REKAPITULASI ANGGARAN BIAYA
Volume
Kategori Harga Satuan Desa Jumlah Total (Rp)
URAIAN Dari Dana Dari Satuan
Biaya
Desa Swadaya ( Rp. ) Swadaya (Rp) Dana Desa (Rp)
a b d e f g=bxf h=cxf
1. BAHAN
1.1 Batu Belah 4.00 M3 I-a 200,000 800,000
1.2 Semen Abu-abu (PC) 28.00 Sak I-b 70,000 1,960,000
1.3 Pasir Pasang 4.00 M3 I-b 250,000 1,000,000
1.4 Pasir Urug 1.00 M3 I-b 220,000 220,000
1.5 Kayu Kelas III (Papan) 35.00 Lbr I-a 17,000 595,000
1.6 Kayu Kelas II 10.00 Lbr I-a 23,000 230,000
1.7 Paku 5 cm - 12 cm 10.00 Kg I-b 20,000 200,000
1.8 Minyak Bekisting 2.00 Kg I-b 25,000 50,000
1.9 Kawat Beton 1.00 Kg I-b 33,000 33,000
1.10 Krikil/Split 1.00 M3 I-b 400,000 400,000
1.11 Besi Beton Polos / Ulir (D 6) 1.00 Btg I-b 46,500 46,500
1.12 Besi Beton Polos / Ulir (D 10) 4.00 Btg I-b 66,000 264,000
1.13 Plywood tebal 9 mm 2.00 Btg I-b 50,000 100,000
1.14 Dolken kayu galam, Ø (8-10) cm, panjang 4 m 14.00 Btg I-a 35,000 490,000
1.15 Hebel 10x20x60 229.00 Bh I-b 10,000 2,290,000
1.16 Drymix PM 380 (Perekat Bata Ringan) 2.00 M3 I-b 45,000 90,000
1.17 Ubin Keramik Polos 30x30 KW I 24.00 M2 I-b 50,000 1,200,000
1.18 Semen Warna 1.00 Sak I-b 75,000 75,000
1.19 Cat interior 14.00 Kg I-b 40,000 560,000
1.20 Alkali 5.00 Kg I-b 25,000 125,000
1.21 Plamir tembok 5.00 Kg I-b 15,000 75,000
1.22 Kayu usuk 5/7 12.00 Btg I-a 18,000 216,000
1.23 Kayu reng 2/3 34.00 Btg I-a 11,000 374,000
1.24 Pintu (Set) 1.00 Bh I-b 900,000 900,000
1.25 Loster 1.00 Bh I-b 45,000 45,000
1.26 Asbes 1.05x 2.10 11.00 M2 I-b 20,000 220,000
1.26 Kayu Papan 3/20 8.00 Lbr I-a 20,000 160,000
1.27 Pipa PVC AW Ø ½" 1.00 Btg I-b 25,000 25,000
1.28 Kran Air 1.00 Bh I-b 7,000 7,000
1.29 T PVC Ø ½" 1.00 Bh I-b 10,000 10,000
1.30 Elbo PVC Ø ½" 1.00 Bh I-b 10,000 10,000
1.31 Sok Drat dalam PVC Ø ½" 1.00 Bh I-b 7,000 7,000
1.32 Lem PVC 2.00 Bh I-b 15,000 30,000
1.33 Seltif 1.00 Bh I-b 5,000 5,000
1.34 Pipa PVC Ø 1" 1.00 Btg I-b 55,000 55,000
1.35 Pipa PVC Ø 2½" 1.00 Btg I-b 140,000 140,000
1.36 Elbo PVC Ø 2½" 1.00 Bh I-b 25,000 25,000
1.37 Floor Drain 1.00 Bh I-b 20,000 20,000
1.38 Pipa PVC Ø 4" 1.00 Btg I-b 340,000 340,000
1.39 Elbo PVC Ø 4" 1.00 Bh I-b 30,000 30,000
1.40 Sok PVC Ø 4" 1.00 Bh I-b 35,000 35,000
1.41 Kloset Jongkok 1.00 Bh I-b 95,000 95,000
1.42 Kabel Lampu 10.00 M I-b 7,000 70,000
1.43 Pipa PVC 3/4 5.00 Btg I-b 35,000 175,000
1.44 Saklar 1.00 Bh I-b 60,000 60,000
1.45 Rumah Lampu 2.00 Bh I-b 25,000 50,000
1.46 Lampu LED 20 WATT (Phillips) 2.00 Bh I-b 70,000 140,000
1.47 Mangkok Saklar 1.00 Bh I-b 15,000 15,000
1.48 KWH 1.00 Bh I-b 1,500,000 1,500,000
1.49 Pompa Air 1.00 Bh I-b 500,000 500,000
Sub Total 1) 16,062,500
2. PERALATAN
2.1 Papan Proyek 1.00 Bh I-a 100,000 100,000
2.2 Prasasti 1.00 Bh I-a 350,000 350,000
2.3 Peralatan 1.00 Bh I.b. 200,000 200,000
Keterangan
Kategori :
I - a Pembelian bahan hasil tenaga manusia
I - b Pembelian bahan hasil industri
8.1 Pekerjaan Pas. Kuda-kuda 8/12 dan Gapit kuda - kuda 6/12
Kayu uk 8/12 1.10 ljr -
Kayu uk 6/12 1.10 ljr -
Besi kawel 15.00 kg -
Paku 5.60 kg -
Tukang 12.00 HOK -
Pekerja 4.00 HOK -
I. PEKERJAAN PERSIAPAN
0,50
0,40
C. Pek. Pembesian
0,05 a. Besi Ø 10 mm
Ø 10
Jumlah besi / sloof = 4.00 Buah
L = …. m Panjang besi = = 39.20
b. Besi Ø 6 mm
0,03 Jumlah sloof = 1.00 Buah
Panjang sloof = 16.00 Meter
0,17 Panjang besi = 0.64 Meter
Ø6 Jarak cincin = 0.15 Meter
Jumlah cincin sloof = 108.00 Buah
0,12
Panjang besi = = 76.03
Besi Ø 6 mm = 76.03 / 12 = 6.34
C. Pek. Pembesian
a. Besi Ø 10 mm
Jumlah besi / sloof = 4.00 Buah
Panjang besi = = 39.20
b. Besi Ø 6 mm
Jumlah sloof = 1.00 Buah
Panjang sloof = 16.00 Meter
Panjang besi = 0.64 Meter
Jarak cincin = 0.15 Meter
Jumlah cincin sloof = 108.00 Buah
1,50 4.2. Pek. Pas. 1/2 batu untuk Batu bata ad. 1 : 4
a. Dinding
Luas 1 = 4.00 x 2.5 = 10
Luas 2 = 2.60 x 6 = 15.6
Luas 3 = 1.50 x 2 = 3
1,50
28.6
Tebal pasangan = 0.10 Meter
Luas Kusen & Roster = 0.70 x 1.90 = 1.33
Jendela 0.40 x 0.15 = 0.06
1,30 1.39
0,80
= 27.21
L= …m
1,30
0,80
L= …m
Tanggal Survey : Dibuat oleh :
#REF!
b. Dinding Depan
Panjang = 0.00 Meter
1,20
Tinggi = 0.00 Meter
L= …m
Luas dinding = ( 5 x 1,20 ) = -
b. Besi Ø 6 mm
0,03
Jumlah kolom = 4.50 Buah
Panjang kolom = 2.25 Meter
Ø6 0,12 Panjang besi = 0.54 Meter
Jarak cincin = 0.15 Meter
0,12 Jumlah cincin kolom = 72.00 Buah
#REF!
Type 2
5.4. Pek. Beton ad. 1 : 2 : 3
Jumlah Kolom = 3.00 Buah
Panjang Kolom = 2.70 Meter
Lebar Kolom = 0.15 Meter
Tebal Kolom = 0.15 Meter
0,03
b. Besi Ø 6 mm
Jumlah kolom = 3.00 Buah
Panjang kolom = 1.80 Meter
Ø6 0,07 Panjang besi = 0.34 Meter
Jarak cincin = 0.15 Meter
0,07 Jumlah cincin kolom = 39.00 Buah
#REF!
b. Besi Ø 6 mm
Jumlah ring balok = 6.00 Buah
Panjang ring balok = 18.00 Meter
Panjang besi = 0.54 Meter
Jarak cincin = 0.20 Meter
Jumlah cincin ring balok = 96.00 Buah
Kayu 8/12 = =
Luas Lisplank = =
#REF!
#REF!
0,20
0,40
2,30
15.2. Pek. Beton ad. 1 : 2 : 3
Panjang Septictank = 2.30 Meter
Lebar Septictank = 1.50 Meter
1,50
Tebal Septictank = 0.10 Meter
2,30
Volume beton = (2,30 x 1,50 x 0,10) = 0.35
0,10
#REF!
2,30 15.4. Pek. Pas. 1/2 batu untuk Batu bata ad. 1 : 2
Luas Plesteran = = -
Dinding
1,00
Volume Galian = (1/4 x 3,14 x 1,00 x 1,00) x 1,00 = -
1,00
#REF!
e. Pek. Resapan
Pipa Cerobong Udara = = 1.00
Pipa Ø 4" = = 0.50
Kerikil 0,15 Elbow Ø 4" = = 1.00
Ijuk 0,05 Kerikil = (1/4 x 3,14 x 0,80 x 0,80) x 0,15 = 0.08
Arang = (1/4 x 3,14 x 0,80 x 0,80) x 0,10 = 0.05
Arang 0,10 = 0,05 x 400 kg/m3 = 20.10
Ijuk 0,05 Ijuk = = 20.00
Tanggal Survey : Dibuat oleh :
#REF!
Form 19
Meter
Meter
M3
M3
M2
M3
M3
oleh :
F!
Form 19
M2
M3
Meter
Btg
Kg
Meter
Btg
Kg
Kg
M2
M3
Meter
oleh :
F!
Form 19
0,05
Ø 10
L = …. m
Meter
Btg
Kg
Meter
Btg 5,00
1,20 2,60 1,20
Kg
1,00 1,00 1,00
Kg
3,00
M2
M2
M3 1,50
L= …m
M2
M2 20.8
M2 1
M2
M2
M2 2
M2 3
M2
M2
oleh :
F!
Form 19
M2
M2
M3
M2
M2
M2
M3
Meter
Btg
Kg
Meter
Btg
Kg
oleh :
F!
Form 19
Kg
M3
Meter
Btg
Kg
Meter
Btg
Kg
Kg
5,00
1,20 2,60 1,20
2,00
3,00
M2
1,00
0,15
0,15
M3
0,05
Ø 10
Meter
L = …. m
Btg
Kg
oleh :
F!
Form 19
0,03
Ø6 0,12
0,12
Meter
Btg
Kg
Kg
Meter
M3
M2
M2
M2
5,00
1,20 2,60 1,20
1,00
1,00 1,00 1,00
3,00
M3
oleh :
F!
Form 19
M3
M2
M2
M2
M2
Meter
Btg
Buah 5,00
Buah
1,20 2,60 1,20
Buah
Buah
Buah
Buah
1,00 1,00 1,00
3,00
Btg
Btg
Buah
Buah
Btg
Buah
Buah
Buah
Buah
Buah
Meter
Btg
Buah
Buah
Buah
Buah
Buah
oleh :
F!
Form 19
Meter
M3
M2
M3
M2
M3
M3
Meter
Meter
oleh :
F!
Form 19
Meter
Btg
Kg
M2
M3
Buah
M2
M3
M2
M3
M2
Meter
oleh :
F!
Form 19
Meter
Meter
Btg
Kg
Buah
Btg
Bh
M3
M3
Kg
Kg
oleh :
F!
Pembangunan Sarana Prasarana Melalui Swakelola TA 2016
Besi Ø 10 mm (Btg)
Kusen pintu (Buah)
Besi Ø 6 mm (Btg)
Pasir Pasang (M3)
TOTAL 3.07 2.21 15.95 1.50 3.73 2,658.28 121.09 0.36 1.00 - 0.52 0.05 0.22 - 13.04 11.12
0,05
0,05 2,00
1,50
Pembangunan Sarana Prasarana Melalui Swakelola TA 2016
Wastafel (Buah)
Minyak Cat (Ltr)
(Buah)
(Buah)
(Btg)
Pekerjaan
TOTAL 2.52 3.33 24.00 503.66 - 16.33 - 5.99 - 2.72 - 1.00 1.00 1.00 1.00 1.00
Pembangunan Sarana Prasarana Melalui Swakelola TA 2016
Mangkok Saklar
Elbo PVC Ø 4"
Rumah Lampu
Lampu (Buah)
Sok PVC Ø 4"
Saklar (Buah)
Sealtif (Buah)
Ø ½" (Buah)
(Buah)
(Buah)
(Buah)
(Buah)
(Btg)
Pekerjaan
I. PEKERJAAN PERSIAPAN
II. PEKERJAAN PONDASI
III. PEKERJAAN SLOOF BETON
IV. PEKERJAAN DINDING
2,00
1,50
V. PEKERJAAN KOLOM PRAKTIS
0,05
VI. PEKERJAAN RING BALOK
0,05
VII. PEKERJAAN RANGKA ATAP
VIII. PEKERJAAN ATAP
IX. PEKERJAAN KUSEN PINTU
X. PEKERJAAN LANTAI RUANGAN
XI. PEKERJAAN PENGECATAN
XII. PEKERJAAN PLUMBING 1.00 2.00 1.00 0.25 1.00 1.00 1.00 1.00 1.00 1.00
XIII. PEKERJAAN ELEKTRIKAL 10.00 5.00 1.00 2.00 2.00 1.00
XIV. PEKERJAAN DRAINASE
XV. PEKERJAAN SEPTICTANK 0.50 1.00
0,05
TOTAL 1.00 2.00 1.00 0.25 1.00 1.00 1.00 1.50 2.00 1.00 10.00 5.00 1.00 2.00 2.00 1.00
0,05
0,05 2,00
1,50
0,05
0,05 2,00
1,50
Pembangunan Sarana Prasarana Melalui Swakelola TA 2016
Upah Pemasangan
Lampu & Saklar
Ijuk (Kg)
Pekerja
Tukang
(Buah)
(Titik)
Pekerjaan
0,05
0,05 2,00
1,50
Pembangunan Sarana Prasarana Desa Melalui Swakelola TA 2016
HARGA SATUAN PEKERJAAN GEDUNG / MCK
Kabupaten #REF! Jenis Prasarana : Pembangunan MCK
Kecamatan #REF! Luas Lantai : 2,25 m2
Desa #REF! Referensi :-Buku Menghitung Anggaran Biaya
Bangunan Karangan Zainal A.Z.
-Buku Dasar Penyusunan Anggaran
Biaya Karangan Ir. J.A.Mukomoko
4.2. Pek. Pas. 1/2 batu untuk Batu G.33h & M3 27.21
bata ad. 1 : 4 G.27
80.00 buah Batu bata 2,176.80 Rp 700 Rp 1,523,760
0.406 M3 Pasir pasangan 11.05 Rp 185,000 Rp 2,043,743
2.530 Sak Semen 68.84 Rp 75,000 Rp 5,163,098
4.500 Pekerja 122.45 Rp 60,000 Rp 7,346,700
1.500 Tukang batu 40.82 Rp 75,000 Rp 3,061,125
14.2. Pek. Pas. 1/2 batu untuk Batu G.33l & M3 1.80
bata ad. 1 : 2 G.27
450.00 buah Batu bata 810.00 Rp 700 Rp 567,000
0.333 M3 Pasir pasangan 0.60 Rp 185,000 Rp 110,889
4.120 Sak Semen 7.42 Rp 75,000 Rp 556,200
4.500 Pekerja 8.10 Rp 60,000 Rp 486,000
1.500 Tukang batu 2.70 Rp 75,000 Rp 202,500
e. Pek. Resapan
1.00 Pipa Cerobong Udara 1.00 Rp 15,000 Rp 15,000
0.50 Pipa Ø 4 " Btg 0.50 Rp 100,000 Rp 50,000
1.00 Elbow Ø 4 " Bh 1.00 Rp 6,000 Rp 6,000
0.08 M3 Kerikil M3 0.08 Rp 200,000 Rp 15,072
20.10 Kg Arang Kg 20.10 Rp 2,500 Rp 50,240
20.00 Kg Ijuk Kg 20.00 Rp 10,000 Rp 200,000
JUMLAH Rp 39,193,648
#REF!
Diperiksa Oleh : Dibuat oleh :
#REF! #REF!
Pendamping Desa Ketua TPK
PNPM Mandiri Perdesaan
UPAH
68 Pekerja HOK 60,000
69 Tukang HOK 75,000
70 Upah Pemasangan Lampu Titik 60,000
71 Upah Pengeboran Sumur Ls 3,000,000
DESA CIMANCAK
PEMBANGUNAN MCK
KECAMATAN BAYAH
KABUPATEN LEBAK
PROPINSI BANTEN
KECAMATAN CILELES
KECAMATAN CILELES
Kecamatan : Cileles
: Cileles
Cileles
DESA CILELES
DESA CILELES
Cileles
: Cileles
Cileles, Mei 2016
Kegiatan MCK
TPK ( .................... )
Kasie Ekbang Desa ( ......................... )
Lokasi : Kp. ................
Jenis Prasarana : MC
nis Prasarana : MCK
#REF! Form 7.e
RENCANA ANGGARAN BIAYA
Propinsi #REF! No. RAB : 02
Kabupaten #REF! Program #REF!
Kecamatan #REF! Jenis Kegiatan : Sumur Bor
Desa #REF! Ukuran/Dimensi : Kedalaman 60 meter
#REF! #REF!
VOLUME HARGA JUMLAH
Kategori
URAIAN Dari Satuan SATUAN TOTAL
Total ADD Biaya
Swadaya ( Rp. ) ( Rp. )
1. BAHAN
1.1 Pipa PVC 4" (untuk cassing) #REF! 0.00 #REF! M3 I.b 75,000 #REF!
1.2 Pipa PVC 1 1/4" (pipa udara) #REF! 0.00 #REF! M3 I.b 20,000 #REF!
1.3 Pipa PVC 1" (pipa isap) #REF! 0.00 #REF! M3 I.b 15,000 #REF!
1.4 Socket drat dalam 1 1/4" #REF! 0.00 #REF! M3 I.b 2,500 #REF!
1.5 Socket drat dalam 1" #REF! 0.00 #REF! Buah I.b 2,500 #REF!
1.6 Knie elbow 1 1/4" #REF! 0.00 #REF! Sak I.b 3,500 #REF!
1.7 Knie Elbow 1" #REF! 0.00 #REF! M3 I.b 2,500 #REF!
1.8 Socket drat luar 1 1/4" #REF! 0.00 #REF! M3 I.b 2,500 #REF!
1.9 Socket drat luar 1" #REF! 0.00 #REF! Btg I.b 2,500 #REF!
1.10 Klep #REF! 0.00 #REF! Btg I.b 15,000 #REF!
1.11 Lem PVC #REF! 0.00 #REF! Kg I.b 5,000 #REF!
1.12 Sealtif #REF! 0.00 #REF! Kg I.b 2,000 #REF!
1.13 Tambang #REF! 0.00 #REF! Kg I.b 3,000 #REF!
1.14 Pipa Inlet 1/2" PVC AW #REF! 0.00 #REF! Kg I.b 12,000 #REF!
1.15 Stop kran Valve 1/2" #REF! 0.00 #REF! Lbr I.b 15,000 #REF!
1.16 Socket drat dalam 3/4" #REF! 0.00 #REF! Btg I.b 2,500 #REF!
1.17 V soc PVC 3/4" #REF! 0.00 #REF! Bh I.b 2,500 #REF!
1.18 Boll Valf 1/2" #REF! 0.00 #REF! Bh I.b 15,000 #REF!
1.19 Penampung Air 1000 liter 1.00 0.00 1.00 Bh I.b 1,500,000 1,500,000
1.20 Menara Air tinggi 5 m 1.00 0.00 1.00 Bh I.b 2,000,000 2,000,000
Sub Total 1) #REF!
2. PERALATAN
2.1 Pompa air #REF! 0.00 #REF! Bh II.b 1,500,000 #REF!
#REF!
Bobot %
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
HOK
#REF!
Ketua TPK
#REF!
Pembangunan Sarana Prasarana Desa Melalui Swakelola TA 2016
Kebutuhan Material
"Pipa AW Ø 1
Pipa Isap
Mata Zet
"½Klep Ø 1
10,00
0
0
,
10
15
Form 19
Btg
Btg
Btg
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Buah
Meter
Btg
Buah
Buah
Buah
Buah
Buah
t oleh :
………….. )
Propinsi #REF!
Kabupaten #REF!
Kecamatan #REF!
Desa #REF!
Kanto
r RW Jenis Prasarana
Pemb. MCK
Rencana
Posyandu
Lokasi :
Dusun V
JUDUL GAMBAR
- Denah Lokasi
Dibuat oleh :
Jalan Utama Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
DENAH LOKASI
#REF!
Lembar ke …. dari ….
Propinsi #REF!
Kabupaten #REF!
Kecamatan #REF!
Desa #REF!
Jenis Prasarana
Pemb. MCK
Lokasi :
Dusun V
Dibuat oleh :
Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
#REF!
Tampak Samping Kiri Tampak Samping Kanan
Lembar ke …. dari ….
Propinsi #REF!
Kabupaten #REF!
Kecamatan #REF!
Desa #REF!
Jenis Prasarana
Pemb. MCK
6,00
1,00 2,00 2,00 1,00
Pondasi Pas. Batu 0,20
belah ad. 1: 4
Propinsi : Banten
1,00
Kabupaten : Tangerang
1,50
0,50
Kecamatan : Rajeg
Desa #REF!
3,00
0,15
0,10 Jenis Prasarana
Pemb. MCK
11,00
0,40
0,50
Lokasi :
2,25
20/20
Dusun V
Dibuat oleh :
0,15
Pondasi Pas. Batu Ketua TPK,
belah ad. 1: 4
0,10
DENAH PONDASI, SLOOF DAN KOLOM
0,30
0,20
#REF!
0,10 0,10
Beton ad. 1 : 2 : 3
4Ø10 0,15 Diperiksa oleh :
0,25
Fasilitator Teknik (FT)
0,20
Ø6 - 15 4Ø10
5,00 Detail Pondasi Teras
( Iskandar Mailan )
Detail Penulangan Sloof
Lembar ke …. dari ….
4,00
2,00 2,00 4Ø10
Propinsi : Banten
3,15
Kabupaten : Tangerang
1,50
Ø6 -15
Kecamatan : Rajeg
Desa #REF!
3,00
0,20
Beton ad. 1 : 2 : 3 Jenis Prasarana
Pemb. MCK
0,20
9,00
Lokasi :
2,25 Dusun V
Detail Penulangan Kolom Type 1
JUDUL GAMBAR
- Denah Ring Balok
2,25
Beton ad. 1 : 2 : 3
#REF!
4Ø10 0,15
0,10 Diperiksa oleh :
0,15 Beton ad. 1 : 2 : 3
Fasilitator Teknik (FT)
Ø6 - 20 0,10
L = …. m 4Ø10
Detail Penulangan Ring Balok Detail Penulangan Kolom Type 2 ( Iskandar Mailan )
Lembar ke …. dari ….
3,15 +
3,00 +
Ring Balok
uk. 15/20 cm
Propinsi : Banten
Pas. 1/2 batu
bata ad. 1 : 4 Kabupaten : Tangerang
Kecamatan : Rajeg
Kolom
Uk. 20/20 0,97 + Desa #REF!
0,45 0,45
0,03 0,03
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
1,95 1,95
0,14 0,14
0,14 0,14
0,07 0,07
( Iskandar Mailan )
Detail Kusen Pintu / K1 (1 Unit) Detail Kusen Pintu / K2 (2 Unit)
Lembar ke …. dari ….
0,14
0,15 0,65 0,15
Propinsi : Banten
0,14
Kaca Polos
0,45
0,03 3 mm Kabupaten : Tangerang
0,30
0,60
0,30 Kecamatan : Rajeg
1,10 0,14
0,14 Desa #REF!
0,07
0,07
Jenis Prasarana
Pemb. MCK
JUDUL GAMBAR
- Detail Kusen Pintu dan Jendela
Triplek pintu - Detail Pintu dan Jendela
0,04
0,04 0,04
Seng plat
0,10
Dibuat oleh :
Ketua TPK,
0,90
1,10
2,05
2,05
0,10
0,10 0,45 0,10
#REF!
0,65 Kaca Polos
3 mm Diperiksa oleh :
0,90
Fasilitator Teknik (FT)
0,80
Detail Pintu K1 (1 Unit) Detail Pintu K2 (2 Unit) Detail Jendela J1 (6 Unit)
( Iskandar Mailan )
Lembar ke …. dari ….
Kecamatan : Rajeg
Lokasi :
1,50
Dusun V
Gording uk. 8/12
JUDUL GAMBAR
- Denah Kuda-kuda dan Rangka Arap
3,00
- Detail Kuda-kuda
Bubungan Reng uk. 2/3
Balok Tarik Kaso uk. 5/7 - Detail rangka atap
0,18
uk. 8/12
11,00
Dibuat oleh :
0,50 Ketua TPK,
2,25
Kuda-kuda
0,50
Lisplank
2,25
#REF!
Diperiksa oleh :
Pas. 1/2 Bata ad.
1,00
1,00
1:4
Gording uk. 8/12
1,50
Bubungan
( Iskandar Mailan )
DENAH KUDA-KUDA DAN RANGKA ATAP Detail Rangka Atap
Lembar ke …. dari ….
Baut U 15 Cm
Kayu uk. 8/12
Plat 30 Cm
Propinsi : Banten
Baut 15 Cm
0,25 Kayu 8/12
Kabupaten : Tangerang
Kayu uk. 8/12
Kecamatan : Rajeg
Detail Pot. 3 - 3
Desa #REF!
Plat U 50 Cm
Baut U 30 Cm
Jenis Prasarana
Pemb. MCK
0,25 Ring Balok 15/15
Bubungan
1,20 Papan Bubungan Lokasi :
Plat 30 cm
Dusun V
Genting
Reng 2/3
Detail Pot. 1 - 1 JUDUL GAMBAR
Kaso 5/7 0,18
- Detail Pot. 1 - 1
- Detail Pot. 2 - 2
- Detail Pot. 3 - 3
- Detail Pot. 4 - 4
Kayu 8/12
Baut U 40 cm
Dibuat oleh :
Baut U 40 cm
Ketua TPK,
Balok tarik 8/12
( Iskandar Mailan )
Detail Pot. 2 - 2
Lembar ke …. dari ….
0,61 0,61
Propinsi : Banten
6,00
1,00 2,00 2,00 1,00 Kabupaten : Tangerang
Kecamatan : Rajeg
1,00
Desa #REF!
1,50
0,61
3,00
Lokasi :
Dusun V
Plafond Triplex
11,00
Ketua TPK,
1,00
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
( Iskandar Mailan )
Lembar ke …. dari ….
Propinsi : Banten
0,90 2,00 2,00 0,90
Kabupaten : Tangerang
Keramik
Uk. 20x25 cm Kecamatan : Rajeg
0,90
0,05 -
1,50 Jenis Prasarana
Pemb. MCK
Keramik
Uk. 30x30 cm
3,00
0,00 + Keramik
Lokasi :
Uk. 20x20 cm
Dusun V
0,10
JUDUL GAMBAR
- Denah Pemasangan Lantai Keramik
2,25
0,00 +
Detail Pasangan Keramik Dibuat oleh :
2,25
Ketua TPK,
0,90
0,10 -
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
( Iskandar Mailan )
Lembar ke …. dari ….
Resapan
Desa #REF!
"½ Pipa PVC AW Ø
1,00
Jenis Prasarana
Pemb. MCK
"Pipa PVC Ø 1
1,50
Lokasi :
Dusun V
Wastafel
3,00
JUDUL GAMBAR
- Denah Pemasangan Instalasi
11,00
Pipa PVC AW Ø
Pompa air "1¼" dan 1 Dibuat oleh :
Ketua TPK,
2,25
Selokan / Got
Ketarangan : #REF!
1,00
Pipa PVC AW Ø ½" Diperiksa oleh :
1,00 2,00 2,00 1,00 Pipa PVC AW Ø 1" Fasilitator Teknik (FT)
Pipa PVC Ø 2½"
6,00 Pipa PVC Ø 4"
Pompa Air
Lembar ke …. dari ….
Septictank
Besi Beton Dibuat oleh :
Ø 10 - 25 Cm
"Pipa AW Ø 4 Ketua TPK,
Cassing
"Pipa AW Ø 4
Cassing
"Pipa PVCØ 4
2,00
Lembar ke …. dari ….
Propinsi : Banten
1,00
Kabupaten : Tangerang
1,50
Kecamatan : Rajeg
Desa #REF!
3,00
Jenis Prasarana
Pemb. MCK
11,00
Lokasi :
2,25
Dusun V
JUDUL GAMBAR
- Denah Instalasi Listrik
2,25
1,00
Dibuat oleh :
1,00
Ketua TPK,
1,00 2,00 2,00 1,00
6,00
#REF!
Lembar ke …. dari ….
Jenis Prasarana
Pemb. MCK
Lokasi :
Dusun V
JUDUL GAMBAR
Dibuat oleh :
Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
#REF!
Lembar ke …. dari ….
B
3,00
1,00 1,20 2,60 1,20 1,00
1,00
A A
2,00
5,00
Jenis Prasarana
Pemb. MCK
1,00
Lokasi :
1,00
Dusun V
JUDUL GAMBAR
B
Dibuat oleh :
Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
#REF!
Lembar ke …. dari ….
Kaso 5/7
2,00
1,00
0,20
0,50
2,50 2,50
Jenis Prasarana
Pemb. MCK
Lokasi :
Dusun V
JUDUL GAMBAR
Dibuat oleh :
Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
( Iskandar Mailan )
Lembar ke …. dari ….
Jenis Prasarana
Pemb. MCK
Lokasi :
Dusun V
JUDUL GAMBAR
- Denah Pondasi, Sloof dan Kolom
Dibuat oleh :
Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
( Iskandar Mailan )
Lembar ke …. dari ….
Jenis Prasarana
Pemb. MCK
Lokasi :
Dusun V
JUDUL GAMBAR
Dibuat oleh :
Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
( Iskandar Mailan )
Lembar ke …. dari ….
Jenis Prasarana
Pemb. MCK
Lokasi :
Dusun V
JUDUL GAMBAR
Dibuat oleh :
Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
( Iskandar Mailan )
Lembar ke …. dari ….
Jenis Prasarana
Pemb. MCK
Lokasi :
Dusun V
JUDUL GAMBAR
- Detail Kusen Pintu dan Jendela
Dibuat oleh :
Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
( Iskandar Mailan )
Lembar ke …. dari ….
Jenis Prasarana
Pemb. MCK
Lokasi :
Dusun V
JUDUL GAMBAR
- Denah Kuda-kuda dan Rangka Arap
Dibuat oleh :
Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
( Iskandar Mailan )
Lembar ke …. dari ….
Jenis Prasarana
Pemb. MCK
Lokasi :
Dusun V
JUDUL GAMBAR
Dibuat oleh :
Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
( Iskandar Mailan )
Lembar ke …. dari ….
Jenis Prasarana
Pemb. MCK
Lokasi :
Dusun V
JUDUL GAMBAR
Dibuat oleh :
Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
( Iskandar Mailan )
Lembar ke …. dari ….
Jenis Prasarana
Pemb. MCK
Lokasi :
Dusun V
JUDUL GAMBAR
- Denah Pemasangan Lantai Keramik
Dibuat oleh :
Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
( Iskandar Mailan )
Lembar ke …. dari ….
Jenis Prasarana
Pemb. MCK
Lokasi :
Dusun V
JUDUL GAMBAR
- Denah Pemasangan Instalasi
Dibuat oleh :
Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
( Iskandar Mailan )
Lembar ke …. dari ….
Jenis Prasarana
Pemb. MCK
Lokasi :
Dusun V
JUDUL GAMBAR
- Denah Bak Mandi & Septictank
Dibuat oleh :
Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
( Iskandar Mailan )
Lembar ke …. dari ….
Jenis Prasarana
Pemb. MCK
Lokasi :
Dusun V
JUDUL GAMBAR
Dibuat oleh :
Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
( Iskandar Mailan )
Lembar ke …. dari ….
Jenis Prasarana
Pemb. MCK
Lokasi :
Dusun V
JUDUL GAMBAR
Dibuat oleh :
Ketua TPK,
#REF!
Diperiksa oleh :
Fasilitator Teknik (FT)
( Iskandar Mailan )
Lembar ke …. dari ….
Pembangunan Sarana Prasarana Desa Melalui Swakelola TA 2016 Form 24.
Propinsi : Banten
Kabupaten : Lebak
Kecamatan : Cileles
DESA
Cipadang
JENIS PRASARANA
MCK KK MISKIN
LOKASI
Tersebar
JUDUL GAMBAR
- Tampak
( ................................ )
Diperiksa oleh :
Pendamping Desa
( ........................... )
Diketahui oleh :
Kasi Ekbang Desa
( .................. )
TAMPAK
Lembar ke …. dari ….
Propinsi : Banten
4Ø10
Kabupaten : Lebak
2,00 Kecamatan : Cileles
DESA
Cipadang
4Ø10 Beton ad. 1 : 2 : 3
0,15 Ø6 -15
JENIS PRASARANA
MCK KK MISKIN
0,15
Kolom praktis
( ................................ )
Diperiksa oleh :
Pendamping Desa
( ........................... )
Diketahui oleh :
Kasi Ekbang Desa
( ....................... )
DENAH DAN DETAIL SLOOF DAN KOLOM
Lembar ke …. dari ….
Propinsi : Banten
Kabupaten : Lebak
Kecamatan : Cileles
DESA
Cipadang
JENIS PRASARANA
MCK KK MISKIN
Resapan
LOKASI
Pipa air kotor Tersebar
JUDUL GAMBAR
- Tampak
A
Dibuat oleh :
TPK
Septictank
( ................................ )
Diperiksa oleh :
Pendamping Desa
( ........................... )
Diketahui oleh :
Kasi Ekbang Desa
( ........................ )
DENAH SEPTICTANK
Lembar ke …. dari ….