Professional Documents
Culture Documents
JK Papr Limited, JKPM, Rayagada
JK Papr Limited, JKPM, Rayagada
Soda recovery
1400 TPD solids
Paper Machine
315,000* TPA
*Installed Capacity
Shut Plants
New Expansion Project 2001 2002 2004 2007 2008
New PD New ET Coating Wills Lime Kiln
Plant Plant Plant Cutter-3 Plant
1988
1988
5.4 MW
PM-4
TG set
1974
1970 1972
Coating
PM-2 PM-3
plant
1962
PM-1
48
45 42
35
Improvement (%)
30 26
15 10
4
0
JKPM C-1 C-2 C-3 C-4 C-5 C-6 C-7 C-8 C-9
-6
-15 -12
C-Competitor
Improvement %
Overall
PAT-1 PAT-2 PAT-7 PAT-1 to PAT- in Last PAT
Company Improvement
Baseline Baseline Baseline 2 Cycle
(%)
JKPM 0.736 0.462 0.2653 37.2 42.6 64
C-1 0.655 0.252 0.2552 61.5 -1.3 61
C-2 0.457 0.569 0.5109 -24.5 10.2 -12
C-3 1.058 0.57 0.5523 46.1 3.1 48
C-4 0.555 0.443 0.3205 20.2 27.7 42
C-5 0.609 0.557 0.3971 8.5 28.7 35
C-6 0.572 0.768 0.5174 -34.3 32.6 10
C-7 0.636 0.321 0.6132 49.5 -91.0 4
C-8 0.684 0.64 0.5038 6.4 21.3 26
C-9 0.591 0.777 0.6248 -31.5 19.6 -6
* Data source- PAT gadget *CII
The mentioned Major Projects are under nascent stage , the values are tentative and indicative only.
Action Taken:
• Multilevel cascade feedforward
control.
• Design change of steam control
valve.
1.05
0.24
1.78 0.14
1.26 0.16
• Resource conservation.
• Making future ready.
Action Taken:
• Logic was prepared to ramp up and down at slow
rate whenever there was a Pressure setpoint change
due to paper break.
• Interactive Operator HMI was created for altering the
ramp rate.
Action Taken:
• Predictive models for each key metric of the
process to recommend optimum chemical
dosage & air flow to get optimum brightness
and steam generation respectively.
• Interactive dashboard for quick decision
making.
Specific ClO2 consumption (Kg / Ton) Specific NaOH consumption (Kg /Ton)
15.5 12
15.08 11.51
11.5
15
14.2 11 10.56
14.5
10.5
14
10
13.5 Before After
Before After
2.7
Before After
0.25
0.21 23000
17000
0.20 22500
23230
23180 22451
22451
22165
22073
20687
12000
20392
22000 22165
0.15
7000
21500
2019-20 2020-21 2021-22
2000 0.10
2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22
Use of Bamboo & Wood dust( MT/Annum) Equivalent Coal ( Lacs of MT) Waste as " % " of total Fuel
energy
1.30 1.27
Bamboo Dust 1.25 1.24
Type of Waste Fuel Total Thermal Waste as "
(waste) GCV
Year Waste as energy ( Million energy ( Million % " of total 1.20
Quantity (Kcal/Kg)
fuel Kcal /kg) Kcal /kg) Fuel energy 1.15
(Ton)
1.10
2019- 1.05
22165 4120 9132 885478.16 1.03 1.03
20 1.00
2020- Bamboo & 0.95
22451 4275 9598 758424.31 1.27
21 Wood Dust
0.90
2021-
23230 4300 9989 803231.90 1.24 2019-20 2020-21 2021-22
22
Before After
High purity purged lime Built up the mechanism
sludge which was to utilize the high purity
generated from the lime sludge back in our
process was disposed of
at low lying areas or
system which serves the
Lime sludge Feeding
landfill. There was no purpose of 3R concept, Month
(MT)
proper mechanism to and thereby reduction of
feed the same in our cost and reduction of
system, resultant effect Q1-21-22 1200
load on landfill. A total of
was wastage of 4763 MT was re used
resources and thereby Q2-21-22 323
during the year. Some
increasing the cost. The
landfill was a big
part of the sludge is also Q3-21-22 2387
challenge due to space used by fish horticulture
constraint. people. Q4-21-22 853
1.40
1.40 33 %
1.28
1.25
1.10 1.08
1.04 1.05
0.94
0.80
2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22
Reduce freshwater
consumption by
1 substituting hot water with 2021 170400 1.8 1 6
back water in EOP & D1
washer spray in bleaching.
Greenco document is
Implementation of of great help to
ISO 50001, the 01 06 implement best
implementation is under practices
progress
22nd National Energy Management Overall Digitalization, Industry State Level Electrical Safety
Best Green Practitioner Award
Award 2021 from CII- ‘’Excellent Awards , Best Electrical Safety
4.0 2022
Energy Efficient Units’’. Practices.