones @ 5 meters span ea 150 555.00 83,250.00
Materials
Roadwork ahead(T1-1) ea 8 3285.00 26,280.00
Workmen Ahead(T1-5) ea 8 1692.00 13,536.00
Lane Status (T2-6-1) ea 8 2658.00 21,264.00
F.2 Temporary hazard Marker (chevron T5-5) ea 10 2403.00 24,030.00
Traffic Cones @ 5 meters span ea 150 555.00 83,250.00
45,150.34
25,341.12
3,994.88
399.49
4,534.00
696,974.96
462,077.10
273,945.36
300
(98,391,735.99)
468,863.62
29,283,254.76
168,360.00
29,283,254.76
337,376.00
1,020,065.54 660,312.22 806,639.10
LABOR MATERIAL EQUIPMENT
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
Unit of Measurement : ha
Output per hour - As Submitted : 0.05
Output per hour - As Evaluated : 0.05
Quantity : 0.24 ha
Item No. / Description : 100(3)a3 Individual Removal of Trees, 501-750 mm dia. (Small)
Unit of Measurement : ls
Output per hour - As Submitted : 1
Output per hour - As Evaluated : 1
Quantity : 1.00 ls
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
B.2
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
Unit of Measurement : sq m
Output per hour - As Submitted : 40
Output per hour - As Evaluated : 40
Quantity : 989.30 sq m
Engineer II Engineer IV
Unit of Measurement : cu m
Output per hour - As Submitted : 80
Output per hour - As Evaluated : 80
Quantity : 14,097.00 cu m
Unit of Measurement : cu m
Output per hour - As Submitted : 20
Output per hour - As Evaluated : 20
Quantity : 383.60 cu m
Unit of Measurement : cu m
Output per hour - As Submitted : 1.25
Output per hour - As Evaluated : 1.25
Quantity : 39.10 cu m
Item No. / Description : 103(6)a Pipe Culverts and Drain Excavation (Common soil)
Unit of Measurement : cu m
Output per hour - As Submitted : 20
Output per hour - As Evaluated : 20
Quantity : 194.30 cu m
Item No. / Description : 104(1)a Embankment from Roadway Excavation (Common Soil)
Unit of Measurement : cu m
Output per hour - As Submitted : 50
Output per hour - As Evaluated : 50
Quantity : 8,916.00 cu m
A.2
Spreading and Compaction
a. Construction Foreman 1 1 109.44 109.44
b. Unskilled Labor 2 1 61.07 122.14
B.2
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
B.2
Spreading and Compaction:
a. Motorized Road Grader, (140hp),G710A 1 1.00 2173.00 2,173.00
b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1846.00 1,846.00
c. Water Truck/Pump(16000 L) 1 0.25 2450.00 612.50
Unit of Measurement : sq m
Output per hour - As Submitted : 300
Output per hour - As Evaluated : 300
Quantity : 32,774.00 sq m
1,111.58
38,169.60
1,738,459.80
10,737,705.01
117,600.00
-98391735.9871388
62.631
116.51
1 3
2 3
4 3
4
4
267,761.60
24.5 98
12.25
14.5
128
453,583.08
0.096
0.128
0.224
c 1.68
6,484.24
65,608.42
5,727.55
110,412.26
7,074.40
12,473.72
40,807.29
2,764,580.29
5,613.03
84,512.16
469.89
375.91
42.290235
11,064.36
5,720.24
33,760.62
2,843.09
42,806.86
75,570.48
2,002,829.61
-
25,299.34
505,975.94
-
Unit of Measurement : cu m
Output per hour - As Submitted : 50
Output per hour - As Evaluated : 50
Quantity : 10,668.00 cu m
Labor
A.1 a. Construction Foreman 1 1 109.44 109.44
b. Unskilled Labor 2 1 61.07 122.14
Equipment
a. Motorized Road Grader (140 HP), G710A 1 1.00 2,173.00 2,173.00
B.1
b. Vibratory Roller (10 mt), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50
Materials
F.1
a. Aggregate Subbase Course( w/ 15% Shrinkage Factor) cu.m. 1.15 750.82 863.44
49,409.91
988,176.84
9,211,209.92
49,409.91 9,211,209.92 988,176.84 10,248,796.67
LABOR MATERIAL EQUIPMENT 10,248,796.67
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
DETAILED UNIT PRICE ANALYSIS (DUPA)
Unit of Measurement : cu m
Output per hour - As Submitted : 50
Output per hour - As Evaluated : 50
Quantity : 2,157.00 cu m
Engineer II Engineer IV
Item No. / Description : 311(1)e1 Portland Cement Concrete Pavement (Unreinforced), 0.28 m thick, 14 days
Unit of Measurement : sq m
Output per hour - As Submitted : 57.50
Output per hour - As Evaluated : 57.50
Quantity : 22,517.26 sq m
Materials
a. Reinforcing Steel Bar kg 0.50 41.27 20.64
b. Curing Compound L 0.29 95.00 27.55
c. Asphalt Sealant L 0.17 47.00 7.99
d. Steel Forms (Rental) m 0.46 78.00 35.88
F.2 d. Sand m³ 0.154 985.82 151.82
e. Gravel m³ 0.28 1095.82 306.83
f. Cement bag 2.79 255.90 714.73
g. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015 8000.00 1.20
h. Pipe Sleeve, 2" Ø m 0.0078 97.00 0.76
i. Grease/Tar L 0.0078 300.00 2.34
Prepared by: .
199,802.91
2,519,792.30
453,853.98
4,720,617.46
28,590,754.52
Item No. / Description : 405(1)a3 Structural Concrete, 20.68 MPa, Class "A", 28 days
Unit of Measurement : cu m
Output per hour - As Submitted : 1.4
Output per hour - As Evaluated : 1.4
Quantity : 192.10 cu m
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL
Materials
a. Lumber, Good - 4 uses bd.ft. 70.00 27.00 472.50
b. Marine Plywood (1/2" x 4' x 8') - 4 uses pc. 1.60 705.00 282.00
F.2 c. Assorted CWN (1kg./100 bd.ft. of Lumber) kg. 0.70 77.00 53.90
d. Cement bag 9.50 255.90 2,431.05
e. Sand cu.m 0.50 985.82 492.91
f. Gravel cu.m 1.00 1095.82 1,095.82
77,891.00
48,137.35
837,925.07
LABOR MATERIAL EQUIPMENT
235,997.59
81,539.04
LABOR MATERIAL EQUIPMENT
927,493.38
LABOR MATERIAL EQUIPMENT
Item No. / Description : 500(1)b3 Pipe Culverts, 910 mm dia. Class IV RCPC
Unit of Measurement : ln m
Output per hour - As Submitted : 1
Output per hour - As Evaluated : 1
Quantity : 63.00 ln m
Labor
A.1 a. Construction Foreman 1 0.57 109.44 62.38
b. Skilled Labor 2 0.57 79.17 90.25
c. Unskilled Labor 4 0.57 61.07 139.24
Sub - Total for A.1 - As Submitted 291.87
Labor
a. Construction Foreman 1 0.57 109.44 62.38
A.2 b. Skilled Labor 2 0.57 79.17 90.25
c. Unskilled Labor 4 0.57 61.07 139.24
Sub - Total for A.2 - As Evaluated 291.87
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
Equipment
B.1 a. Backhoe (0.80 m³) 1 0.29 1537.00 445.73
b. Plate Compactor (5 hp) 1 0.29 123.00 35.67
Minor Tools (10% of Labor) 29.19
Sub - Total for B.1 - As Submitted 510.59
Equipment
a. Backhoe (0.80 m³) 1 0.29 1537.00 445.73
B.2 b. Plate Compactor (5 hp) 1 0.29 123.00 35.67
Minor Tools (10% of Labor) 29.19
Sub - Total for B.2 - As Evaluated 510.59
C.1 Total (A.1 + B.1) - As Submitted 802.46
C.2 Total (A.2 + B.2) - As Evaluated 802.46
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 802.46
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 802.46
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Cement bag 1.08 255.90 276.37
F.1 b. Sand cu.m. 0.061 985.82 60.14
c. RC Pipes (910 mm Ø) pc 1 5154.19 5,154.19
d. Sand Bedding/Selected Sandy Soil cu.m. 0.128 985.82 126.18
Sub - Total for F.1 - As Submitted 5,616.88
Materials
a. Cement bag 1.08 255.90 276.37
b. Sand cu.m. 0.061 985.82 60.14
F.2
c. RC Pipes (910 mm Ø) pc 1 5154.19 5,154.19
d. Sand Bedding/Selected Sandy Soil cu.m. 0.128 985.82 126.18
Sub - Total for F.2 - As Evaluated 5,616.88
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 6,419.34
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 6,419.34
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 641.93
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 641.93
I.1 Contractor's Profit (CP) - As Submitted 8% 513.55
I.2 Contractor's Profit (CP) - As Evaluated 8% 513.55
J.1 Value Added Tax (VAT) - As Submitted 5% 378.74
J.2 Value Added Tax (VAT) - As Evaluated 5% 378.74
K.1 Total Unit Cost - As Submitted 7,953.57
K.2 Total Unit Cost - As Evaluated 7,953.57
Item No. / Description : 500(1)b5 Pipe Culverts, 1220 mm dia. Class IV RCPC
Unit of Measurement : ln m
Output per hour - As Submitted : 1
Output per hour - As Evaluated : 1
Quantity : 6.00 ln m
Labor
A.1 a. Construction Foreman 1 0.8 109.44 87.55
b. Skilled Laborer 2 0.8 79.17 126.67
c. Laborer 4 0.8 61.07 195.42
Sub - Total for A.1 - As Submitted 409.65
Labor
a. Construction Foreman 1 0.8 109.44 87.55
A.2 b. Skilled Laborer 2 0.8 79.17 126.67
c. Laborer 4 0.8 61.07 195.42
Sub - Total for A.2 - As Evaluated 409.65
Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
B.1 a. Backhoe (0.80 m³) 1 0.40 1537.00 614.80
b. Plate Compactor (5 hp) 1 0.40 123.00 49.20
Minor Tools (10% of Labor) 40.96
Sub - Total for B.1 - As Submitted 704.96
Equipment
a. Backhoe (0.80 m³) 1 0.40 1537.00 614.80
B.2 b. Plate Compactor (5 hp) 1 0.40 123.00 49.20
Minor Tools (10% of Labor) 40.96
Sub - Total for B.2 - As Evaluated 704.96
C.1 Total (A.1 + B.1) - As Submitted 1,114.61
C.2 Total (A.2 + B.2) - As Evaluated 1,114.61
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 1,114.61
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 1,114.61
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Cement bag 1.404 255.90 359.28
F.1 b. Sand cu.m. 0.08 985.82 78.87
c. RC Pipes (1220 mm Ø) pc 1 8681.29 8,681.29
d. Sand Bedding/Selected Sandy Soil cu.m. 0.17 985.82 167.59
Labor
A.1 a. Construction Foreman 1 1.00 109.44 109.44
b. Skilled Labor 2 1.00 79.17 158.34
c. Unskilled Labor 8 1.00 61.07 488.56
Sub - Total for A.1 - As Submitted 756.34
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.2 b. Skilled Labor 2 1.00 79.17 158.34
c. Unskilled Labor 8 1.00 61.07 488.56
Sub - Total for A.2 - As Evaluated 756.34
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
Equipment
B.1 a. One Bagger Mixer 1 1.00 172.00 172.00
b. Water Truck/ Pump (16000 L) 1 0.05 2450.00 122.50
Minor Tools (5% of Labor Cost) 37.82
Sub - Total for B.1 - As Submitted 332.32
Equipment
a. One Bagger Mixer 1 1.00 172.00 172.00
B.2 b. Water Truck/ Pump (16000 L) 1 0.05 2450.00 122.50
Minor Tools (5% of Labor Cost) 37.82
Sub - Total for B.2 - As Evaluated 332.32
C.1 Total (A.1 + B.1) - As Submitted 1,088.66
C.2 Total (A.2 + B.2) - As Evaluated 1,088.66
D.1 Output per hour - As Submitted 1.25
D.2 Output per hour - As Evaluated 1.25
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 870.93
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 870.93
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Cement bag 3.00 255.90 767.70
b. Sand cu.m. 0.25 985.82 246.46
c. Gravel Fill cu.m. 0.015 1095.82 16.44
F.1 d. Weep Holes (PVC) m 0.30 144.67 43.40
e. Filter Cloth m² 0.015 175.00 2.63
f. Boulders (15 - 25 kg) cu.m. 0.90 1085.82 977.24
268 cum to be utilize from grouted riprap removal
Miscellaneous (1% of Materials Cost) 20.54
Sub - Total for F.1 - As Submitted 2,074.39
Materials
a. Cement bag 3.00 255.90 767.70
b. Sand cu.m. 0.25 985.82 246.46
c. Gravel Fill cu.m. 0.02 1095.82 16.44
d. Weep Holes (PVC) m 0.30 144.67 43.40
e. Filter Cloth m² 0.02 175.00 2.63
f. Boulders (15 - 25 kg) cu.m. 0.90 1085.82 977.24
Miscellaneous (1% of Materials Cost) 20.54
Sub - Total for F.2 - As Evaluated 2,074.39
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 2,945.32
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 2,945.32
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 294.53
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 294.53
I.1 Contractor's Profit (CP) - As Submitted 8% 235.63
I.2 Contractor's Profit (CP) - As Evaluated 8% 235.63
J.1 Value Added Tax (VAT) - As Submitted 5% 173.77
J.2 Value Added Tax (VAT) - As Evaluated 5% 173.77
K.1 Total Unit Cost - As Submitted 3,649.25
K.2 Total Unit Cost - As Evaluated 3,649.25
Materials
a. Cement bag 5.50 255.90 1,407.45
b. Sand cu.m 0.30 985.82 295.75
F.1 c. Gravel Fill cu.m 0.02 1095.82 21.92
d. Weep Holes (PVC) m 0.30 144.67 43.40
e. Filter Cloth sq.m 0.015 175.00 2.63
f. Boulders cu.m 1.05 1085.82 1,140.11
Miscellaneous (1% of Materials Cost) 29.11
Sub - Total for F.1 - As Submitted 2,940.36
Materials
a. Cement bag 5.50 255.90 1,407.45
b. Sand cu.m 0.30 985.82 295.75
c. Gravel Fill cu.m 0.02 1095.82 21.92
d. Weep Holes (PVC) m 0.30 144.67 43.40
e. Filter Cloth sq.m 0.02 175.00 2.63
f. Boulders cu.m 1.05 1085.82 1,140.11
Miscellaneous (1% of Materials Cost) 29.11
Sub - Total for F.2 - As Evaluated 2,940.36
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 3,702.03
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 3,702.03
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 370.20
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 370.20
I.1 Contractor's Profit (CP) - As Submitted 8% 296.16
I.2 Contractor's Profit (CP) - As Evaluated 8% 296.16
J.1 Value Added Tax (VAT) - As Submitted 5% 218.42
J.2 Value Added Tax (VAT) - As Evaluated 5% 218.42
K.1 Total Unit Cost - As Submitted 4,586.82
K.2 Total Unit Cost - As Evaluated 4,586.82
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL
Unit of Measurement : cu m
Output per hour - As Submitted : 3.125
Output per hour - As Evaluated : 3.125
Quantity : 8.00 cu m
Equipment
B.1
Minor Tools (10% of Labor Cost) 75.63
Materials
F.1
a. Boulders cu.m. 1.05 1085.82 1,140.11
Unit of Measurement : cu m
Output per hour - As Submitted : 2.5
Output per hour - As Evaluated : 2.5
Quantity : 44.00 cu m
Labor
a. Construction Foreman 1 1 109.44 109.44
A.1 b. Skilled Laborer 2 1 79.17 158.34
c. Laborer 8 1 61.07 488.56
Equipment
B.1
Engineer II Engineer IV
Unit of Measurement : sq m
Output per hour - As Submitted : 100
Output per hour - As Evaluated : 100
Quantity : 39.30 sq m
Materials
a. Filter Cloth sq.m 1.05 175.00 183.75
F.1
Miscellaneous (5% of Materials Cost)
18,388.07
32,167.01
353,863.56
2,457.89
4,229.79
55,722.17
998,852.86
438,871.12
3,424,411.04
22,595.66
13,812.23
140,549.25
1,936.23
193.62
9,120.89
13,311.58
105,164.88
297.24
119.08
7,221.38
1,057,839.53 4,096,053.17 489,392.85 5,643,285.56
LABOR MATERIAL EQUIPMENT 5,643,285.56
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL
Item No. / Description : 603(3)a1 Metal Guardrails (Metal Beam) Including Post, Single (W-Beam)
Unit of Measurement : ln m
Output per hour - As Submitted : 4.20
Output per hour - As Evaluated : 4.20
Quantity : 190.50 ln m
Labor
Equipment
a. Cargo Truck (10 T) 1 0.25 1,212.00 303.00
B.1
Minor Tools (5% of Labor Cost) 25.60
Materials
F.1 a. Metal Guardrails (Metal Beam) Including Post m 1.00 2,755.91 2,755.91
and other accessories
Item No. / Description : 603(4)b Metal Beam End Piece (Bull Nose)
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.1
b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Equipment
a. Cargo Truck (9 - 10 mt) 1 1.00 1,212.00 1,212.00
B.1
Minor Tools(5% of Labor Cost) 15.54
Materials
F.1 a. Metal Beam End Piece bull nose including accessories ea 1.00 22,135.00 22,135.00
Item No. / Description : 605 (1)u4 Warning Signs 450 x 700 mm, W4-2PA, Road Width Sign Road Narrows
Labor
A.1 a. Construction Foreman 1 1.00 109.44 109.44
b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Sub - Total for A.1 - As Submitted 310.75
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.2 b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Sub - Total for A.2 - As Evaluated 310.75
Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
B.1
a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
Minor Tools (10% of Labor Cost)
Sub - Total for B.1 - As Submitted 195.75
Equipment
a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
B.2
Minor Tools (10% of Labor Cost)
Sub - Total for B.2 - As Evaluated 195.75
C.1 Total (A.1 + B.1) - As Submitted 506.50
C.2 Total (A.2 + B.2) - As Evaluated 506.50
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 506.50
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 506.5
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Portland Cement bag 0.48 255.9 122.83
b. Sand m³ 0.025 985.82 24.65
c. Gravel m³ 0.050 1095.82 54.79
F.1 d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
e. 3" Ø GI Pipe m 3.10 492.58 1,527.01
f. Plate kg 2.00 48.00 96.00
g. Bolts, 5 mm Ø pc 12.00 10.00 120.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00 4200.00 4,200.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 93.40 7.47
Sub - Total for F.1 - As Submitted 6,206.75
Materials
a. Portland Cement bag 0.48 255.90 122.83
b. Sand m³ 0.03 985.82 24.65
c. Gravel m³ 0.05 1095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
e. 3" Ø GI Pipe m 3.10 492.58 1,527.01
f. Plate kg 2.00 48.00 96.00
g. Bolts, 5 mm Ø pc 12.00 10.00 120.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00 4200.00 4,200.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 93.40 7.47
Sub - Total for F.2 - As Evaluated 6,206.75
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 6,713.25
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 6,713.25
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 671.32
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 671.32
I.1 Contractor's Profit (CP) - As Submitted 8% 537.06
I.2 Contractor's Profit (CP) - As Evaluated 8% 537.06
J.1 Value Added Tax (VAT) - As Submitted 5% 396.08
J.2 Value Added Tax (VAT) - As Evaluated 5% 396.08
K.1 Total Unit Cost - As Submitted 8,317.72
K.2 Total Unit Cost - As Evaluated 8,317.72
Labor
Equipment
Materials
Materials
a. Portland Cement bag 0.48 255.90 122.83
b. Sand cu.m 0.025 985.82 24.65
c. Gravel cu.m 0.05 1,095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
F.2 e. 75mm Ø GI Pipe m 3.25 492.58 1,600.90
f. GI Flat Bar, 1 1/2"x1/8" kg 5.00 48.00 240.00
g. GI Bolts w/ Nuts & Washer, 5 mm Ø pc 3.00 10.00 30.00
h. GI Bolts w/ Nuts & Washer, 2 mm Ø pc 12.00 10.00 120.00
i. Sign Face, 3 mm thk Aluminum Sheet pc 2.00 3,500.00 7,000.00
j. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 93.40 7.47
Miscellaneous (0.3% of Materials Cost) 27.76
Labor
A.1 a. Construction Foreman 1 1 109.44 109.44
c. Unskilled Labor 2 1 61.07 122.14
Equipment
B.1
a. Cargo Truck (9 - 10 mt) 1 0.25 1212.00 303.00
Unit of Measurement : sq m
Output per hour - As Submitted : 25
Output per hour - As Evaluated : 25
Quantity : 1,079.74 sq m
Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)
Labor
A.1 a. Construction Foreman 1 1 109.44 109.44
b. Skilled laborer 2 1 79.17 158.34
c. Laborer 6 1 61.07 366.42
Sub - Total for A.1 - As Submitted 634.20
Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 b. Skilled laborer 2 1 79.17 158.34
c. Laborer 6 1 61.07 366.42
Sub - Total for A.2 - As Evaluated 634.20
Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
a. Cargo Truck/Delivery Truck (2 - 5 mt) 1 1.00 783.00 783.00
B.1
b. Applicator Machine 1 1.00 93.75 93.75
c. Kneading Machine 1 1.00 187.50 187.50
Minor Tools (10% of Labor) 63.42
Sub - Total for B.1 - As Submitted 1,127.67
Equipment
a. Cargo Truck/Delivery Truck (2 - 5 mt) 1 1.00 783.00 783.00
b. Applicator Machine 1 1.00 93.75 93.75
B.2
c. Kneading Machine 1 1.00 187.50 187.50
Minor Tools (10% of Labor) 63.42
Sub - Total for B.2 - As Evaluated 1,127.67
C.1 Total (A.1 + B.1) - As Submitted 1,761.87
C.2 Total (A.2 + B.2) - As Evaluated 1,761.87
D.1 Output per hour - As Submitted 25.00
D.2 Output per hour - As Evaluated 25.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 70.47
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 70.47
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Thermoplastic Paint (White) bag 0.325 1585.00 515.13
b. Glass Beads bag 0.033 2310.00 76.23
F.1 c. Primer L 0.120 72.00 8.64
d. LPG (50 kg) cyl 0.004 5000.00 20.00
e. LPG (12 kg) cyl 0.002 1200.00 2.40
f. Calsumine kg 0.125 3.00 0.38
Miscellaneous (5% of Materials Cost) 31.14
Sub - Total for F.1 - As Submitted 653.91
Materials
a. Thermoplastic Paint (White) bag 0.325 1585.00 515.13
b. Glass Beads bag 0.033 2310.00 76.23
c. Primer L 0.120 72.00 8.64
d. LPG (50 kg) cyl 0.004 5000.00 20.00
e. LPG (12 kg) cyl 0.002 1200.00 2.40
f. Calsumine kg 0.125 3.00 0.38
Miscellaneous (5% of Materials Cost) 31.14
Sub - Total for F.2 - As Evaluated 653.91
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 724.38
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 724.38
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 72.44
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 72.44
I.1 Contractor's Profit (CP) - As Submitted 8% 57.95
I.2 Contractor's Profit (CP) - As Evaluated 8% 57.95
J.1 Value Added Tax (VAT) - As Submitted 5% 42.74
J.2 Value Added Tax (VAT) - As Evaluated 5% 42.74
K.1 Total Unit Cost - As Submitted 897.51
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL
Unit of Measurement : sq m
Output per hour - As Submitted : 25
Output per hour - As Evaluated : 25
Quantity : 1,008.24 sq m
Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)
Labor
A.1 a. Construction Foreman 1 1 109.44 109.44
b. Skilled laborer 2 1 79.17 158.34
c. Laborer 6 1 61.07 366.42
Sub - Total for A.1 - As Submitted 634.20
Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 b. Skilled laborer 2 1 79.17 158.34
c. Laborer 6 1 61.07 366.42
Sub - Total for A.2 - As Evaluated 634.20
Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
a. Cargo Truck/Delivery Truck (2 - 5 mt) 1 1.00 783.00 783.00
B.1
b. Applicator Machine 1 1.00 93.75 93.75
c. Kneading Machine 1 1.00 187.50 187.50
Minor Tools (10% of Labor) 63.42
Sub - Total for B.1 - As Submitted 1,127.67
Equipment
a. Cargo Truck/Delivery Truck (2 - 5 mt) 1 1.00 783.00 783.00
b. Applicator Machine 1 1.00 93.75 93.75
B.2
c. Kneading Machine 1 1.00 187.50 187.50
Minor Tools (10% of Labor) 63.42
Sub - Total for B.2 - As Evaluated 1,127.67
C.1 Total (A.1 + B.1) - As Submitted 1,761.87
C.2 Total (A.2 + B.2) - As Evaluated 1,761.87
D.1 Output per hour - As Submitted 25.00
D.2 Output per hour - As Evaluated 25.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 70.47
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 70.47
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Thermoplastic Paint (Yellow) bag 0.325 1585.00 515.13
b. Glass Beads bag 0.033 2310.00 76.23
F.1 c. Primer L 0.120 125.00 15.00
d. LPG (50 kg) cyl 0.004 5000.00 20.00
e. LPG (12 kg) cyl 0.002 1200.00 2.40
f. Calsumine kg 0.125 3.00 0.38
Miscellaneous (5% of Materials Cost) 31.46
Sub - Total for F.1 - As Submitted 660.59
Materials
a. Thermoplastic Paint (Yellow) bag 0.325 1585.00 515.13
b. Glass Beads bag 0.033 2310.00 76.23
c. Primer L 0.120 125.00 15.00
d. LPG (50 kg) cyl 0.004 5000.00 20.00
e. LPG (12 kg) cyl 0.002 1200.00 2.40
f. Calsumine kg 0.125 3.00 0.38
Miscellaneous (5% of Materials Cost) 31.46
Sub - Total for F.2 - As Evaluated 660.59
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 731.06
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 731.06
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 73.11
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 73.11
I.1 Contractor's Profit (CP) - As Submitted 8% 58.48
I.2 Contractor's Profit (CP) - As Evaluated 8% 58.48
J.1 Value Added Tax (VAT) - As Submitted 5% 43.13
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL
Unit of Measurement : ln m
Output per hour - As Submitted : 15
Output per hour - As Evaluated : 15
Quantity : 128.40 ln m
Unit of Measurement : sq m
Output per hour - As Submitted : 35
Output per hour - As Evaluated : 35
Quantity : 756.80 sq m
14,904.49
525,000.86
932.25
3,682.61
398,430.00
310.75
195.75
5,545.93
1,864.50
1,174.50
37,240.49
621.50
391.50
11,991.86
621.50
391.50
11,991.86
310.75
195.75
5,995.93
621.50
391.50
11,091.86
621.50
391.50
11,091.86
5,593.50
4,082.85
167,083.20
38,905.44
50,904.00
25,200.00
27,390.84
48,703.62
706,051.16
25,577.03
45,478.48
666,029.73
5,118.88
511.89
67,654.02
12,930.47
27,781.05
61,544.87
FORMULA : T = D ÷ R
FORMULA : T = D ÷ R
EQUIPMENT/LABOR
TOTAL 2,725.17
FORMULA : T = D ÷ R
EQUIPMENT/LABOR
TOTAL 2,725.17
FORMULA : T = D ÷ R
EQUIPMENT/LABOR
TOTAL 2,725.17
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
FORMULA : T = D ÷ R
EQUIPMENT/LABOR
FORMULA : T = D ÷ R
TOTAL 2,725.17
681.29 / lm
FORMULA : T = D ÷ R
EQUIPMENT/LABOR
FORMULA : T = D ÷ R
EQUIPMENT/LABOR
TOTAL 2,725.17
FORMULA : T = D ÷ R
EQUIPMENT/LABOR
TOTAL 2,725.17
FORMULA : T = D ÷ R
Formula:
( Dh - Dl ) ( Ap - Al )
C.D. = + Dl
( Ah - Al )
where:
Dh = Reference Duration (Higher) = 225 C.D.
Dl = Reference Duration (Lower) = 198 C.D.
Ah = Reference Amount (Higher) = 150.000 Million
Al = Reference Amount (Lower) = 100.000 Million
MONTH JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC TOTAL
CALENDAR DAYS 31 29 31 30 31 30 31 31 30 6 280
SUNDAYS 4 5 4 4 5 4 4 5 4 4 43
RAINY DAYS 1 1 1 1 1 1 1 1 1 1 10
HOLIDAYS 2 1 0 3 1 1 1 2 11
NET WORKING DAYS 24 22 26 22 24 24 25 23 25 1 216
No. of pre-determined
unworkable days = 64 C.D.
=
F. E / A ### 661
G. F x C ### ###
8.73
6
25
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
A.1.1(16) Operation & Maintenance of Field Office for the Engineer mo 8.00
PART C EARTHWORK
100(3)a3 Individual Removal of Trees, 501-750 mm dia. (Small) each 1,680.00 1,680.00
101(1) Removal Structures and Obstruction ls 1.00 1.00 Grouted riprap lined canal = 1225.06 cu.m.
101(2) Removal of Actual Structures/Obstruction each 28.00 28.00 headwall=22 each ; wingwall = 2 each
Removal of Actual Structure/Obstruction, 0.23m thick PCCP
101(3)b3 sq m 989.30 989.30 Concrete Pavement
(Unreinforced)
101(10) Removal of Existing Road Signs each 20.00 20.00
103(1)a Structure Excavation (Common Soil) cu m 383.60 383.60 for RCBC and RCPC
103(6)a Pipe Culverts and Drain Excavation (Common soil) cu m 194.30 194.30 for RCBC, RCPC and Grouted Riprap Lined Canal
405(1)a3 Structural Concrete, 20.68 MPa, Class "A", 28 days ln m 192.10 192.10
603(3)a1 Metal Guardrail (Metal Beam) Including Post, Single, W-Beam ln m 190.50 190.50
603(4)b Metal Beam End Piece (Bull Nose) each 18.00 18.00
245,560.68 245,560.68
16,826.96 134,615.69
25,993.72 87,338.91
5,531.12 11,062.25
1,353,330.32 1,353,330.32
1,033,265.62 1,033,265.62
354,244.80 354,244.80
202,789.11 48,669.39 -
9,287.90 15,603,674.59 -
893,746.06 - 893,746.06
3,190.10 - 89,322.81
145.45 143,897.23 -
1,211.01 24,220.12 -
246.57 3,475,875.21 -
291.10 - 111,665.11
1,601.68 - 62,625.53
291.10 - 56,560.30
288.82 2,575,137.72 -
20.08 658,250.07 -
- -
- -
1,190.31 12,698,259.08 -
- -
- -
1,567.90 3,381,956.52 -
1,857.91 41,835,114.97 -
- -
- -
64.43 - 1,194,338.29
8,030.15 - 1,542,592.19
- -
- -
7,953.57 - 501,074.70
12,887.63 - 77,325.80
3,649.25 - 6,024,185.29
4,586.82 - 219,249.89
1,742.46 - 13,939.67
3,336.19 - 146,792.34
240.79 - 9,463.10
- -
- -
3,662.57 697,719.22 -
27,742.92 499,372.58 -
7,498.96 7,498.96 -
8,317.72 49,906.29 -
8,056.51 16,113.02 -
8,056.51 16,113.02 -
8,056.51 8,056.51 -
7,498.96 14,997.92 -
7,498.96 14,997.92 -
12,166.95 219,005.09 -
28.27 142,496.70 -
897.51 969,078.43 -
905.78 913,248.62 -
707.16 - 90,799.86
167.41 - 126,695.66
Total : 98,393,454.03
POW: 98,391,735.99
1,718.05
LABOR RATES (June 2019)
RESOURCE CODE BASIC WAGE
NO. DESCRIPTION LABOR COST FACTOR LEAVES 13 MONTH PAY
DAILY MONTHLY
1 Foreman 1.80 712.80 18,592.20 712.80 1,549.35
7 Skilled Laborer 1.30 514.80 13,427.70 514.80 1,118.98
9 Unskilled Laborer 1.00 396.00 10,329.00 396.00 860.75
1. Earthmoving Equipment
1.1 Bulldozer D6H SERIES II PSDS/DD 165.00 3,379.00
1.2 Bulldozer w/ Ripper D6H SERIES II PSDS/DD 165.00 3,885.85
1.3 Payloader LX80-2C 1.50 m³/1.95 yd³ 110.00 1,733.00
1.4 Motorized Road Grader G710A 140.00 2,173.00
1.5 Road Grader w/ Scarifier G710A 140.00 2,824.90
2. Compaction Equipment
2.1 Pneumatic Tire Roller 9-WHL, 9.00X20, 4PR 10 mt 107.00 561.00
2.2 Vibratory Roller SD100DC 10 mt 125.00 1,846.00
2.3 Tandem Steel Roller CC421 10.10 mt 123.40 1,652.00
2.4 Plate Compactor 400-500 Gasoline Engine 5.00 123.00
3. Lifting Equipment
3.1 Crawler Crane All Models 36-40 mt 190.00 1,902.00
3.2 Truck Mounted Crane All Models 31-35 mt 238.00 1,861.00
3.3 Truck Mounted Crane All Models 41-45 mt 246.00 2,606.00
4. Excavating Equipment
4.1 Backhoe SE 130 LC-2 0.80 m³/1.04 yd³ 99.00 1,537.00
4.2 Backhoe w/ Breaker SE 130 LC-2 0.80 m³/1.04 yd³ 99.00 1,998.10
4.3 Backhoe, Wheel Mounted PW60N-1 0.28 m³/0.37 yd³ 50.00 922.00
5. Foundation Equipment
5.1 Vibro Hammer DPD600T Hydraulic Pile Driver 60 ton 201.00 2,123.00
6. Asphalting Equipment
6.1 Asphalt Distributor ROSCO/5 ton 3000 USG 100.00 936.00
6.2 Asphalt Paver NF220BIIVDM 80.00 1,833.00
7. Concreting Equipment
7.1 Concrete Screeder Wacker Truss Screed 5.50 545.00
7.2 Concrete Paver COMMANDER III, FOUR-TRACK 6,765.00
7.3 One Bagger Mixer 4-6 ft³/min 172.00
7.4 Transit Mixer All Models 5-6 yd³ 175.00 1,318.00
8. Hauling Equipment
8.1 Dumptruck All Models 12 yd³ 290.00 1,420.00
8.2 Cargo/Service Truck All Models 2-5 mt 160.00 783.00
8.3 Boom Truck All Models 2-5 mt 160.00 1,017.90
8.4 Cargo/Service Truck All Models 9-10 mt 270.00 1,212.00
8.5 Water Truck/Pump All Makes 16000 L 360.00 2,450.00
9. Air Equipment
9.1 Air Compressor All Models 356-450 cfm 130.00 965.00
9.2 Air Compressor All Models 161-185 cfm 69.00 502.00
9.3 Air Compressor All Models 15-35 cfm 20.00 205.00
9.4 Diamond Drill CP-8 201.25
9.5 Jackhammer 150.00
9.6 Pneumatic Drilling Machine 170.00
10. Pumping Equipment
10.1 Water Pump, 100 mm suction Ø 2,667.00 50.00 16.00 266.25
EMBANKMENT
300.00 340.00 310.00 410.00 345.00
COMMON BORROW
PILING
REINFORCING STEEL
42.00 41.00 43.00 40.00
REINFORCING STEEL BARS DEFORMED GRADE 40
49.00 52.00 52.00 53.00
REINFORCING STEEL BARS DEFORMED GRADE 60
75.00 58.00 85.00 60.00
G.I TIE WIRE # 16
STRUCTURAL CONCRETE
63.00 61.00 65.00 62.00 64.00
COMMON NAILS ASSORTED
720.00 720.00 900.00 720.00
GRAVEL G1
455.00 520.00 750.00 750.00
FINE AGGREGATE
15.00 13.00 15.00 15.00
LUMBER COCO
34.00 45.00 36.00 35.00 40.00
LUMBER GOOD
340.00 350.00 370.00 387.50 350.00
PLYWOOD MARINE (0.00625M X 1.2M X 2.44M)
650.00 710.00 650.00 668.00 670.00
PLYWOOD MARINE (0.0125M X 1.2M X 2.44M)
541.00 530.00 545.00 650.00 535.00
PLYWOOD ORDINARY (0.0125M X 1.4M X 2.44M)
310.00 315.00 330.00 313.00 292.00
PLYWOOD ORDINARY (0.00625M X 1.4M X 2.44M)
GUARDRAIL
742.00 1,350.00 1,350.00 1,350.00 1,350.00
METAL BEAM END PIECE
PAVEMENT MARKINGS
2,310.00 2,310.00 2,310.00 2,310.00 2,310.00
GLASS BEADS (PRE-MIX)
125.00 188.00 125.00 213.00 125.00
PRIMER WHITE
122.00 229.00 122.00 255.00 122.00
PRIMER YELLOW
90.00 90.00 95.00 87.00 87.00
LPG CYLINDER
1,585.00 1,585.00 1,585.00 1,585.00 1,585.00
PAINT THERMOPLASTIC WHITE
1,800.00 1,800.00 1,800.00 1,800.00 1,800.00
PAINT THERMOPLASTIC YELLOW
HYDRAULIC CEMENT
258.00 225.00 257.00 255.00 273.00
PORTLAND CEMENT
BITUMINOUS MATERIALS
KG 60.38
63.00 60.00 60.00
KG 63.50
67.00 64.00 64.00
21,680.00 21,415.00 21,084.00 LNM 21,251.63
49.00 KG 51.00
FORM POW-2015-01B-00
DUST/
OUTPUT NO. OF MAN- SAFETY SAFETY SAFETY WORKING EAR BODY RUBBER EYE
ITEM NO. / DESCRIPTION QUANTITY WORKERS DAYS RAIN COATS GAS LANYARD FACEMASK Medical kit
PER HOUR PERSONNEL DAYS HELMET SHOES VEST GLOVES MUFF HARNESS BOOTS GOGGLES
MASK
100(1) Foreman 1 0.6 0.6 0.6 0.6 0.6 0.6 0.18 0 0 0 0 0.6 0 0.6
0.24 0.05 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Clearing and Grubbing
Unskilled Laborer 2 0.6 1.2 1.2 1.2 1.2 1.2 0.36 0 0 0 0 1.2 0 1.2
100(3)a3 Foreman 1 210 210 210 210 210 210 63 0 0 0 0 210 0 210
Individual Removal of Trees, 501-750 1,680.00 1.00 Skilled Laborer 1 210 210 210 210 210 210 63 0 0 0 0 210 0 210
mm dia. (Small) Unskilled Laborer 2 210 420 420 420 420 420 126 0 0 0 0 420 0 420
101(1) Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.039 0 0 0 0 0.13 0 0.13
Portland Cement Concrete Pavement 22,517.26 57.50 Skilled Laborer 4 48.95 195.8 195.8 0 195.8 195.8 58.74 0 0 0 0 195.8 195.8 195.8
(Unreinforced), 0.28 m thick, 14 days Unskilled Laborer 12 48.95 587.4 587.4 0 587.4 587.4 176.22 0 0 0 0 587.4 587.4 587.4
404(1)a Foreman 1 12.87 12.87 12.87 12.87 12.87 12.87 3.861 0 0 0 0 12.87 0 12.87
18,537.14 180.00 Skilled Laborer 2 12.87 25.74 25.74 25.74 25.74 25.74 7.722 0 0 0 0 25.74 0 25.74
Reinforcing Steel , Grade 40
Unskilled Laborer 8 12.87 102.96 102.96 102.96 102.96 102.96 30.888 0 0 0 0 102.96 0 102.96
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
DUST/
OUTPUT NO. OF MAN- SAFETY SAFETY SAFETY WORKING EAR BODY RUBBER EYE
ITEM NO. / DESCRIPTION QUANTITY WORKERS DAYS RAIN COATS GAS LANYARD FACEMASK Medical kit
PER HOUR PERSONNEL DAYS HELMET SHOES VEST GLOVES MUFF HARNESS BOOTS GOGGLES
MASK
405(1)a3 Foreman 1 17.15 17.15 17.15 0 17.15 17.15 5.145 0 0 0 0 17.15 17.15 17.15
Structural Concrete, 20.68 MPa, 192.10 1.40 Skilled Laborer 8 17.15 137.2 137.2 0 137.2 137.2 41.16 0 0 0 0 137.2 137.2 137.2
Class "A", 28 days Unskilled Laborer 16 17.15 274.4 274.4 0 274.4 274.4 82.32 0 0 0 0 274.4 274.4 274.4
500(1)b3 Foreman 1 7.88 7.88 7.88 7.88 7.88 7.88 2.364 0 0 0 0 7.88 0 7.88
Pipe Culverts, 910 mm dia. Class IV 63.00 1.000 Skilled Laborer 2 7.88 15.76 15.76 15.76 15.76 15.76 4.728 0 0 0 0 15.76 0 15.76
RCPC Unskilled Laborer 4 7.88 31.52 31.52 31.52 31.52 31.52 9.456 0 0 0 0 31.52 0 31.52
500(1)b5 Foreman 1 0.02 0.02 0.02 0.02 0.02 0.02 0.006 0 0 0 0 0.02 0 0.02
Gabions,1m x 1m x 2m, Metallic 44.00 2.500 Skilled Laborer 2 2.2 4.4 4.4 4.4 4.4 4.4 1.32 0 0 0 0 4.4 0 4.4
Coated Unskilled Laborer 8 2.2 17.6 17.6 17.6 17.6 17.6 5.28 0 0 0 0 17.6 0 17.6
511(3) Foreman 1 0.05 0.05 0.05 0.05 0.05 0.05 0.015 0 0 0 0 0.05 0 0.05
39.30 100.000 Skilled Laborer 2 0.05 0.1 0.1 0.1 0.1 0.1 0.03 0 0 0 0 0.1 0 0.1
Filter Cloth
Unskilled Laborer 8 0.05 0.4 0.4 0.4 0.4 0.4 0.12 0 0 0 0 0.4 0 0.4
603(3)a1 Foreman 1 5.67 5.67 5.67 5.67 5.67 5.67 1.701 0 0 0 0 5.67 0 5.67
Metal Guardrails (Metal Beam) 190.50 4.20 Skilled Laborer 2 5.67 11.34 11.34 11.34 11.34 11.34 3.402 0 0 0 0 11.34 0 11.34
Including Post, Single (W-Beam)
Unskilled Laborer 4 5.67 22.68 22.68 22.68 22.68 22.68 6.804 0 0 0 0 22.68 0 22.68
603(4)b Foreman 1 0.38 0.38 0.38 0.38 0.38 0.38 0.114 0 0 0 0 0.38 0 0.38
18.00 6.00 Skilled Laborer 1 0.38 0.38 0.38 0.38 0.38 0.38 0.114 0 0 0 0 0.38 0 0.38
Metal Beam End Piece (Bull Nose)
Unskilled Laborer 2 0.38 0.76 0.76 0.76 0.76 0.76 0.228 0 0 0 0 0.76 0 0.76
605(1)l3 Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.039 0 0 0 0 0.13 0 0.13
Warning Signs, 750 mm, W2-6C, 1.00 1.00 Skilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.039 0 0 0 0 0.13 0 0.13
Intersection and Junction Signs Side
Road Junction L or R Unskilled Laborer 2 0.13 0.26 0.26 0.26 0.26 0.26 0.078 0 0 0 0 0.26 0 0.26
605 (1)u4 Foreman 1 0.75 0.75 0.75 0.75 0.75 0.75 0.225 0 0 0 0 0.75 0 0.75
Warning Signs 450 x 700 mm, W4- 6.00 1.00 Skilled Laborer 1 0.75 0.75 0.75 0.75 0.75 0.75 0.225 0 0 0 0 0.75 0 0.75
2PA, Road Width Sign Road Narrows
Unskilled Laborer 2 0.75 1.5 1.5 1.5 1.5 1.5 0.45 0 0 0 0 1.5 0 1.5
605(1)ai2 Foreman 1 0.25 0.25 0.25 0.25 0.25 0.25 0.075 0 0 0 0 0.25 0 0.25
Warning Signs, 750mm x 750mm, 2.00 1.00 Skilled Laborer 1 0.25 0.25 0.25 0.25 0.25 0.25 0.075 0 0 0 0 0.25 0 0.25
W6-1C, Pedestrian and School Signs
Pedestrian Crossing Ahead Unskilled Laborer 2 0.25 0.5 0.5 0.5 0.5 0.5 0.15 0 0 0 0 0.5 0 0.5
605(1)aj2 Foreman 1 0.25 0.25 0.25 0.25 0.25 0.25 0.075 0 0 0 0 0.25 0 0.25
Warning Signs, 750mm x 750mm, 2.00 1.00 Skilled Laborer 1 0.25 0.25 0.25 0.25 0.25 0.25 0.075 0 0 0 0 0.25 0 0.25
W6-2C, Pedestrian and School Signs
Children Crossing Unskilled Laborer 2 0.25 0.5 0.5 0.5 0.5 0.5 0.15 0 0 0 0 0.5 0 0.5
605(2)a3 Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.039 0 0 0 0 0.13 0 0.13
Regulatory Signs, 750mm x 750mm, 1.00 1.00 Skilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.039 0 0 0 0 0.13 0 0.13
R1-1C, Priority Signs Stop
Unskilled Laborer 2 0.13 0.26 0.26 0.26 0.26 0.26 0.078 0 0 0 0 0.26 0 0.26
605(2)ai3 Foreman 1 0.25 0.25 0.25 0.25 0.25 0.25 0.075 0 0 0 0 0.25 0 0.25
Regulatory Signs, 750 mm, R6-8C, 2.00 1.00 Skilled Laborer 1 0.25 0.25 0.25 0.25 0.25 0.25 0.075 0 0 0 0 0.25 0 0.25
Miscellaneous Signs Pedestrian
Crossing Unskilled Laborer 2 0.25 0.5 0.5 0.5 0.5 0.5 0.15 0 0 0 0 0.5 0 0.5
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
DUST/
OUTPUT NO. OF MAN- SAFETY SAFETY SAFETY WORKING EAR BODY RUBBER EYE
ITEM NO. / DESCRIPTION QUANTITY WORKERS DAYS RAIN COATS GAS LANYARD FACEMASK Medical kit
PER HOUR PERSONNEL DAYS HELMET SHOES VEST GLOVES MUFF HARNESS BOOTS GOGGLES
MASK
605(2)aj3 Foreman 1 0.25 0.25 0.25 0.25 0.25 0.25 0.075 0 0 0 0 0.25 0 0.25
Regulatory Signs, 750 mm ,R6-9C, 2.00 1.00 Skilled Laborer 1 0.25 0.25 0.25 0.25 0.25 0.25 0.075 0 0 0 0 0.25 0 0.25
Miscellaneous Signs School Children
Crossing Unskilled Laborer 2 0.25 0.5 0.5 0.5 0.5 0.5 0.15 0 0 0 0 0.5 0 0.5
605(6)e1 Foreman 1 2.25 2.25 2.25 2.25 2.25 2.25 0.675 0 0 0 0 2.25 0 2.25
Hazard Markers, 450x600mm, 18.00 1.00 Skilled Laborer 1 2.25 2.25 2.25 2.25 2.25 2.25 0.675 0 0 0 0 2.25 0 2.25
Chevron Signs Unskilled Laborer 2 2.25 4.5 4.5 4.5 4.5 4.5 1.35 0 0 0 0 4.5 0 4.5
611(1) Foreman 1 21 21 21 21 21 21 6.3 0 0 0 0 21 0 21
5,040.00 30.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Trees Furnishing and Transplanting
Unskilled Laborer 2 21 42 42 42 42 42 12.6 0 0 0 0 42 0 42
612(1) Foreman 1 5.4 5.4 5.4 5.4 5.4 5.4 1.62 0 0 0 0 5.4 0 5.4
Reflectorized Thermoplastic 1,079.74 25.00 Skilled Laborer 2 5.4 10.8 10.8 10.8 10.8 10.8 3.24 0 0 0 0 10.8 0 10.8
Pavement Markings (White) Unskilled Laborer 6 5.4 32.4 32.4 32.4 32.4 32.4 9.72 0 0 0 0 32.4 0 32.4
612(2) Foreman 1 5.04 5.04 5.04 5.04 5.04 5.04 1.512 0 0 0 0 5.04 0 5.04
Reflectorized Thermoplastic 1,008.24 25.00 Skilled Laborer 2 5.04 10.08 10.08 10.08 10.08 10.08 3.024 0 0 0 0 10.08 0 10.08
Pavement Markings (Yellow) Unskilled Laborer 6 5.04 30.24 30.24 30.24 30.24 30.24 9.072 0 0 0 0 30.24 0 30.24
622(2)c Foreman 1 1.07 1.07 1.07 1.07 1.07 1.07 0.321 0 0 0 0 1.07 0 1.07
128.40 15.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Cocologs/Fascine, CN300
Unskilled Laborer 1 1.07 1.07 1.07 1.07 1.07 1.07 0.321 0 0 0 0 1.07 0 1.07
622(3)b Foreman 1 2.7 2.7 2.7 2.7 2.7 2.7 0.81 0 0 0 0 2.7 0 2.7
756.80 35.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Vegetation, Vetiver Grass System
Unskilled Laborer 1 2.7 2.7 2.7 2.7 2.7 2.7 0.81 0 0 0 0 2.7 0 2.7
A. TOTAL, PERSONNEL/MAN-DAYS 245 1731.3 4789.15 4789.15 1712.37 4789.15 4781.69 1436.745 0 0 0 0 4789.15 0 3076.78 4789.15
B. SERVICE LIFE, DAYS 730 365 180 3 730 1 730 730 730 1 365 60
C. PURCHASE COST, PPh 180.55 1,012.00 400.00 23.00 245.00 63.25 602.60 1,263.85 1,083.30 5.00 506.00 300.00
D. UNIT COST / MAN-DAY (C ÷ B) 0.25 2.77 2.22 7.67 0.34 63.25 0.83 1.73 1.48 10.00 1.39 5.00
E. DIRECT COST FOR PPE's (D x A (Man-days)) 1,197.29 4,743.26 10,631.91 36,675.56 488.49 - - - - 47,891.50 4,276.72 23,945.75
F. SAFETY OFFICER/PRACTITIONER (PART TIME) @ P15,000.00/MONTH (AS PER D.O. 56, S2005, consider atleast 4 hours per week)
G. HEALTH PERSONNEL (FULL TIME) @ P8,400.00/MONTH (AS PER D.O. 56, S2005)
H. SANITATION AIDE
I. EQUIPMENT
J. Revised Construction Safety Guidelines for the Implementation of Infrastructure Projects During COVID-19 Public Health Crisis
H. TOTAL DIRECT COST (E + F + G + H + I + J)
I. OCM (9% OF H)
J. PROFIT (8% OF H)
K. VAT (5% OF H + I + J)
L. TOTAL COST (H + I + J + K)
AVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
129,850.50
245,460.79
177,568.81
273,945.36
34,360.92
332,226.60
1,193,412.98
-
95,473.04
64,444.30
1,353,330.32 1,353,330.32
1,353,330.32 -
1,353,330.32
Project : 6M. X 6M CAMPHOUSE
Location : FOR REGIONAL OFFICE PROJECTS
Subject : BILL OF MATERIALS
A. STRUCTURAL/MASONRY/FORMWORKS
1.00 CEMENT 44.00 BAG 255.90 11,259.60
2.00 SAND 3.00 CU M 985.82 2,957.46
3.00 GRAVEL 3.00 CU M 1,095.82 3,287.46
4.00 12MMø X 9.00M DEFORMED BARS 53.30 KG 41.27 2,199.69
5.00 10MMø X 12.00M DEFORMED BARS 73.90 KG 41.27 3,049.85
6.00 10MMø X 6.00M DEFORMED BARS 120.00 KG 41.27 4,952.40
7.00 #16 G.I. TIE WIRE 10.00 KG 89.00 890.00
9.00 4" CONCRETE HOLLOW BLOCKS 310.00 PC 28.00 8,680.00
10.00 1/2" THK. 4' X 8' PLYWOOD 1.00 SHT 705.00 705.00
11.00 ASSORTED NAILS CW NAILS 5.00 KG 77.00 385.00
TOTAL 38,366.46
B. FLOORING/FLOOR FRAMING/STAIRS
1.00 10 - 2" X 6" X 10' COCO LUMBER (RAFTER) 160.00 BD FT 16.00 2,560.00
2.00 6 - 2" X 4" X 10' COCO LUMBER (GIRTS) 70.00 BD FT 16.00 1,120.00
3.00 45 - 2" X 6" X 10' COCO LUMBER (GIRDER) 420.00 BD FT 16.00 6,720.00
2.00 14 - 2" X 4" X 10' COCO LUMBER (FLOOR JOIST/BLOCKS) 196.84 BD FT 16.00 3,149.38
3.00 1/2" X 2' X 4' MARINE PLYWOOD FLOORING 11.00 SHTS. 705.00 7,755.00
2.00 1 - 2" X 12" X 16' COCO LUMBER (STRINGER) 32.00 BD FT 16.00 512.00
6.00 4 - 2" X 12" X 10' COCO LUMBER (THREAD) 80.00 BD FT 16.00 1,280.00
7.00 6 - 1" X 10" X 10' COCO LUMBER (FASCIA) 50.00 BD FT 16.00 800.00
8.00 16MM Ø X 11" MACHINE BOLTS W/ NUTS & WASHERS 18.00 PC 100.00 1,800.00
9.00 1/4" THK. X 2" FLAT BAR (SCRAP) 1.00 PC 150.00 150.00
10.00 ASSORTED NAILS CW NAILS 12.00 KG 77.00 924.00
TOTAL 26,770.38
D. ROOFING/ROOF FRAMING
1.00 6 - 4" X 4" X 10' COCO LUMBER (POST) 80.00 BD FT 16.00 1,280.00
2.00 7 - 4" X 4" X 12' COCO LUMBER (POST) 150.00 BD FT 16.00 2,400.00
3.00 6 - 2" X 6" X 10' COCO LUMBER (GIRTS) 60.00 BD FT 16.00 960.00
4.00 6 - 2" X 4" X 14' COCO LUMBER (RAFTER) 75.00 BD FT 16.00 1,200.00
5.00 24 - 2" X 3" X 14' COCO LUMBER (PURLINS) 180.39 BD FT 16.00 2,886.26
6.00 GA.26 CORRUGATED G.I. SHEET ROOFING 67.00 SQ M 300.00 20,100.00
7.00 GA. 26 36" X 8' PLAIN GI. SHEET (RIDGE ROLL) 8.00 L.M. 220.00 1,760.00
8.00 ASSORTED NAILS CW NAILS 12.00 KG 77.00 924.00
9.00 ROOF NAILS 5.00 KG 75.00 375.00
TOTAL 31,885.26
NO. ITEM DESCRIPTION QUANTITY UNIT UNIT COST AMOUNT
E. ELECTRICAL
1.00 8.0 SQ. MM. THHN WIRE 20.00 M 55.00 1,100.00
2.00 3.5 SQ. MM. THHN WIRE 50.00 M 26.00 1,300.00
3.00 2.0 SQ. MM. THHN WIRE 35.00 M 25.00 875.00
4.00 2X3 PVC RECEPTACLE 4.00 PC 35.00 140.00
5.00 4X4 PVC JUNCTION BOX 8.00 PC 48.00 384.00
6.00 2X4 PVC UTILITY BOX 8.00 PC 38.00 304.00
7.00 SWITCHES 5.00 PC 175.00 875.00
8.00 DOUBLE CONVENIENCE OUTLET 3.00 PC 86.00 258.00
9.00 SINGLE GANG PLATE 5.00 PC 54.00 270.00
10.00 20AT FUSE 1.00 PC 320.00 320.00
11.00 15 AT FUSE 1.00 PC 320.00 320.00
12.00 4-BRANCH PANEL BOARD 1.00 SET 850.00 850.00
13.00 18W COMPACT FLOURESCENT LAMP 4.00 PC 124.00 496.00
14.00 20W FLOURESCENT LAMP 4.00 SET 220.00 880.00
15.00 MOLDFLEX 40.00 M 10.00 400.00
16.00 ELECTRICAL TAPE 2.00 PC 35.00 70.00
TOTAL 8,842.00
F. PLUMBING
0.00
Length= 791.45 ln m
(1 x 1m)
concrete Works
t L w/h #
slab 0.15 791.45 1.30 1.00 154.33
bracing 0.15 1.30 0.20 159.29 6.21
beam 0.10 791.45 0.15 2.00 23.74
column 0.20 1.00 0.20 318.58 12.74
. total 197.03
factor
cement 9 1773.286
sand 0.5 98.516
gravel 1 197.032
reinforcing bars
H/L # of bars # of units
slab 791.45 4 1 3165.80
bracing 1.30 2.00 159.29 414.15
beam 791.45 2.00 2.00 3165.80
column 1.00 4.00 318.58 1274.32
total 8020.07 8421.078
L # of bars # of units
actual hor. - 791.45 2 2 3,165.80 3166.00
actual vert. - 0.95 2,067.00 2 3,927.30 3927.00
total 7093.00
Plastering
L W # of faces
791.45 0.9 2 1,424.61
factor
Cement 0.192 273.52512
Washed Sand 0.016 22.79376
791.45
FINAL
FACTOR
cement 3335.92 4.21
sand 248.45 0.31
gravel 197.03 0.25
reinforcing bars 17000.98 21.48
6" CHB Load Bea 15987.00 20.20
Length= 141.73 ln m
(1 x 1m- varies)
concrete Works
t L w/h #
slab 0.15 141.73 1.30 1.00 27.64
bracing 0.15 1.30 0.20 29.35 1.14
beam 0.10 141.73 0.15 3.00 6.38
column 0.20 1.00 0.20 58.69 2.35
. total 37.51
factor
cement 9 337.566
sand 0.5 18.754
gravel 1 37.507
reinforcing bars
H/L # of bars # of units
slab 141.73 4 1 566.92
bracing 1.30 2.00 29.35 76.30
beam 141.73 2.00 3.00 850.38
column 1.20 4.00 58.69 281.72
total 1775.32 1864.087
Masonry
L W # of units
141.73 0.8 2 226.768
factor
6" CHB Load Bearing 12.5 2863.000
Cement 1.018 230.850
Washed Sand 0.0844 19.139
0.016 3.628
Tie Wire 0.021 5.000
L # of bars # of units
actual hor. - 141.73 2 2 566.92 567.00
actual vert. - 0.95 377.00 2 716.30 716.00
total 1283.00
Plastering
L W # of faces
141.73 0.9 2 255.11
factor
Cement 0.192 48.981888
Washed Sand 0.016 4.081824
141.73
FINAL
FACTOR
cement 617.40 4.36
sand 45.60 0.32
gravel 37.51 0.26
reinforcing bars 3499.30 24.69
6" CHB Load Bea 2863.00 20.20
Average 933.18
FINAL
cement 4.29
sand 0.32
gravel 0.26
reinforcing bars 23.09
6" CHB Load Bea 20.20
8311.68 kg
3832.75 kg
13 159.00
4856.54 kg
1843.49 kg
776.16 kg
13 29.00
879.65 kg
2,067.00
377.00
500(3)b1 Lined Canal, Rectangular,Concrete
ITEM # DESCRIPTION
404(1)a REINFORCING STEEL, GRADE 40
405(1)a3 STRUCTURAL CONCRETE, CLASS A
ln m 211.00
UNIT QUANTITY
kgs 2,260.00
cu m 56.00
Cement 3.39
Sand 0.133
Gravel 0.265
RSB, grade40 10.71
Tie wire 0.214
Plywood 1.00
Coco Lumber 85.00
CWN 0.85
10.71 kgs
0.27 cu.m
PICK UP
Computation of Rental Rates
Fully-Maintained basis
FULLY-OPERATED BASIS
Err:509 /hr
Err:509 /day
Err:509 /month
0.023478 )
CRF
1,270,000.00
0.023478 )
0.240360363
6.25 ###