You are on page 1of 218

ROAD WIDENING ON SPECIFIC LOCATIONS ALONG

SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD


(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO
ORIENTAL

Php0.00

CY 2022 DPWH REGULAR INFRASTRUCTURE PROGRAM


Reference No. ______
November 26, 2022

CHECKLIST
(Program of Works / Approved Budget for the Contract)

Project : ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR


BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO
K1683+257.000, DAVAO ORIENTAL

Location : DAVAO ORIENTAL

Annex A - Executive Summary


Annex B - Certificate of Reasonableness
Annex C - Approved Budget for the Contract
Annex D - Program of Works
Annex E - Detailed Unit Price Analysis
Annex F - Construction Drawing

TEOFILA U. TAN
Chief, Planning and Design Division
Reference No. ______
November 26, 2022
Republic of the Philippines
Department of Public Works and Highways
OFFICE OF THE REGIONAL DIRECTOR
Region XI, Davao City

EXECUTIVE SUMMARY
(Program of Works / Approved Budget for the Contract)

FOR : ALLAN S. BORROMEO,PhD.,CESO III


Regional Director

THRU : ARTURO P. LONGYAPON


Assistant Regional Director

1. Subject : ROAD WIDENING ON SPECIFIC LOCATIONS ALONG


(Project/Location) SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO
ORIENTAL

2. Contract ID :
3. Implementing Office : DPWH Region XI ,Regional Office
4. Reviewing Office : Planning and Design Division
5. Mode of Contracting : Public Bidding
6. Source of Fund : FY 2021 Regular Infrastructure program
6. Allocation : Php0.00
7. Approved Budget for : Php98,393,454.04
the Contract (ABC)
8. Action Recommended : For Approval
9. Remarks : This Office after review found the proposed Program of Works
(POW) and Approved Budget for the Contract (ABC) reasonable as
corrected
Attached herewith are the following:
1. Construction Drawing prepared by DPWH Region XI ,Regional
Office and reviewed by this Office.

2. Detailed Unit Price Analysis submitted by the Implementing


Office which were reviewed based on quantity take off, outputs
and mark-ups.
TEOFILA U. TAN
Chief, Planning and Design Division
CERTIFICATE OF REASONABLENESS OF COST ESTIMATE

Project : ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO
OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

Location : DAVAO ORIENTAL


Station Limits : 0
0

Project Length : Net Length


Road 0

Duration : 280 C.D.

SCOPE OF WORK

AMOUNT PERCENT
ITEM NO. DESCRIPTION (TOTAL COST) WEIGHT

Part A FACILITIES FOR THE ENGINEER 380,176.36 #NAME?

Part B OTHER GENERAL REQUIREMENTS 2,839,241.90 #NAME?

Part C EARTHWORK 23,743,644.14 #NAME?

Part D SUBBASE AND BASE COURSE 12,698,259.08 #NAME?

Part E SURFACE COURSE 45,217,071.49 #NAME?

Part F DRAINGE CONSTRUCTION 2,736,930.48 #NAME?

Part G DRAINAGE AND SLOPE PROTECTION STRUCTURES 6,835,775.36 #NAME?

Part H MISCELLANEOUS STRUCTURE #NAME? #NAME?

Grand Total #NAME? #NAME?

Cost per kilometer of Concreting = 3.360 km


(excludes Part A & B ,)

#NAME?
Concreting = = #NAME?
3.360 km

TEOFILA U. TAN
Chief, Planning and Design Division
98,393,454.04 #NAME?
3.412
Department of Public Works and Highways (DPWH)

PROGRAM OF WORK/BUDGET COST

ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO
OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
Project Name : Net Length : (a) Road
Scope of Works : Widening (2 into 4 lanes), 280mm THK, PCCP (b) Bridge

Project ID : : Construction of manhholes, box culverts, concrete and CHB lined (c ) Others
canal, cross drains and other minor drainage structures
Location : DAVAO ORIENTAL Target Start Date :
: : Removal of guardrails Total Project Duration : 280 Calendar days
Station Limits (As
per RBIA) : Installation of chevron and warning signs No. of Pre-determined :
Unworkable Days
64 Calendar days
: Removal, Furnishing and transplanting of trees
: Application of reflectorized thermoplastic pavement markings No. of Working Days : 216 Calendar days
Appropriation : Php0.00
Source of Fund : CY 2022 DPWH REGULAR INFRASTRUCTURE PROGRAM : Installation of metal guardrails

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part A: FACILITIES FOR THE ENGINEER PLS SEE FORM POW 0.40% 316,901.36 0.40% 316,901.36
B: OTHER GENERAL REQUIREMENTS 3.17% 2,521,377.78 3.17% 2,521,377.78
C: EARTHWORK 24.06% 19,163,554.59 24.06% 19,163,554.59
D: SUBBASE AND BASE COURSE 12.87% 10,248,796.67 12.87% 10,248,796.67
E: SURFACE COURSE 45.82% 36,494,811.53 45.82% 36,494,811.53
F: DRAINGE CONSTRUCTION 2.77% 2,208,983.43 2.77% 2,208,983.43
G: DRAINAGE AND SLOPE PROTECTION STRUCTURES 7.08% 5,643,285.56 7.08% 5,643,285.56
H: MISCELLANEOUS STRUCTURE 3.84% 3,055,770.61 3.84% 3,055,770.61

Total 100.00% 79,653,481.53 100.00% 79,653,481.53

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 5,360,863.45 5,360,863.45 A. Total Direct Cost 79,653,481.53 79,653,481.53
2. Materials 49,900,393.43 49,900,393.43 B. OCM and Profit 14,054,569.93 14,054,569.93
PLS SEE FORM POW 3. Rental of Equipment 24,357,863.73 24,357,863.73 C. Value Added Tax 4,683,684.53 4,683,684.53
4. Provisional Sum / Daywork D. Total Construction Cost 98,391,735.99 98,391,735.99
5. OCM and Profit 14,054,569.93 14,054,569.93 E. Eng'g & Administrative Overhead, 3.50% - -
6. Value Added Tax 4,683,684.53 4,683,684.53 F. RROW Acquisition - -
7. Eng'g & Administrative Overhead, 3.50% - - G. Physical Reserved (Contingency)
8. RROW Acquisition - -
9. Physical Reserved (Contingency)
10. TOTAL ESTIMATED COST 98,357,375.07 98,357,375.07 H. TOTAL ESTIMATED COST 98,391,735.99 98,391,735.99

Preparation and Submission: Evaluation: Approval

Prepared By: Checked/Submitted By: Reviewed as to Unit Cost: Recommending Approval: Approved:
JESSICA B. APOSTOL JUDY ANN T. BERNARDINO TEOFILA U. TAN ARTURO P. LONGYAPON REY PETER B. GILLE, DM
Engineer II Engineer IV Chief, Planning & Design Division Assistant Regional Director OIC - Regional Director
PROJECT COST
RROW
CIVIL WORKS -

Amount less OCM Amount less profit TOTAL


Total Amount 79,653,481.53 79,653,481.53
less: Part A 118,708.72
Part B 2,441,957.96 337,376.00
77,092,814.86 79,316,105.53
7,709,281.49 6,345,288.44 14,054,569.93
10% 8%

(34,360.92)

79,619,120.61

(98,391,735.987) 29,283,254.76 - - ###


(3.36)
(3,360.00)
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
DAVAO ORIENTAL

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED

PART A FACILITIES FOR THE ENGINEER

A.1.1(3) Construction of Field Office for the Engineer 1.00 1.00 ls 198,192.64 198,192.64 198,192.64 198,192.64 245,560.68 245,560.68

A.1.1(16) Operation & Maintenance of Field Office for the Engineer 8.00 8.00 mo 118,708.72 118,708.72 14,838.59 14,838.59 16,826.96 16,826.96

TOTAL OF PART A 316,901.36 316,901.36

PART B OTHER GENERAL REQUIREMENTS

B.4(1) Construction survey and staking 3.36 3.36 km 70,491.46 70,491.46 20,979.60 20,979.60 25,993.72 25,993.72

B.5 Project Billboard / Signboard 2.00 2.00 each 8,928.37 8,928.37 4,464.18 4,464.18 5,531.12 5,531.12

B.7(2) Occupational Safety and Health Program 1.00 1.00 ls 1,193,412.98 1,193,412.98 1,193,412.98 1,193,412.98 1,353,330.32 1,353,330.32

B.8(2) Traffic Management 1.00 1.00 ls 911,168.98 911,168.98 911,168.98 911,168.98 1,033,265.62 1,033,265.62

B.9 Mobilization / Demobilization 1.00 1.00 ls 337,376.00 337,376.00 337,376.00 337,376.00 354,244.80 354,244.80

TOTAL OF PART B 2,521,377.78 2,521,377.78

PART C EARTHWORK

100(1) Clearing and Grubbing 0.24 0.24 ha 39,281.18 39,281.18 163,671.60 163,671.60 202,789.11 202,789.11

100(3)a3 Individual Removal of Trees, 501-750 mm dia. (Small) 1,680.00 1,680.00 each 12,593,764.81 12,593,764.81 7,496.29 7,496.29 9,287.90 9,287.90

101(1) Removal of Structures and Obstruction 1.00 1.00 ls 721,344.68 721,344.68 721,344.68 721,344.68 893,746.06 893,746.06

101(2) Removal of Actual Structures/Obstruction 28.00 28.00 each 72,092.66 72,092.66 2,574.74 2,574.74 3,190.10 3,190.10

11 of 3
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED

Removal of Actual Structure/Obstruction, 0.23m thick PCCP


101(3)b3 989.30 989.30 sq m 116,139.81 116,139.81 117.40 117.40 145.45 145.45
(Unreinforced)

101(10) Removal of Existing Road Signs 20.00 20.00 each 19,548.12 19,548.12 977.41 977.41 1,211.01 1,211.01

102(2) Surplus Common Excavation 14,097.00 14,097.00 cu m 2,805,387.58 2,805,387.58 199.01 199.01 246.57 246.57

103(1)a Structure Excavation (Common soil) 383.60 383.60 cu m 90,125.19 90,125.19 234.95 234.95 291.10 291.10

103(3) Foundation Fill 39.10 39.10 cu m 50,545.22 50,545.22 1,292.72 1,292.72 1,601.68 1,601.68

103(6)a Pipe Culverts and Drain Excavation (Common soil) 194.30 194.30 cu m 45,649.96 45,649.96 234.95 234.95 291.10 291.10

104(1)a Embankment from Roadway Excavation (Common Soil) 8,916.00 8,916.00 cu m 2,078,400.09 2,078,400.09 233.11 233.11 288.82 288.82

105(1)a Subgrade Preparation (Common Material) 32,774.00 32,774.00 sq m 531,275.28 531,275.28 16.21 16.21 20.08 20.08

TOTAL OF PART C 19,163,554.59 19,163,554.59

PART D SUBBASE AND BASE COURSE

200(1) Aggregate Subbase Course 10,668.00 10,668.00 cu m 10,248,796.67 10,248,796.67 960.70 960.70 1,190.31 1,190.31

TOTAL OF PART D 10,248,796.67 10,248,796.67

PART E SURFACE COURSE

300(1) Gravel Surface Course 2,157.00 2,157.00 cu m 2,729,585.57 2,729,585.57 1,265.45 1,265.45 1,567.90 1,567.90

Portland Cement Concrete Pavement (Unreinforced), 0.28 m thick,


311(1)e1 22,517.26 22,517.26 sq m 33,765,225.96 33,765,225.96 1,499.53 1,499.53 1,857.91 1,857.91
14 days

TOTAL OF PART E 36,494,811.53 36,494,811.53

12 of 3
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED

PART F DRAINGE CONSTRUCTION

404(1)a Reinforcing Steel , Grade 40 18,537.14 18,537.14 kg 963,953.42 963,953.42 52.00 52.00 64.43 64.43

405(1)a3 Structural Concrete, 20.68 MPa, Class "A", 28 days 192.10 192.10 cu m 1,245,030.01 1,245,030.01 6,481.16 6,481.16 8,030.15 8,030.15

TOTAL OF PART F 2,208,983.43 2,208,983.43

PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES

500(1)b3 Pipe Culverts, 910 mm dia. Class IV RCPC 63.00 63.00 ln m 404,418.65 404,418.65 6,419.34 6,419.34 7,953.57 7,953.57

500(1)b5 Pipe Culverts, 1220 mm dia. Class IV RCPC 6.00 6.00 ln m 62,409.85 62,409.85 10,401.64 10,401.64 12,887.63 12,887.63

505(2)a Grouted Riprap, Class A 1,650.80 1,650.80 cu m 4,862,135.02 4,862,135.02 2,945.32 2,945.32 3,649.25 3,649.25

506(1) Stone Masonry 47.80 47.80 cu m 176,957.14 176,957.14 3,702.03 3,702.03 4,586.82 4,586.82

508 (1) Hand Laid Rock Embankment 8.00 8.00 cu m 11,250.74 11,250.74 1,406.34 1,406.34 1,742.46 1,742.46

511(1)a3 Gabions,1m x 1m x 2m, Metallic Coated 44.00 44.00 cu m 118,476.47 118,476.47 2,692.65 2,692.65 3,336.19 3,336.19

511(3) Filter Cloth 39.30 39.30 sq m 7,637.70 7,637.70 194.34 194.34 240.79 240.79

TOTAL OF PART G 5,643,285.56 5,643,285.56

PART H MISCELLANEOUS STRUCTURE

603(3)a1 Metal Guardrails (Metal Beam) Including Post, Single (W-Beam) 190.50 190.50 ln m 563,130.93 563,130.93 2,956.07 2,956.07 3,662.57 3,662.57

603(4)b Metal Beam End Piece (Bull Nose) 18.00 18.00 each 403,044.86 403,044.86 22,391.38 22,391.38 27,742.92 27,742.92

Warning Signs, 750 mm, W2-6C, Intersection and Junction Signs


605(1)l3 1.00 1.00 each 6,052.43 6,052.43 6,052.43 6,052.43 7,498.96 7,498.96
Side Road Junction L or R
Warning Signs 450 x 700 mm, W4-2PA, Road Width Sign Road
605 (1)u4 Narrows 6.00 6.00 each 40,279.49 40,279.49 6,713.25 6,713.25 8,317.72 8,317.72

13 of 3
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
TOTAL UNIT COST (DIRECT+INDIRECT)
ITEM NO. DESCRIPTION UNIT
AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS EVALUATED

Warning Signs, 750mm x 750mm, W6-1C, Pedestrian and School


605(1)ai2 2.00 2.00 each 13,004.86 13,004.86 6,502.43 6,502.43 8,056.51 8,056.51
Signs Pedestrian Crossing Ahead

Warning Signs, 750mm x 750mm, W6-2C, Pedestrian and School


605(1)aj2 2.00 2.00 each 13,004.86 13,004.86 6,502.43 6,502.43 8,056.51 8,056.51
Signs Children Crossing

605(2)a3 Regulatory Signs, 750mm x 750mm, R1-1C, Priority Signs Stop 1.00 1.00 each 6,502.43 6,502.43 6,502.43 6,502.43 8,056.51 8,056.51

Regulatory Signs, 750 mm, R6-8C, Miscellaneous Signs Pedestrian


605(2)ai3 2.00 2.00 each 12,104.86 12,104.86 6,052.43 6,052.43 7,498.96 7,498.96
Crossing

Regulatory Signs, 750 mm ,R6-9C, Miscellaneous Signs School


605(2)aj3 2.00 2.00 each 12,104.86 12,104.86 6,052.43 6,052.43 7,498.96 7,498.96
Children Crossing

605(6)e1 Hazard Markers, 450x600mm, Chevron Signs 18.00 18.00 each 176,759.55 176,759.55 9,819.98 9,819.98 12,166.95 12,166.95

611(1) Trees Furnishing and Transplanting 5,040.00 5,040.00 each 115,009.44 115,009.44 22.82 22.82 28.27 28.27

612(1) Reflectorized Thermoplastic Pavement Markings (White) 1,079.74 1,079.74 sq m 782,145.62 782,145.62 724.38 724.38 897.51 897.51

612(2) Reflectorized Thermoplastic Pavement Markings (Yellow) 1,008.24 1,008.24 sq m 737,085.25 737,085.25 731.06 731.06 905.78 905.78

622(2)c Cocologs/Fascine, CN300 128.40 128.40 ln m 73,284.79 73,284.79 570.75 570.75 707.16 707.16

622(3)b Vegetation, Vetiver Grass System 756.80 756.80 sq m 102,256.38 102,256.38 135.12 135.12 167.41 167.41

TOTAL OF PART H 3,055,770.61 3,055,770.61

GRAND TOTAL 79,653,481.53 79,653,481.53

79,653,481.53
-

14 of 3
245,560.68

134,615.69 380,176.36

87,338.91

11,062.25

1,353,330.32

1,033,265.62

354,244.80 2,839,241.90

48,669.39

15,603,674.59

893,746.06

89,322.81

15 of 3
143,897.23

24,220.12

3,475,875.21

111,665.11

62,625.53

56,560.30

2,575,137.72

658,250.07 23,743,644.14

12,698,259.08 12,698,259.08

3,381,956.52

41,835,114.97 45,217,071.49

16 of 3
-

1,194,338.29

1,542,592.19 2,736,930.48

501,074.70

77,325.80

6,024,185.29

219,249.89

13,939.67 6,835,775.36

146,792.34

9,463.10

697,719.22

499,372.58

7,498.96

49,906.29

17 of 3
16,113.02

16,113.02

8,056.51

14,997.92

14,997.92

219,005.09

142,496.70

969,078.43

913,248.62

90,799.86

126,695.66

#REF!

98,391,735.99

#REF!

18 of 3
Department of Public Works and Highways (DPWH)

ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

APPROVED BUDGET FOR THE CONTRACT


Contract Duration: 280 Calendar days
QTY UNIT TOTAL DIRECT TOTAL MARK-UP 5% VAT TOTAL INDIRECT
ITEM NO. DESCRIPTION TOTAL COST UNIT COST
COST % VALUE COST

PART A FACILITIES FOR THE ENGINEER

AS EVALUATED 1.00 ls 198,192.64 18 35,674.67 11,693.37 47,368.04 245,560.68 245,560.68


A.1.1(3) Construction of Field Office for the Engineer
AS SUBMITTED 1.00 ls 198,192.64 18 35,674.67 11,693.37 47,368.04 245,560.68 245,560.68

AS EVALUATED 8.00 mo 118,708.72 8 9,496.70 6,410.27 15,906.97 134,615.69 16,826.96


A.1.1(16) Operation & Maintenance of Field Office for the Engineer
AS SUBMITTED 8.00 mo 118,708.72 8 9,496.70 6,410.27 15,906.97 134,615.69 16,826.96

AS EVALUATED 316,901.36 45,171.37 18,103.64 63,275.01 380,176.37


TOTAL OF PART A
AS SUBMITTED 316,901.36 45,171.37 18,103.64 63,275.01 380,176.37

PART B OTHER GENERAL REQUIREMENTS

AS EVALUATED 3.360 km 70,491.46 18 12,688.46 4,159.00 16,847.46 87,338.92 25,993.73


B.4(1) Construction survey and staking
AS SUBMITTED 3.360 km 70,491.46 18 12,688.46 4,159.00 16,847.46 87,338.92 25,993.73

AS EVALUATED 2.00 each 8,928.37 18 1,607.11 526.77 2,133.88 11,062.24 5,531.12


B.5 Project Billboard / Signboard
AS SUBMITTED 2.00 each 8,928.37 18 1,607.11 526.77 2,133.88 11,062.24 5,531.12

AS EVALUATED 1.00 ls 1,193,412.98 8 95,473.04 64,444.30 159,917.34 1,353,330.31 1,353,330.31


B.7(2) Occupational Safety and Health Program
AS SUBMITTED 1.00 ls 1,193,412.98 8 95,473.04 64,444.30 159,917.34 1,353,330.31 1,353,330.31

AS EVALUATED 1.00 ls 911,168.98 8 72,893.52 49,203.12 122,096.64 1,033,265.62 1,033,265.62


B.8(2) Traffic Management
AS SUBMITTED 1.00 ls 911,168.98 8 72,893.52 49,203.12 122,096.64 1,033,265.62 1,033,265.62

AS EVALUATED 1.00 ls 337,376.00 - 16,868.80 16,868.80 354,244.80 354,244.80


B.9 Mobilization / Demobilization
AS SUBMITTED 1.00 ls 337,376.00 - 16,868.80 16,868.80 354,244.80 354,244.80

AS EVALUATED 2,521,377.78 182,662.12 135,201.99 317,864.11 2,839,241.89


TOTAL OF PART B
AS SUBMITTED 2,521,377.78 182,662.12 135,201.99 317,864.11 2,839,241.89

PART C EARTHWORK

AS EVALUATED 0.24 ha 39,281.18 18 7,070.61 2,317.59 9,388.20 48,669.39 202,789.11


100(1) Clearing and Grubbing
AS SUBMITTED 0.24 ha 39,281.18 18 7,070.61 2,317.59 9,388.20 48,669.39 202,789.11

AS EVALUATED 1,680.00 each 12,593,764.81 18 2,266,877.67 743,032.12 3,009,909.79 15,603,674.59 9,287.90


100(3)a3 Individual Removal of Trees, 501-750 mm dia. (Small)
AS SUBMITTED 1,680.00 each 12,593,764.81 18 2,266,877.67 743,032.12 3,009,909.79 15,603,674.59 9,287.90

Page 19 OF 4
QTY UNIT TOTAL DIRECT TOTAL MARK-UP 5% VAT TOTAL INDIRECT
ITEM NO. DESCRIPTION TOTAL COST UNIT COST
COST % VALUE COST

AS EVALUATED 1.00 ls 721,344.68 18 129,842.04 42,559.34 172,401.38 893,746.06 893,746.06


101(1) Removal of Structures and Obstruction
AS SUBMITTED 1.00 ls 721,344.68 18 129,842.04 42,559.34 172,401.38 893,746.06 893,746.06

AS EVALUATED 28.00 each 72,092.66 18 12,976.68 4,253.47 17,230.15 89,322.81 3,190.10


101(2) Removal of Actual Structures/Obstruction
AS SUBMITTED 28.00 each 72,092.66 18 12,976.68 4,253.47 17,230.15 89,322.81 3,190.10

AS EVALUATED 989.30 sq m 116,139.81 18 20,905.17 6,852.25 27,757.42 143,897.23 145.45


Removal of Actual Structure/Obstruction, 0.23m thick PCCP
101(3)b3
(Unreinforced)
AS SUBMITTED 989.30 sq m 116,139.81 18 20,905.17 6,852.25 27,757.42 143,897.23 145.45

AS EVALUATED 20.00 each 19,548.12 18 3,518.66 1,153.34 4,672.00 24,220.12 1,211.01


101(10) Removal of Existing Road Signs
AS SUBMITTED 20.00 each 19,548.12 18 3,518.66 1,153.34 4,672.00 24,220.12 1,211.01

AS EVALUATED 14,097.00 cu m 2,805,387.58 18 504,969.76 165,517.87 670,487.63 3,475,875.22 246.57


102(2) Surplus Common Excavation
AS SUBMITTED 14,097.00 cu m 2,805,387.58 18 504,969.76 165,517.87 670,487.63 3,475,875.22 246.57

AS EVALUATED 383.60 cu m 90,125.19 18 16,222.53 5,317.39 21,539.92 111,665.11 291.10


103(1)a Structure Excavation (Common soil)
AS SUBMITTED 383.60 cu m 90,125.19 18 16,222.53 5,317.39 21,539.92 111,665.11 291.10

AS EVALUATED 39.10 cu m 50,545.22 18 9,098.14 2,982.17 12,080.31 62,625.53 1,601.68


103(3) Foundation Fill
AS SUBMITTED 39.10 cu m 50,545.22 18 9,098.14 2,982.17 12,080.31 62,625.53 1,601.68

AS EVALUATED 194.30 cu m 45,649.96 18 8,216.99 2,693.35 10,910.34 56,560.30 291.10


103(6)a Pipe Culverts and Drain Excavation (Common soil)
AS SUBMITTED 194.30 cu m 45,649.96 18 8,216.99 2,693.35 10,910.34 56,560.30 291.10

AS EVALUATED 8,916.00 cu m 2,078,400.09 18 374,112.02 122,625.61 496,737.63 2,575,137.72 288.82


104(1)a Embankment from Roadway Excavation (Common Soil)
AS SUBMITTED 8,916.00 cu m 2,078,400.09 18 374,112.02 122,625.61 496,737.63 2,575,137.72 288.82

AS EVALUATED 32,774.00 sq m 531,275.28 18 95,629.55 31,345.24 126,974.79 658,250.07 20.08


105(1)a Subgrade Preparation (Common Material)
AS SUBMITTED 32,774.00 sq m 531,275.28 18 95,629.55 31,345.24 126,974.79 658,250.07 20.08

AS EVALUATED 19,163,554.59 3,449,439.83 1,130,649.74 4,580,089.57 23,743,644.16


TOTAL OF PART C
AS SUBMITTED 19,163,554.59 3,449,439.83 1,130,649.74 4,580,089.57 23,743,644.16

PART D SUBBASE AND BASE COURSE

AS EVALUATED 10,668.00 cu m 10,248,796.67 18 1,844,783.40 604,679.00 2,449,462.40 12,698,259.07 1,190.31


200(1) Aggregate Subbase Course
AS SUBMITTED 10,668.00 cu m 10,248,796.67 18 1,844,783.40 604,679.00 2,449,462.40 12,698,259.07 1,190.31

AS EVALUATED 10,248,796.67 1,844,783.40 604,679.00 2,449,462.40 12,698,259.07


TOTAL OF PART D
AS SUBMITTED 10,248,796.67 1,844,783.40 604,679.00 2,449,462.40 12,698,259.07

PART E SURFACE COURSE

Page 20 OF 4
QTY UNIT TOTAL DIRECT TOTAL MARK-UP 5% VAT TOTAL INDIRECT
ITEM NO. DESCRIPTION TOTAL COST UNIT COST
COST % VALUE COST

AS EVALUATED 2,157.00 cu m 2,729,585.57 18 491,325.40 161,045.55 652,370.95 3,381,956.53 1,567.90


300(1) Gravel Surface Course
AS SUBMITTED 2,157.00 cu m 2,729,585.57 18 491,325.40 161,045.55 652,370.95 3,381,956.53 1,567.90

AS EVALUATED 22,517.26 sq m 33,765,225.96 18 6,077,740.67 1,992,148.33 8,069,889.00 41,835,114.97 1,857.91


Portland Cement Concrete Pavement (Unreinforced), 0.28 m thick, 14
311(1)e1
days
AS SUBMITTED 22,517.26 sq m 33,765,225.96 18 6,077,740.67 1,992,148.33 8,069,889.00 41,835,114.97 1,857.91

AS EVALUATED 36,494,811.53 6,569,066.08 2,153,193.88 8,722,259.96 45,217,071.49


TOTAL OF PART E
AS SUBMITTED 36,494,811.53 6,569,066.08 2,153,193.88 8,722,259.96 45,217,071.49

PART F DRAINGE CONSTRUCTION

AS EVALUATED 18,537.14 kg 963,953.42 18 173,511.62 56,873.25 230,384.87 1,194,338.29 64.43


404(1)a Reinforcing Steel , Grade 40
AS SUBMITTED 18,537.14 kg 963,953.42 18 173,511.62 56,873.25 230,384.87 1,194,338.29 64.43

AS EVALUATED 192.10 cu m 1,245,030.01 18 224,105.40 73,456.77 297,562.17 1,542,592.19 8,030.15


405(1)a3 Structural Concrete, 20.68 MPa, Class "A", 28 days
AS SUBMITTED 192.10 cu m 1,245,030.01 18 224,105.40 73,456.77 297,562.17 1,542,592.19 8,030.15

AS EVALUATED 2,208,983.43 397,617.02 130,330.02 527,947.04 2,736,930.47


TOTAL OF PART F
AS SUBMITTED 2,208,983.43 397,617.02 130,330.02 527,947.04 2,736,930.47

PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES

AS EVALUATED 63.00 ln m 404,418.65 18 72,795.36 23,860.70 96,656.06 501,074.70 7,953.57


500(1)b3 Pipe Culverts, 910 mm dia. Class IV RCPC
AS SUBMITTED 63.00 ln m 404,418.65 18 72,795.36 23,860.70 96,656.06 501,074.70 7,953.57

AS EVALUATED 6.00 ln m 62,409.85 18 11,233.77 3,682.18 14,915.95 77,325.80 12,887.63


500(1)b5 Pipe Culverts, 1220 mm dia. Class IV RCPC
AS SUBMITTED 6.00 ln m 62,409.85 18 11,233.77 3,682.18 14,915.95 77,325.80 12,887.63

AS EVALUATED 1,650.80 cu m 4,862,135.02 18 875,184.30 286,865.97 1,162,050.27 6,024,185.29 3,649.25


505(2)a Grouted Riprap, Class A
AS SUBMITTED 1,650.80 cu m 4,862,135.02 18 875,184.30 286,865.97 1,162,050.27 6,024,185.29 3,649.25

AS EVALUATED 47.80 cu m 176,957.14 18 31,852.28 10,440.47 42,292.75 219,249.89 4,586.82


506(1) Stone Masonry
AS SUBMITTED 47.80 cu m 176,957.14 18 31,852.28 10,440.47 42,292.75 219,249.89 4,586.82

AS EVALUATED 8.00 cu m 11,250.74 18 2,025.13 663.79 2,688.92 13,939.66 1,742.46


508 (1) Hand Laid Rock Embankment
AS SUBMITTED 8.00 cu m 11,250.74 18 2,025.13 663.79 2,688.92 13,939.66 1,742.46

AS EVALUATED 44.00 cu m 118,476.47 18 21,325.76 6,990.11 28,315.87 146,792.34 3,336.19


511(1)a3 Gabions,1m x 1m x 2m, Metallic Coated
AS SUBMITTED 44.00 cu m 118,476.47 18 21,325.76 6,990.11 28,315.87 146,792.34 3,336.19

AS EVALUATED 39.30 sq m 7,637.70 18 1,374.79 450.62 1,825.41 9,463.10 240.79


511(3) Filter Cloth
AS SUBMITTED 39.30 sq m 7,637.70 18 1,374.79 450.62 1,825.41 9,463.10 240.79

Page 21 OF 4
QTY UNIT TOTAL DIRECT TOTAL MARK-UP 5% VAT TOTAL INDIRECT
ITEM NO. DESCRIPTION TOTAL COST UNIT COST
COST % VALUE COST

AS EVALUATED 5,643,285.56 1,015,791.40 332,953.84 1,348,745.24 6,992,030.80


TOTAL OF PART G
AS SUBMITTED 5,643,285.56 1,015,791.40 332,953.84 1,348,745.24 6,992,030.80

PART H MISCELLANEOUS STRUCTURE

AS EVALUATED 190.50 ln m 563,130.93 18 101,363.57 33,224.72 134,588.29 697,719.21 3,662.57


603(3)a1 Metal Guardrails (Metal Beam) Including Post, Single (W-Beam)
AS SUBMITTED 190.50 ln m 563,130.93 18 101,363.57 33,224.72 134,588.29 697,719.21 3,662.57

Page 22 OF 4
QTY UNIT TOTAL DIRECT TOTAL MARK-UP 5% VAT TOTAL INDIRECT
ITEM NO. DESCRIPTION TOTAL COST UNIT COST
COST % VALUE COST

AS EVALUATED 18.00 each 403,044.86 18 72,548.08 23,779.65 96,327.73 499,372.59 27,742.92


603(4)b Metal Beam End Piece (Bull Nose)
AS SUBMITTED 18.00 each 403,044.86 18 72,548.08 23,779.65 96,327.73 499,372.59 27,742.92

AS EVALUATED 1.00 each 6,052.43 18 1,089.44 357.09 1,446.53 7,498.96 7,498.96


Warning Signs, 750 mm, W2-6C, Intersection and Junction Signs Side
605(1)l3
Road Junction L or R
AS SUBMITTED 1.00 each 6,052.43 18 1,089.44 357.09 1,446.53 7,498.96 7,498.96

Warning Signs 450 x 700 mm, W4-2PA, Road Width Sign Road AS EVALUATED 6.00 each 40,279.49 18 7,250.31 2,376.49 9,626.80 49,906.29 8,317.72
605 (1)u4 Narrows
AS SUBMITTED 6.00 each 40,279.49 18 7,250.31 2,376.49 9,626.80 49,906.29 8,317.72

AS EVALUATED 2.00 each 13,004.86 18 2,340.87 767.29 3,108.16 16,113.02 8,056.51


Warning Signs, 750mm x 750mm, W6-1C, Pedestrian and School
605(1)ai2
Signs Pedestrian Crossing Ahead
AS SUBMITTED 2.00 each 13,004.86 18 2,340.87 767.29 3,108.16 16,113.02 8,056.51

AS EVALUATED 2.00 each 13,004.86 18 2,340.87 767.29 3,108.16 16,113.02 8,056.51


Warning Signs, 750mm x 750mm, W6-2C, Pedestrian and School
605(1)aj2
Signs Children Crossing
AS SUBMITTED 2.00 each 13,004.86 18 2,340.87 767.29 3,108.16 16,113.02 8,056.51

AS EVALUATED 1.00 each 6,502.43 18 1,170.44 383.64 1,554.08 8,056.51 8,056.51


605(2)a3 Regulatory Signs, 750mm x 750mm, R1-1C, Priority Signs Stop
AS SUBMITTED 1.00 each 6,502.43 18 1,170.44 383.64 1,554.08 8,056.51 8,056.51

AS EVALUATED 2.00 each 12,104.86 18 2,178.87 714.19 2,893.06 14,997.92 7,498.96


Regulatory Signs, 750 mm, R6-8C, Miscellaneous Signs Pedestrian
605(2)ai3
Crossing
AS SUBMITTED 2.00 each 12,104.86 18 2,178.87 714.19 2,893.06 14,997.92 7,498.96

AS EVALUATED 2.00 each 12,104.86 18 2,178.87 714.19 2,893.06 14,997.92 7,498.96


Regulatory Signs, 750 mm ,R6-9C, Miscellaneous Signs School
605(2)aj3
Children Crossing
AS SUBMITTED 2.00 each 12,104.86 18 2,178.87 714.19 2,893.06 14,997.92 7,498.96

AS EVALUATED 18.00 each 176,759.55 18 31,816.72 10,428.81 42,245.53 219,005.08 12,166.95


605(6)e1 Hazard Markers, 450x600mm, Chevron Signs
AS SUBMITTED 18.00 each 176,759.55 18 31,816.72 10,428.81 42,245.53 219,005.08 12,166.95

AS EVALUATED 5,040.00 each 115,009.44 18 20,701.70 6,785.56 27,487.26 142,496.70 28.27


611(1) Trees Furnishing and Transplanting
AS SUBMITTED 5,040.00 each 115,009.44 18 20,701.70 6,785.56 27,487.26 142,496.70 28.27

AS EVALUATED 1,079.74 sq m 782,145.62 18 140,786.21 46,146.59 186,932.80 969,078.43 897.51


612(1) Reflectorized Thermoplastic Pavement Markings (White)
AS SUBMITTED 1,079.74 sq m 782,145.62 18 140,786.21 46,146.59 186,932.80 969,078.43 897.51

AS EVALUATED 1,008.24 sq m 737,085.25 18 132,675.34 43,488.03 176,163.37 913,248.62 905.78


612(2) Reflectorized Thermoplastic Pavement Markings (Yellow)
AS SUBMITTED 1,008.24 sq m 737,085.25 18 132,675.34 43,488.03 176,163.37 913,248.62 905.78

AS EVALUATED 128.40 ln m 73,284.79 18 13,191.26 4,323.80 17,515.06 90,799.85 707.16


622(2)c Cocologs/Fascine, CN300
AS SUBMITTED 128.40 ln m 73,284.79 18 13,191.26 4,323.80 17,515.06 90,799.85 707.16

AS EVALUATED 756.80 sq m 102,256.38 18 18,406.15 6,033.13 24,439.28 126,695.66 167.41


622(3)b Vegetation, Vetiver Grass System
AS SUBMITTED 756.80 sq m 102,256.38 18 18,406.15 6,033.13 24,439.28 126,695.66 167.41

Page 23 OF 4
QTY UNIT TOTAL DIRECT TOTAL MARK-UP 5% VAT TOTAL INDIRECT
ITEM NO. DESCRIPTION TOTAL COST UNIT COST
COST % VALUE COST

AS EVALUATED 3,055,770.61 550,038.71 180,290.47 730,329.18 3,786,099.79


TOTAL OF PART H
AS SUBMITTED 3,055,770.61 550,038.71 180,290.47 730,329.18 3,786,099.79

AS EVALUATED 79,653,481.53 14,054,569.93 4,685,402.58 18,739,972.51 98,393,454.04

AS SUBMITTED 79,653,481.53 14,054,569.93 4,685,402.58 18,739,972.51 98,393,454.04


79,653,481.53 14,054,569.93 4,683,684.53 18,738,254.46 98,391,735.99
- - 1,718.05 1,718.05 1,718.05

Preparation and Submission: Evaluation: Approval:

Prepared By: Reviewed as to Unit Cost: Recommending Approval:

JESSICA B. APOSTOL TEOFILA U TAN ARTURO P. LONGYAPON


Engineer II CHIEF, Planning and Design Division Assistant Regional Director

Checked/Submitted By: Approved:

JUDY ANN T. BERNARDINO REY PETER B. GILLE, DM


Engineer IV Regional Director

Page 24 OF 4
245,560.68

16,826.96

262,387.64

25,993.73

5,531.12

1,353,330.31

1,033,265.62

354,244.80

2,772,365.58

202,789.11

9,287.90

Page 25 OF 4
893,746.06

3,190.10

1,211.01

246.57

291.10

1,601.68

291.10

288.82

20.08

1,112,963.53

1,190.31

Page 26 OF 4
1,567.90

1,857.91

3,425.81

64.43

8,030.15

8,094.58

7,953.57

12,887.63

3,649.25

4,586.82

1,742.46

3,336.19

240.79

Page 27 OF 4
30,819.73

3,662.57

Page 28 OF 4
27,742.92

7,498.96

8,317.72

8,056.51

8,056.51

8,056.51

7,498.96

7,498.96

12,166.95

28.27

897.51

905.78

707.16

167.41

Page 29 OF 4
- 61,483.68

4,296,086.87 #NAME? #NAME?

98,391,735.99
- 79,653,481.53
- 14,054,569.93 1190
1,718.05 4,683,684.53

98,357,375.07

Page 30 OF 4
Department of Public Works and Highways (DPWH)
FORM ABC-2015-02-00

ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

SUMMARY OF APPROVED BUDGET FOR THE CONTRACT


Contract Duration: 264 C.D.
TOTAL MARK-UP 5% VAT TOTAL INDIRECT
ITEM NO. DESCRIPTION ESTIMATED DIRECT COST TOTAL COST
% VALUE COST
AS EVALUATED 316,901.36 18 45,171.37 18,103.64 63,275.01 380,176.37
PART A FACILITIES FOR THE ENGINEER
AS SUBMITTED 316,901.36 18 45,171.37 18,103.64 63,275.01 380,176.37
AS EVALUATED 2,521,377.78 18 182,662.12 135,201.99 317,864.11 2,839,241.89
PART B OTHER GENERAL REQUIREMENTS
AS SUBMITTED 2,521,377.78 18 182,662.12 135,201.99 317,864.11 2,839,241.89
AS EVALUATED 19,163,554.59 18 3,449,439.83 1,130,649.74 4,580,089.57 23,743,644.16
PART C EARTHWORK
AS SUBMITTED 19,163,554.59 18 3,449,439.83 1,130,649.74 4,580,089.57 23,743,644.16
AS EVALUATED 10,248,796.67 18 1,844,783.40 604,679.00 2,449,462.40 12,698,259.07
PART D SUBBASE AND BASE COURSE
AS SUBMITTED 10,248,796.67 18 1,844,783.40 604,679.00 2,449,462.40 12,698,259.07
AS EVALUATED 36,494,811.53 18 6,569,066.08 2,153,193.88 8,722,259.96 45,217,071.49
PART E SURFACE COURSE
AS SUBMITTED 36,494,811.53 18 6,569,066.08 2,153,193.88 8,722,259.96 45,217,071.49
AS EVALUATED 2,208,983.43 18 397,617.02 130,330.02 527,947.04 2,736,930.47
PART F DRAINAGE CONSTRUCTION
AS SUBMITTED 2,208,983.43 18 397,617.02 130,330.02 527,947.04 2,736,930.47
AS EVALUATED 5,643,285.56 18 1,015,791.40 332,953.84 1,348,745.24 6,992,030.80
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
AS SUBMITTED 5,643,285.56 18 1,015,791.40 332,953.84 1,348,745.24 6,992,030.80
AS EVALUATED 3,055,770.61 18 550,038.71 180,290.47 730,329.18 3,786,099.79
PART H MISCELLANEOUS STRUCTURE
AS SUBMITTED 3,055,770.61 18 550,038.71 180,290.47 730,329.18 3,786,099.79
AS EVALUATED 79,653,481.53 14,054,569.93 4,685,402.54 18,739,972.47 98,393,454.00
GRAND TOTAL
AS SUBMITTED 79,653,481.53 14,054,569.93 4,685,402.54 18,739,972.47 98,393,454.00
79,653,481.53 14,054,569.93 4,685,402.58 18,739,972.51 98,393,454.04
- - - (0.04) (0.04) (0.04)
Preparation and Submission: Evaluation: Approval:

Prepared By: Reviewed as to Unit Cost: Recommending Approval:

JESSICA B. APOSTOL TEOFILA U TAN ARTURO P. LONGYAPON


Engineer II CHIEF, Planning and Design Division Assistant Regional Director

Checked/Submitted By: Approved:

JUDY ANN T. BERNARDINO REY PETER B. GILLE, D.M.


Engineer IV OIC - Regional Director

Summary of ABC
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART A FACILITIES FOR THE ENGINEER

AS SUBMITTED 1.00 ls 152,455.88 45,736.76 - 198,192.64 18.00% 35,674.67 11,693.37 245,560.68


A.1.1(3) Construction of Field Office for the Engineer
AS EVALUATED 1.00 ls 152,455.88 45,736.76 - 198,192.64 18.00% 35,674.67 11,693.37 245,560.68

AS SUBMITTED 8.00 mo 41,092.72 77,616.00 - 118,708.72 8.00% 9,496.70 6,410.27 134,615.69


A.1.1(16) Operation & Maintenance of Field Office for the Engineer
AS EVALUATED 8.00 mo 41,092.72 77,616.00 118,708.72 8.00% 9,496.70 6,410.27 134,615.69

AS SUBMITTED 193,548.60 123,352.76 - 316,901.36 18.00% 45,171.37 18,103.64 380,176.36


TOTAL OF PART A
AS EVALUATED 193,548.60 123,352.76 - 316,901.36 18.00% 45,171.37 18,103.64 380,176.36

PART B OTHER GENERAL REQUIREMENTS

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 8.00% - - -

AS EVALUATED - - - - - - 8.00% - - -

AS SUBMITTED - 8.00% - - -

AS EVALUATED - - - - - - 8.00% - - -

AS SUBMITTED - 0.00% - - -

AS EVALUATED - - - - - - 0.00% - - -

AS SUBMITTED - - - - 18.00% - - -
TOTAL OF PART B
AS EVALUATED - - - - 18.00% - - -

PART C EARTHWORKS

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

32 of 218
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
AS EVALUATED - - - - - - 18.00% - - -

33 of 218
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - - - - 18.00% - - -
TOTAL OF PART C
AS EVALUATED - - - - 18.00% - - -

PART D SUBBASE AND BASE COURSE

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - - - - 18.00% - - -
TOTAL OF PART D
AS EVALUATED - - - - 18.00% - - -

PART E SURFACE COURSE

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - - - - 18.00% - - -
TOTAL OF PART E
AS EVALUATED - - - - 18.00% - - -

PART F DRAINAGE CONSTRUCTION

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - - - - 18.00% - - -
TOTAL OF PART F

34 of 218
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
TOTAL OF PART F
AS EVALUATED - - - - 18.00% - - -

35 of 218
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES

AS SUBMITTED - 18.00% - - -

AS EVALUATED - 0 - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - 0 - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - 0 - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - 0 - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - 0 - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - 0 - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - 0 - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - 0 - - - - 18.00% - - -

AS SUBMITTED - - - - 18.00% - - -
TOTAL OF PART G
AS EVALUATED - - - - 18.00% - - -

PART H MISCELLANEOUS STRUCTURES

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

36 of 218
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - 18.00% - - -

AS EVALUATED - - - - - - 18.00% - - -

AS SUBMITTED - - - - 18.00% - - -
TOTAL OF PART H
AS EVALUATED - - - - 18.00% - - -

AS SUBMITTED 193,548.60 123,352.76 - 316,901.36 18.00% 45,171.37 18,103.63 380,176.35


GRAND TOTAL
AS EVALUATED 193,548.60 123,352.76 - 316,901.36 18.00% 45,171.37 18,103.63 380,176.35

37 of 218
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : A.1.1(3) Construction of Field Office for the Engineer

Unit of Measurement : ls
Output per hour - As Submitted :
Output per hour - As Evaluated :
Quantity : 1.0 ls

Designation No. of Person/s No. of Hours/s Hourly Rate Amount (Php)

Labor
A.1
Labor 1 ls 45,736.76 45,736.76

Sub - Total for A.1 - As Submitted 45,736.76


Labor
Labor 1 ls 45,736.76 45,736.76
A.2

Sub - Total for A.2 - As Evaluated 45,736.76


Name and Capacity No. of Unit/s No. of Hours/s Hourly Rate Amount (Php)

B.1 Equipment

Sub - Total for B.1 - As Submitted


Equipment
B.2
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted
C.2 Total (A.2 + B.2) - As Evaluated
D.1 Output per hour - As Submitted
D.2 Output per hour - As Evaluated
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
STRUCTURAL / MASONRY / FORMWORKS ls 1.0 38,366.46 38,366.46
FLOORING / FLOOR FRAMING / STAIRS ls 1.0 26,770.38 26,770.38
F.1 PARTITION, SIDING, DOOR / WINDOWS ls 1.0 36,346.28 36,346.28
ROOFING AND ROOF FRAMING ls 1.0 31,885.26 31,885.26
ELECTRICAL ls 1.0 8,842.00 8,842.00
PLUMBING ls 1.0 10,245.50 10,245.50
Sub - Total for F.1 - As Submitted 152,455.88
Materials
STRUCTURAL / MASONRY / FORMWORKS ls 1.0 38,366.46 38,366.46
FLOORING / FLOOR FRAMING / STAIRS ls 1.0 26,770.38 26,770.38
PARTITION, SIDING, DOOR / WINDOWS ls 1.0 36,346.28 36,346.28
F.2 ROOFING AND ROOF FRAMING ls 1.0 31,885.26 31,885.26
ELECTRICAL ls 1.0 8,842.00 8,842.00
PLUMBING ls 1.0 10,245.50 10,245.50

Sub - Total for F.2 - As Evaluated 152,455.88


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 198,192.64
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 198,192.64
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 19,819.26
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 19,819.26
I.1 Contractor's Profit (CP) - As Submitted 8% 15,855.41
I.2 Contractor's Profit (CP) - As Evaluated 8% 15,855.41
J.1 Value Added Tax (VAT) - As Submitted 5% 11,693.37
J.2 Value Added Tax (VAT) - As Evaluated 5% 11,693.37
K.1 Total Unit Cost - As Submitted 245,560.68
K.2 Total Unit Cost - As Evaluated 245,560.68

Prepared by: Checked/Reviewed by:


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
JESSICA B. APOSTOL JUDY ANN T. BERNARDINO
Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : A.1.1(16) Operation & Maintenance of Field Office for the Engineer

Unit of Measurement : mo
Output per hour - As Submitted :
Output per hour - As Evaluated :
Quantity : 8.0 mo

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)

Labor
A.1
Utility man 1 1 9,702.00 9,702.00

Sub - Total for A.1 - As Submitted 9,702.00


Labor
Utility man 1 1 9,702.00 9,702.00
A.2

Sub - Total for A.2 - As Evaluated 9,702.00


Name and Capacity No. of Unit/s No. of Hours/s Hourly Rate Amount (Php)

B.1 Equipment

Sub - Total for B.1 - As Submitted


Equipment
B.2
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 9,702.00
C.2 Total (A.2 + B.2) - As Evaluated 9,702.00
D.1 Output per hour - As Submitted 1
D.2 Output per hour - As Evaluated 1
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 9,702.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 9,702.00
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
Coupon Bond short ream 0.20 146.55 29.31
Coupon bond long ream 0.20 235.40 47.08
Envelope short dozen 0.20 27.00 5.40
Envelope long dozen 0.20 33.00 6.60
ballpen Assorted Color dozen 0.20 57.00 11.40
log book pc 0.20 42.75 8.55
Stapler no.35 pc 0.20 212.75 42.55
Staple wire no.35 box 0.20 27.75 5.55
Bulletin/cork board 2 x 3 pc 0.20 1,225.00 245.00
File tray in & out pc 0.20 299.75 59.95
F.1 fastener plastic coated box 0.20 28.75 5.75
mechanical pencil box 0.20 477.00 95.40
masking tape roll 0.20 39.00 7.80
paper clip plastic coated box 0.20 20.75 4.15
Folder long dozen 0.20 56.75 11.35
Stabilo Hi-liter Assorted color pc 0.20 29.75 5.95
Sign pen( G-Tech) pc 0.20 80.00 16.00
Ink printer( black,blue,red,yellow) set 0.20 2,644.00 528.80
Utilities
a. Water Bill mo 1 1,000.00 1,000.00
b. Electricity Bill mo 1 3,000.00 3,000.00

Sub - Total for F.1 - As Submitted 5,136.59


Materials
Coupon Bond short ream 0.20 146.55 29.31
Coupon bond long ream 0.20 235.40 47.08
Envelope short dozen 0.20 27.00 5.40
F.2 Envelope long dozen 0.20 33.00 6.60
ballpen Assorted Color dozen 0.20 57.00 11.40
log book pc 0.20 42.75 8.55
F.2
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
Stapler no.35 pc 0.20 212.75 42.55
Staple wire no.35 box 0.20 27.75 5.55
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

Name and Specification Unit Quantity Unit Cost Amount (Php)


Bulletin/cork board 2 x 3 pc 0.20 1,225.00 245.00
File tray in & out pc 0.20 299.75 59.95
fastener plastic coated box 0.20 28.75 5.75
mechanical pencil box 0.20 477.00 95.40
masking tape roll 0.20 39.00 7.80
paper clip plastic coated box 0.20 20.75 4.15
Folder long dozen 0.20 56.75 11.35
Stabilo Hi-liter Assorted color pc 0.20 29.75 5.95
Sign pen( G-Tech) pc 0.20 80.00 16.00
Ink printer( black,blue,red,yellow) set 0.20 2,644.00 528.80
Utilities
a. Water Bill mo 1.00 1,000.00 1,000.00
b. Electricity Bill mo 1.00 3,000.00 3,000.00

Sub - Total for F.2 - As Evaluated 5,136.59


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 14,838.59
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 14,838.59
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10%
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10%
I.1 Contractor's Profit (CP) - As Submitted 8% 1,187.09
I.2 Contractor's Profit (CP) - As Evaluated 8% 1,187.09
J.1 Value Added Tax (VAT) - As Submitted 5% 801.28
J.2 Value Added Tax (VAT) - As Evaluated 5% 801.28386
K.1 Total Unit Cost - As Submitted 16,826.96
K.2 Total Unit Cost - As Evaluated 16,826.96

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
LABOR MATERIAL EQUIPMENT

45,736.76

152,455.88
77,616.00

41,092.72
123,352.76 193,548.60 -
LABOR MATERIAL EQUIPMENT
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : B.4(1) Construction survey and staking

Unit of Measurement : km
Output per hour - As Submitted :
Output per hour - As Evaluated :
Quantity : 3.360 km

Designation No. of Person/s No. of days Hourly Rate Amount (Php)

Labor
Instrumentman 2 2 875.52 3,502.08
A.1
surveyman 4 2 875.52 7,004.16
laborer 3 2 488.56 2,931.36

Sub - Total for A.1 - As Submitted 13,437.60


Labor
Instrumentman 2 2 875.52 3,502.08
surveyman 4 2 875.52 7,004.16
A.2
laborer 3 2 488.56 2,931.36

Sub - Total for A.2 - As Evaluated 13,437.60


Name and Capacity No. of Unit/s No. of mo Monthly Rate Amount (Php)
B.1 Equipment
-
Sub - Total for B.1 - As Submitted -
Equipment
B.2
Sub - Total for B.2 - As Evaluated
C.1 Total (A.1 + B.1) - As Submitted 13,437.60
C.2 Total (A.2 + B.2) - As Evaluated 13,437.60
D.1 Output per hour - As Submitted 1
D.2 Output per hour - As Evaluated 1
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 13,437.60
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 13,437.60
Name and Specification Unit Quantity Unit Cost Amount (Php)

Materials
2 x 2 x 8 coco lumber=70 pcs bd dt 300 12.00 3,600.00
F.1
paint gal 6 614.00 3,684.00
Field books pcs 6 43.00 258.00

Sub - Total for F.1 - As Submitted 7,542.00


Materials
2 x 2 x 8 coco lumber=70 pcs bd dt 300 12.00 3,600.00
paint gal 6 614.00 3,684.00
F.2
Field books pcs 6 43.00 258.00

Sub - Total for F.2 - As Evaluated 7,542.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 20,979.60
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 20,979.60
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 2,097.96
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 2,097.96
I.1 Contractor's Profit (CP) - As Submitted 8% 1,678.37
I.2 Contractor's Profit (CP) - As Evaluated 8% 1,678.37
J.1 Value Added Tax (VAT) - As Submitted 5% 1,237.80
J.2 Value Added Tax (VAT) - As Evaluated 5% 1,237.80
K.1 Total Unit Cost - As Submitted 25,993.72
K.2 Total Unit Cost - As Evaluated 25,993.72

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
Engineer II Engineer IV

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : B.5 Project Billboard / Signboard


Unit of Measurement : each
Output per hour - As Submitted :
Output per hour - As Evaluated :
Quantity : 2.00 each
Designation No. of Person/s No. of days Daily Rate Amount (Php)
Labor
A.1 a. Construction Foreman 1 1 875.52 875.52
b. Skilled Labor 1 1 633.36 633.36
c. Unskilled Labor 1 1 488.56 488.56
Sub - Total for A.1 - As Submitted 1,997.44
Labor
a. Construction Foreman 1 1 875.52 875.52
A.2 b. Skilled Labor 1 1 633.36 633.36
c. Unskilled Labor 1 1 488.56 488.56
Sub - Total for A.2 - As Evaluated 1,997.44
Name and Capacity No. of Unit/s No. of mo Monthly Rate Amount (Php)
Equipment
B.1
Minor Tools (10% of Labor Cost) 199.74
Sub - Total for B.1 - As Submitted 199.74
Equipment
B.2 Minor Tools (10% of Labor Cost) 199.74
Sub - Total for B.2 - As Evaluated 199.74
C.1 Total (A.1 + B.1) - As Submitted 2,197.18
C.2 Total (A.2 + B.2) - As Evaluated 2,197.18
D.1 Output per hour - As Submitted 1
D.2 Output per hour - As Evaluated 1
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 2,197.18
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 2,197.18
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
Post 3-2"x3"x10' bd.ft 15 13.00 195.00
Diagonal bracing 3-2"x3"x10' bd.ft 15 13.00 195.00
Cross Bracing 2-2"x2"x10' bd.ft 10 13.00 130.00
F.1
Wooden Stake 1-2"x2"x10' bd.ft 4 13.00 52.00
1/2" thk x 4 x 8 Marine Plywood sht 1 710.00 710.00
Assorted C.W. Nails kg 1 61.00 61.00
Tarpaulin (1.2mx2.4m) sq ft 33 28.00 924.00
Sub - Total for F.1 - As Submitted 2,267.00
Materials
Post 3-2"x3"x10' bd.ft 15 13.00 195.00
Diagonal bracing 3-2"x3"x10' bd.ft 15 13.00 195.00
Cross Bracing 2-2"x2"x10' bd.ft 10 13.00 130.00
F.2 Wooden Stake 1-2"x2"x10' bd.ft 4 13.00 52.00
1/2" thk x 4 x 8 Marine Plywood sht 1 710.00 710.00
Assorted C.W. Nails kg 1 61.00 61.00
Tarpaulin (1.2mx2.4m) sq ft 33 28.00 924.00
Sub - Total for F.2 - As Evaluated 2,267.00
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 4,464.18
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 4,464.18
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 446.42
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 446.42
I.1 Contractor's Profit (CP) - As Submitted 8% 357.13
I.2 Contractor's Profit (CP) - As Evaluated 8% 357.13
J.1 Value Added Tax (VAT) - As Submitted 5% 263.39
J.2 Value Added Tax (VAT) - As Evaluated 5% 263.39
K.1 Total Unit Cost - As Submitted 5,531.12
K.2 Total Unit Cost - As Evaluated 5,531.12

Prepared by: Checked/Reviewed by:


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : B.7(2) Occupational Safety and Health Program


Unit of Measurement : ls
Output per hour - As Submitted :
Output per hour - As Evaluated :
Quantity : 1.00 ls

Designation No. of Person/s No. of days Hourly Rate Amount (Php)

Labor
A.1 a. Safety Practitioner/Officer (Full time) 1 280 875.52 245,460.79
b. Health Personnel (Full time First Aider) 1 280 633.36 177,568.81
c. Sanitation aide 2 280 488.56 273,945.36
Sub - Total for A.1 - As Submitted 696,974.96
Labor
a. Safety Practitioner/Officer (Full time) 1 280 875.52 245,460.79
A.2 b. Health Personnel (Full time First Aider) 1 280 633.36 177,568.81
c. Sanitation aide 2 280 488.56 273,945.36
Sub - Total for A.2 - As Evaluated 696,974.96
Name and Capacity No. of Unit/s No. of hrs Monthly Rate Amount (Php)
Equipment
a. Portable Mist-Based Sanitation Tent 1 2242.88 9.79 21,957.80
B.1 b. Thermal Scanner (w/ rechargeable battery) 2 2242.88 1.03 4,620.33
c. Power Sprayer with complete accessories 1 2242.88 3.47 7,782.79

Sub - Total for B.1 - As Submitted 34,360.92


Equipment
a. Portable Mist-Based Sanitation Tent 1 2242.88 9.79 21,957.80
B.2 b. Thermal Scanner (w/ rechargeable battery) 2 2242.88 1.03 4,620.33
c. Power Sprayer with complete accessories 1 2242.88 3.47 7,782.79
Sub - Total for B.2 - As Evaluated 34,360.92
C.1 Total (A.1 + B.1) - As Submitted 731,335.88
C.2 Total (A.2 + B.2) - As Evaluated 731,335.88
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 731,335.88
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 731,335.88
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Safety Helmet man days 4789.15 0.25 1,197.29
b. Safety Shoes man days 1712.37 2.77 4,743.26
c. Safety vest man days 4789.15 2.22 10,631.91
d. Working Gloves man days 4781.69 7.67 36,675.56
e. Rubber Boots man days 3076.78 1.39 4,276.72
f. Face Mask (Surgical/Cloth) man days 4789.15 10.00 47,891.50
g. Eye Googles man days 4789.15 5.00 23,945.75
Optional (if necessary)
F.1 Rain coats (30% of the duration) man days 1436.745 0.34 488.49

Department Order No. 39 s. 2020


Revised Construction Safety Guidelines for the Implementation of Infrastructure Projects During COVID-19 Public Health Crisis
COVID 19 Rapid Antibody Test
Antiseptics and Disinfectant
h. Sanitizing Solution lit 841 100.00 84,108.00
i. Ethyl Alcohol lit 280 185.00 51,866.60
j. Disinfectant Spray can 140 1000.00 140,180.00
k. Liquid Hand Soap lit 280 200.00 56,072.00
Sub - Total for F.1 - As Submitted 462,077.10
Materials
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
a. Safety Helmet man days 4789.15 0.25 1,197.29
b. Safety Shoes man days 1712.37 2.77 4,743.26
c. Safety vest man days 4789.15 2.22 10,631.91
d. Working Gloves man days 4781.69 7.67 36,675.56
e. Rubber Boots man days 3076.78 1.39 4,276.72
f. Face Mask (Surgical/Cloth) man days 4789.15 10.00 47,891.50
g. Eye Googles man days 4789.15 5.00 23,945.75
Optional (if necessary)
F.2
Rain coats (30% of the duration) man days 1436.745 0.34 488.49

COVID 19 Rapid Antibody Test


Antiseptics and Disinfectant
h. Sanitizing Solution lit 841 100.00 84,108.00
i. Ethyl Alcohol lit 280 185.00 51,866.60
j. Disinfectant Spray can 140 1000.00 140,180.00
k. Liquid Hand Soap lit 280 200.00 56,072.00
Sub - Total for F.2 - As Evaluated 462,077.10
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 1,193,412.98
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 1,193,412.98
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10%
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10%
I.1 Contractor's Profit (CP) - As Submitted 8% 95,473.04
I.2 Contractor's Profit (CP) - As Evaluated 8% 95,473.04
J.1 Value Added Tax (VAT) - As Submitted 5% 64,444.30
J.2 Value Added Tax (VAT) - As Evaluated 5% 64,444.30
K.1 Total Unit Cost - As Submitted 1,353,330.32
K.2 Total Unit Cost - As Evaluated 1,353,330.32

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : B.8(2) Traffic Management

Unit of Measurement : ls
Output per hour - As Submitted :
Output per hour - As Evaluated :
Quantity : 1.00 ls

Designation No. of Person/s No. of hrs Hourly Rate Amount (Php)


Labor

A.1 Traffic controller 2 8 61.07 273,945.36

Sub - Total for A.1 - As Submitted 273,945.36


Labor

Traffic controller 2 8 61.07 273,945.36


A.2

Sub - Total for A.2 - As Evaluated 273,945.36


Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
Barricade Flasher light 8 8.00 0.65 11,662.98
(3 volts,battery operated,amber color wl lifespan
B.1 consideration of 6t month)
stake truck 1 2.00 712 399,232.64
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
B.1
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
tower light 1 1 905.75 57,968.00

Sub - Total for B.1 - As Submitted 468,863.62


Equipment
Barricade Flasher light 8 8.00 0.65 11,662.98
(3 volts,battery operated,amber color wl lifespan
consideration of 6t month)
B.2
stake truck 1 2.00 712 399,232.64
tower light 1 1.00 905.75 57,968.00

Sub - Total for B.2 - As Evaluated 468,863.62


C.1 Total (A.1 + B.1) - As Submitted 742,808.98
C.2 Total (A.2 + B.2) - As Evaluated 742,808.98
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 742,808.98
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 742,808.98
Name and Specification Unit Quantity Unit Cost Amount (Php)

Materials
LAY OUT 5
Roadwork ahead(T1-1) ea 8 3285.00 26,280.00
Workmen Ahead(T1-5) ea 8 1692.00 13,536.00
Lane Status (T2-6-1) ea 8 2658.00 21,264.00
F.1
Temporary hazard Marker (chevron T5-5) ea 10 2403.00 24,030.00
Traffic Cones @ 5 meters span ea 150 555.00 83,250.00

Sub - Total for F.1 - As Submitted 168,360.00


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

Name and Specification Unit Quantity Unit Cost Amount (Php)

Materials
Roadwork ahead(T1-1) ea 8 3285.00 26,280.00
Workmen Ahead(T1-5) ea 8 1692.00 13,536.00
Lane Status (T2-6-1) ea 8 2658.00 21,264.00
F.2 Temporary hazard Marker (chevron T5-5) ea 10 2403.00 24,030.00
Traffic Cones @ 5 meters span ea 150 555.00 83,250.00

Sub - Total for F.2 - As Evaluated 168,360.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 911,168.98
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 911,168.98
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10%
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10%
I.1 Contractor's Profit (CP) - As Submitted 8% 72,893.52
I.2 Contractor's Profit (CP) - As Evaluated 8% 72,893.52
J.1 Value Added Tax (VAT) - As Submitted 5% 49,203.12
J.2 Value Added Tax (VAT) - As Evaluated 5% 49,203.12
K.1 Total Unit Cost - As Submitted 1,033,265.62
K.2 Total Unit Cost - As Evaluated 1,033,265.62

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : B.9 Mobilization / Demobilization


Unit of Measurement : ls
Output per hour - As Submitted :
Output per hour - As Evaluated :
Quantity : 1.00 ls

Designation No. of Person/s No. of days Hourly Rate Amount (Php)


A.1 Labor
-
Sub - Total for A.1 - As Submitted -
Labor
A.2
Sub - Total for A.2 - As Evaluated
Name and Capacity No. of Unit/s No. of hrs Monthly Rate Amount (Php)
Equipment 192.00 1189 228,288.00
a. Backhoe 4 32.00
b. Bulldozer w/ ripper 4 32.00
c. Backhoe w/ Pavement breaker 4 32.00
d. Grader 4 32.00
e. Road Roller 4 32.00
f. payloader 4 32.00
B.1 g. Transit mixer 4 32.00 1279 40,928.00
h. Dumptruck 6 48.00 1420 68,160.00

Mobilization 1% of Direct Cost


Direct Cost Amount 76,815,202.40
1%
Mobilization 1% of Direct Cost 768,152.02

Sub - Total for B.1 - As Submitted 337,376.00


Equipment 192.00 1189 228,288.00
a. Backhoe 4 32.00
b. Bulldozer w/ ripper 4 32.00
c. Backhoe w/ Pavement breaker 4 32.00
d. Grader 4 32.00
e. Road Roller 4 32.00
f. payloader 4 32.00
g. Transit mixer 4 32.00 1279 40,928.00
h. Dumptruck 6 48.00 1420 68,160.00

Mobilization 1% of Direct Cost


Direct Cost Amount 76,815,202.40
1%
Mobilization 1% of Direct Cost 768,152.02

Sub - Total for B.2 - As Evaluated 337,376.00


C.1 Total (A.1 + B.1) - As Submitted 337,376.00
C.2 Total (A.2 + B.2) - As Evaluated 337,376.00
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 337,376.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 337,376.00
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
-
Sub - Total for F.1 - As Submitted -
Materials
F.2
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
F.2
Sub - Total for F.2 - As Evaluated
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 337,376.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 337,376.00
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10%
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10%
I.1 Contractor's Profit (CP) - As Submitted 8%
I.2 Contractor's Profit (CP) - As Evaluated 8%
J.1 Value Added Tax (VAT) - As Submitted 5% 16,868.80
J.2 Value Added Tax (VAT) - As Evaluated 5% 16,868.80
K.1 Total Unit Cost - As Submitted 354,244.80
K.2 Total Unit Cost - As Evaluated 354,244.80

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
LABOR MATERIAL EQUIPMENT

45,150.34

25,341.12
3,994.88

399.49

4,534.00
696,974.96

462,077.10
273,945.36

300
(98,391,735.99)
468,863.62

29,283,254.76

168,360.00
29,283,254.76

337,376.00
1,020,065.54 660,312.22 806,639.10
LABOR MATERIAL EQUIPMENT
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 100(1) Clearing and Grubbing

Unit of Measurement : ha
Output per hour - As Submitted : 0.05
Output per hour - As Evaluated : 0.05
Quantity : 0.24 ha

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


Labor
A.1 a. Construction Foreman 1 1 109.44 109.44
b. Unskilled Labor 2 1 61.07 122.14

Sub - Total for A.1 - As Submitted 231.58


Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 b. Unskilled Labor 2 1 61.07 122.14

Sub - Total for A.2 - As Evaluated 231.58


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
Equipment
a. Dump Truck (12 yd³) 2 1.00 1420.00 2,840.00
B.1
b. Payloader (1.50 m³) 1 1.00 1733.00 1,733.00
c. Bulldozer, D6H SERIES II PSDS/DD 1 1.00 3379.00 3,379.00

Sub - Total for B.1 - As Submitted 7,952.00


Equipment
a. Dump Truck (12 yd³) 2 1.00 1420.00 2,840.00
b. Payloader (1.50 m³) 1 1.00 1733.00 1,733.00
B.2
c. Bulldozer, D6H SERIES II PSDS/DD 1 1.00 3379.00 3,379.00

Sub - Total for B.2 - As Evaluated 7,952.00


C.1 Total (A.1 + B.1) - As Submitted 8,183.58
C.2 Total (A.2 + B.2) - As Evaluated 8,183.58
D.1 Output per hour - As Submitted 0.05
D.2 Output per hour - As Evaluated 0.05
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 163,671.60
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 163,671.60
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials

Sub - Total for F.1 - As Submitted


Materials
F.2
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 163,671.60
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 163,671.60
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 16,367.16
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 16,367.16
I.1 Contractor's Profit (CP) - As Submitted 8% 13,093.73
I.2 Contractor's Profit (CP) - As Evaluated 8% 13,093.73
J.1 Value Added Tax (VAT) - As Submitted 5% 9,656.62
J.2 Value Added Tax (VAT) - As Evaluated 5% 9,656.62
K.1 Total Unit Cost - As Submitted 202,789.11
K.2 Total Unit Cost - As Evaluated 202,789.11

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 100(3)a3 Individual Removal of Trees, 501-750 mm dia. (Small)

Unit of Measurement : each


Output per hour - As Submitted : 1
Output per hour - As Evaluated : 1
Quantity : 1,680.00 each

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


Labor
a. Construction Foreman 1 3.33 109.44 364.44
A.1 b. Skilled laborer 1 3.33 79.17 263.64
c. Laborer 2 3.33 61.07 406.73

Sub - Total for A.1 - As Submitted 1,034.80


Labor
a. Construction Foreman 1 3.33 109.44 364.44
b. Skilled laborer 1 3.33 79.17 263.64
A.2
c. Laborer 2 3.33 61.07 406.73

Sub - Total for A.2 - As Evaluated 1,034.80


Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
a. Backhoe (0.80 m³) 1 2.50 1,537.00 3,842.50
b. Dumptruck (12 yd³) 1 1.67 1,420.00 2,371.40
B.1
c. Chain saw 1 1.67 75.36 125.85
Minor Tools (5% of Labor Cost) 51.74

Sub - Total for B.1 - As Submitted 6,391.49


Equipment
a. Backhoe (0.80 m³) 1 2.50 1,537.00 3,842.50
b. Dumptruck (12 yd³) 1 1.67 1,420.00 2,371.40
B.2 c. Chain saw 1 1.67 75.36 125.85
Minor Tools (5% of Labor Cost) 51.74

Sub - Total for B.2 - As Evaluated 6,391.49


C.1 Total (A.1 + B.1) - As Submitted 7,426.29
C.2 Total (A.2 + B.2) - As Evaluated 7,426.29
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 7,426.29
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 7,426.29
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
F.1 a. Rope, 1"Ø - 5 uses m 20 3.50 70.00

Sub - Total for F.1 - As Submitted 70.00


Materials
a. Rope, 1"Ø - 5 uses m 20 3.50 70.00
F.2

Sub - Total for F.2 - As Evaluated 70.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 7,496.29
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 7,496.29
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 749.63
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 749.63
I.1 Contractor's Profit (CP) - As Submitted 8% 599.70
I.2 Contractor's Profit (CP) - As Evaluated 8% 599.70
J.1 Value Added Tax (VAT) - As Submitted 5% 442.28
J.2 Value Added Tax (VAT) - As Evaluated 5% 442.28
K.1 Total Unit Cost - As Submitted 9,287.90
K.2 Total Unit Cost - As Evaluated 9,287.90
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 101(1) Removal of Structures and Obstruction

Unit of Measurement : ls
Output per hour - As Submitted : 1
Output per hour - As Evaluated : 1
Quantity : 1.00 ls

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


Labor
For Grouted Riprap and CHB Lined Canal
a. Construction Foreman 1 40 109.44 4,377.60
b. Unskilled Laborer 4 40 61.07 9,771.20

Removal of Street Lights


a. Construction Foreman 1 120 109.44 13,132.80
A.1
b. Skilled Laborer 4 120 79.17 38,001.60
b. Unskilled Laborer 6 120 61.07 43,970.40

Reinstallation of Street Lights


a. Construction Foreman 1 200 109.44 21,888.00
b. Skilled Laborer 4 200 79.17 63,336.00
b. Unskilled Laborer 6 200 61.07 73,284.00

Sub - Total for A.1 - As Submitted 267,761.60


Labor
For Grouted Riprap and CHB Lined Canal
a. Construction Foreman 1 40 109.44 4,377.60
b. Unskilled Laborer 4 40 61.07 9,771.20

Removal of Street Lights


a. Construction Foreman 1 120 109.44 13,132.80
b. Skilled Laborer 4 120 79.17 38,001.60
A.2
b. Unskilled Laborer 6 120 61.07 43,970.40

Reinstallation of Street Lights


a. Construction Foreman 1 200 109.44 21,888.00
b. Skilled Laborer 4 200 79.17 63,336.00
b. Unskilled Laborer 6 200 61.07 73,284.00

Sub - Total for A.2 - As Evaluated 267,761.60


Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
For Grouted Riprap and CHB Lined Canal
a. Dump Truck (12 yd³) 1 40 1,420.00 56,800.00
b. Backhoe (0.80 m³) 1 30 1,537.00 46,110.00

Removal of Street Lights


a. Dump Truck (12 yd³) 1 30.00 1,420.00 42,600.00
B.1
d. Boom Truck 1 50.00 1,017.90 50,895.00

Reinstallation of Street Lights


a. Dump Truck (12 yd³) 1 100.00 1,420.00 142,000.00
d. Boom Truck 1 100.00 1,017.90 101,790.00

Minor Tools (5% of Labor) 13,388.08


B.1

ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

Sub - Total for B.1 - As Submitted 453,583.08


Equipment
For Grouted Riprap and CHB Lined Canal
a. Dump Truck (12 yd³) 1 40 1420.00 56,800.00
b. Backhoe (0.80 m³) 1 30 1537.00 46,110.00

B.2
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

Removal of Street Lights


a. Dump Truck (12 yd³) 1 30 1420 42,600.00
d. Boom Truck 1 50 1017.9 50,895.00
B.2

Reinstallation of Street Lights


a. Dump Truck (12 yd³) 1 100 1420 142,000.00
d. Boom Truck 1 100 1017.9 101,790.00

Minor Tools (5% of Labor) 13,388.08

Sub - Total for B.2 - As Evaluated 453,583.08


C.1 Total (A.1 + B.1) - As Submitted 721,344.68
C.2 Total (A.2 + B.2) - As Evaluated 721,344.68
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 721,344.68
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 721,344.68
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials

Sub - Total for F.1 - As Submitted -


Materials
F.2 -
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 721,344.68
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 721,344.68
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 72,134.47
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 72,134.47
I.1 Contractor's Profit (CP) - As Submitted 8% 57,707.57
I.2 Contractor's Profit (CP) - As Evaluated 8% 57,707.57
J.1 Value Added Tax (VAT) - As Submitted 5% 42,559.34
J.2 Value Added Tax (VAT) - As Evaluated 5% 42,559.34
K.1 Total Unit Cost - As Submitted 893,746.06
K.2 Total Unit Cost - As Evaluated 893,746.06

Prepared by: Checked/ Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 101(2) Removal of Actual Structures/Obstruction

Unit of Measurement : each


Output per hour - As Submitted : 1
Output per hour - As Evaluated : 1
Quantity : 28.00 each

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


Labor
A.1 a. Construction Foreman 1 1.00 109.44 109.44
b. Unskilled Labor 2 1.00 61.07 122.14

Sub - Total for A.1 - As Submitted 231.58


Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.2 b. Unskilled Labor 2 1.00 61.07 122.14

Sub - Total for A.2 - As Evaluated 231.58


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
Equipment
a. Backhoe (0.80 cu m) 1 1.00 1537.00 1,537.00
B.1
b. Cargo Truck (5 T)) 1 1.00 783.00 783.00
Minor Tools (10% of Labor) 23.16

Sub - Total for B.1 - As Submitted 2,343.16


Equipment
a. Backhoe (0.80 cu m) 1 1.00 1537.00 1,537.00
b. Cargo Truck (5 T)) 1 1.00 783.00 783.00
B.2
Minor Tools (10% of Labor) 23.16

Sub - Total for B.2 - As Evaluated 2,343.16


C.1 Total (A.1 + B.1) - As Submitted 2,574.74
C.2 Total (A.2 + B.2) - As Evaluated 2,574.74
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 2,574.74
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 2,574.74
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials

Sub - Total for F.1 - As Submitted


Materials
F.2
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 2,574.74
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 2,574.74
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 257.47
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 257.47
I.1 Contractor's Profit (CP) - As Submitted 8% 205.98
I.2 Contractor's Profit (CP) - As Evaluated 8% 205.98
J.1 Value Added Tax (VAT) - As Submitted 5% 151.91
J.2 Value Added Tax (VAT) - As Evaluated 5% 151.91
K.1 Total Unit Cost - As Submitted 3,190.10
K.2 Total Unit Cost - As Evaluated 3,190.10

Prepared by: Checked/Reviewed by:


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 101(3)b3


Removal of Actual Structure/Obstruction, 0.23m thick PCCP (Unreinforced)

Unit of Measurement : sq m
Output per hour - As Submitted : 40
Output per hour - As Evaluated : 40
Quantity : 989.30 sq m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


Labor
A.1 a. Construction Foreman 1 1 109.44 109.44
b. Laborer 2 1 61.07 122.14

Sub - Total for A.1 - As Submitted 231.58


Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 b. Laborer 2 1 61.07 122.14

Sub - Total for A.2 - As Evaluated 231.58


Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
a. Backhoe w/ Pavement Breaker (0.80 m³) 1 1.00 1998.10 1,998.10
B.1 b. Payloader (1.50 m³), LX80-2C 1 1.00 1733.00 1,733.00
c. Dump Truck (12 yd³) 1 0.50 1420.00 710.00
Minor Tools(10% of Labor Cost) 23.16

Sub - Total for B.1 - As Submitted 4,464.26


Equipment
a. Backhoe w/ Pavement Breaker (0.80 m³) 1 1.00 1998.10 1,998.10
b. Payloader (1.50 m³), LX80-2C 1 1.00 1733.00 1,733.00
B.2 c. Dump Truck (12 yd³) 1 0.50 1420.00 710.00
Minor Tools(10% of Labor Cost) 23.16

Sub - Total for B.2 - As Evaluated 4,464.26


C.1 Total (A.1 + B.1) - As Submitted 4,695.84
C.2 Total (A.2 + B.2) - As Evaluated 4,695.84
D.1 Output per hour - As Submitted 40.00
D.2 Output per hour - As Evaluated 40.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 117.40
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 117.40
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
-
Sub - Total for F.1 - As Submitted -
Materials
F.2 -
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 117.40
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 117.40
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 11.74
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 11.74
I.1 Contractor's Profit (CP) - As Submitted 8% 9.39
I.2 Contractor's Profit (CP) - As Evaluated 8% 9.39
J.1 Value Added Tax (VAT) - As Submitted 5% 6.93
J.2 Value Added Tax (VAT) - As Evaluated 5% 6.93
K.1 Total Unit Cost - As Submitted 145.45
K.2 Total Unit Cost - As Evaluated 145.45
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 101(10) Removal of Existing Road Signs

Unit of Measurement : each


Output per hour - As Submitted : 1
Output per hour - As Evaluated : 1
Quantity : 20.00 each

Designation No. of Person/s No. of days Hourly Rate Amount (Php)


Labor
a. Construction Foreman 1 1 109.44 109.44
A.1
b. Unskilled Labor 4 1 61.07 244.28

Sub - Total for A.1 - As Submitted 353.72


Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 b. Unskilled Labor 4 1 61.07 244.28

Sub - Total for A.2 - As Evaluated 353.72


Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
a. Cargo Truck (10 T) 1 0.50 1212.00 606.00
B.1
Minor Tools (5% of Labor) 17.69

Sub - Total for B.1 - As Submitted 623.69


Equipment
a. Cargo Truck (10 T) 1 0.50 1212.00 606.00
B.2 Minor Tools (5% of Labor) 17.69

Sub - Total for B.2 - As Evaluated 623.69


C.1 Total (A.1 + B.1) - As Submitted 977.41
C.2 Total (A.2 + B.2) - As Evaluated 977.41
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 977.41
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 977.41
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
F.1

Sub - Total for F.1 - As Submitted


Materials
F.2
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 977.41
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 977.41
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 97.74
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 97.74
I.1 Contractor's Profit (CP) - As Submitted 8% 78.19
I.2 Contractor's Profit (CP) - As Evaluated 8% 78.19
J.1 Value Added Tax (VAT) - As Submitted 5% 57.67
J.2 Value Added Tax (VAT) - As Evaluated 5% 57.67
K.1 Total Unit Cost - As Submitted 1,211.01
K.2 Total Unit Cost - As Evaluated 1,211.01

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

Engineer II Engineer IV

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 102(2) Surplus Common Excavation

Unit of Measurement : cu m
Output per hour - As Submitted : 80
Output per hour - As Evaluated : 80
Quantity : 14,097.00 cu m

Designation No. of Person/s No. of days Hourly Rate Amount (Php)


Labor
A.1 a. Construction Foreman 1 1 109.44 109.44
b. Unskilled Labor 2 1 61.07 122.14

Sub - Total for A.1 - As Submitted 231.58


Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 b. Unskilled Labor 2 1 61.07 122.14

Sub - Total for A.2 - As Evaluated 231.58


Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
a. Bulldozer, D6H SERIES II PSDS/DD 1 1.00 3379.00 3,379.00
b. Payloader (1.50 m³) 1 1.00 1733.00 1,733.00
B.1 c. Payloader (1.50 m³) at disposal site 1 0.30 1733.00 519.90
d. Dump Truck (12 yd³) 3 2.00 1420.00 8,520.00
e. Backhoe ( 0.80 m³ ) 1 1.00 1537.00 1,537.00

Sub - Total for B.1 - As Submitted 15,688.90


Equipment
a. Bulldozer, D6H SERIES II PSDS/DD 1 1.00 3379.00 3,379.00
b. Payloader (1.50 m³) 1 1.00 1733.00 1,733.00
c. Payloader (1.50 m³) at disposal site 1 0.30 1733.00 519.90
B.2
d. Dump Truck (12 yd³) 3 2.00 1420.00 8,520.00
e. Backhoe ( 0.80 m³ ) 1 1.00 1537.00 1,537.00

Sub - Total for B.2 - As Evaluated 15,688.90


C.1 Total (A.1 + B.1) - As Submitted 15,920.48
C.2 Total (A.2 + B.2) - As Evaluated 15,920.48
D.1 Output per hour - As Submitted 80.00
D.2 Output per hour - As Evaluated 80.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 199.01
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 199.01
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
-
Sub - Total for F.1 - As Submitted -
Materials
F.2
Sub - Total for F.2 - As Evaluated -
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 199.01
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 199.01
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 19.90
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 19.90
I.1 Contractor's Profit (CP) - As Submitted 8% 15.92
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

I.2 Contractor's Profit (CP) - As Evaluated 8% 15.92


J.1 Value Added Tax (VAT) - As Submitted 5% 11.74
J.2 Value Added Tax (VAT) - As Evaluated 5% 11.74
K.1 Total Unit Cost - As Submitted 246.57
K.2 Total Unit Cost - As Evaluated 246.57

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 103(1)a Structure Excavation (Common soil)

Unit of Measurement : cu m
Output per hour - As Submitted : 20
Output per hour - As Evaluated : 20
Quantity : 383.60 cu m

Designation No. of Person/s No. of days Hourly Rate Amount (Php)


Labor
A.1 a. Construction Foreman 1 1 109.44 109.44
b. Laborer 3 1 61.07 183.21

Sub - Total for A.1 - As Submitted 292.65


Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 b. Laborer 3 1 61.07 183.21

Sub - Total for A.2 - As Evaluated 292.65


Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
a. Dump Truck (12 yd³) 2 1.00 1420.00 2,840.00
B.1
b. Backhoe ( 0.80 m³ ) 1 1.00 1537.00 1,537.00
Minor Tools (10% of Labor Cost) 29.27

Sub - Total for B.1 - As Submitted 4,406.27


Equipment
a. Dump Truck (12 yd³) 2 1.00 1420.00 2,840.00
B.2 b. Backhoe ( 0.80 m³ ) 1 1.00 1537.00 1,537.00
Minor Tools (10% of Labor Cost) 29.27
Sub - Total for B.2 - As Evaluated 4,406.27
C.1 Total (A.1 + B.1) - As Submitted 4,698.92
C.2 Total (A.2 + B.2) - As Evaluated 4,698.92
D.1 Output per hour - As Submitted 20.00
D.2 Output per hour - As Evaluated 20.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 234.95
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 234.95
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
-
Sub - Total for F.1 - As Submitted -
Materials
F.2
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 234.95
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 234.95
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 23.49
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 23.49
I.1 Contractor's Profit (CP) - As Submitted 8% 18.80
I.2 Contractor's Profit (CP) - As Evaluated 8% 18.80
J.1 Value Added Tax (VAT) - As Submitted 5% 13.86
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

J.2 Value Added Tax (VAT) - As Evaluated 5% 13.86


K.1 Total Unit Cost - As Submitted 291.10
K.2 Total Unit Cost - As Evaluated 291.10

Prepared by: Prepared by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 103(3) Foundation Fill

Unit of Measurement : cu m
Output per hour - As Submitted : 1.25
Output per hour - As Evaluated : 1.25
Quantity : 39.10 cu m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


Labor
a. Construction Foreman 1 1 109.44 109.44
A.1
b. Unskilled Labor 4 1 61.07 244.28

Sub - Total for A.1 - As Submitted 353.72


Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 b. Unskilled Labor 4 1 61.07 244.28

Sub - Total for A.2 - As Evaluated 353.72


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
Equipment
a. Plate Compactor (5 hp) 1 1.00 123.00 123.00
B.1 b. Water Truck/Pump (16000 L) 1 0.01 2,450.00 24.50
Minor Tools (10% of Labor Cost) 35.37

Sub - Total for B.1 - As Submitted 182.87


Equipment
a. Plate Compactor (5 hp) 1 1.00 123.00 123.00
b. Water Truck/Pump (16000 L) 1 0.01 2,450.00 24.50
B.2
Minor Tools (10% of Labor Cost) 35.37

Sub - Total for B.2 - As Evaluated 182.87


C.1 Total (A.1 + B.1) - As Submitted 536.59
C.2 Total (A.2 + B.2) - As Evaluated 536.59
D.1 Output per hour - As Submitted 1.25
D.2 Output per hour - As Evaluated 1.25
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 429.27
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 429.27
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
F.1 a. Filling Materials cu.m. 1.15 750.82 863.44

Sub - Total for F.1 - As Submitted 863.44


Materials
a. Filling Materials cu.m. 1.15 750.82 863.44
F.2

Sub - Total for F.2 - As Evaluated 863.44


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 1,292.72
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 1,292.72
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 129.27
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 129.27


I.1 Contractor's Profit (CP) - As Submitted 8% 103.42
I.2 Contractor's Profit (CP) - As Evaluated 8% 103.42
J.1 Value Added Tax (VAT) - As Submitted 5% 76.27
J.2 Value Added Tax (VAT) - As Evaluated 5% 76.27
K.1 Total Unit Cost - As Submitted 1,601.68
K.2 Total Unit Cost - As Evaluated 1,601.68

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 103(6)a Pipe Culverts and Drain Excavation (Common soil)

Unit of Measurement : cu m
Output per hour - As Submitted : 20
Output per hour - As Evaluated : 20
Quantity : 194.30 cu m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


Labor
A.1 a. Construction Foreman 1 1 109.44 109.44
b. Unskilled Labor 3 1 61.07 183.21

Sub - Total for A.1 - As Submitted 292.65


Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 b. Unskilled Labor 3 1 61.07 183.21

Sub - Total for A.2 - As Evaluated 292.65


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
Equipment
a. Dump Truck (12 yd³) 2 1.00 1,420.00 2,840.00
B.1
b. Backhoe (0.80 m³) 1 1.00 1,537.00 1,537.00
Minor Tools (10% of Labor Cost) 29.27

Sub - Total for B.1 - As Submitted 4,406.27


Equipment
a. Dump Truck (12 yd³) 2 1.00 1,420.00 2,840.00
b. Backhoe (0.80 m³) 1 1.00 1,537.00 1,537.00
B.2
Minor Tools (10% of Labor Cost) 29.27

Sub - Total for B.2 - As Evaluated 4,406.27


C.1 Total (A.1 + B.1) - As Submitted 4,698.92
C.2 Total (A.2 + B.2) - As Evaluated 4,698.92
D.1 Output per hour - As Submitted 20.00
D.2 Output per hour - As Evaluated 20.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 234.95
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 234.95
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials

Sub - Total for F.1 - As Submitted


Materials
F.2
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 234.95
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 234.95
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 23.49


H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 23.49
I.1 Contractor's Profit (CP) - As Submitted 8% 18.80
I.2 Contractor's Profit (CP) - As Evaluated 8% 18.80
J.1 Value Added Tax (VAT) - As Submitted 5% 13.86
J.2 Value Added Tax (VAT) - As Evaluated 5% 13.86
K.1 Total Unit Cost - As Submitted 291.10
K.2 Total Unit Cost - As Evaluated 291.10

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 104(1)a Embankment from Roadway Excavation (Common Soil)

Unit of Measurement : cu m
Output per hour - As Submitted : 50
Output per hour - As Evaluated : 50
Quantity : 8,916.00 cu m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


Labor
For Excavation Work:
a. Construction Foreman 1 0.83 109.44 90.84
b. Unskilled Labor 2 0.83 61.07 101.38
A.1

Spreading and Compaction


a. Construction Foreman 1 1 109.44 109.44
b. Unskilled Labor 2 1 61.07 122.14

Sub - Total for A.1 - As Submitted 423.79


Labor
For Excavation Work:
a. Construction Foreman 1 0.83 109.44 90.84
b. Unskilled Labor 2 0.83 61.07 101.38

A.2
Spreading and Compaction
a. Construction Foreman 1 1 109.44 109.44
b. Unskilled Labor 2 1 61.07 122.14

Sub - Total for A.2 - As Evaluated 423.79


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
Equipment
For Excavation Work:
a. Bulldozer, D6H SERIES II PSDS/DD 1 0.83 3379.00 2,804.57
b. Payloader (1.50 m³) 1 0.83 1733.00 1,438.39
c. Dump Truck (12 yd³) 2 0.83 1420.00 2,357.20
B.1

Spreading and Compaction:


a. Motorized Road Grader, (140hp),G710A 1 1.00 2173.00 2,173.00
b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1846.00 1,846.00
c. Water Truck/Pump(16000 L) 1 0.25 2450.00 612.50

Sub - Total for B.1 - As Submitted 11,231.66


Equipment
For Excavation Work:
a. Bulldozer, D6H SERIES II PSDS/DD 1 0.83 3379.00 2,804.57
b. Payloader (1.50 m³) 1 0.83 1733.00 1,438.39

B.2
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

c. Dump Truck (12 yd³) 2 0.83 1420.00 2,357.20

B.2
Spreading and Compaction:
a. Motorized Road Grader, (140hp),G710A 1 1.00 2173.00 2,173.00
b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1846.00 1,846.00
c. Water Truck/Pump(16000 L) 1 0.25 2450.00 612.50

Sub - Total for B.2 - As Evaluated 11,231.66


C.1 Total (A.1 + B.1) - As Submitted 11,655.45
C.2 Total (A.2 + B.2) - As Evaluated 11,655.45
D.1 Output per hour - As Submitted 50.00
D.2 Output per hour - As Evaluated 50.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 233.11
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 233.11

Name and Specification Unit Quantity Unit Cost Amount (Php)


F.1 Materials

Sub - Total for F.1 - As Submitted


Materials
F.2
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 233.11
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 233.11
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 23.31
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 23.31
I.1 Contractor's Profit (CP) - As Submitted 8% 18.65
I.2 Contractor's Profit (CP) - As Evaluated 8% 18.65
J.1 Value Added Tax (VAT) - As Submitted 5% 13.75
J.2 Value Added Tax (VAT) - As Evaluated 5% 13.75
K.1 Total Unit Cost - As Submitted 288.82
K.2 Total Unit Cost - As Evaluated 288.82

Prepared by: Checked/Reviewed by:


JESSICA B. APOSTOL JUDY ANN T. BERNARDINO
Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 105(1)a Subgrade Preparation (Common Material)

Unit of Measurement : sq m
Output per hour - As Submitted : 300
Output per hour - As Evaluated : 300
Quantity : 32,774.00 sq m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


Labor
A.1 a. Construction Foreman 1 1 109.44 109.44
b. Unskilled Labor 2 1 61.07 122.14

Sub - Total for A.1 - As Submitted 231.58


Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 b. Unskilled Labor 2 1 61.07 122.14

Sub - Total for A.2 - As Evaluated 231.58


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
Equipment
a. Motorized Road Grader, (140hp),G710A 1 1.00 2173.00 2,173.00
B.1
b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1846.00 1,846.00
c. Water Truck/Pump(16000 L) 1 0.25 2450.00 612.50

Sub - Total for B.1 - As Submitted 4,631.50


Equipment
a. Motorized Road Grader, (140hp),G710A 1 1.00 2173.00 2,173.00
b. Vibratory Roller (10 m.t.), SD100DC 1 1.00 1846.00 1,846.00
B.2
c. Water Truck/Pump(16000 L) 1 0.25 2450.00 612.50

Sub - Total for B.2 - As Evaluated 4,631.50


C.1 Total (A.1 + B.1) - As Submitted 4,863.08
C.2 Total (A.2 + B.2) - As Evaluated 4,863.08
D.1 Output per hour - As Submitted 300.00
D.2 Output per hour - As Evaluated 300.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 16.21
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 16.21
Name and Specification Unit Quantity Unit Cost Amount (Php)
F.1 Materials
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
F.1

Sub - Total for F.1 - As Submitted


Materials
F.2
Sub - Total for F.2 - As Evaluated
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 16.21
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 16.21
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 1.62
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 1.62
I.1 Contractor's Profit (CP) - As Submitted 8% 1.30
I.2 Contractor's Profit (CP) - As Evaluated 8% 1.30
J.1 Value Added Tax (VAT) - As Submitted 5% 0.96
J.2 Value Added Tax (VAT) - As Evaluated 5% 0.96
K.1 Total Unit Cost - As Submitted 20.08
K.2 Total Unit Cost - As Evaluated 20.08

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
LABOR MATERIAL EQUIPMENT

1,111.58

38,169.60
1,738,459.80

10,737,705.01

117,600.00
-98391735.9871388

62.631
116.51

1 3
2 3
4 3

4
4

267,761.60
24.5 98
12.25

14.5
128
453,583.08
0.096
0.128
0.224

c 1.68
6,484.24

65,608.42
5,727.55

110,412.26
7,074.40

12,473.72
40,807.29

2,764,580.29
5,613.03

84,512.16

469.89
375.91
42.290235
11,064.36

5,720.24

33,760.62
2,843.09

42,806.86
75,570.48

2,002,829.61
-
25,299.34

505,975.94
-

2,187,816.78 151,360.62 16,824,377.19 19,163,554.59


LABOR MATERIAL EQUIPMENT 19,163,554.59
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 200(1) Aggregate Subbase Course

Unit of Measurement : cu m
Output per hour - As Submitted : 50
Output per hour - As Evaluated : 50
Quantity : 10,668.00 cu m

Designation No. of Person/s No. of hour/s Hourly Rate Amount (Php)

Labor
A.1 a. Construction Foreman 1 1 109.44 109.44
b. Unskilled Labor 2 1 61.07 122.14

Sub - Total for A.1 - As Submitted 231.58


Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 b. Unskilled Labor 2 1 61.07 122.14

Sub - Total for A.2 - As Evaluated 231.58


Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)

Equipment
a. Motorized Road Grader (140 HP), G710A 1 1.00 2,173.00 2,173.00
B.1
b. Vibratory Roller (10 mt), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50

Sub - Total for B.1 - As Submitted 4,631.50


Equipment
a. Motorized Road Grader (140 HP), G710A 1 1.00 2,173.00 2,173.00
b. Vibratory Roller (10 mt), SD100DC 1 1.00 1,846.00 1,846.00
B.2
c. Water Truck/Pump (16000 L) 1 0.25 2,450.00 612.50

Sub - Total for B.2 - As Evaluated 4,631.50


C.1 Total (A.1 + B.1) - As Submitted 4,863.08
C.2 Total (A.2 + B.2) - As Evaluated 4,863.08
D.1 Output per hour - As Submitted 50.00
D.2 Output per hour - As Evaluated 50.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 97.26
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 97.26
Name and Specification Unit Quantity Unit Cost Amount (Php)

Materials
F.1
a. Aggregate Subbase Course( w/ 15% Shrinkage Factor) cu.m. 1.15 750.82 863.44

Sub - Total for F.1 - As Submitted 863.44


Materials
a. Aggregate Subbase Course( w/ 15% Shrinkage Factor) cu.m. 1.15 750.82 863.44
F.2

Sub - Total for F.2 - As Evaluated 863.44


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 960.70
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 960.70
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 96.07
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 96.07
I.1 Contractor's Profit (CP) - As Submitted 8% 76.86
I.2 Contractor's Profit (CP) - As Evaluated 8% 76.86
J.1 Value Added Tax (VAT) - As Submitted 5% 56.68
J.2 Value Added Tax (VAT) - As Evaluated 5% 56.68
K.1 Total Unit Cost - As Submitted 1,190.31
K.2 Total Unit Cost - As Evaluated 1,190.31

Prepared by: Checked/Reviewed by:


JESSICA B. APOSTOL JUDY ANN T. BERNARDINO
Engineer II Engineer IV
LABOR MATERIAL EQUIPMENT

49,409.91

988,176.84

9,211,209.92
49,409.91 9,211,209.92 988,176.84 10,248,796.67
LABOR MATERIAL EQUIPMENT 10,248,796.67
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 300(1) Gravel Surface Course

Unit of Measurement : cu m
Output per hour - As Submitted : 50
Output per hour - As Evaluated : 50
Quantity : 2,157.00 cu m

Designation No. of Person/s No. of hrs Hourly Rate Amount (Php)


Labor
a. Construction Foreman 1 1 109.44 109.44
A.1
b. Unskilled Labor 2 1 61.07 122.14

Sub - Total for A.1 - As Submitted 231.58


Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 b. Unskilled Labor 2 1 61.07 122.14

Sub - Total for A.2 - As Evaluated 231.58


Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00
B.1 b. Vibratory Roller (10 mt), SD100DC 1 1.00 1,846.00 1,846.00
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B.1 - As Submitted 4,631.50


Equipment
a. Motorized Road Grader (140 hp), G710A 1 1.00 2,173.00 2,173.00
b. Vibratory Roller (10 mt), SD100DC 1 1.00 1,846.00 1,846.00
B.2
c. Water Truck/Pump (16000L) 1 0.25 2,450.00 612.50

Sub - Total for B.2 - As Evaluated 4,631.50


C.1 Total (A.1 + B.1) - As Submitted 4,863.08
C.2 Total (A.2 + B.2) - As Evaluated 4,863.08
D.1 Output per hour - As Submitted 50.00
D.2 Output per hour - As Evaluated 50.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 97.26
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 97.26
Name and Specification Unit Qty Unit Cost Amount (Php)
Materials
a. Uncrushed Aggregate Surface Course cu.m. 1.15 1015.82 1,168.19
F.1
(w/ 15% Shrinkage Factor)

Sub - Total for F.1 - As Submitted 1,168.19


Materials
a. Uncrushed Aggregate Surface Course cu.m. 1.15 1015.82 1,168.19
F.2 (w/ 15% Shrinkage Factor)

Sub - Total for F.2 - As Evaluated 1,168.19


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 1,265.45
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 1,265.45
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 126.55
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 126.55
I.1 Contractor's Profit (CP) - As Submitted 8% 101.24
I.2 Contractor's Profit (CP) - As Evaluated 8% 101.24
J.1 Value Added Tax (VAT) - As Submitted 5% 74.66
J.2 Value Added Tax (VAT) - As Evaluated 5% 74.66
K.1 Total Unit Cost - As Submitted 1,567.90
K.2 Total Unit Cost - As Evaluated 1,567.90

Prepared by: Checked/ Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

Engineer II Engineer IV

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 311(1)e1 Portland Cement Concrete Pavement (Unreinforced), 0.28 m thick, 14 days

Unit of Measurement : sq m
Output per hour - As Submitted : 57.50
Output per hour - As Evaluated : 57.50
Quantity : 22,517.26 sq m

Designation No. of Person/s No. of hrs Hourly Rate Amount (Php)


Labor
a. Construction Foreman 1 1 109.44 109.44
A.1 b. Skilled Labor 4 1 79.17 316.68
c. Unskilled Labor 12 1 61.07 732.84

Sub - Total for A.1 - As Submitted 1,158.96


Labor
a. Construction Foreman 1 1 109.44 109.44
b. Skilled Labor 4 1 79.17 316.68
A.2
c. Unskilled Labor 12 1 61.07 732.84

Sub - Total for A.2 - As Evaluated 1,158.96


Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
a. Transit Mixer (5 m³) 4 1.00 1,318.00 5,272.00
b. Concrete Vibrator 2 1.00 91.25 182.50
c. Concrete Batch Plant (30 m³) 1 1.00 1,759.50 1,759.50
d. Payloader (1.50 m³), LX80-2C 1 1.00 1,733.00 1,733.00
B.1 e. Concrete Screeder (5.5 hp) 1 1.00 545.00 545.00
f. Water Truck/Pump (16000L) 1 1.00 2,450.00 2,450.00
g. Concrete Saw (7.5 hp), 14" Blade Ø 1 1.00 32.63 32.63
h. Bar Cutter, Single Phase 1 0.10 219.75 21.98
Minor Tools (5% of Labor Cost) 57.95

Sub - Total for B.1 - As Submitted 12,054.55


Equipment
a. Transit Mixer (5 m³) 4 1 1,318.00 5,272.00
b. Concrete Vibrator 2 1 91.25 182.50
c. Concrete Batch Plant (30 m³) 1 1 1,759.50 1,759.50
d. Payloader (1.50 m³), LX80-2C 1 1 1,733.00 1,733.00
e. Concrete Screeder (5.5 hp) 1 1 545.00 545.00
B.2
f. Water Truck/Pump (16000L) 1 1 2,450.00 2,450.00
g. Concrete Saw (7.5 hp), 14" Blade Ø 1 1 32.63 32.63
h. Bar Cutter, Single Phase 1 0.1 219.75 21.98
Minor Tools (5% of Labor Cost) 57.95

Sub - Total for B.2 - As Evaluated 12,054.55


C.1 Total (A.1 + B.1) - As Submitted 13,213.51
C.2 Total (A.2 + B.2) - As Evaluated 13,213.51
D.1 Output per hour - As Submitted 57.50
D.2 Output per hour - As Evaluated 57.50
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 229.80
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 229.80
Name and Specification Unit Qty Unit Cost Amount (Php)
Materials
a. Reinforcing Steel Bar kg 0.5 41.27 20.64
b. Curing Compound L 0.29 95.00 27.55
c. Asphalt Sealant L 0.17 47.00 7.99
d. Steel Forms (Rental) m 0.46 78.00 35.88
d. Sand m³ 0.154 985.82 151.82
F.1
e. Gravel m³ 0.28 1,095.82 306.83
f. Cement bag 2.79 255.90 714.73
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD
F.1
(S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

g. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015 8,000.00 1.20


h. Pipe Sleeve, 2" Ø m 0.0078 97.00 0.76
i. Grease/Tar L 0.0078 300.00 2.34

Sub - Total for F.1 - As Submitted 1,269.73

Name and Specification Unit Qty Unit Cost Amount (Php)

Materials
a. Reinforcing Steel Bar kg 0.50 41.27 20.64
b. Curing Compound L 0.29 95.00 27.55
c. Asphalt Sealant L 0.17 47.00 7.99
d. Steel Forms (Rental) m 0.46 78.00 35.88
F.2 d. Sand m³ 0.154 985.82 151.82
e. Gravel m³ 0.28 1095.82 306.83
f. Cement bag 2.79 255.90 714.73
g. Concrete Saw (Diamond Blade 14" Ø) pc 0.00015 8000.00 1.20
h. Pipe Sleeve, 2" Ø m 0.0078 97.00 0.76
i. Grease/Tar L 0.0078 300.00 2.34

Sub - Total for F.2 - As Evaluated 1,269.73


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 1,499.53
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 1,499.53
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 149.95
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 149.95
I.1 Contractor's Profit (CP) - As Submitted 8% 119.96
I.2 Contractor's Profit (CP) - As Evaluated 8% 119.96
J.1 Value Added Tax (VAT) - As Submitted 5% 88.47
J.2 Value Added Tax (VAT) - As Evaluated 5% 88.47
K.1 Total Unit Cost - As Submitted 1,857.91
K.2 Total Unit Cost - As Evaluated 1,857.91

Prepared by: .

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
9,990.36

199,802.91

2,519,792.30
453,853.98

4,720,617.46
28,590,754.52

463,844.34 31,110,546.82 4,920,420.37 36,494,811.53


LABOR MATERIAL EQUIPMENT 36,494,811.53
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 404(1)a Reinforcing Steel , Grade 40


Unit of Measurement : kg
Output per hour - As Submitted : 180
Output per hour - As Evaluated : 180
Quantity : 18,537.14 kg

Designation No. of Person/s No. of days Hourly Rate Amount (Php)


Labor
a. Construction Foreman 1 1 109.44 109.44
A.1 b. Skilled Labor 2 1 79.17 158.34
c. Unskilled Labor 8 1 61.07 488.56

Sub - Total for A.1 - As Submitted 756.34


Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 b. Skilled Labor 2 1 79.17 158.34
c. Unskilled Labor 8 1 61.07 488.56
Sub - Total for A.2 - As Evaluated 756.34
Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
a. Bar Cutter 1 0.50 219.75 109.88
B.1 b. Bar Bender 1 0.50 351.50 175.75
c. Cargo Truck (9 - 10 mt) 1 0.15 1212.00 181.80

Sub - Total for B.1 - As Submitted 467.43


Equipment
a. Bar Cutter 1 0.50 219.75 109.88
b. Bar Bender 1 0.50 351.50 175.75
B.2
c. Cargo Truck (9 - 10 mt) 1 0.15 1212.00 181.80

Sub - Total for B.2 - As Evaluated 467.43


C.1 Total (A.1 + B.1) - As Submitted 1,223.77
C.2 Total (A.2 + B.2) - As Evaluated 1,223.77
D.1 Output per hour - As Submitted 180.00
D.2 Output per hour - As Evaluated 180.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 6.80
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 6.80
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Tie Wire (2% of RSB) kg. 0.021 89.00 1.87
F.1 b. Reinforcing Steel Bar, Grade 40 kg. 1.05 41.27 43.33
(w/ 5% Wastage)

Sub - Total for F.1 - As Submitted 45.20


Materials
a. Tie Wire (2% of RSB) kg. 0.021 89.00 1.87
b. Reinforcing Steel Bar, Grade 40 kg. 1.05 41.27 43.33
F.2
(w/ 5% Wastage)

Sub - Total for F.2 - As Evaluated 45.20


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 52.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 52.00
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 5.20
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 5.20
I.1 Contractor's Profit (CP) - As Submitted 8% 4.16
I.2 Contractor's Profit (CP) - As Evaluated 8% 4.16
J.1 Value Added Tax (VAT) - As Submitted 5% 3.07
J.2 Value Added Tax (VAT) - As Evaluated 5% 3.07
K.1 Total Unit Cost - As Submitted 64.43
K.2 Total Unit Cost - As Evaluated 64.43

Prepared by: Checked/Reviewed by:


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 405(1)a3 Structural Concrete, 20.68 MPa, Class "A", 28 days

Unit of Measurement : cu m
Output per hour - As Submitted : 1.4
Output per hour - As Evaluated : 1.4
Quantity : 192.10 cu m

Designation No. of Person/s No. of days Hourly Rate Amount (Php)


Labor
a. Construction Foreman 1 1 109.44 109.44
b. Skilled Labor 4 1 79.17 316.68
c. Unskilled Labor 8 1 61.07 488.56
A.1
Installation/Removal of Formworks
a. Skilled Labor 4 1 79.17 316.68
b. Unskilled Labor 8 1 61.07 488.56

Sub - Total for A.1 - As Submitted 1,719.92


Labor
a. Construction Foreman 1 1 109.44 109.44
b. Skilled Labor 4 1 79.17 316.68
c. Unskilled Labor 8 1 61.07 488.56
A.2
Installation/Removal of Formworks
a. Skilled Labor 4 1 79.17 316.68
b. Unskilled Labor 8 1 61.07 488.56

Sub - Total for A.2 - As Evaluated 1,719.92


Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
a. One Bagger Mixer 1 1.00 172.00 172.00
B.1 b. Concrete Vibrator 1 1.00 91.25 91.25
c. Water Truck/Pump (16000 L) 1 0.10 2450.00 245.00
Minor Tools (5% of Labor) 86.00

Sub - Total for B.1 - As Submitted 594.25


Equipment
a. One Bagger Mixer 1 1.00 172.00 172.00
b. Concrete Vibrator 1 1.00 91.25 91.25
B.2 c. Water Truck/Pump (16000 L) 1 0.10 2450.00 245.00
Minor Tools (5% of Labor) 86.00

Sub - Total for B.2 - As Evaluated 594.25


C.1 Total (A.1 + B.1) - As Submitted 2,314.17
C.2 Total (A.2 + B.2) - As Evaluated 2,314.17
D.1 Output per hour - As Submitted 1.40
D.2 Output per hour - As Evaluated 1.40
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 1,652.98
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 1,652.98
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Lumber, Good - 4 uses bd.ft. 70.00 27.00 472.50
b. Marine Plywood (1/2" x 4' x 8') - 4 uses pc. 1.60 705.00 282.00
F.1 c. Assorted CWN (1kg./100 bd.ft. of Lumber) kg. 0.70 77.00 53.90
d. Cement bag 9.50 255.90 2,431.05
e. Sand cu.m 0.50 985.82 492.91
f. Gravel cu.m 1.00 1095.82 1,095.82
F.1

ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

Sub - Total for F.1 - As Submitted 4,828.18


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

Name and Specification Unit Quantity Unit Cost Amount (Php)

Materials
a. Lumber, Good - 4 uses bd.ft. 70.00 27.00 472.50
b. Marine Plywood (1/2" x 4' x 8') - 4 uses pc. 1.60 705.00 282.00
F.2 c. Assorted CWN (1kg./100 bd.ft. of Lumber) kg. 0.70 77.00 53.90
d. Cement bag 9.50 255.90 2,431.05
e. Sand cu.m 0.50 985.82 492.91
f. Gravel cu.m 1.00 1095.82 1,095.82

Sub - Total for F.2 - As Evaluated 4,828.18


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 6,481.16
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 6,481.16
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 648.12
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 648.12
I.1 Contractor's Profit (CP) - As Submitted 8% 518.49
I.2 Contractor's Profit (CP) - As Evaluated 8% 518.49
J.1 Value Added Tax (VAT) - As Submitted 5% 382.39
J.2 Value Added Tax (VAT) - As Evaluated 5% 382.39
K.1 Total Unit Cost - As Submitted 8,030.15
K.2 Total Unit Cost - As Evaluated 8,030.15

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
LABOR MATERIAL EQUIPMENT

77,891.00

48,137.35

837,925.07
LABOR MATERIAL EQUIPMENT

235,997.59

81,539.04
LABOR MATERIAL EQUIPMENT
927,493.38
LABOR MATERIAL EQUIPMENT

313,888.60 1,765,418.45 129,676.39 2,208,983.43


LABOR MATERIAL EQUIPMENT 2,208,983.43
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 500(1)b3 Pipe Culverts, 910 mm dia. Class IV RCPC

Unit of Measurement : ln m
Output per hour - As Submitted : 1
Output per hour - As Evaluated : 1
Quantity : 63.00 ln m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)

Labor
A.1 a. Construction Foreman 1 0.57 109.44 62.38
b. Skilled Labor 2 0.57 79.17 90.25
c. Unskilled Labor 4 0.57 61.07 139.24
Sub - Total for A.1 - As Submitted 291.87
Labor
a. Construction Foreman 1 0.57 109.44 62.38
A.2 b. Skilled Labor 2 0.57 79.17 90.25
c. Unskilled Labor 4 0.57 61.07 139.24
Sub - Total for A.2 - As Evaluated 291.87
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
Equipment
B.1 a. Backhoe (0.80 m³) 1 0.29 1537.00 445.73
b. Plate Compactor (5 hp) 1 0.29 123.00 35.67
Minor Tools (10% of Labor) 29.19
Sub - Total for B.1 - As Submitted 510.59
Equipment
a. Backhoe (0.80 m³) 1 0.29 1537.00 445.73
B.2 b. Plate Compactor (5 hp) 1 0.29 123.00 35.67
Minor Tools (10% of Labor) 29.19
Sub - Total for B.2 - As Evaluated 510.59
C.1 Total (A.1 + B.1) - As Submitted 802.46
C.2 Total (A.2 + B.2) - As Evaluated 802.46
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 802.46
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 802.46
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Cement bag 1.08 255.90 276.37
F.1 b. Sand cu.m. 0.061 985.82 60.14
c. RC Pipes (910 mm Ø) pc 1 5154.19 5,154.19
d. Sand Bedding/Selected Sandy Soil cu.m. 0.128 985.82 126.18
Sub - Total for F.1 - As Submitted 5,616.88
Materials
a. Cement bag 1.08 255.90 276.37
b. Sand cu.m. 0.061 985.82 60.14
F.2
c. RC Pipes (910 mm Ø) pc 1 5154.19 5,154.19
d. Sand Bedding/Selected Sandy Soil cu.m. 0.128 985.82 126.18
Sub - Total for F.2 - As Evaluated 5,616.88
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 6,419.34
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 6,419.34
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 641.93
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 641.93
I.1 Contractor's Profit (CP) - As Submitted 8% 513.55
I.2 Contractor's Profit (CP) - As Evaluated 8% 513.55
J.1 Value Added Tax (VAT) - As Submitted 5% 378.74
J.2 Value Added Tax (VAT) - As Evaluated 5% 378.74
K.1 Total Unit Cost - As Submitted 7,953.57
K.2 Total Unit Cost - As Evaluated 7,953.57

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 500(1)b5 Pipe Culverts, 1220 mm dia. Class IV RCPC

Unit of Measurement : ln m
Output per hour - As Submitted : 1
Output per hour - As Evaluated : 1
Quantity : 6.00 ln m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)

Labor
A.1 a. Construction Foreman 1 0.8 109.44 87.55
b. Skilled Laborer 2 0.8 79.17 126.67
c. Laborer 4 0.8 61.07 195.42
Sub - Total for A.1 - As Submitted 409.65
Labor
a. Construction Foreman 1 0.8 109.44 87.55
A.2 b. Skilled Laborer 2 0.8 79.17 126.67
c. Laborer 4 0.8 61.07 195.42
Sub - Total for A.2 - As Evaluated 409.65
Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)

Equipment
B.1 a. Backhoe (0.80 m³) 1 0.40 1537.00 614.80
b. Plate Compactor (5 hp) 1 0.40 123.00 49.20
Minor Tools (10% of Labor) 40.96
Sub - Total for B.1 - As Submitted 704.96
Equipment
a. Backhoe (0.80 m³) 1 0.40 1537.00 614.80
B.2 b. Plate Compactor (5 hp) 1 0.40 123.00 49.20
Minor Tools (10% of Labor) 40.96
Sub - Total for B.2 - As Evaluated 704.96
C.1 Total (A.1 + B.1) - As Submitted 1,114.61
C.2 Total (A.2 + B.2) - As Evaluated 1,114.61
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 1,114.61
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 1,114.61
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Cement bag 1.404 255.90 359.28
F.1 b. Sand cu.m. 0.08 985.82 78.87
c. RC Pipes (1220 mm Ø) pc 1 8681.29 8,681.29
d. Sand Bedding/Selected Sandy Soil cu.m. 0.17 985.82 167.59

Sub - Total for F.1 - As Submitted 9,287.03


Materials
a. Cement bag 1.404 255.90 359.28
b. Sand cu.m. 0.08 985.82 78.87
F.2 c. RC Pipes (1220 mm Ø) pc 1 8681.29 8,681.29
d. Sand Bedding/Selected Sandy Soil cu.m. 0.17 985.82 167.59

Sub - Total for F.2 - As Evaluated 9,287.03


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 10,401.64
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 10,401.64
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 1,040.16
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 1,040.16
I.1 Contractor's Profit (CP) - As Submitted 8% 832.13
I.2 Contractor's Profit (CP) - As Evaluated 8% 832.13
J.1 Value Added Tax (VAT) - As Submitted 5% 613.70
J.2 Value Added Tax (VAT) - As Evaluated 5% 613.70
K.1 Total Unit Cost - As Submitted 12,887.63
K.2 Total Unit Cost - As Evaluated 12,887.63

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 505(2)a Grouted Riprap, Class A


Unit of Measurement : cu m
Output per hour - As Submitted : 1.25
Output per hour - As Evaluated : 1.25
Quantity : 1,650.80 cu m
Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)

Labor
A.1 a. Construction Foreman 1 1.00 109.44 109.44
b. Skilled Labor 2 1.00 79.17 158.34
c. Unskilled Labor 8 1.00 61.07 488.56
Sub - Total for A.1 - As Submitted 756.34
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.2 b. Skilled Labor 2 1.00 79.17 158.34
c. Unskilled Labor 8 1.00 61.07 488.56
Sub - Total for A.2 - As Evaluated 756.34
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
Equipment
B.1 a. One Bagger Mixer 1 1.00 172.00 172.00
b. Water Truck/ Pump (16000 L) 1 0.05 2450.00 122.50
Minor Tools (5% of Labor Cost) 37.82
Sub - Total for B.1 - As Submitted 332.32
Equipment
a. One Bagger Mixer 1 1.00 172.00 172.00
B.2 b. Water Truck/ Pump (16000 L) 1 0.05 2450.00 122.50
Minor Tools (5% of Labor Cost) 37.82
Sub - Total for B.2 - As Evaluated 332.32
C.1 Total (A.1 + B.1) - As Submitted 1,088.66
C.2 Total (A.2 + B.2) - As Evaluated 1,088.66
D.1 Output per hour - As Submitted 1.25
D.2 Output per hour - As Evaluated 1.25
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 870.93
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 870.93
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Cement bag 3.00 255.90 767.70
b. Sand cu.m. 0.25 985.82 246.46
c. Gravel Fill cu.m. 0.015 1095.82 16.44
F.1 d. Weep Holes (PVC) m 0.30 144.67 43.40
e. Filter Cloth m² 0.015 175.00 2.63
f. Boulders (15 - 25 kg) cu.m. 0.90 1085.82 977.24
268 cum to be utilize from grouted riprap removal
Miscellaneous (1% of Materials Cost) 20.54
Sub - Total for F.1 - As Submitted 2,074.39
Materials
a. Cement bag 3.00 255.90 767.70
b. Sand cu.m. 0.25 985.82 246.46
c. Gravel Fill cu.m. 0.02 1095.82 16.44
d. Weep Holes (PVC) m 0.30 144.67 43.40
e. Filter Cloth m² 0.02 175.00 2.63
f. Boulders (15 - 25 kg) cu.m. 0.90 1085.82 977.24
Miscellaneous (1% of Materials Cost) 20.54
Sub - Total for F.2 - As Evaluated 2,074.39
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 2,945.32
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 2,945.32
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 294.53
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 294.53
I.1 Contractor's Profit (CP) - As Submitted 8% 235.63
I.2 Contractor's Profit (CP) - As Evaluated 8% 235.63
J.1 Value Added Tax (VAT) - As Submitted 5% 173.77
J.2 Value Added Tax (VAT) - As Evaluated 5% 173.77
K.1 Total Unit Cost - As Submitted 3,649.25
K.2 Total Unit Cost - As Evaluated 3,649.25

Prepared by: Checked/Reviewed by:


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 506(1) Stone Masonry


Unit of Measurement : cu m
Output per hour - As Submitted : 1.60
Output per hour - As Evaluated : 1.60
Quantity : 47.80 cu m
Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)
Labor
A.1 a. Construction Foreman 1 1.00 109.44 109.44
b. Skilled Labor 2 1.00 79.17 158.34
c. Unskilled Labor 8 1.00 61.07 488.56
Sub - Total for A.1 - As Submitted 756.34
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.2 b. Skilled Labor 2 1.00 79.17 158.34
c. Unskilled Labor 8 1.00 61.07 488.56
Sub - Total for A.2 - As Evaluated 756.34
Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
Equipment
a. One Bagger Mixer 1 1.00 172.00 172.00
B.1
b. Water Truck/Pump (16000 L) 1 0.05 2450.00 122.50
c. Backhoe (Wheel Type 0.28 m³) 1 0.10 922.00 92.20
Minor Tools (10% of Labor Cost) 75.63
Sub - Total for B.1 - As Submitted 462.33
Equipment
a. One Bagger Mixer 1 1.00 172.00 172.00
b. Water Truck/Pump (16000 L) 1 0.05 2450.00 122.50
B.2
c. Backhoe (Wheel Type 0.28 m³) 1 0.10 922.00 92.20
Minor Tools (10% of Labor Cost) 75.63
Sub - Total for B.2 - As Evaluated 462.33
C.1 Total (A.1 + B.1) - As Submitted 1,218.67
C.2 Total (A.2 + B.2) - As Evaluated 1,218.67
D.1 Output per hour - As Submitted 1.60
D.2 Output per hour - As Evaluated 1.60
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 761.67
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 761.67
Name and Specification Unit Quantity Unit Cost Amount (Php)

Materials
a. Cement bag 5.50 255.90 1,407.45
b. Sand cu.m 0.30 985.82 295.75
F.1 c. Gravel Fill cu.m 0.02 1095.82 21.92
d. Weep Holes (PVC) m 0.30 144.67 43.40
e. Filter Cloth sq.m 0.015 175.00 2.63
f. Boulders cu.m 1.05 1085.82 1,140.11
Miscellaneous (1% of Materials Cost) 29.11
Sub - Total for F.1 - As Submitted 2,940.36
Materials
a. Cement bag 5.50 255.90 1,407.45
b. Sand cu.m 0.30 985.82 295.75
c. Gravel Fill cu.m 0.02 1095.82 21.92
d. Weep Holes (PVC) m 0.30 144.67 43.40
e. Filter Cloth sq.m 0.02 175.00 2.63
f. Boulders cu.m 1.05 1085.82 1,140.11
Miscellaneous (1% of Materials Cost) 29.11
Sub - Total for F.2 - As Evaluated 2,940.36
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 3,702.03
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 3,702.03
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 370.20
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 370.20
I.1 Contractor's Profit (CP) - As Submitted 8% 296.16
I.2 Contractor's Profit (CP) - As Evaluated 8% 296.16
J.1 Value Added Tax (VAT) - As Submitted 5% 218.42
J.2 Value Added Tax (VAT) - As Evaluated 5% 218.42
K.1 Total Unit Cost - As Submitted 4,586.82
K.2 Total Unit Cost - As Evaluated 4,586.82
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 508 (1) Hand Laid Rock Embankment

Unit of Measurement : cu m
Output per hour - As Submitted : 3.125
Output per hour - As Evaluated : 3.125
Quantity : 8.00 cu m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.1
b. Skilled Labor 2 1.00 79.17 158.34
c. Unskilled Labor 8 1.00 61.07 488.56

Sub - Total for A.1 - As Submitted 756.34


Labor
a. Construction Foreman 1 1.00 109.44 109.44
b. Skilled Labor 2 1.00 79.17 158.34
A.2
c. Unskilled Labor 8 1.00 61.07 488.56

Sub - Total for A.2 - As Evaluated 756.34


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)

Equipment
B.1
Minor Tools (10% of Labor Cost) 75.63

Sub - Total for B.1 - As Submitted 75.63


Equipment
Minor Tools (10% of Labor Cost) 75.63
B.2

Sub - Total for B.2 - As Evaluated 75.63


C.1 Total (A.1 + B.1) - As Submitted 831.97
C.2 Total (A.2 + B.2) - As Evaluated 831.97
D.1 Output per hour - As Submitted 3.125
D.2 Output per hour - As Evaluated 3.125
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 266.23
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 266.23
Name and Specification Unit Quantity Unit Cost Amount (Php)

Materials
F.1
a. Boulders cu.m. 1.05 1085.82 1,140.11

Sub - Total for F.1 - As Submitted 1,140.11


Materials
a. Boulders cu.m. 1.05 1085.82 1,140.11
F.2

Sub - Total for F.2 - As Evaluated 1,140.11


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 1,406.34
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 1,406.34
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 140.63
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 140.63
I.1 Contractor's Profit (CP) - As Submitted 8% 112.51
I.2 Contractor's Profit (CP) - As Evaluated 8% 112.51
J.1 Value Added Tax (VAT) - As Submitted 5% 82.97
J.2 Value Added Tax (VAT) - As Evaluated 5% 82.97
K.1 Total Unit Cost - As Submitted 1,742.46
K.2 Total Unit Cost - As Evaluated 1,742.46

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 511(1)a3 Gabions,1m x 1m x 2m, Metallic Coated

Unit of Measurement : cu m
Output per hour - As Submitted : 2.5
Output per hour - As Evaluated : 2.5
Quantity : 44.00 cu m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)

Labor
a. Construction Foreman 1 1 109.44 109.44
A.1 b. Skilled Laborer 2 1 79.17 158.34
c. Laborer 8 1 61.07 488.56

Sub - Total for A.1 - As Submitted 756.34


Labor
a. Construction Foreman 1 1 109.44 109.44
b. Skilled Laborer 2 1 79.17 158.34
A.2 c. Laborer 8 1 61.07 488.56

Sub - Total for A.2 - As Evaluated 756.34


Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)

Equipment
B.1

Sub - Total for B.1 - As Submitted


Equipment
B.2

Sub - Total for B.2 - As Evaluated


C.1 Total (A.1 + B.1) - As Submitted 756.34
C.2 Total (A.2 + B.2) - As Evaluated 756.34
D.1 Output per hour - As Submitted 2.50
D.2 Output per hour - As Evaluated 2.50
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 302.54
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 302.54
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Gabion Wire Mesh (1m x 1m x 2m) pc 0.5 2500.00 1,250.00
F.1 w/ complete accessories)
b. Boulders cu.m 1.05 1085.82 1,140.11

Sub - Total for F.1 - As Submitted 2,390.11


Materials
a. Gabion Wire Mesh (1m x 1m x 2m) pc 0.5 2500.00 1,250.00
w/ complete accessories)
F.2 b. Boulders cu.m 1.05 1085.82 1,140.11

Sub - Total for F.2 - As Evaluated 2,390.11


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 2,692.65
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 2,692.65
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 269.26
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 269.26
I.1 Contractor's Profit (CP) - As Submitted 8% 215.41
I.2 Contractor's Profit (CP) - As Evaluated 8% 215.41
J.1 Value Added Tax (VAT) - As Submitted 5% 158.87
J.2 Value Added Tax (VAT) - As Evaluated 5% 158.87
K.1 Total Unit Cost - As Submitted 3,336.19
K.2 Total Unit Cost - As Evaluated 3,336.19

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

Engineer II Engineer IV

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 511(3) Filter Cloth

Unit of Measurement : sq m
Output per hour - As Submitted : 100
Output per hour - As Evaluated : 100
Quantity : 39.30 sq m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


Labor
a. Construction Foreman 1 1 109.44 109.44
A.1 b. Skilled Laborer 2 1 79.17 158.34
c. Laborer 8 1 61.07 488.56

Sub - Total for A.1 - As Submitted 756.34


Labor
a. Construction Foreman 1 1 109.44 109.44
b. Skilled Laborer 2 1 79.17 158.34
A.2 c. Laborer 8 1 61.07 488.56

Sub - Total for A.2 - As Evaluated 756.34


Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
B.1 a. Cargo Truck (9 - 10 mt) 1 0.25 1212.00 303.00

Sub - Total for B.1 - As Submitted 303.00


Equipment
a. Cargo Truck (9 - 10 mt) 1 0.25 1212.00 303.00
B.2

Sub - Total for B.2 - As Evaluated 303.00


C.1 Total (A.1 + B.1) - As Submitted 1,059.34
C.2 Total (A.2 + B.2) - As Evaluated 1,059.34
D.1 Output per hour - As Submitted 100.00
D.2 Output per hour - As Evaluated 100.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 10.59
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 10.59
Name and Specification Unit Quantity Unit Cost Amount (Php)

Materials
a. Filter Cloth sq.m 1.05 175.00 183.75
F.1
Miscellaneous (5% of Materials Cost)

Sub - Total for F.1 - As Submitted 183.75


Materials
a. Filter Cloth sq.m 1.05 175.00 183.75
Miscellaneous (5% of Materials Cost)
F.2

Sub - Total for F.2 - As Evaluated 183.75


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 194.34
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 194.34
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 19.43
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 19.43
I.1 Contractor's Profit (CP) - As Submitted 8% 15.55
I.2 Contractor's Profit (CP) - As Evaluated 8% 15.55
J.1 Value Added Tax (VAT) - As Submitted 5% 11.47
J.2 Value Added Tax (VAT) - As Evaluated 5% 11.47
K.1 Total Unit Cost - As Submitted 240.79
K.2 Total Unit Cost - As Evaluated 240.79

Prepared by: Checked/Reviewed by:


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
LABOR MATERIAL EQUIPMENT

18,388.07

32,167.01

353,863.56
2,457.89

4,229.79

55,722.17
998,852.86

438,871.12

3,424,411.04
22,595.66

13,812.23

140,549.25
1,936.23

193.62

9,120.89
13,311.58

105,164.88
297.24

119.08

7,221.38
1,057,839.53 4,096,053.17 489,392.85 5,643,285.56
LABOR MATERIAL EQUIPMENT 5,643,285.56
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 603(3)a1 Metal Guardrails (Metal Beam) Including Post, Single (W-Beam)

Unit of Measurement : ln m
Output per hour - As Submitted : 4.20
Output per hour - As Evaluated : 4.20
Quantity : 190.50 ln m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)

Labor

A.1 a. Construction Foreman 1 1.00 109.44 109.44


b. Skilled Labor 2 1.00 79.17 158.34
c. Unskilled Labor 4 1.00 61.07 244.28

Sub - Total for A.1 - As Submitted 512.06


Labor
a. Construction Foreman 1 1.00 109.44 109.44
b. Skilled Labor 2 1.00 79.17 158.34
A.2 c. Unskilled Labor 4 1.00 61.07 244.28

Sub - Total for A.2 - As Evaluated 512.06


Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)

Equipment
a. Cargo Truck (10 T) 1 0.25 1,212.00 303.00
B.1
Minor Tools (5% of Labor Cost) 25.60

Sub - Total for B.1 - As Submitted 328.60


Equipment
a. Cargo Truck (10 T) 1 0.25 1,212.00 303.00
Minor Tools (5% of Labor Cost) 25.60
B.2

Sub - Total for B.2 - As Evaluated 328.60


C.1 Total (A.1 + B.1) - As Submitted 840.66
C.2 Total (A.2 + B.2) - As Evaluated 840.66
D.1 Output per hour - As Submitted 4.20
D.2 Output per hour - As Evaluated 4.20
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 200.16
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 200.16
Name and Specification Unit Quantity Unit Cost Amount (Php)

Materials
F.1 a. Metal Guardrails (Metal Beam) Including Post m 1.00 2,755.91 2,755.91
and other accessories

Sub - Total for F.1 - As Submitted 2,755.91


Materials
a. Metal Guardrails (Metal Beam) Including Post m 1.00 2,755.91 2,755.91
F.2 and other accessories

Sub - Total for F.2 - As Evaluated 2,755.91


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 2,956.07
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 2,956.07
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 295.61
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 295.61
I.1 Contractor's Profit (CP) - As Submitted 8% 236.49
I.2 Contractor's Profit (CP) - As Evaluated 8% 236.49
J.1 Value Added Tax (VAT) - As Submitted 5% 174.41
J.2 Value Added Tax (VAT) - As Evaluated 5% 174.41
K.1 Total Unit Cost - As Submitted 3,662.57
K.2 Total Unit Cost - As Evaluated 3,662.57

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 603(4)b Metal Beam End Piece (Bull Nose)

Unit of Measurement : each


Output per hour - As Submitted : 6.00
Output per hour - As Evaluated : 6.00
Quantity : 18.00 each

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)

Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.1
b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14

Sub - Total for A.1 - As Submitted 310.75


Labor
a. Construction Foreman 1 1.00 109.44 109.44
b. Skilled Labor 1 1.00 79.17 79.17
A.2
c. Unskilled Labor 2 1.00 61.07 122.14

Sub - Total for A.2 - As Evaluated 310.75


Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)

Equipment
a. Cargo Truck (9 - 10 mt) 1 1.00 1,212.00 1,212.00
B.1
Minor Tools(5% of Labor Cost) 15.54

Sub - Total for B.1 - As Submitted 1,227.54


Equipment
a. Cargo Truck (9 - 10 mt) 1 1.00 1,212.00 1,212.00
Minor Tools(5% of Labor Cost) 15.54
B.2

Sub - Total for B.2 - As Evaluated 1,227.54


C.1 Total (A.1 + B.1) - As Submitted 1,538.29
C.2 Total (A.2 + B.2) - As Evaluated 1,538.29
D.1 Output per hour - As Submitted 6.00
D.2 Output per hour - As Evaluated 6.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 256.38
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 256.38
Name and Specification Unit Quantity Unit Cost Amount (Php)

Materials
F.1 a. Metal Beam End Piece bull nose including accessories ea 1.00 22,135.00 22,135.00

Sub - Total for F.1 - As Submitted 22,135.00


Materials
a. Metal Beam End Piece bull nose including accessories ea 1.00 22,135.00 22,135.00
F.2

Sub - Total for F.2 - As Evaluated 22,135.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 22,391.38
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 22,391.38
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 2,239.14
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 2,239.14
I.1 Contractor's Profit (CP) - As Submitted 8% 1,791.31
I.2 Contractor's Profit (CP) - As Evaluated 8% 1,791.31
J.1 Value Added Tax (VAT) - As Submitted 5% 1,321.09
J.2 Value Added Tax (VAT) - As Evaluated 5% 1,321.09
K.1 Total Unit Cost - As Submitted 27,742.92
K.2 Total Unit Cost - As Evaluated 27,742.92

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)


Warning Signs, 750 mm, W2-6C, Intersection and Junction Signs Side Road
605(1)l3
Item No. / Description : Junction L or R
Unit of Measurement : each
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
Quantity : 1.00 each
Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.1
b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Sub - Total for A.1 - As Submitted 310.75
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.2 b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Sub - Total for A.2 - As Evaluated 310.75
Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
B.1 a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
Minor Tools (10% of Labor Cost)
Sub - Total for B.1 - As Submitted 195.75
Equipment
a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
B.2
Minor Tools (10% of Labor Cost)
Sub - Total for B.2 - As Evaluated 195.75
C.1 Total (A.1 + B.1) - As Submitted 506.50
C.2 Total (A.2 + B.2) - As Evaluated 506.50
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 506.50
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 506.5
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Portland Cement bag 0.48 255.9 122.83
b. Sand m³ 0.025 985.82 24.65
c. Gravel m³ 0.050 1,095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
F.1
e. 3" Ø GI Pipe m 3.10 425.00 1,317.50
f. Plate kg 2.00 48.00 96.00
g. Bolts, 5 mm Ø pc 12.00 10.00 120.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00 3,750.00 3,750.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 77.00 6.16
Sub - Total for F.1 - As Submitted 5,545.93
Materials
a. Portland Cement bag 0.48 255.90 122.83
b. Sand m³ 0.03 985.82 24.65
c. Gravel m³ 0.05 1095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
F.2 e. 3" Ø GI Pipe m 3.10 425.00 1,317.50
f. Plate kg 2.00 48.00 96.00
g. Bolts, 5 mm Ø pc 12.00 10.00 120.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00 3750.00 3,750.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 77.00 6.16
Sub - Total for F.2 - As Evaluated 5,545.93
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 6,052.43
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 6,052.43
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 605.24
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 605.24
I.1 Contractor's Profit (CP) - As Submitted 8% 484.19
I.2 Contractor's Profit (CP) - As Evaluated 8% 484.19
J.1 Value Added Tax (VAT) - As Submitted 5% 357.09
J.2 Value Added Tax (VAT) - As Evaluated 5% 357.09
K.1 Total Unit Cost - As Submitted 7,498.96
K.2 Total Unit Cost - As Evaluated 7,498.96

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 605 (1)u4 Warning Signs 450 x 700 mm, W4-2PA, Road Width Sign Road Narrows

Unit of Measurement : each


Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
Quantity : 6.00 each
Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)

Labor
A.1 a. Construction Foreman 1 1.00 109.44 109.44
b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Sub - Total for A.1 - As Submitted 310.75
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.2 b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Sub - Total for A.2 - As Evaluated 310.75

Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)

Equipment
B.1
a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
Minor Tools (10% of Labor Cost)
Sub - Total for B.1 - As Submitted 195.75
Equipment
a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
B.2
Minor Tools (10% of Labor Cost)
Sub - Total for B.2 - As Evaluated 195.75
C.1 Total (A.1 + B.1) - As Submitted 506.50
C.2 Total (A.2 + B.2) - As Evaluated 506.50
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 506.50
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 506.5
Name and Specification Unit Quantity Unit Cost Amount (Php)

Materials
a. Portland Cement bag 0.48 255.9 122.83
b. Sand m³ 0.025 985.82 24.65
c. Gravel m³ 0.050 1095.82 54.79
F.1 d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
e. 3" Ø GI Pipe m 3.10 492.58 1,527.01
f. Plate kg 2.00 48.00 96.00
g. Bolts, 5 mm Ø pc 12.00 10.00 120.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00 4200.00 4,200.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 93.40 7.47
Sub - Total for F.1 - As Submitted 6,206.75
Materials
a. Portland Cement bag 0.48 255.90 122.83
b. Sand m³ 0.03 985.82 24.65
c. Gravel m³ 0.05 1095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
e. 3" Ø GI Pipe m 3.10 492.58 1,527.01
f. Plate kg 2.00 48.00 96.00
g. Bolts, 5 mm Ø pc 12.00 10.00 120.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00 4200.00 4,200.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 93.40 7.47
Sub - Total for F.2 - As Evaluated 6,206.75
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 6,713.25
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 6,713.25
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 671.32
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 671.32
I.1 Contractor's Profit (CP) - As Submitted 8% 537.06
I.2 Contractor's Profit (CP) - As Evaluated 8% 537.06
J.1 Value Added Tax (VAT) - As Submitted 5% 396.08
J.2 Value Added Tax (VAT) - As Evaluated 5% 396.08
K.1 Total Unit Cost - As Submitted 8,317.72
K.2 Total Unit Cost - As Evaluated 8,317.72

Prepared by: Checked/Reviewed by:


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
DETAILED UNIT PRICE ANALYSIS (DUPA)
Warning Signs, 750mm x 750mm, W6-1C, Pedestrian and School Signs Pedestrian
Item No. / Description : 605(1)ai2 Crossing Ahead
Unit of Measurement : each
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
Quantity : 2.00 each
Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.1
b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Sub - Total for A.1 - As Submitted 310.75
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.2 b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Sub - Total for A.2 - As Evaluated 310.75
Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
B.1 a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
Minor Tools (10% of Labor Cost)
Sub - Total for B.1 - As Submitted 195.75
Equipment
a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
B.2
Minor Tools (10% of Labor Cost)
Sub - Total for B.2 - As Evaluated 195.75
C.1 Total (A.1 + B.1) - As Submitted 506.50
C.2 Total (A.2 + B.2) - As Evaluated 506.50
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 506.50
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 506.5
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Portland Cement bag 0.48 255.9 122.83
b. Sand m³ 0.025 985.82 24.65
c. Gravel m³ 0.050 1,095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
F.1
e. 3" Ø GI Pipe m 3.10 425.00 1,317.50
f. Plate kg 2.00 48.00 96.00
g. Bolts, 5 mm Ø pc 12.00 10.00 120.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00 4,200.00 4,200.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 77.00 6.16
Sub - Total for F.1 - As Submitted 5,995.93
Materials
a. Portland Cement bag 0.48 255.90 122.83
b. Sand m³ 0.03 985.82 24.65
c. Gravel m³ 0.05 1095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
F.2 e. 3" Ø GI Pipe m 3.10 425.00 1,317.50
f. Plate kg 2.00 48.00 96.00
g. Bolts, 5 mm Ø pc 12.00 10.00 120.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00 4200.00 4,200.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 77.00 6.16
Sub - Total for F.2 - As Evaluated 5,995.93
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 6,502.43
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 6,502.43
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 650.24
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 650.24
I.1 Contractor's Profit (CP) - As Submitted 8% 520.19
I.2 Contractor's Profit (CP) - As Evaluated 8% 520.19
J.1 Value Added Tax (VAT) - As Submitted 5% 383.64
J.2 Value Added Tax (VAT) - As Evaluated 5% 383.64
K.1 Total Unit Cost - As Submitted 8,056.51
K.2 Total Unit Cost - As Evaluated 8,056.51

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)


Warning Signs, 750mm x 750mm, W6-2C, Pedestrian and School Signs Children
Item No. / Description : 605(1)aj2 Crossing
Unit of Measurement : each
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
Quantity : 2.00 each
Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.1
b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Sub - Total for A.1 - As Submitted 310.75
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.2 b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Sub - Total for A.2 - As Evaluated 310.75
Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
B.1 a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
Minor Tools (10% of Labor Cost)
Sub - Total for B.1 - As Submitted 195.75
Equipment
a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
B.2
Minor Tools (10% of Labor Cost)
Sub - Total for B.2 - As Evaluated 195.75
C.1 Total (A.1 + B.1) - As Submitted 506.50
C.2 Total (A.2 + B.2) - As Evaluated 506.50
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 506.50
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 506.5
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Portland Cement bag 0.48 255.9 122.83
b. Sand m³ 0.025 985.82 24.65
c. Gravel m³ 0.050 1,095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
F.1
e. 3" Ø GI Pipe m 3.10 425.00 1,317.50
f. Plate kg 2.00 48.00 96.00
g. Bolts, 5 mm Ø pc 12.00 10.00 120.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00 4,200.00 4,200.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 77.00 6.16
Sub - Total for F.1 - As Submitted 5,995.93
Materials
a. Portland Cement bag 0.48 255.90 122.83
b. Sand m³ 0.03 985.82 24.65
c. Gravel m³ 0.05 1095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
F.2 e. 3" Ø GI Pipe m 3.10 425.00 1,317.50
f. Plate kg 2.00 48.00 96.00
g. Bolts, 5 mm Ø pc 12.00 10.00 120.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00 4200.00 4,200.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 77.00 6.16
Sub - Total for F.2 - As Evaluated 5,995.93
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 6,502.43
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 6,502.43
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 650.24
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 650.24
I.1 Contractor's Profit (CP) - As Submitted 8% 520.19
I.2 Contractor's Profit (CP) - As Evaluated 8% 520.19
J.1 Value Added Tax (VAT) - As Submitted 5% 383.64
J.2 Value Added Tax (VAT) - As Evaluated 5% 383.64
K.1 Total Unit Cost - As Submitted 8,056.51
K.2 Total Unit Cost - As Evaluated 8,056.51

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)


605(2)a3 Regulatory Signs, 750mm x 750mm, R1-1C, Priority Signs Stop
Item No. / Description :
Unit of Measurement : each
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
Quantity : 1.00 each
Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.1
b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Sub - Total for A.1 - As Submitted 310.75
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.2 b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Sub - Total for A.2 - As Evaluated 310.75
Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
B.1 a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
Minor Tools (10% of Labor Cost)
Sub - Total for B.1 - As Submitted 195.75
Equipment
a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
B.2
Minor Tools (10% of Labor Cost)
Sub - Total for B.2 - As Evaluated 195.75
C.1 Total (A.1 + B.1) - As Submitted 506.50
C.2 Total (A.2 + B.2) - As Evaluated 506.50
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 506.50
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 506.5
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Portland Cement bag 0.48 255.9 122.83
b. Sand m³ 0.025 985.82 24.65
c. Gravel m³ 0.050 1,095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
F.1
e. 3" Ø GI Pipe m 3.10 425.00 1,317.50
f. Plate kg 2.00 48.00 96.00
g. Bolts, 5 mm Ø pc 12.00 10.00 120.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00 4,200.00 4,200.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 77.00 6.16
Sub - Total for F.1 - As Submitted 5,995.93
Materials
a. Portland Cement bag 0.48 255.90 122.83
b. Sand m³ 0.03 985.82 24.65
c. Gravel m³ 0.05 1095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
F.2 e. 3" Ø GI Pipe m 3.10 425.00 1,317.50
f. Plate kg 2.00 48.00 96.00
g. Bolts, 5 mm Ø pc 12.00 10.00 120.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00 4200.00 4,200.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 77.00 6.16
Sub - Total for F.2 - As Evaluated 5,995.93
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 6,502.43
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 6,502.43
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 650.24
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 650.24
I.1 Contractor's Profit (CP) - As Submitted 8% 520.19
I.2 Contractor's Profit (CP) - As Evaluated 8% 520.19
J.1 Value Added Tax (VAT) - As Submitted 5% 383.64
J.2 Value Added Tax (VAT) - As Evaluated 5% 383.64
K.1 Total Unit Cost - As Submitted 8,056.51
K.2 Total Unit Cost - As Evaluated 8,056.51

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)


605(2)ai3
Item No. / Description : Regulatory Signs, 750 mm, R6-8C, Miscellaneous Signs Pedestrian Crossing
Unit of Measurement : each
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
Quantity : 2.00 each
Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.1
b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Sub - Total for A.1 - As Submitted 310.75
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.2 b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Sub - Total for A.2 - As Evaluated 310.75
Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
B.1 a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
Minor Tools (10% of Labor Cost)
Sub - Total for B.1 - As Submitted 195.75
Equipment
a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
B.2
Minor Tools (10% of Labor Cost)
Sub - Total for B.2 - As Evaluated 195.75
C.1 Total (A.1 + B.1) - As Submitted 506.50
C.2 Total (A.2 + B.2) - As Evaluated 506.50
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 506.50
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 506.5
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Portland Cement bag 0.48 255.9 122.83
b. Sand m³ 0.025 985.82 24.65
c. Gravel m³ 0.050 1,095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
F.1
e. 3" Ø GI Pipe m 3.10 425.00 1,317.50
f. Plate kg 2.00 48.00 96.00
g. Bolts, 5 mm Ø pc 12.00 10.00 120.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00 3,750.00 3,750.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 77.00 6.16
Sub - Total for F.1 - As Submitted 5,545.93
Materials
a. Portland Cement bag 0.48 255.90 122.83
b. Sand m³ 0.03 985.82 24.65
c. Gravel m³ 0.05 1095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
F.2 e. 3" Ø GI Pipe m 3.10 425.00 1,317.50
f. Plate kg 2.00 48.00 96.00
g. Bolts, 5 mm Ø pc 12.00 10.00 120.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00 3750.00 3,750.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 77.00 6.16
Sub - Total for F.2 - As Evaluated 5,545.93
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 6,052.43
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 6,052.43
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 605.24
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 605.24
I.1 Contractor's Profit (CP) - As Submitted 8% 484.19
I.2 Contractor's Profit (CP) - As Evaluated 8% 484.19
J.1 Value Added Tax (VAT) - As Submitted 5% 357.09
J.2 Value Added Tax (VAT) - As Evaluated 5% 357.09
K.1 Total Unit Cost - As Submitted 7,498.96
K.2 Total Unit Cost - As Evaluated 7,498.96

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)


605(2)aj3
Item No. / Description : Regulatory Signs, 750 mm ,R6-9C, Miscellaneous Signs School Children Crossing
Unit of Measurement : each
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00
Quantity : 2.00 each
Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.1
b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Sub - Total for A.1 - As Submitted 310.75
Labor
a. Construction Foreman 1 1.00 109.44 109.44
A.2 b. Skilled Labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14
Sub - Total for A.2 - As Evaluated 310.75
Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
B.1 a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
Minor Tools (10% of Labor Cost)
Sub - Total for B.1 - As Submitted 195.75
Equipment
a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75
B.2
Minor Tools (10% of Labor Cost)
Sub - Total for B.2 - As Evaluated 195.75
C.1 Total (A.1 + B.1) - As Submitted 506.50
C.2 Total (A.2 + B.2) - As Evaluated 506.50
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 506.50
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 506.5
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Portland Cement bag 0.48 255.9 122.83
b. Sand m³ 0.025 985.82 24.65
c. Gravel m³ 0.050 1,095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
F.1
e. 3" Ø GI Pipe m 3.10 425.00 1,317.50
f. Plate kg 2.00 48.00 96.00
g. Bolts, 5 mm Ø pc 12.00 10.00 120.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00 3,750.00 3,750.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 77.00 6.16
Sub - Total for F.1 - As Submitted 5,545.93
Materials
a. Portland Cement bag 0.48 255.90 122.83
b. Sand m³ 0.03 985.82 24.65
c. Gravel m³ 0.05 1095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
F.2 e. 3" Ø GI Pipe m 3.10 425.00 1,317.50
f. Plate kg 2.00 48.00 96.00
g. Bolts, 5 mm Ø pc 12.00 10.00 120.00
h. Sign Face, 3 mm thk Aluminum Sheet pc 1.00 3750.00 3,750.00
i. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 77.00 6.16
Sub - Total for F.2 - As Evaluated 5,545.93
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 6,052.43
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 6,052.43
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 605.24
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 605.24
I.1 Contractor's Profit (CP) - As Submitted 8% 484.19
I.2 Contractor's Profit (CP) - As Evaluated 8% 484.19
J.1 Value Added Tax (VAT) - As Submitted 5% 357.09
J.2 Value Added Tax (VAT) - As Evaluated 5% 357.09
K.1 Total Unit Cost - As Submitted 7,498.96
K.2 Total Unit Cost - As Evaluated 7,498.96

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 605(6)e1 Hazard Markers, 450x600mm, Chevron Signs

Unit of Measurement : each


Output per hour - As Submitted : 1
Output per hour - As Evaluated : 1
Quantity : 18.00 each

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)

Labor

a. Construction Foreman 1 1.00 109.44 109.44


A.1 b. Skilled labor 1 1.00 79.17 79.17
c. Unskilled Labor 2 1.00 61.07 122.14

Sub - Total for A.1 - As Submitted 310.75


Labor

a. Construction Foreman 1 1.00 109.44 109.44


b. Skilled labor 1 1.00 79.17 79.17
A.2 c. Unskilled Labor 2 1.00 61.07 122.14

Sub - Total for A.2 - As Evaluated 310.75


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)

Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75


B.1
Minor Tools (10% of Labor Cost) 31.08

Sub - Total for B.1 - As Submitted 226.83


Equipment

a. Cargo Truck (2 - 5 mt) 1 0.25 783.00 195.75


Minor Tools (10% of Labor Cost) 31.08
B.2

Sub - Total for B.2 - As Evaluated 226.83


C.1 Total (A.1 + B.1) - As Submitted 537.58
C.2 Total (A.2 + B.2) - As Evaluated 537.58
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 537.58
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 537.58
Name and Specification Unit Quantity Unit Cost Amount (Php)

Materials

a. Portland Cement bag 0.48 255.90 122.83


b. Sand cu.m 0.025 985.82 24.65
c. Gravel cu.m 0.05 1,095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
e. 75mm Ø GI Pipe m 3.25 492.58 1,600.90
F.1 f. GI Flat Bar, 1 1/2"x1/8" kg 5.00 48.00 240.00
g. GI Bolts w/ Nuts & Washer, 5 mm Ø pc 3.00 10.00 30.00
h. GI Bolts w/ Nuts & Washer, 2 mm Ø pc 12.00 10.00 120.00
i. Sign Face, 3 mm thk Aluminum Sheet pc 2.00 3,500.00 7,000.00
j. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 93.40 7.47
Miscellaneous (0.3% of Materials Cost) 27.76

Sub - Total for F.1 - As Submitted 9,282.40


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

Name and Specification Unit Quantity Unit Cost Amount (Php)

Materials
a. Portland Cement bag 0.48 255.90 122.83
b. Sand cu.m 0.025 985.82 24.65
c. Gravel cu.m 0.05 1,095.82 54.79
d. Form Lumber, Good - 4 uses bd-ft 8.00 27.00 54.00
F.2 e. 75mm Ø GI Pipe m 3.25 492.58 1,600.90
f. GI Flat Bar, 1 1/2"x1/8" kg 5.00 48.00 240.00
g. GI Bolts w/ Nuts & Washer, 5 mm Ø pc 3.00 10.00 30.00
h. GI Bolts w/ Nuts & Washer, 2 mm Ø pc 12.00 10.00 120.00
i. Sign Face, 3 mm thk Aluminum Sheet pc 2.00 3,500.00 7,000.00
j. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.08 93.40 7.47
Miscellaneous (0.3% of Materials Cost) 27.76

Sub - Total for F.2 - As Evaluated 9,282.40


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 9,819.98
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 9,819.98
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 982.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 982.00
I.1 Contractor's Profit (CP) - As Submitted 8% 785.60
I.2 Contractor's Profit (CP) - As Evaluated 8% 785.60
J.1 Value Added Tax (VAT) - As Submitted 5% 579.38
J.2 Value Added Tax (VAT) - As Evaluated 5% 579.38
K.1 Total Unit Cost - As Submitted 12,166.95
K.2 Total Unit Cost - As Evaluated 12,166.95

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 611(1) Trees Furnishing and Transplanting

Unit of Measurement : each


Output per hour - As Submitted : 30
Output per hour - As Evaluated : 30
Quantity : 5,040.00 each

Designation No. of Person/s No. of days Hourly Rate Amount (Php)

Labor
A.1 a. Construction Foreman 1 1 109.44 109.44
c. Unskilled Labor 2 1 61.07 122.14

Sub - Total for A.1 - As Submitted 231.58


Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 c. Unskilled Labor 2 1 61.07 122.14

Sub - Total for A.2 - As Evaluated 231.58


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)

Equipment
B.1
a. Cargo Truck (9 - 10 mt) 1 0.25 1212.00 303.00

Sub - Total for B.1 - As Submitted 303.00


Equipment
a. Cargo Truck (9 - 10 mt) 1 0.25 1212.00 303.00
B.2

Sub - Total for B.2 - As Evaluated 303.00


C.1 Total (A.1 + B.1) - As Submitted 534.58
C.2 Total (A.2 + B.2) - As Evaluated 534.58
D.1 Output per hour - As Submitted 30.00
D.2 Output per hour - As Evaluated 30.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 17.82
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 17.8193333333333
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
F.1
a. Trees (Delivered at Site) pc 1.00 5 5.00

Sub - Total for F.1 - As Submitted 5.00


Materials
a. Trees (Delivered at Site) pc 1.00 5 5.00
F.2

Sub - Total for F.2 - As Evaluated 5.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 22.82
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 22.82
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 2.28
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 2.28
I.1 Contractor's Profit (CP) - As Submitted 8% 1.83
I.2 Contractor's Profit (CP) - As Evaluated 8% 1.83
J.1 Value Added Tax (VAT) - As Submitted 5% 1.35
J.2 Value Added Tax (VAT) - As Evaluated 5% 1.35
K.1 Total Unit Cost - As Submitted 28.27
K.2 Total Unit Cost - As Evaluated 28.27

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 612(1) Reflectorized Thermoplastic Pavement Markings (White)

Unit of Measurement : sq m
Output per hour - As Submitted : 25
Output per hour - As Evaluated : 25
Quantity : 1,079.74 sq m
Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)

Labor
A.1 a. Construction Foreman 1 1 109.44 109.44
b. Skilled laborer 2 1 79.17 158.34
c. Laborer 6 1 61.07 366.42
Sub - Total for A.1 - As Submitted 634.20
Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 b. Skilled laborer 2 1 79.17 158.34
c. Laborer 6 1 61.07 366.42
Sub - Total for A.2 - As Evaluated 634.20
Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)

Equipment
a. Cargo Truck/Delivery Truck (2 - 5 mt) 1 1.00 783.00 783.00
B.1
b. Applicator Machine 1 1.00 93.75 93.75
c. Kneading Machine 1 1.00 187.50 187.50
Minor Tools (10% of Labor) 63.42
Sub - Total for B.1 - As Submitted 1,127.67
Equipment
a. Cargo Truck/Delivery Truck (2 - 5 mt) 1 1.00 783.00 783.00
b. Applicator Machine 1 1.00 93.75 93.75
B.2
c. Kneading Machine 1 1.00 187.50 187.50
Minor Tools (10% of Labor) 63.42
Sub - Total for B.2 - As Evaluated 1,127.67
C.1 Total (A.1 + B.1) - As Submitted 1,761.87
C.2 Total (A.2 + B.2) - As Evaluated 1,761.87
D.1 Output per hour - As Submitted 25.00
D.2 Output per hour - As Evaluated 25.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 70.47
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 70.47
Name and Specification Unit Quantity Unit Cost Amount (Php)

Materials
a. Thermoplastic Paint (White) bag 0.325 1585.00 515.13
b. Glass Beads bag 0.033 2310.00 76.23
F.1 c. Primer L 0.120 72.00 8.64
d. LPG (50 kg) cyl 0.004 5000.00 20.00
e. LPG (12 kg) cyl 0.002 1200.00 2.40
f. Calsumine kg 0.125 3.00 0.38
Miscellaneous (5% of Materials Cost) 31.14
Sub - Total for F.1 - As Submitted 653.91
Materials
a. Thermoplastic Paint (White) bag 0.325 1585.00 515.13
b. Glass Beads bag 0.033 2310.00 76.23
c. Primer L 0.120 72.00 8.64
d. LPG (50 kg) cyl 0.004 5000.00 20.00
e. LPG (12 kg) cyl 0.002 1200.00 2.40
f. Calsumine kg 0.125 3.00 0.38
Miscellaneous (5% of Materials Cost) 31.14
Sub - Total for F.2 - As Evaluated 653.91
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 724.38
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 724.38
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 72.44
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 72.44
I.1 Contractor's Profit (CP) - As Submitted 8% 57.95
I.2 Contractor's Profit (CP) - As Evaluated 8% 57.95
J.1 Value Added Tax (VAT) - As Submitted 5% 42.74
J.2 Value Added Tax (VAT) - As Evaluated 5% 42.74
K.1 Total Unit Cost - As Submitted 897.51
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

K.2 Total Unit Cost - As Evaluated 897.51

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 612(2) Reflectorized Thermoplastic Pavement Markings (Yellow)

Unit of Measurement : sq m
Output per hour - As Submitted : 25
Output per hour - As Evaluated : 25
Quantity : 1,008.24 sq m
Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)
Labor
A.1 a. Construction Foreman 1 1 109.44 109.44
b. Skilled laborer 2 1 79.17 158.34
c. Laborer 6 1 61.07 366.42
Sub - Total for A.1 - As Submitted 634.20
Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 b. Skilled laborer 2 1 79.17 158.34
c. Laborer 6 1 61.07 366.42
Sub - Total for A.2 - As Evaluated 634.20
Name and Capacity No. of Unit/s No. of hrs Hourly Rate Amount (Php)
Equipment
a. Cargo Truck/Delivery Truck (2 - 5 mt) 1 1.00 783.00 783.00
B.1
b. Applicator Machine 1 1.00 93.75 93.75
c. Kneading Machine 1 1.00 187.50 187.50
Minor Tools (10% of Labor) 63.42
Sub - Total for B.1 - As Submitted 1,127.67
Equipment
a. Cargo Truck/Delivery Truck (2 - 5 mt) 1 1.00 783.00 783.00
b. Applicator Machine 1 1.00 93.75 93.75
B.2
c. Kneading Machine 1 1.00 187.50 187.50
Minor Tools (10% of Labor) 63.42
Sub - Total for B.2 - As Evaluated 1,127.67
C.1 Total (A.1 + B.1) - As Submitted 1,761.87
C.2 Total (A.2 + B.2) - As Evaluated 1,761.87
D.1 Output per hour - As Submitted 25.00
D.2 Output per hour - As Evaluated 25.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 70.47
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 70.47
Name and Specification Unit Quantity Unit Cost Amount (Php)

Materials
a. Thermoplastic Paint (Yellow) bag 0.325 1585.00 515.13
b. Glass Beads bag 0.033 2310.00 76.23
F.1 c. Primer L 0.120 125.00 15.00
d. LPG (50 kg) cyl 0.004 5000.00 20.00
e. LPG (12 kg) cyl 0.002 1200.00 2.40
f. Calsumine kg 0.125 3.00 0.38
Miscellaneous (5% of Materials Cost) 31.46
Sub - Total for F.1 - As Submitted 660.59
Materials
a. Thermoplastic Paint (Yellow) bag 0.325 1585.00 515.13
b. Glass Beads bag 0.033 2310.00 76.23
c. Primer L 0.120 125.00 15.00
d. LPG (50 kg) cyl 0.004 5000.00 20.00
e. LPG (12 kg) cyl 0.002 1200.00 2.40
f. Calsumine kg 0.125 3.00 0.38
Miscellaneous (5% of Materials Cost) 31.46
Sub - Total for F.2 - As Evaluated 660.59
G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 731.06
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 731.06
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 73.11
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 73.11
I.1 Contractor's Profit (CP) - As Submitted 8% 58.48
I.2 Contractor's Profit (CP) - As Evaluated 8% 58.48
J.1 Value Added Tax (VAT) - As Submitted 5% 43.13
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

J.2 Value Added Tax (VAT) - As Evaluated 5% 43.13


K.1 Total Unit Cost - As Submitted 905.78
K.2 Total Unit Cost - As Evaluated 905.78

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 622(2)c Cocologs/Fascine, CN300

Unit of Measurement : ln m
Output per hour - As Submitted : 15
Output per hour - As Evaluated : 15
Quantity : 128.40 ln m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


Labor
a. Construction Foreman 1 1 109.44 109.44
A.1
c. Unskilled Labor 8 1 61.07 488.56

Sub - Total for A.1 - As Submitted 598.00


Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 c. Unskilled Labor 8 1 61.07 488.56

Sub - Total for A.2 - As Evaluated 598.00


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
Equipment
B.1 Minor Tools (10% of Labor) 59.80

Sub - Total for B.1 - As Submitted 59.80


Equipment
Minor Tools (10% of Labor) 59.80
B.2
Sub - Total for B.2 - As Evaluated 59.80
C.1 Total (A.1 + B.1) - As Submitted 657.80
C.2 Total (A.2 + B.2) - As Evaluated 657.80
D.1 Output per hour - As Submitted 15.00
D.2 Output per hour - As Evaluated 15.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 43.85
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 43.85
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Coco Fiber Roll (CGR 300) ln m 1.05 501.81 526.90
F.1
(Price includes nylon ropes and live stakes)

Sub - Total for F.1 - As Submitted 526.90


Materials
a. Coco Fiber Roll (CGR 300) ln m 1.05 501.81 526.90
F.2 (Price includes nylon ropes and live stakes)

Sub - Total for F.2 - As Evaluated 526.90


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 570.75
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 570.75
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 57.08
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 57.08
I.1 Contractor's Profit (CP) - As Submitted 8% 45.66
I.2 Contractor's Profit (CP) - As Evaluated 8% 45.66
J.1 Value Added Tax (VAT) - As Submitted 5% 33.67
J.2 Value Added Tax (VAT) - As Evaluated 5% 33.67
K.1 Total Unit Cost - As Submitted 707.16
K.2 Total Unit Cost - As Evaluated 707.16

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000
TO K1683+257.000, DAVAO ORIENTAL

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No. / Description : 622(3)b Vegetation, Vetiver Grass System

Unit of Measurement : sq m
Output per hour - As Submitted : 35
Output per hour - As Evaluated : 35
Quantity : 756.80 sq m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (Php)


Labor
a. Construction Foreman 1 1 109.44 109.44
A.1
c. Unskilled Labor 8 1 61.07 488.56

Sub - Total for A.1 - As Submitted 598.00


Labor
a. Construction Foreman 1 1 109.44 109.44
A.2 c. Unskilled Labor 8 1 61.07 488.56

Sub - Total for A.2 - As Evaluated 598.00


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (Php)
Equipment
Water Truck/Pump (16000 L) 1 0.50 2,450.00 1,225.00
B.1
Minor Tools (10% of Labor) 59.80

Sub - Total for B.1 - As Submitted 1,284.80


Equipment
Water Truck/Pump (16000 L) 1 0.50 2,450.00 1,225.00
B.2 Minor Tools (10% of Labor) 59.80

Sub - Total for B.2 - As Evaluated 1,284.80


C.1 Total (A.1 + B.1) - As Submitted 1,882.80
C.2 Total (A.2 + B.2) - As Evaluated 1,882.80
D.1 Output per hour - As Submitted 35.00
D.2 Output per hour - As Evaluated 35.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 53.79
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 53.79
Name and Specification Unit Quantity Unit Cost Amount (Php)
Materials
a. Vetiver Grass System sq m 1.05 77.45 81.32
F.1
(Price includes cocopeat fertilizer)

Sub - Total for F.1 - As Submitted 81.32


Materials
a. Vetiver Grass System sq m 1.05 77.45 81.32
F.2 (Price includes cocopeat fertilizer)

Sub - Total for F.2 - As Evaluated 81.32


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 135.12
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 135.12
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% 13.51
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% 13.51
I.1 Contractor's Profit (CP) - As Submitted 8% 10.81
I.2 Contractor's Profit (CP) - As Evaluated 8% 10.81
J.1 Value Added Tax (VAT) - As Submitted 5% 7.97
J.2 Value Added Tax (VAT) - As Evaluated 5% 7.97
K.1 Total Unit Cost - As Submitted 167.41
K.2 Total Unit Cost - As Evaluated 167.41

Prepared by: Checked/Reviewed by:

JESSICA B. APOSTOL JUDY ANN T. BERNARDINO


Engineer II Engineer IV
23,225.58

14,904.49

525,000.86
932.25

3,682.61

398,430.00
310.75

195.75

5,545.93
1,864.50

1,174.50

37,240.49
621.50

391.50

11,991.86
621.50

391.50

11,991.86
310.75

195.75

5,995.93
621.50

391.50

11,091.86
621.50

391.50

11,091.86
5,593.50

4,082.85

167,083.20
38,905.44

50,904.00

25,200.00
27,390.84

48,703.62

706,051.16
25,577.03

45,478.48

666,029.73
5,118.88

511.89

67,654.02
12,930.47

27,781.05

61,544.87

144,645.99 2,711,943.63 199,180.99 3,055,770.61


3,055,770.61
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

CALCULATION OF CYCLING TIME FOR HAULING EQUIPMENT

ESTIMATED TRAVEL SPEED, LOADING/UNLOADING & ALLOWANCE FOR DELAY

ROAD SURFACE DUMP TRUCK TRAVEL SPEED (KM / HR)


TERRAIN CONDITION
CONDITION LOADED EMPTY
PAVED 35 55
FLAT
UNPAVED 30 45
PAVED 30 40
ROLLING
UNPAVED 25 35
PAVED 20 30
MOUNTAINOUS
UNPAVED 15 25
LOADING TIME (min) 3
UNLOADING TIME (min) 2
ALLOWANCE FOR DELAY (min) 10% of Cycle Time

FORMULA FOR THE CALCULATION OF DUMP TRUCK TRAVEL TIME

FORMULA : T = D ÷ R

Where: T = Time, Time of Travel (h)


D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)

COMPUTATION OF CYCLE TIME, T


Items = Sand, Gravel, Item 200, Item 300, Boulders
Quarry Site = Casauman/ baganga Quarry
Quantity = 8.00 cu m
Ave. Hauling Distance = 26 km (less 5 km free haul)
Terrain = Paved/Unpaved Flat/Rolling/Mountainous
Travel Speed Loaded = 25.00 km/hr
Travel Speed Empty = 35.00 km/hr

Loaded Travel Time = 63.36 min


Unload and Maneuver = 2.00 min
Return Empty = 45.26 min
Cycle Time = 110.62 min
Allowance for Delay = 11.06 min

Total Cycle Time = 121.68 min


= 2.03 hr
EQUIPMENT/LABOR

Designation No. of Units No. of Hours Rate/Hour Amount


Labor
61.07
a. Unskilled Labor 1 2.03 123.97
Name and Capacity No. of Units No. of Hours Rate/Hour Amount
Equipment
1,420.00
a. Dumptruck 1 2.03 2,882.60
TOTAL 3,006.57

COST OF HAULING : 375.82 / cu.m

MATERIALS from CCIS: 3rd Quarter 2019

DESCRIPTION CCIS HAULING COST TOTAL AMOUNT


Sand = 610.00 375.82 /cu m 985.82 /cu m
Gravel = 720.00 375.82 /cu m 1,095.82 /cu m
Item 200 = 375.00 375.82 /cu m 750.82 /cu m
Item 300 = 640.00 375.82 /cu m 1,015.82 /cu m
Boulders = 710.00 375.82 /cu m 1,085.82 /cu m
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

CALCULATION OF CYCLING TIME FOR HAULING EQUIPMENT

ESTIMATED TRAVEL SPEED, LOADING/UNLOADING & ALLOWANCE FOR DELAY

ROAD SURFACE DUMP TRUCK TRAVEL SPEED (KM / HR)


TERRAIN CONDITION
CONDITION LOADED EMPTY
PAVED 35 55
FLAT
UNPAVED 30 45
PAVED 30 40
ROLLING
UNPAVED 25 35
PAVED 20 30
MOUNTAINOUS
UNPAVED 15 25
LOADING TIME (min) 3
UNLOADING TIME (min) 2
ALLOWANCE FOR DELAY (min) 10% of Cycle Time

FORMULA FOR THE CALCULATION OF DUMP TRUCK TRAVEL TIME

FORMULA : T = D ÷ R

Where: T = Time, Time of Travel (h)


D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)

COMPUTATION OF CYCLE TIME, T


Items = Cement
Quarry Site =
Quantity = 250.00 bags
Ave. Hauling Distance = 24 km (less 5 km free haul)
Terrain = Paved/Unpaved Flat/Rolling/Mountainous
Travel Speed Loaded = 25.00 km/hr
Travel Speed Empty = 35.00 km/hr

Loaded Travel Time = 57.36 min


Unload and Maneuver = 2.00 min
Return Empty = 40.97 min
Cycle Time = 100.33 min
Allowance for Delay = 10.03 min

Total Cycle Time = 110.36 min


= 1.84 hr

EQUIPMENT/LABOR

Designation No. of Units No. of Hours Rate/Hour Amount


Labor
a. Unskilled Labor 1 1.84 61.07 112.37

Name and Capacity No. of Units No. of Hours Rate/Hour Amount


Equipment
a. Dumptruck 1 1.84 1,420.00 2,612.80

TOTAL 2,725.17

COST OF HAULING : 10.90 / bag

MATERIALS from CCIS: 3rd Quarter 2019

DESCRIPTION CCIS HAULING COST TOTAL AMOUNT


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

CALCULATION OF CYCLING TIME FOR HAULING EQUIPMENT

ESTIMATED TRAVEL SPEED, LOADING/UNLOADING & ALLOWANCE FOR DELAY

ROAD SURFACE DUMP TRUCK TRAVEL SPEED (KM / HR)


TERRAIN CONDITION
CONDITION LOADED EMPTY
PAVED 35 55
FLAT
UNPAVED 30 45
PAVED 30 40
ROLLING
UNPAVED 25 35
PAVED 20 30
MOUNTAINOUS
UNPAVED 15 25
LOADING TIME (min) 3
UNLOADING TIME (min) 2
ALLOWANCE FOR DELAY (min) 10% of Cycle Time

FORMULA FOR THE CALCULATION OF DUMP TRUCK TRAVEL TIME

FORMULA : T = D ÷ R

Where: T = Time, Time of Travel (h)


D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)

Cement = 245.00 10.90 / bag 255.90 / bag

COMPUTATION OF CYCLE TIME, T


Items = Reinforcing Bar
Quarry Site =
Quantity = 10,000.00 kg
Ave. Hauling Distance = 24 km (less 5 km free haul)
Terrain = Paved/Unpaved Flat/Rolling/Mountainous
Travel Speed Loaded = 25.00 km/hr
Travel Speed Empty = 35.00 km/hr

Loaded Travel Time = 57.36 min


Unload and Maneuver = 2.00 min
Return Empty = 40.97 min
Cycle Time = 100.33 min
Allowance for Delay = 10.03 min

Total Cycle Time = 110.36 min


= 1.84 hr

EQUIPMENT/LABOR

Designation No. of Units No. of Hours Rate/Hour Amount


Labor
a. Unskilled Labor 1 1.84 61.07 112.37

Name and Capacity No. of Units No. of Hours Rate/Hour Amount


Equipment
a. Dumptruck 1 1.84 1,420.00 2,612.80

TOTAL 2,725.17

COST OF HAULING : 0.27 / kg


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

CALCULATION OF CYCLING TIME FOR HAULING EQUIPMENT

ESTIMATED TRAVEL SPEED, LOADING/UNLOADING & ALLOWANCE FOR DELAY

ROAD SURFACE DUMP TRUCK TRAVEL SPEED (KM / HR)


TERRAIN CONDITION
CONDITION LOADED EMPTY
PAVED 35 55
FLAT
UNPAVED 30 45
PAVED 30 40
ROLLING
UNPAVED 25 35
PAVED 20 30
MOUNTAINOUS
UNPAVED 15 25
LOADING TIME (min) 3
UNLOADING TIME (min) 2
ALLOWANCE FOR DELAY (min) 10% of Cycle Time

FORMULA FOR THE CALCULATION OF DUMP TRUCK TRAVEL TIME

FORMULA : T = D ÷ R

Where: T = Time, Time of Travel (h)


D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)

MATERIALS from CCIS: 3rd Quarter 2019

DESCRIPTION CCIS HAULING COST TOTAL AMOUNT


Grade 40 = 41.00 0.27 / kg 41.27 / kg
Grade 60 = 51.00 0.27 / kg 51.27 / kg

COMPUTATION OF CYCLE TIME, T


Items = 910 mm Ø RCPC
Quarry Site =
Quantity = 6.00 pcs
Ave. Hauling Distance = 24 km (less 5 km free haul)
Terrain = Paved/Unpaved Flat/Rolling/Mountainous
Travel Speed Loaded = 25.00 km/hr
Travel Speed Empty = 35.00 km/hr

Loaded Travel Time = 57.36 min


Unload and Maneuver = 2.00 min
Return Empty = 40.97 min
Cycle Time = 100.33 min
Allowance for Delay = 10.03 min

Total Cycle Time = 110.36 min


= 1.84 hr

EQUIPMENT/LABOR

Designation No. of Units No. of Hours Rate/Hour Amount


Labor
a. Unskilled Labor 1 1.84 61.07 112.37

Name and Capacity No. of Units No. of Hours Rate/Hour Amount


Equipment
a. Dumptruck 1 1.84 1,420.00 2,612.80

TOTAL 2,725.17
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

CALCULATION OF CYCLING TIME FOR HAULING EQUIPMENT

ESTIMATED TRAVEL SPEED, LOADING/UNLOADING & ALLOWANCE FOR DELAY

ROAD SURFACE DUMP TRUCK TRAVEL SPEED (KM / HR)


TERRAIN CONDITION
CONDITION LOADED EMPTY
PAVED 35 55
FLAT
UNPAVED 30 45
PAVED 30 40
ROLLING
UNPAVED 25 35
PAVED 20 30
MOUNTAINOUS
UNPAVED 15 25
LOADING TIME (min) 3
UNLOADING TIME (min) 2
ALLOWANCE FOR DELAY (min) 10% of Cycle Time

FORMULA FOR THE CALCULATION OF DUMP TRUCK TRAVEL TIME

FORMULA : T = D ÷ R

Where: T = Time, Time of Travel (h)


D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)

COST OF HAULING : 454.19 / pc

MATERIALS from CCIS: 3rd Quarter 2019

DESCRIPTION CCIS HAULING COST TOTAL AMOUNT


910 mm Ø RCPC = 4,700.00 454.19 / pc 5154.19 / pc

COMPUTATION OF CYCLE TIME, T

Items = 1220 mm Ø RCPC


Quarry Site =
Quantity = 4.00 lm
Ave. Hauling Distance = 24 km (less 5 km free haul)
Terrain = Paved/Unpaved Flat/Rolling/Mountainous
Travel Speed Loaded = 25.00 km/hr
Travel Speed Empty = 35.00 km/hr

Loaded Travel Time = 57.36 min


Unload and Maneuver = 2.00 min
Return Empty = 40.97 min
Cycle Time = 100.33 min
Allowance for Delay = 10.03 min

Total Cycle Time = 110.36 min


= 1.84 hr

EQUIPMENT/LABOR

Designation No. of Units No. of Hours Rate/Hour Amount


Labor
a. Unskilled Labor 1 1.84 61.07 112.37

Name and Capacity No. of Units No. of Hours Rate/Hour Amount


Equipment
a. Dumptruck 1 1.84 1,420.00 2,612.80
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

CALCULATION OF CYCLING TIME FOR HAULING EQUIPMENT

ESTIMATED TRAVEL SPEED, LOADING/UNLOADING & ALLOWANCE FOR DELAY

ROAD SURFACE DUMP TRUCK TRAVEL SPEED (KM / HR)


TERRAIN CONDITION
CONDITION LOADED EMPTY
PAVED 35 55
FLAT
UNPAVED 30 45
PAVED 30 40
ROLLING
UNPAVED 25 35
PAVED 20 30
MOUNTAINOUS
UNPAVED 15 25
LOADING TIME (min) 3
UNLOADING TIME (min) 2
ALLOWANCE FOR DELAY (min) 10% of Cycle Time

FORMULA FOR THE CALCULATION OF DUMP TRUCK TRAVEL TIME

FORMULA : T = D ÷ R

Where: T = Time, Time of Travel (h)


D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)

TOTAL 2,725.17

681.29 / lm

MATERIALS from CCIS: 3rd Quarter 2019

DESCRIPTION CCIS HAULING COST TOTAL AMOUNT


1220 mm Ø RCPC = 8,000.00 681.29 / lm 8,681.29 / lm
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

CALCULATION OF CYCLING TIME FOR HAULING EQUIPMENT

ESTIMATED TRAVEL SPEED, LOADING/UNLOADING & ALLOWANCE FOR DELAY

ROAD SURFACE DUMP TRUCK TRAVEL SPEED (KM / HR)


TERRAIN CONDITION
CONDITION LOADED EMPTY
PAVED 35 55
FLAT
UNPAVED 30 45
PAVED 30 40
ROLLING
UNPAVED 25 35
PAVED 20 30
MOUNTAINOUS
UNPAVED 15 25
LOADING TIME (min) 3
UNLOADING TIME (min) 2
ALLOWANCE FOR DELAY (min) 10% of Cycle Time

FORMULA FOR THE CALCULATION OF DUMP TRUCK TRAVEL TIME

FORMULA : T = D ÷ R

Where: T = Time, Time of Travel (h)


D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)

COMPUTATION OF CYCLE TIME, T


Items = Surplus Common Excavation
Quarry Site =
Quantity = 10.00 cu m
Ave. Hauling Distance = 15.00 km (less 5 km free haul)
Terrain = Paved/Unpaved Flat/Rolling/Mountainous
Travel Speed Loaded = 30.00 km/hr
Travel Speed Empty = 40.00 km/hr

Loaded Travel Time = 30.00 min


Unload and Maneuver = 2.00 min
Return Empty = 22.50 min
Cycle Time = 54.50 min
Allowance for Delay = 5.45 min

Total Cycle Time = 59.95 min


= 1.00 hr

EQUIPMENT/LABOR

Name and Capacity No. of Units No. of Hours


Equipment
a. Dumptruck 1 1.00
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

CALCULATION OF CYCLING TIME FOR HAULING EQUIPMENT

ESTIMATED TRAVEL SPEED, LOADING/UNLOADING & ALLOWANCE FOR DELAY

ROAD SURFACE DUMP TRUCK TRAVEL SPEED (KM / HR)


TERRAIN CONDITION
CONDITION LOADED EMPTY
PAVED 35 55
FLAT
UNPAVED 30 45
PAVED 30 40
ROLLING
UNPAVED 25 35
PAVED 20 30
MOUNTAINOUS
UNPAVED 15 25
LOADING TIME (min) 3
UNLOADING TIME (min) 2
ALLOWANCE FOR DELAY (min) 10% of Cycle Time

FORMULA FOR THE CALCULATION OF DUMP TRUCK TRAVEL TIME

FORMULA : T = D ÷ R

Where: T = Time, Time of Travel (h)


D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)

COMPUTATION OF CYCLE TIME, T


Items = Coco log
District =
Quantity = 400.00 lm
Ave. Hauling Distance = 24 km (less 5 km free haul)
Terrain =
Travel Speed Loaded = 25.00 km/hr
Travel Speed Empty = 35.00 km/hr

Loaded Travel Time = 57.36 min


Unload and manuever = 2.00 min
Return Empty = 40.97 min
Cycle Time = 100.33 min
Allowance for Delay = 10.03 min

Total Cycle Time = 110.36 min


= 1.84 hr

EQUIPMENT/LABOR

Designation No. of Units No. of Hours Rate/Hour Amount


Labor
a. Unskilled Labor 1 1.84 61.07 112.37

Name and Capacity No. of Units No. of Hours Rate/Hour Amount


Equipment
a. Dumptruck 1 1.84 1,420.00 2,612.80

TOTAL 2,725.17

COST OF HAULING : 6.81 / pc

MATERIALS from CCIS: 3rd Quarter 2019


DESCRIPTION CCIS HAULING COST TOTAL AMOUNT
Coco log = 495.00 6.81 / pc 501.81 / pc
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

CALCULATION OF CYCLING TIME FOR HAULING EQUIPMENT

ESTIMATED TRAVEL SPEED, LOADING/UNLOADING & ALLOWANCE FOR DELAY

ROAD SURFACE DUMP TRUCK TRAVEL SPEED (KM / HR)


TERRAIN CONDITION
CONDITION LOADED EMPTY
PAVED 35 55
FLAT
UNPAVED 30 45
PAVED 30 40
ROLLING
UNPAVED 25 35
PAVED 20 30
MOUNTAINOUS
UNPAVED 15 25
LOADING TIME (min) 3
UNLOADING TIME (min) 2
ALLOWANCE FOR DELAY (min) 10% of Cycle Time

FORMULA FOR THE CALCULATION OF DUMP TRUCK TRAVEL TIME

FORMULA : T = D ÷ R

Where: T = Time, Time of Travel (h)


D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)

COMPUTATION OF CYCLE TIME, T


Items = Vegetation
District =
Quantity = 500.00 lm
Ave. Hauling Distance = 24 km (less 5 km free haul)
Terrain =
Travel Speed Loaded = 25.00 km/hr
Travel Speed Empty = 35.00 km/hr

Loaded Travel Time = 57.36 min


Unload and manuever = 2.00 min
Return Empty = 40.97 min
Cycle Time = 100.33 min
Allowance for Delay = 10.03 min

Total Cycle Time = 110.36 min


= 1.84 hr

EQUIPMENT/LABOR

Designation No. of Units No. of Hours Rate/Hour Amount


Labor
a. Unskilled Labor 1 1.84 61.07 112.37

Name and Capacity No. of Units No. of Hours Rate/Hour Amount


Equipment
a. Dumptruck 1 1.84 1,420.00 2,612.80

TOTAL 2,725.17

COST OF HAULING : 5.45 / pc

MATERIALS from CCIS: 3rd Quarter 2019


DESCRIPTION CCIS HAULING COST TOTAL AMOUNT
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN),
K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

CALCULATION OF CYCLING TIME FOR HAULING EQUIPMENT

ESTIMATED TRAVEL SPEED, LOADING/UNLOADING & ALLOWANCE FOR DELAY

ROAD SURFACE DUMP TRUCK TRAVEL SPEED (KM / HR)


TERRAIN CONDITION
CONDITION LOADED EMPTY
PAVED 35 55
FLAT
UNPAVED 30 45
PAVED 30 40
ROLLING
UNPAVED 25 35
PAVED 20 30
MOUNTAINOUS
UNPAVED 15 25
LOADING TIME (min) 3
UNLOADING TIME (min) 2
ALLOWANCE FOR DELAY (min) 10% of Cycle Time

FORMULA FOR THE CALCULATION OF DUMP TRUCK TRAVEL TIME

FORMULA : T = D ÷ R

Where: T = Time, Time of Travel (h)


D = Distance, Hauling Distance (km)
R = Rate, Travel Speed (km/h)

Vegetation = 72.00 5.45 / pc 77.45 / pc


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL
ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

DERIVATION OF PROJECT DURATION

Project Category / Level of Improvement: Widening


Reference : Department Order No. 44, series of 2012

Formula:

( Dh - Dl ) ( Ap - Al )
C.D. = + Dl
( Ah - Al )

where:
Dh = Reference Duration (Higher) = 225 C.D.
Dl = Reference Duration (Lower) = 198 C.D.
Ah = Reference Amount (Higher) = 150.000 Million
Al = Reference Amount (Lower) = 100.000 Million

Appropriation, amount to be programmed


Ap = = 134.000 Million

( 225 C.D. - 198 C.D. ) x ( 134.000 Million - 100.000 Million )


C.D. = + 198 C.D.
( 150.000 Million - 100.000 Million )
( 27 C.D. ) x ( 34.000 Million )
= + 198 C.D.
( 50.000 Million )

= 216 C.D. Working Days

MONTH JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC TOTAL
CALENDAR DAYS 31 29 31 30 31 30 31 31 30 6 280
SUNDAYS 4 5 4 4 5 4 4 5 4 4 43
RAINY DAYS 1 1 1 1 1 1 1 1 1 1 10
HOLIDAYS 2 1 0 3 1 1 1 2 11
NET WORKING DAYS 24 22 26 22 24 24 25 23 25 1 216

Pre-determined Unworkable Days

No. of Sundays = 43 C.D.


Rainy Days = 10 C.D.
Holidays = 11 C.D.

No. of pre-determined
unworkable days = 64 C.D.
=

PROJECT DURATIO = 280 C.D.


COMPUTATION
SECTION 2 New Road Opening SECTION 2 New Road Opening
Adjusted Total #REF! 125,000,000.00
Length 1 -km 5.17 1 -km
A. Reference/ 15,122,557.11 15,122,557.11
B. Reference duration ### ###
C. Duration reduction factor ### ###
D. Mobilization & Demobilization(### ###
E. Adjusted To #REF! 10,000,000,000.00

F. E / A ### 661

G. F x C ### ###

H. F + Mobilization & demobilizat### ###

SAY ### C.D 262 C.D

8.73

6
25
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

ITEM NO. DESCRIPTION UNIT Roadway Drainage QUANTITY REMARKS

PART A FACILITIES FOR THE ENGINEER

A.1.1(3) Construction of Field Office for the Engineer ls 1.00

A.1.1(16) Operation & Maintenance of Field Office for the Engineer mo 8.00

PART B OTHER GENERAL REQUIREMENTS

B.4(1) Construction survey and staking km 3.360

B.5 Project Billboard / Signboard each 2.00

B.7(2) Occupational Safety and Health Program ls 1.00

B.8(2) Traffic Management ls 1.00

B.9 Mobilization / Demobilization ls 1.00

PART C EARTHWORK

100(1) Clearing and Grubbing ha 0.24 0.24

100(3)a3 Individual Removal of Trees, 501-750 mm dia. (Small) each 1,680.00 1,680.00

101(1) Removal Structures and Obstruction ls 1.00 1.00 Grouted riprap lined canal = 1225.06 cu.m.

101(2) Removal of Actual Structures/Obstruction each 28.00 28.00 headwall=22 each ; wingwall = 2 each
Removal of Actual Structure/Obstruction, 0.23m thick PCCP
101(3)b3 sq m 989.30 989.30 Concrete Pavement
(Unreinforced)
101(10) Removal of Existing Road Signs each 20.00 20.00

102(2) Surplus Common Excavation cu m 14,097.00 14,097.00

103(1)a Structure Excavation (Common Soil) cu m 383.60 383.60 for RCBC and RCPC

103(3) Foundation Fill cu m 39.10 39.10 for RCBC and RCPC

103(6)a Pipe Culverts and Drain Excavation (Common soil) cu m 194.30 194.30 for RCBC, RCPC and Grouted Riprap Lined Canal

104(1)a Embankment from Roadway Excavation (Common Soil) cu m 8,916.00 8,916.00

105(1)a Subgrade Preparation (Common Material) sq m 32,774.00 32,774.00

PART D SUBBASE AND BASE COURSE

200(1) Aggregate Subbase Course cu m 10,668.00 10,668.00

PART E SURFACE COURSES

300 (1) Gravel Surface Course cu m 2,157.00 2,157.00

Portland Cement Concrete Pavement (Unreinforced),0.28 m


311 (1) e1 sq m 22,517.26 22,517.26
thick,14 days

PART F DRAINAGE CONSTRUCTION

404 (1)a Reinforcing Steel, Grade 40 kg 18,537.14 18,537.14

405(1)a3 Structural Concrete, 20.68 MPa, Class "A", 28 days ln m 192.10 192.10

PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES

500(1)b3 Pipe Culverts, 910 mm dia. Class IV RCPC ln m 63.00 63.00

500(1)b5 Pipe Culverts, 1220 mm dia. Class IV RCPC ln m 6.00 6.00

505(2)a Grouted Riprap, Class A cu m 1,650.80 1,650.80

506(1) Stone Masonry cu m 47.80 47.80

508 (1) Hand Laid Rock Embankment cu m 8.00 8.00

511(1)a3 Gabions,1m x 1m x 2m, Metallic Coated cu m 44.00 44.00

511(3) Filter Cloth sq m 39.30 39.30

PART H MISCELLANEOUS STRUCTURE

603(3)a1 Metal Guardrail (Metal Beam) Including Post, Single, W-Beam ln m 190.50 190.50

603(4)b Metal Beam End Piece (Bull Nose) each 18.00 18.00

Warning Signs, 750 mm, W2-6C, Intersection and Junction


605(1)l3 each 1.00 1.00
Signs Side Road Junction L or R

Warning Signs 450x700 mm, W4-2PA, Road Width Sign Road


605(1)u4 each 6.00 6.00
Narrows

Warning Signs, 750mm x 750mm, W6-1C, Pedestrian and


605(1)ai2 each 2.00 2.00
School Signs Pedestrian Crossing Ahead

Warning Signs, 750mm x 750mm, W6-2C, Pedestrian and


605(1)aj2 each 2.00 2.00
School Signs Children Crossing

Regulatory Signs, 750mm x 750mm, R1-1C, Priority Signs Stop


605(2)a3 each 1.00 1.00

Regulatory Signs, 750 mm, R6-8C, Miscellaneous Signs


605(2)ai3 each 2.00 2.00
Pedestrian Crossing
Regulatory Signs, 750 mm ,R6-9C, Miscellaneous Signs
605(2)aj3 each 2.00 2.00
School Children Crossing

605(6)e1 Hazard Markers, 450x600mm, Chevron Signs each 18.00 18.00

611(1) Trees (Furnishing and Transplanting) each 5,040.00 5,040.00

612(1) Reflectorized Thermoplstic Pavement Markings (White) sq m 1,079.74 1,079.74

612(2) Reflectorized Thermoplstic Pavement Markings (Yellow) sq m 1,008.24 1,008.24

622(2)c Coco-Logs/ Fascine ln m 128.40 128.40

622(3)b Vegetation (Vetiver Grass System) sq m 756.80 756.80


Adjusted Cost Non-Civil Works Roadway Drainage

245,560.68 245,560.68

16,826.96 134,615.69

25,993.72 87,338.91

5,531.12 11,062.25

1,353,330.32 1,353,330.32

1,033,265.62 1,033,265.62

354,244.80 354,244.80

202,789.11 48,669.39 -

9,287.90 15,603,674.59 -

893,746.06 - 893,746.06

3,190.10 - 89,322.81

145.45 143,897.23 -

1,211.01 24,220.12 -

246.57 3,475,875.21 -

291.10 - 111,665.11

1,601.68 - 62,625.53

291.10 - 56,560.30

288.82 2,575,137.72 -

20.08 658,250.07 -

- -

- -

1,190.31 12,698,259.08 -

- -

- -

1,567.90 3,381,956.52 -

1,857.91 41,835,114.97 -

- -

- -

64.43 - 1,194,338.29

8,030.15 - 1,542,592.19

- -

- -

7,953.57 - 501,074.70

12,887.63 - 77,325.80

3,649.25 - 6,024,185.29

4,586.82 - 219,249.89

1,742.46 - 13,939.67

3,336.19 - 146,792.34

240.79 - 9,463.10

- -

- -

3,662.57 697,719.22 -

27,742.92 499,372.58 -

7,498.96 7,498.96 -

8,317.72 49,906.29 -

8,056.51 16,113.02 -

8,056.51 16,113.02 -

8,056.51 8,056.51 -

7,498.96 14,997.92 -
7,498.96 14,997.92 -

12,166.95 219,005.09 -

28.27 142,496.70 -

897.51 969,078.43 -

905.78 913,248.62 -

707.16 - 90,799.86

167.41 - 126,695.66

3,219,418.26 84,013,659.17 11,160,376.60

Total : 98,393,454.03

POW: 98,391,735.99

1,718.05
LABOR RATES (June 2019)
RESOURCE CODE BASIC WAGE
NO. DESCRIPTION LABOR COST FACTOR LEAVES 13 MONTH PAY
DAILY MONTHLY
1 Foreman 1.80 712.80 18,592.20 712.80 1,549.35
7 Skilled Laborer 1.30 514.80 13,427.70 514.80 1,118.98
9 Unskilled Laborer 1.00 396.00 10,329.00 396.00 860.75

EQUIPMENT RENTAL RATES (ROADS)


E1. List of equipment adopted in the standard DUPA with make, model and capacity
FLYWHEEL
HORSEPOWE RENTAL RATE
DESCRIPTION MODEL CAPACITY
R PER HOUR

1. Earthmoving Equipment
1.1 Bulldozer D6H SERIES II PSDS/DD 165.00 3,379.00
1.2 Bulldozer w/ Ripper D6H SERIES II PSDS/DD 165.00 3,885.85
1.3 Payloader LX80-2C 1.50 m³/1.95 yd³ 110.00 1,733.00
1.4 Motorized Road Grader G710A 140.00 2,173.00
1.5 Road Grader w/ Scarifier G710A 140.00 2,824.90
2. Compaction Equipment
2.1 Pneumatic Tire Roller 9-WHL, 9.00X20, 4PR 10 mt 107.00 561.00
2.2 Vibratory Roller SD100DC 10 mt 125.00 1,846.00
2.3 Tandem Steel Roller CC421 10.10 mt 123.40 1,652.00
2.4 Plate Compactor 400-500 Gasoline Engine 5.00 123.00
3. Lifting Equipment
3.1 Crawler Crane All Models 36-40 mt 190.00 1,902.00
3.2 Truck Mounted Crane All Models 31-35 mt 238.00 1,861.00
3.3 Truck Mounted Crane All Models 41-45 mt 246.00 2,606.00
4. Excavating Equipment
4.1 Backhoe SE 130 LC-2 0.80 m³/1.04 yd³ 99.00 1,537.00
4.2 Backhoe w/ Breaker SE 130 LC-2 0.80 m³/1.04 yd³ 99.00 1,998.10
4.3 Backhoe, Wheel Mounted PW60N-1 0.28 m³/0.37 yd³ 50.00 922.00
5. Foundation Equipment
5.1 Vibro Hammer DPD600T Hydraulic Pile Driver 60 ton 201.00 2,123.00
6. Asphalting Equipment
6.1 Asphalt Distributor ROSCO/5 ton 3000 USG 100.00 936.00
6.2 Asphalt Paver NF220BIIVDM 80.00 1,833.00
7. Concreting Equipment
7.1 Concrete Screeder Wacker Truss Screed 5.50 545.00
7.2 Concrete Paver COMMANDER III, FOUR-TRACK 6,765.00
7.3 One Bagger Mixer 4-6 ft³/min 172.00
7.4 Transit Mixer All Models 5-6 yd³ 175.00 1,318.00
8. Hauling Equipment
8.1 Dumptruck All Models 12 yd³ 290.00 1,420.00
8.2 Cargo/Service Truck All Models 2-5 mt 160.00 783.00
8.3 Boom Truck All Models 2-5 mt 160.00 1,017.90
8.4 Cargo/Service Truck All Models 9-10 mt 270.00 1,212.00
8.5 Water Truck/Pump All Makes 16000 L 360.00 2,450.00
9. Air Equipment
9.1 Air Compressor All Models 356-450 cfm 130.00 965.00
9.2 Air Compressor All Models 161-185 cfm 69.00 502.00
9.3 Air Compressor All Models 15-35 cfm 20.00 205.00
9.4 Diamond Drill CP-8 201.25
9.5 Jackhammer 150.00
9.6 Pneumatic Drilling Machine 170.00
10. Pumping Equipment
10.1 Water Pump, 100 mm suction Ø 2,667.00 50.00 16.00 266.25

12. Shop Equipment


12.1 Welding Machine Gas/Diesel Driven 300.00 48.00 371.00

13. Special Support Equipment


13.1 Chainsaw HUSQVARNA 2100 CD with CR22, 7ft Reach, 9 in Standard Blade 75.36
14. Miscellaneous Equipment
14.1 Concrete Vibrator Flexible Shaft Type 2" Head Ø with 5 Amperes Gasoline Drive Unit 91.25
14.2 Concrete Saw 14" Blade Ø with 4 3/4" Cutting Depth 7.50 32.63
14.3 Bar Cutter 25 mm Maximum Rebar Ø (Grade 40), Single Phase 219.75
14.4 Bar Bender 25 mm Maximum Rebar Ø, Three Phase 351.50
15. Plants
15.1 Asphalt Concrete Plant Complete with: Cold Freed System, bins, feeder and 4,286.63
collecting conveyors. Drying and Burner System, feed
conveyors drum and fully modulating burner. Fuel feed
system. Screening-Weighing-Mixing System, hot elevator,
vibrating screen, hot bins, weighing scale and twinshaft
pugmill mixer. Dust collection and filler feeding system,
bag filter and exhaust fan. Tehrmal Hot Oil System,
delivery pump and heater and Computerized Plant Control
System.
1,759.50
Complete with: cement silo and screw conveyor system.
Water and supply system. Aggregate storage bins with
vibrators and conveyors system. Weigh hopper with
electronic loadcell for aggregates, cement, water and
admixture. Central twinshaft mixer. Hydraulic System and
15.2 Concrete Batch Plant Computerized Plant Control System.
18. Others
18.1 Power Broom, Towed Type With Engine 2 m wide 6-30 km/h Sweeping Capacity 130.54
18.2 Hydroseeding Machine 952.00
18.3 Applicator Machine 93.75
18.4 Kneading Machine 187.50
18.5 Drop Hammer 200.00
18.6 Cutting Outfit 45.45
18.7 Steel Wheel w/ Nylon Rope 300.00
18.8 Improvised Bamboo w/ Bucket 200.00
18.9 Asphalt Kettle/Drum 10.00
MATERIALS PRICE DATA
2021 CCIS 1st QUARTER (Davao Oriental 1st Only)

DAVAO DEL DAVAO


MATERIAL DESCRIPTION COMVAL DAVAO CITY DEO NORTE DAVAO DEL SUR OCCIDENTAL

EMBANKMENT
300.00 340.00 310.00 410.00 345.00
COMMON BORROW

AGGREGATE SUBBASE COURSE


365.00 480.00 365.00 525.00 400.00
ITEM 200 AGGREGATE SUBBASE COURSE MATERIAL

AGGREGATE BASE COURSE


525.00 644.00 580.00 615.00 695.00
FILLER MATERIAL

AGGREGATE SURFACE COURSE

770.00 745.00 640.00 660.00 700.00


ITEM 300 UNCRUSHED GRADING A

PORTLAND CEMENT CONCRETE PAVEMENT


4,348.00 4,975.00 4,663.00 4,850.00
READY MIX CONCRETE 3500 PSI @ 7 DAYS
95.00 80.00 100.00 85.00 100.00
CURING COMPOUND
75.00 75.00 75.00 75.00 68.00
STEEL FORMS 28 CM WIDTH

PILING

STEEL SHEET PILES FY36 60.00 60.00 60.00 60.00 60.00

STEEL SHEET PILES FY50 61.00 64.00 64.00 64.00 60.00


21,323.00 20,958.00 21,124.00 21,126.00 21,303.00
STEEL CASING 10MM THICK @ 1200MM DIA.

WELDING ROD 105.00 100.00 110.00 114.00 125.00

REINFORCING STEEL
42.00 41.00 43.00 40.00
REINFORCING STEEL BARS DEFORMED GRADE 40
49.00 52.00 52.00 53.00
REINFORCING STEEL BARS DEFORMED GRADE 60
75.00 58.00 85.00 60.00
G.I TIE WIRE # 16

STRUCTURAL CONCRETE
63.00 61.00 65.00 62.00 64.00
COMMON NAILS ASSORTED
720.00 720.00 900.00 720.00
GRAVEL G1
455.00 520.00 750.00 750.00
FINE AGGREGATE
15.00 13.00 15.00 15.00
LUMBER COCO
34.00 45.00 36.00 35.00 40.00
LUMBER GOOD
340.00 350.00 370.00 387.50 350.00
PLYWOOD MARINE (0.00625M X 1.2M X 2.44M)
650.00 710.00 650.00 668.00 670.00
PLYWOOD MARINE (0.0125M X 1.2M X 2.44M)
541.00 530.00 545.00 650.00 535.00
PLYWOOD ORDINARY (0.0125M X 1.4M X 2.44M)
310.00 315.00 330.00 313.00 292.00
PLYWOOD ORDINARY (0.00625M X 1.4M X 2.44M)

PRESTRESSED CONCRETE STRUCTURES


27,612.00 27,117.00 27,364.00 27,468.00 27,859.00
PRESTRESSED CONCRETE AASHTO GIRDER TYPE IV (21-27

PIPE CULVERTS AND STORM DRAINS


4,700.00 4,700.00 4,700.00 4,700.00 4,700.00
REINFORCED CONCRETE PIPE CLASS IV DIA 36" (910MM)
8,000.00 8,000.00 8,000.00 8,000.00 8,000.00
REINFORCED CONCRETE PIPE CLASS IV DIA 48" (1220MM)
11,000.00 11,000.00 11,000.00 11,000.00 11,000.00
REINFORCED CONCRETE PIPE CLASS IV DIA 60" (1524MM)

MANHOLES, INLETS AND CATCH BASINS


24.00 24.00 28.00 28.00 28.00
CHB LOAD BEARING (150MM X 203MM X 406MM)
10.00 7.00 10.00 9.00 9.00
CHB ORDINARY (101MM X 203MM X 406MM)

GABIONS & MATTRESSES


2,500.00 2,500.00 2,500.00 2,500.00 2,500.00
GABIONS METALLIC COATED, 1M X 1M X 2M
2,700.00 2,700.00 2,700.00 2,700.00 2,700.00
GABIONS PVC COATED, 1M X 1M X 2M
4,550.00 4,550.00 4,550.00 4,550.00 4,550.00
MATTRESS METALLIC COATED 0.3M X 2M X 6M
4,995.00 4,995.00 4,995.00 4,995.00 4,995.00
MATTRESS PVC COATED 0.3M X 2M X 6M
175.00 175.00 175.00 175.00 175.00
FILTER CLOTH

GUARDRAIL
742.00 1,350.00 1,350.00 1,350.00 1,350.00
METAL BEAM END PIECE

PAVEMENT MARKINGS
2,310.00 2,310.00 2,310.00 2,310.00 2,310.00
GLASS BEADS (PRE-MIX)
125.00 188.00 125.00 213.00 125.00
PRIMER WHITE
122.00 229.00 122.00 255.00 122.00
PRIMER YELLOW
90.00 90.00 95.00 87.00 87.00
LPG CYLINDER
1,585.00 1,585.00 1,585.00 1,585.00 1,585.00
PAINT THERMOPLASTIC WHITE
1,800.00 1,800.00 1,800.00 1,800.00 1,800.00
PAINT THERMOPLASTIC YELLOW

BIO ENGINEERING SOLUTION


118.00 108.00 120.00 120.00 118.00
COCO - NET CGN 400
143.00 130.00 130.00 130.00 143.00
COCO - NET CGN 700
385.00 350.00 350.00 350.00 385.00
COCO - LOGS/FASCINE, CGR 200
495.00 450.00 450.00 450.00 495.00
COCO - LOGS/FASCINE, CGR 300
50.00 50.00 80.00 72.00 72.00
VEGETATION (VETIVER GRASS SYSTEM)

HYDRAULIC CEMENT
258.00 225.00 257.00 255.00 273.00
PORTLAND CEMENT

BITUMINOUS MATERIALS

ASPHALT CUT - BACK (RC70) 47,000.00 47,000.00 47,000.00 47,000.00 47,000.00


9,000.00 8,400.00 8,500.00 9,000.00 9,000.00
ASPHALT PLANT MIX HOT

PLUMBING AND FIXTURES


2,675.00 2,378.00 2,509.00 2,425.00 2,446.00
G.I PIPES (76MM D)
434.00 434.00 434.00 386.00 434.00
PVC PIPES (76MM D)
2019)
SOCIAL BENEFITS RATE PER
RATE PER DAY RATE PER HOUR
MONTH
SSS PHILHEALTH PAG-IBIG
1,510.00 255.64 100.00 22,719.99 871.05 109.44
1,090.00 184.63 100.00 16,436.11 630.14 79.17
850.00 142.02 100.00 12,677.77 486.05 61.07
y)

DAVAO ORIENTAL DAVAO ORIENTAL


1ST 2ND DAVAO CITY 2ND UNIT

320.00 285.00 300.00 CU M 326.25

375.00 350.00 365.00 CU M 403.13

540.00 525.00 620.00 CU M 593.00

640.00 650.00 745.00 CU M 693.75

5,172.00 5,172.00 4,640.00 CU M 4,831.43

95.00 95.00 80.00 L 91.25

78.00 75.00 75.00 LN M 74.50

KG 60.38
63.00 60.00 60.00
KG 63.50
67.00 64.00 64.00
21,680.00 21,415.00 21,084.00 LNM 21,251.63

115.00 120.00 100.00 KG

41.00 44.00 KG 50.20

49.00 KG 51.00

89.00 68.00 KG 72.50 35-45 kgs/roll

77.00 75.00 KGS 93.40

720.00 720.00 860.00 CU M 765.71

610.00 650.00 620.00 CU M 622.14

16.00 12.00 15.00 BDFT 12.63

27.00 30.00 40.00 BDFT 35.88

350.00 350.00 PC 416.25

705.00 650.00 665.00 PC 671.00

545.00 520.00 540.00 PC 550.75

330.00 320.00 315.00 PC 315.63

28,998.00 28,156.00 27,216.00 LNM 27,723.75


4,700.00 4,700.00 4,700.00 PC 4,700.00

8,000.00 8,000.00 8,000.00 PC 8,000.00

11,000.00 11,000.00 11,000.00 PC 11,000.00

29.00 28.00 28.00 PC 27.13

20.00 11.00 10.00 PC 10.75

2,500.00 2,500.00 2,500.00 PC 2,500.00

2,700.00 2,700.00 2,700.00 PC 2,700.00

4,550.00 4,550.00 4,550.00 PC 4,550.00

4,995.00 4,995.00 4,995.00 PC 4,995.00

175.00 175.00 175.00 SQ M 175.00

1,350.00 1,350.00 1,350.00 PC 1,274.00

2,310.00 2,310.00 2,310.00 BAG 2,310.00

125.00 255.00 125.00 LTR 160.13

128.00 281.00 122.00 LTR 172.63

100.00 100.00 90.00 KG 92.38


1,585.00 1,585.00 1,585.00 BAG 1,585.00

1,800.00 1,800.00 1,944.00 BAG 1,818.00

118.00 118.00 108.00 SQ M 116.00

143.00 143.00 130.00 SQ M 136.50

385.00 385.00 350.00 LN M 367.50

495.00 495.00 450.00 LN M 472.50

72.00 72.00 72.00 SQ M 67.50

245.00 278.00 259.00 BAG 256.25

47,000.00 47,000.00 47,000.00 MTON


9,884.00 9,000.00 8,500.00 MTON 8,910.50

2,550.00 2,750.00 PC 2,955.50

450.00 434.00 434.00 PC 430.00


ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

FORM POW-2015-01B-00

MINIMUM EQUIPMENT REQUIREMENT


Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Bulldozer, D6H SERIES II PSDS/DD 1 26
2 Bulldozer w/ Ripper, D6H SERIES II PSDS/DD 1 27
3 Payloader (1.50 m3), LX80-2C 1.50 m3 / 1.95 yd3 3 28
4 Motorized Road Grader (140 hp), G710A 1 29
5 Vibratory Roller (10 mt), SD100DC 10 mt 1 30
6 Plate Compactor (5 hp) 1 31
7 Backhoe (0.80 m3) 0.80 m3 / 1.04 yd3 1 32
8 Backhoe w/ Breaker (0.80 m3) 0.80 m3 / 1.04 yd3 1 33
9 Concrete Screeder 1 34
10 One Bagger Mixer 4-6 ft3 / min 1 35
11 Transit Mixer 5-6 yd3 4 36
12 Dump Truck (12 yd3) 12 yd3 6 37
13 Boom Truck (2 - 5 mt) 2-5 mt 1 38
14 Cargo/Service Truck 9-10 mt 1 39
15 Water Truck/Pump (16000 L) 16000L 1 40
16 Air Compressor (161 - 185 cfm) 1 41
17 Pneumatic Drilling Machine 2 42
18 Chainsaw 1 43
19 Concrete Vibrator 2 44
20 Concrete Saw (7.5 hp), 14" Blade Ø 1 45
21 Bar Cutter 1 46
22 Concrete Batch Plant (30 m 3) 1 47
23 Applicator Machine 1 48
24 Kneading Machine 1 49
25 50
26 51
27 52
28 53
29 54
30 55
31 56
32 57
33 58
34 59
35 60
36 61
37 62
38 63
SUB-TOTAL 36 SUB-TOTAL 0
TOTAL 36
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

DETAILED CALCULATIONS ON COST OF CONSTRUCTION SAFETY AND HEALTH

DUST/
OUTPUT NO. OF MAN- SAFETY SAFETY SAFETY WORKING EAR BODY RUBBER EYE
ITEM NO. / DESCRIPTION QUANTITY WORKERS DAYS RAIN COATS GAS LANYARD FACEMASK Medical kit
PER HOUR PERSONNEL DAYS HELMET SHOES VEST GLOVES MUFF HARNESS BOOTS GOGGLES
MASK

100(1) Foreman 1 0.6 0.6 0.6 0.6 0.6 0.6 0.18 0 0 0 0 0.6 0 0.6
0.24 0.05 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Clearing and Grubbing
Unskilled Laborer 2 0.6 1.2 1.2 1.2 1.2 1.2 0.36 0 0 0 0 1.2 0 1.2
100(3)a3 Foreman 1 210 210 210 210 210 210 63 0 0 0 0 210 0 210

Individual Removal of Trees, 501-750 1,680.00 1.00 Skilled Laborer 1 210 210 210 210 210 210 63 0 0 0 0 210 0 210
mm dia. (Small) Unskilled Laborer 2 210 420 420 420 420 420 126 0 0 0 0 420 0 420
101(1) Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.039 0 0 0 0 0.13 0 0.13

Removal of Structures and 1.00 1.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


Obstruction Unskilled Laborer 4 0.13 0.52 0.52 0.52 0.52 0.52 0.156 0 0 0 0 0.52 0 0.52
101(2) Foreman 1 3.5 3.5 3.5 3.5 3.5 3.5 1.05 0 0 0 0 3.5 0 3.5

Removal of Actual 28.00 1.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


Structures/Obstruction Unskilled Laborer 2 3.5 7 7 7 7 7 2.1 0 0 0 0 7 0 7
101(3)b3 Foreman 1 3.09 3.09 3.09 3.09 3.09 3.09 0.927 0 0 0 0 3.09 0 3.09
Removal of Actual 989.30 40.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Structure/Obstruction, 0.23m thick
PCCP (Unreinforced) Unskilled Laborer 2 3.09 6.18 6.18 6.18 6.18 6.18 1.854 0 0 0 0 6.18 0 6.18
101(10) Foreman 1 2.5 2.5 2.5 2.5 2.5 2.5 0.75 0 0 0 0 2.5 0 2.5
20.00 1.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Removal of Existing Road Signs
Unskilled Laborer 4 2.5 10 10 10 10 10 3 0 0 0 0 10 0 10
102(2) Foreman 1 22.03 22.03 22.03 22.03 22.03 22.03 6.609 0 0 0 0 22.03 0 22.03
14,097.00 80.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Surplus Common Excavation
Unskilled Laborer 2 22.03 44.06 44.06 44.06 44.06 44.06 13.218 0 0 0 0 44.06 0 44.06
103(1)a Foreman 1 2.4 2.4 2.4 2.4 2.4 2.4 0.72 0 0 0 0 2.4 0 2.4
383.60 20.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Structure Excavation (Common soil)
Unskilled Laborer 3 2.4 7.2 7.2 7.2 7.2 7.2 2.16 0 0 0 0 7.2 0 7.2
103(3) Foreman 1 3.91 3.91 3.91 3.91 3.91 3.91 1.173 0 0 0 0 3.91 0 3.91
39.10 1.25 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Foundation Fill
Unskilled Laborer 4 3.91 15.64 15.64 15.64 15.64 15.64 4.692 0 0 0 0 15.64 0 15.64
103(6)a Foreman 1 1.21 1.21 1.21 1.21 1.21 1.21 0.363 0 0 0 0 1.21 0 1.21

Pipe Culverts and Drain Excavation 194.30 20.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


(Common soil) Unskilled Laborer 3 1.21 3.63 3.63 3.63 3.63 3.63 1.089 0 0 0 0 3.63 0 3.63
104(1)a Foreman 1 22.29 22.29 22.29 22.29 22.29 22.29 6.687 0 0 0 0 22.29 0 22.29

Embankment from Roadway 8,916.00 50.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


Excavation (Common Soil) Unskilled Laborer 4 22.29 89.16 89.16 89.16 89.16 89.16 26.748 0 0 0 0 89.16 0 89.16
105(1)a Foreman 1 13.66 13.66 13.66 13.66 13.66 13.66 4.098 0 0 0 0 13.66 0 13.66

Subgrade Preparation (Common 32,774.00 300.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


Material) Unskilled Laborer 2 13.66 27.32 27.32 27.32 27.32 27.32 8.196 0 0 0 0 27.32 0 27.32
200(1) Foreman 1 26.67 26.67 26.67 26.67 26.67 26.67 8.001 0 0 0 0 26.67 0 26.67
10,668.00 50.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Aggregate Subbase Course
Unskilled Laborer 2 26.67 53.34 53.34 53.34 53.34 53.34 16.002 0 0 0 0 53.34 0 53.34
300(1) Foreman 1 5.39 5.39 5.39 5.39 5.39 5.39 1.617 0 0 0 0 5.39 0 5.39
2,157.00 50.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Gravel Surface Course
Unskilled Laborer 2 5.39 10.78 10.78 10.78 10.78 10.78 3.234 0 0 0 0 10.78 0 10.78
311(1)e1 Foreman 1 48.95 48.95 48.95 0 48.95 48.95 14.685 0 0 0 0 48.95 48.95 48.95

Portland Cement Concrete Pavement 22,517.26 57.50 Skilled Laborer 4 48.95 195.8 195.8 0 195.8 195.8 58.74 0 0 0 0 195.8 195.8 195.8
(Unreinforced), 0.28 m thick, 14 days Unskilled Laborer 12 48.95 587.4 587.4 0 587.4 587.4 176.22 0 0 0 0 587.4 587.4 587.4
404(1)a Foreman 1 12.87 12.87 12.87 12.87 12.87 12.87 3.861 0 0 0 0 12.87 0 12.87
18,537.14 180.00 Skilled Laborer 2 12.87 25.74 25.74 25.74 25.74 25.74 7.722 0 0 0 0 25.74 0 25.74
Reinforcing Steel , Grade 40
Unskilled Laborer 8 12.87 102.96 102.96 102.96 102.96 102.96 30.888 0 0 0 0 102.96 0 102.96
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

DETAILED CALCULATIONS ON COST OF CONSTRUCTION SAFETY AND HEALTH

DUST/
OUTPUT NO. OF MAN- SAFETY SAFETY SAFETY WORKING EAR BODY RUBBER EYE
ITEM NO. / DESCRIPTION QUANTITY WORKERS DAYS RAIN COATS GAS LANYARD FACEMASK Medical kit
PER HOUR PERSONNEL DAYS HELMET SHOES VEST GLOVES MUFF HARNESS BOOTS GOGGLES
MASK

405(1)a3 Foreman 1 17.15 17.15 17.15 0 17.15 17.15 5.145 0 0 0 0 17.15 17.15 17.15

Structural Concrete, 20.68 MPa, 192.10 1.40 Skilled Laborer 8 17.15 137.2 137.2 0 137.2 137.2 41.16 0 0 0 0 137.2 137.2 137.2
Class "A", 28 days Unskilled Laborer 16 17.15 274.4 274.4 0 274.4 274.4 82.32 0 0 0 0 274.4 274.4 274.4
500(1)b3 Foreman 1 7.88 7.88 7.88 7.88 7.88 7.88 2.364 0 0 0 0 7.88 0 7.88

Pipe Culverts, 910 mm dia. Class IV 63.00 1.000 Skilled Laborer 2 7.88 15.76 15.76 15.76 15.76 15.76 4.728 0 0 0 0 15.76 0 15.76
RCPC Unskilled Laborer 4 7.88 31.52 31.52 31.52 31.52 31.52 9.456 0 0 0 0 31.52 0 31.52
500(1)b5 Foreman 1 0.02 0.02 0.02 0.02 0.02 0.02 0.006 0 0 0 0 0.02 0 0.02

Pipe Culverts, 1220 mm dia. Class IV 6.00 35.000 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


RCPC Unskilled Laborer 8 0.02 0.16 0.16 0.16 0.16 0.16 0.048 0 0 0 0 0.16 0 0.16
505(2)a Foreman 1 165.08 165.08 165.08 0 165.08 165.08 49.524 0 0 0 0 165.08 165.08 165.08
1,650.80 1.250 Skilled Laborer 2 165.08 330.16 330.16 0 330.16 330.16 99.048 0 0 0 0 330.16 330.16 330.16
Grouted Riprap, Class A
Unskilled Laborer 8 165.08 1320.64 1320.64 0 1320.64 1320.64 396.192 0 0 0 0 1320.64 1320.64 1320.64
506(1) Foreman 1 3.73 3.73 3.73 3.73 3.73 3.73 1.119 0 0 0 0 3.73 0 3.73
47.80 1.600 Skilled Laborer 2 3.73 7.46 7.46 7.46 7.46 2.238 0 0 0 0 7.46 0 7.46
Stone Masonry
Unskilled Laborer 8 3.73 29.84 29.84 29.84 29.84 29.84 8.952 0 0 0 0 29.84 0 29.84
508 (1) Foreman 1 0.32 0.32 0.32 0.32 0.32 0.32 0.096 0 0 0 0 0.32 0 0.32
8.00 3.125 Skilled Laborer 2 0.32 0.64 0.64 0.64 0.64 0.64 0.192 0 0 0 0 0.64 0 0.64
Hand Laid Rock Embankment
Unskilled Laborer 8 0.32 2.56 2.56 2.56 2.56 2.56 0.768 0 0 0 0 2.56 0 2.56
511(1)a3 Foreman 1 2.2 2.2 2.2 2.2 2.2 2.2 0.66 0 0 0 0 2.2 0 2.2

Gabions,1m x 1m x 2m, Metallic 44.00 2.500 Skilled Laborer 2 2.2 4.4 4.4 4.4 4.4 4.4 1.32 0 0 0 0 4.4 0 4.4
Coated Unskilled Laborer 8 2.2 17.6 17.6 17.6 17.6 17.6 5.28 0 0 0 0 17.6 0 17.6
511(3) Foreman 1 0.05 0.05 0.05 0.05 0.05 0.05 0.015 0 0 0 0 0.05 0 0.05
39.30 100.000 Skilled Laborer 2 0.05 0.1 0.1 0.1 0.1 0.1 0.03 0 0 0 0 0.1 0 0.1
Filter Cloth
Unskilled Laborer 8 0.05 0.4 0.4 0.4 0.4 0.4 0.12 0 0 0 0 0.4 0 0.4
603(3)a1 Foreman 1 5.67 5.67 5.67 5.67 5.67 5.67 1.701 0 0 0 0 5.67 0 5.67
Metal Guardrails (Metal Beam) 190.50 4.20 Skilled Laborer 2 5.67 11.34 11.34 11.34 11.34 11.34 3.402 0 0 0 0 11.34 0 11.34
Including Post, Single (W-Beam)
Unskilled Laborer 4 5.67 22.68 22.68 22.68 22.68 22.68 6.804 0 0 0 0 22.68 0 22.68
603(4)b Foreman 1 0.38 0.38 0.38 0.38 0.38 0.38 0.114 0 0 0 0 0.38 0 0.38
18.00 6.00 Skilled Laborer 1 0.38 0.38 0.38 0.38 0.38 0.38 0.114 0 0 0 0 0.38 0 0.38
Metal Beam End Piece (Bull Nose)
Unskilled Laborer 2 0.38 0.76 0.76 0.76 0.76 0.76 0.228 0 0 0 0 0.76 0 0.76
605(1)l3 Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.039 0 0 0 0 0.13 0 0.13
Warning Signs, 750 mm, W2-6C, 1.00 1.00 Skilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.039 0 0 0 0 0.13 0 0.13
Intersection and Junction Signs Side
Road Junction L or R Unskilled Laborer 2 0.13 0.26 0.26 0.26 0.26 0.26 0.078 0 0 0 0 0.26 0 0.26
605 (1)u4 Foreman 1 0.75 0.75 0.75 0.75 0.75 0.75 0.225 0 0 0 0 0.75 0 0.75
Warning Signs 450 x 700 mm, W4- 6.00 1.00 Skilled Laborer 1 0.75 0.75 0.75 0.75 0.75 0.75 0.225 0 0 0 0 0.75 0 0.75
2PA, Road Width Sign Road Narrows
Unskilled Laborer 2 0.75 1.5 1.5 1.5 1.5 1.5 0.45 0 0 0 0 1.5 0 1.5
605(1)ai2 Foreman 1 0.25 0.25 0.25 0.25 0.25 0.25 0.075 0 0 0 0 0.25 0 0.25
Warning Signs, 750mm x 750mm, 2.00 1.00 Skilled Laborer 1 0.25 0.25 0.25 0.25 0.25 0.25 0.075 0 0 0 0 0.25 0 0.25
W6-1C, Pedestrian and School Signs
Pedestrian Crossing Ahead Unskilled Laborer 2 0.25 0.5 0.5 0.5 0.5 0.5 0.15 0 0 0 0 0.5 0 0.5
605(1)aj2 Foreman 1 0.25 0.25 0.25 0.25 0.25 0.25 0.075 0 0 0 0 0.25 0 0.25
Warning Signs, 750mm x 750mm, 2.00 1.00 Skilled Laborer 1 0.25 0.25 0.25 0.25 0.25 0.25 0.075 0 0 0 0 0.25 0 0.25
W6-2C, Pedestrian and School Signs
Children Crossing Unskilled Laborer 2 0.25 0.5 0.5 0.5 0.5 0.5 0.15 0 0 0 0 0.5 0 0.5
605(2)a3 Foreman 1 0.13 0.13 0.13 0.13 0.13 0.13 0.039 0 0 0 0 0.13 0 0.13
Regulatory Signs, 750mm x 750mm, 1.00 1.00 Skilled Laborer 1 0.13 0.13 0.13 0.13 0.13 0.13 0.039 0 0 0 0 0.13 0 0.13
R1-1C, Priority Signs Stop
Unskilled Laborer 2 0.13 0.26 0.26 0.26 0.26 0.26 0.078 0 0 0 0 0.26 0 0.26
605(2)ai3 Foreman 1 0.25 0.25 0.25 0.25 0.25 0.25 0.075 0 0 0 0 0.25 0 0.25
Regulatory Signs, 750 mm, R6-8C, 2.00 1.00 Skilled Laborer 1 0.25 0.25 0.25 0.25 0.25 0.25 0.075 0 0 0 0 0.25 0 0.25
Miscellaneous Signs Pedestrian
Crossing Unskilled Laborer 2 0.25 0.5 0.5 0.5 0.5 0.5 0.15 0 0 0 0 0.5 0 0.5
ROAD WIDENING ON SPECIFIC LOCATIONS ALONG SURIGAO DEL SUR BDRY.- DAVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

DETAILED CALCULATIONS ON COST OF CONSTRUCTION SAFETY AND HEALTH

DUST/
OUTPUT NO. OF MAN- SAFETY SAFETY SAFETY WORKING EAR BODY RUBBER EYE
ITEM NO. / DESCRIPTION QUANTITY WORKERS DAYS RAIN COATS GAS LANYARD FACEMASK Medical kit
PER HOUR PERSONNEL DAYS HELMET SHOES VEST GLOVES MUFF HARNESS BOOTS GOGGLES
MASK

605(2)aj3 Foreman 1 0.25 0.25 0.25 0.25 0.25 0.25 0.075 0 0 0 0 0.25 0 0.25
Regulatory Signs, 750 mm ,R6-9C, 2.00 1.00 Skilled Laborer 1 0.25 0.25 0.25 0.25 0.25 0.25 0.075 0 0 0 0 0.25 0 0.25
Miscellaneous Signs School Children
Crossing Unskilled Laborer 2 0.25 0.5 0.5 0.5 0.5 0.5 0.15 0 0 0 0 0.5 0 0.5
605(6)e1 Foreman 1 2.25 2.25 2.25 2.25 2.25 2.25 0.675 0 0 0 0 2.25 0 2.25

Hazard Markers, 450x600mm, 18.00 1.00 Skilled Laborer 1 2.25 2.25 2.25 2.25 2.25 2.25 0.675 0 0 0 0 2.25 0 2.25
Chevron Signs Unskilled Laborer 2 2.25 4.5 4.5 4.5 4.5 4.5 1.35 0 0 0 0 4.5 0 4.5
611(1) Foreman 1 21 21 21 21 21 21 6.3 0 0 0 0 21 0 21
5,040.00 30.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Trees Furnishing and Transplanting
Unskilled Laborer 2 21 42 42 42 42 42 12.6 0 0 0 0 42 0 42
612(1) Foreman 1 5.4 5.4 5.4 5.4 5.4 5.4 1.62 0 0 0 0 5.4 0 5.4

Reflectorized Thermoplastic 1,079.74 25.00 Skilled Laborer 2 5.4 10.8 10.8 10.8 10.8 10.8 3.24 0 0 0 0 10.8 0 10.8
Pavement Markings (White) Unskilled Laborer 6 5.4 32.4 32.4 32.4 32.4 32.4 9.72 0 0 0 0 32.4 0 32.4
612(2) Foreman 1 5.04 5.04 5.04 5.04 5.04 5.04 1.512 0 0 0 0 5.04 0 5.04

Reflectorized Thermoplastic 1,008.24 25.00 Skilled Laborer 2 5.04 10.08 10.08 10.08 10.08 10.08 3.024 0 0 0 0 10.08 0 10.08
Pavement Markings (Yellow) Unskilled Laborer 6 5.04 30.24 30.24 30.24 30.24 30.24 9.072 0 0 0 0 30.24 0 30.24
622(2)c Foreman 1 1.07 1.07 1.07 1.07 1.07 1.07 0.321 0 0 0 0 1.07 0 1.07
128.40 15.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Cocologs/Fascine, CN300
Unskilled Laborer 1 1.07 1.07 1.07 1.07 1.07 1.07 0.321 0 0 0 0 1.07 0 1.07
622(3)b Foreman 1 2.7 2.7 2.7 2.7 2.7 2.7 0.81 0 0 0 0 2.7 0 2.7
756.80 35.00 Skilled Laborer 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Vegetation, Vetiver Grass System
Unskilled Laborer 1 2.7 2.7 2.7 2.7 2.7 2.7 0.81 0 0 0 0 2.7 0 2.7
A. TOTAL, PERSONNEL/MAN-DAYS 245 1731.3 4789.15 4789.15 1712.37 4789.15 4781.69 1436.745 0 0 0 0 4789.15 0 3076.78 4789.15
B. SERVICE LIFE, DAYS 730 365 180 3 730 1 730 730 730 1 365 60
C. PURCHASE COST, PPh 180.55 1,012.00 400.00 23.00 245.00 63.25 602.60 1,263.85 1,083.30 5.00 506.00 300.00
D. UNIT COST / MAN-DAY (C ÷ B) 0.25 2.77 2.22 7.67 0.34 63.25 0.83 1.73 1.48 10.00 1.39 5.00
E. DIRECT COST FOR PPE's (D x A (Man-days)) 1,197.29 4,743.26 10,631.91 36,675.56 488.49 - - - - 47,891.50 4,276.72 23,945.75
F. SAFETY OFFICER/PRACTITIONER (PART TIME) @ P15,000.00/MONTH (AS PER D.O. 56, S2005, consider atleast 4 hours per week)
G. HEALTH PERSONNEL (FULL TIME) @ P8,400.00/MONTH (AS PER D.O. 56, S2005)
H. SANITATION AIDE
I. EQUIPMENT
J. Revised Construction Safety Guidelines for the Implementation of Infrastructure Projects During COVID-19 Public Health Crisis
H. TOTAL DIRECT COST (E + F + G + H + I + J)
I. OCM (9% OF H)
J. PROFIT (8% OF H)
K. VAT (5% OF H + I + J)
L. TOTAL COST (H + I + J + K)
AVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

OST OF CONSTRUCTION SAFETY AND HEALTH


AVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

OST OF CONSTRUCTION SAFETY AND HEALTH


AVAO OR. COASTAL ROAD (S00140MN), K1679+897.000 TO K1683+257.000, DAVAO ORIENTAL

OST OF CONSTRUCTION SAFETY AND HEALTH

129,850.50
245,460.79
177,568.81
273,945.36
34,360.92
332,226.60
1,193,412.98
-
95,473.04
64,444.30
1,353,330.32 1,353,330.32

1,353,330.32 -
1,353,330.32
Project : 6M. X 6M CAMPHOUSE
Location : FOR REGIONAL OFFICE PROJECTS
Subject : BILL OF MATERIALS

NO. ITEM DESCRIPTION QUANTITY UNIT UNIT COST AMOUNT

A. STRUCTURAL/MASONRY/FORMWORKS
1.00 CEMENT 44.00 BAG 255.90 11,259.60
2.00 SAND 3.00 CU M 985.82 2,957.46
3.00 GRAVEL 3.00 CU M 1,095.82 3,287.46
4.00 12MMø X 9.00M DEFORMED BARS 53.30 KG 41.27 2,199.69
5.00 10MMø X 12.00M DEFORMED BARS 73.90 KG 41.27 3,049.85
6.00 10MMø X 6.00M DEFORMED BARS 120.00 KG 41.27 4,952.40
7.00 #16 G.I. TIE WIRE 10.00 KG 89.00 890.00
9.00 4" CONCRETE HOLLOW BLOCKS 310.00 PC 28.00 8,680.00
10.00 1/2" THK. 4' X 8' PLYWOOD 1.00 SHT 705.00 705.00
11.00 ASSORTED NAILS CW NAILS 5.00 KG 77.00 385.00
TOTAL 38,366.46

B. FLOORING/FLOOR FRAMING/STAIRS
1.00 10 - 2" X 6" X 10' COCO LUMBER (RAFTER) 160.00 BD FT 16.00 2,560.00
2.00 6 - 2" X 4" X 10' COCO LUMBER (GIRTS) 70.00 BD FT 16.00 1,120.00
3.00 45 - 2" X 6" X 10' COCO LUMBER (GIRDER) 420.00 BD FT 16.00 6,720.00
2.00 14 - 2" X 4" X 10' COCO LUMBER (FLOOR JOIST/BLOCKS) 196.84 BD FT 16.00 3,149.38
3.00 1/2" X 2' X 4' MARINE PLYWOOD FLOORING 11.00 SHTS. 705.00 7,755.00
2.00 1 - 2" X 12" X 16' COCO LUMBER (STRINGER) 32.00 BD FT 16.00 512.00
6.00 4 - 2" X 12" X 10' COCO LUMBER (THREAD) 80.00 BD FT 16.00 1,280.00
7.00 6 - 1" X 10" X 10' COCO LUMBER (FASCIA) 50.00 BD FT 16.00 800.00
8.00 16MM Ø X 11" MACHINE BOLTS W/ NUTS & WASHERS 18.00 PC 100.00 1,800.00
9.00 1/4" THK. X 2" FLAT BAR (SCRAP) 1.00 PC 150.00 150.00
10.00 ASSORTED NAILS CW NAILS 12.00 KG 77.00 924.00
TOTAL 26,770.38

C. PARTITIONS/SIDINGS/CEILING/DOORS & WINDOWS


1.00 1/4" X 4' X 8' MARINE PLYWOOD 41.00 PC 350.00 14,350.00
2.00 123 - 2" X 3" X 10' COCO LUMBER (STUDS & NAILERS) 420.00 BD FT 16.00 6,720.00
3.00 60 - 2" X 2" X 8' COCO LUMBER (CEIL. FRAMES ) 311.39 BD FT 16.00 4,982.28
4.00 LOCKSETS 5.00 SET 1,550.00 7,750.00
5.00 3 1/2" X 3 1/2" BUTT HINGES 9.00 PAIR 100.00 900.00
6.00 2" X 2" BUTT HINGES 18.00 PAIR 40.00 720.00
7.00 ASSORTED NAILS CW NAILS 12.00 KG 77.00 924.00
TOTAL 36,346.28

D. ROOFING/ROOF FRAMING

1.00 6 - 4" X 4" X 10' COCO LUMBER (POST) 80.00 BD FT 16.00 1,280.00
2.00 7 - 4" X 4" X 12' COCO LUMBER (POST) 150.00 BD FT 16.00 2,400.00
3.00 6 - 2" X 6" X 10' COCO LUMBER (GIRTS) 60.00 BD FT 16.00 960.00
4.00 6 - 2" X 4" X 14' COCO LUMBER (RAFTER) 75.00 BD FT 16.00 1,200.00
5.00 24 - 2" X 3" X 14' COCO LUMBER (PURLINS) 180.39 BD FT 16.00 2,886.26
6.00 GA.26 CORRUGATED G.I. SHEET ROOFING 67.00 SQ M 300.00 20,100.00
7.00 GA. 26 36" X 8' PLAIN GI. SHEET (RIDGE ROLL) 8.00 L.M. 220.00 1,760.00
8.00 ASSORTED NAILS CW NAILS 12.00 KG 77.00 924.00
9.00 ROOF NAILS 5.00 KG 75.00 375.00
TOTAL 31,885.26
NO. ITEM DESCRIPTION QUANTITY UNIT UNIT COST AMOUNT

E. ELECTRICAL
1.00 8.0 SQ. MM. THHN WIRE 20.00 M 55.00 1,100.00
2.00 3.5 SQ. MM. THHN WIRE 50.00 M 26.00 1,300.00
3.00 2.0 SQ. MM. THHN WIRE 35.00 M 25.00 875.00
4.00 2X3 PVC RECEPTACLE 4.00 PC 35.00 140.00
5.00 4X4 PVC JUNCTION BOX 8.00 PC 48.00 384.00
6.00 2X4 PVC UTILITY BOX 8.00 PC 38.00 304.00
7.00 SWITCHES 5.00 PC 175.00 875.00
8.00 DOUBLE CONVENIENCE OUTLET 3.00 PC 86.00 258.00
9.00 SINGLE GANG PLATE 5.00 PC 54.00 270.00
10.00 20AT FUSE 1.00 PC 320.00 320.00
11.00 15 AT FUSE 1.00 PC 320.00 320.00
12.00 4-BRANCH PANEL BOARD 1.00 SET 850.00 850.00
13.00 18W COMPACT FLOURESCENT LAMP 4.00 PC 124.00 496.00
14.00 20W FLOURESCENT LAMP 4.00 SET 220.00 880.00
15.00 MOLDFLEX 40.00 M 10.00 400.00
16.00 ELECTRICAL TAPE 2.00 PC 35.00 70.00
TOTAL 8,842.00
F. PLUMBING

1.00 4"ø X 10' PVC PIPE S-1000 3.00 PC 620.00 1,860.00


2.00 2"ø X 10' PVC PIPE S-1000 1.00 PC 291.00 291.00
3.00 4"ø PVC WYE 4.00 PC 100.00 400.00
4.00 4"ø PVC CLEAN-OUT 4.00 PC 59.00 236.00
5.00 4"ø 90DEG.PVC ELBOW 2.00 PC 81.00 162.00
6.00 4"ø 45DEG.PVC ELBOW 2.00 PC 60.00 120.00
7.00 4"ø PVC P-TRAP 2.00 PC 95.00 190.00
8.00 2"ø PVC P-TRAP 2.00 PC 62.50 125.00
5.00 2"ø 90DEG.PVC ELBOW 2.00 PC 21.00 42.00
8.00 4" FLOOR DRAIN 2.00 PC 280.00 560.00
9.00 1/2"ø PE PIPE SDR-II 20.00 M 19.00 380.00
10.00 1/2 GI ELBOW 5.00 PC 21.50 107.50
11.00 1/2 GI TEE 2.00 PC 20.00 40.00
12.00 BRONZE FAUCET 3.00 PC 150.00 450.00
13.00 WATER CLOSET 2.00 SET 1,200.00 2,400.00
14.00 KITCHEN SINK 1.00 SET 900.00 900.00
15.00 1/2ø X 28" GI NIPPLE 1.00 PC. 52.00 52.00
16.00 1/2 X 4 GI NIPPLE 3.00 PC. 8.00 24.00
17.00 3/4 TEFLON TAPE 2.00 PC. 8.00 16.00
18.00 PVC SOLVENT 1.00 CAN 190.00 190.00
19.00 USED STEEL DRUMS 2.00 PC 850.00 1,700.00
TOTAL 10,245.50

TOTAL MATERIAL COST 152,455.88

TOTAL LABOR COST 45,736.76

GRAND TOTAL 198,192.64


(98,391,735.99)
152,455.88

0.00
Length= 791.45 ln m
(1 x 1m)
concrete Works
t L w/h #
slab 0.15 791.45 1.30 1.00 154.33
bracing 0.15 1.30 0.20 159.29 6.21
beam 0.10 791.45 0.15 2.00 23.74
column 0.20 1.00 0.20 318.58 12.74
. total 197.03
factor
cement 9 1773.286
sand 0.5 98.516
gravel 1 197.032

reinforcing bars
H/L # of bars # of units
slab 791.45 4 1 3165.80
bracing 1.30 2.00 159.29 414.15
beam 791.45 2.00 2.00 3165.80
column 1.00 4.00 318.58 1274.32
total 8020.07 8421.078

12mm dia. Def. bar x 6m 1559.46 pcs


say 1560.00

10mm dia. Def. bar x 6m


dowel 0.50 1.00 318.58 159.29 159.29

STIRRUPS (10mm dia. Def. bar x 6m)


H/L # of bars # of units
bracing 0.2 5 159.29 159.29 159.00
beam 0.15 5,276.33 2 1582.9 1583.00
slab 1.3 2,639.00 1 3,430.70 3431.00
column 0.4 7 318.58 892.024 892.00
total 6224.29

10mm dia. Def. bar x 6m 1037.38 pc


say 1037.00
Masonry
L W # of units
791.45 0.8 2 1266.32
factor
6" CHB Load Bearing 12.5 15987.000
Cement 1.018 1289.114
Washed Sand 0.0844 106.877
0.016 20.261
Tie Wire 0.021 27.922

L # of bars # of units
actual hor. - 791.45 2 2 3,165.80 3166.00
actual vert. - 0.95 2,067.00 2 3,927.30 3927.00
total 7093.00

10mm dia. Def. bar x 6m 1313.51851852 pc


say 1314

Plastering
L W # of faces
791.45 0.9 2 1,424.61
factor
Cement 0.192 273.52512
Washed Sand 0.016 22.79376

791.45
FINAL
FACTOR
cement 3335.92 4.21
sand 248.45 0.31
gravel 197.03 0.25
reinforcing bars 17000.98 21.48
6" CHB Load Bea 15987.00 20.20

Length= 141.73 ln m
(1 x 1m- varies)
concrete Works
t L w/h #
slab 0.15 141.73 1.30 1.00 27.64
bracing 0.15 1.30 0.20 29.35 1.14
beam 0.10 141.73 0.15 3.00 6.38
column 0.20 1.00 0.20 58.69 2.35
. total 37.51
factor
cement 9 337.566
sand 0.5 18.754
gravel 1 37.507

reinforcing bars
H/L # of bars # of units
slab 141.73 4 1 566.92
bracing 1.30 2.00 29.35 76.30
beam 141.73 2.00 3.00 850.38
column 1.20 4.00 58.69 281.72
total 1775.32 1864.087

12mm dia. Def. bar x 6m 345.20 pcs


say 346.00

10mm dia. Def. bar x 6m


dowel 0.50 1.00 58.69 29.35 29.35

STIRRUPS (10mm dia. Def. bar x 6m)


H/L # of bars # of units
bracing 0.2 5 29.35 29.346 29.00
beam 0.15 944.87 3 425.19 425.00
slab 1.3 473.00 1 614.90 615.00
column 0.4 7 58.69 164.3376 164.00
total 1262.35

10mm dia. Def. bar x 6m 210.39 pc


say 210.00

Masonry
L W # of units
141.73 0.8 2 226.768
factor
6" CHB Load Bearing 12.5 2863.000
Cement 1.018 230.850
Washed Sand 0.0844 19.139
0.016 3.628
Tie Wire 0.021 5.000

L # of bars # of units
actual hor. - 141.73 2 2 566.92 567.00
actual vert. - 0.95 377.00 2 716.30 716.00
total 1283.00

10mm dia. Def. bar x 6m 237.592592593 pc


say 238

Plastering
L W # of faces
141.73 0.9 2 255.11
factor
Cement 0.192 48.981888
Washed Sand 0.016 4.081824

141.73
FINAL
FACTOR
cement 617.40 4.36
sand 45.60 0.32
gravel 37.51 0.26
reinforcing bars 3499.30 24.69
6" CHB Load Bea 2863.00 20.20

Average 933.18
FINAL

cement 4.29
sand 0.32
gravel 0.26
reinforcing bars 23.09
6" CHB Load Bea 20.20
8311.68 kg

0.8 0.15 5.33333333333333


791.45 0.15 5,276.33

3832.75 kg
13 159.00

4856.54 kg
1843.49 kg

0.8 0.15 5.33333333333333


141.73 0.15 944.87

776.16 kg
13 29.00

879.65 kg
2,067.00
377.00
500(3)b1 Lined Canal, Rectangular,Concrete

ITEM # DESCRIPTION
404(1)a REINFORCING STEEL, GRADE 40
405(1)a3 STRUCTURAL CONCRETE, CLASS A
ln m 211.00

UNIT QUANTITY
kgs 2,260.00
cu m 56.00

Cement 3.39
Sand 0.133
Gravel 0.265
RSB, grade40 10.71
Tie wire 0.214
Plywood 1.00
Coco Lumber 85.00
CWN 0.85
10.71 kgs
0.27 cu.m
PICK UP
Computation of Rental Rates

Fully-Maintained basis

Rfm = 1.15 x AC x CRF x ( 2 + 0.023478


U CRF

AC Acquistion Cost = 1,293,000.00 strada


CRF Capital Recovery Factor = 0.240360363 (7 Years Economic Life)
U Average Utilization = 2,000.00 hours / year

= 1.15 x 1,293,000.00 x 0.240360363 x ( 2 + 0.023478


2,000 0.240360363

= 1.15 x 155.39 x 2.0976783

Rfm = 374.859 per hour


= 2,998.87 per day
= 74,971.83 per month

Computation of Rental Rates

FULLY-OPERATED BASIS

Rfo = Rfm + Fuel cost+ Lube cost + Vat

Fuel cost = 2.7 liter/hrs x 44 118.800 /hr ###

Lube cost = 20% 23.760 /hr ###

Operator Wage = Err:509 /hr Err:509

Rfm = 374.859 /hr ###


Err:509
vat(12%)

Err:509 /hr

Err:509 /day
Err:509 /month
0.023478 )
CRF

1,270,000.00

0.023478 )
0.240360363

6.25 ###

You might also like