WORK WISE DETAILED PROGRESS REPORT OF TRIBAL WELFARE, ENGINEERING DIVISION, BHADRACHALAM, KHAMMAM DIST.

AS ON 22.07.2021
Cumulativ Value of Total Percenta
Estimate Date fixed EOT Expdr. value of ge of
Agt/ e Present
Sl. Cost Year of Name of for recommen Upto work done work
No.
Mandal No. of Houses
Sanction the Scheme
ref.No.& Expenditure incurred- Expenditur work Stage of Remarks
e incurred but not
Rs: in Completio ded/sanctio March/ done
Date done work
lakhs n ned 2014 paid. (17/4x10
1 2 3 4 5 6 7 8 9 10 11 12 13 (10+13)
14 15 (14+15)
16 17 18 19
0)
Grant: DBHK
Thallada
1 Gopalapeta 50 252.00 2016-17 DBHK - 0.00 0.00 0.00 0.00 0.00 252.00 252.00 0 Completed handed over

2 Baswapuram 20 100.80 2016-17 DBHK - 0.00 0.00 0.00 0.00 0.00 100.80 100.80 0 Completed handed over

3 Mittapalli 20 100.80 2016-17 DBHK - 0.00 0.00 0.00 0.00 0.00 100.80 100.80 0 Completed handed over
Grand Total 90.00 453.60 0.00 0.00 0.00 0.00 0.00 453.60 453.60