You are on page 1of 12

BILL OF QUANTITY

FOR

ASSOCIATION OF RESIDENT DOCTORS,


MODIBO ADAMA
UNIVERSITY TEACHING HOSPITAL YOLA,
ADAMAWA STATE.

PREPARED BY: DE-ROYAL CUNSULT


Q/S: 0803207556

PROPOSED THREE BEDROOM DETACHED


ASSOCIATION OF RESIDENT DOCTORS, MODIBO ADAMA
UNIVERSITY, YOLA
THREE BEDROOM DETACHED
Substructures (Provisional)
Site preparation; preserving vegetable soil

Items Description Quantity Unit Rate amount


A Excavating average 150mm deep; depositing 125 M2 90,00.00 11,250
in temporary spoil heaps; on site

Excavation
Starting from strip level; not exceeding 1.5 deep

Trenches
B 28 M3 550.00 15,400
Pits
C 3 M3 600.00 1800.00
Disposal

D 48 M3 200.00 9,600.00
Excavated materials; backfilling
E 32 M3 200.00 6,400.00
Surplus excavated material; removing from
site

Hardcore or the like; laterite


F 48 M2 2,700 129,600
Bed; 300mm thick

In-situ concrete; plain

Weak; mix (1:10) 40mm aggregate

G 2.73 M3 28,000 76,440


Blinding; 50mm

In-situ concrete; reinforced normal; mix


15N/mm2 40mm aggregate
5 M3 42,000 210,000
Foundations in trenches; not exceeding
H
150mm thick

To collection
460,490
A Bases; 300mm thick 2 M3 29,000 58,000

B Beds or the like; 100mm thick 8 M3 42,000 336,000

C Columns; 0.05 – 0.10m2 2 M3 42,000 84,000

Reinforcement; fabric b5 4483


Reference A142; 15mm end and side laps

D Beds: 100mm thick 209 M2 800 167,200

Reinforcement: bars: high yield: hot rolled


B5 449 columns, bases or the likes

F 12mm diameter bar 68 Kg 500 34,000

Formwork to reinforce in-situ concrete


formwork generally

Sides; vertical or battering; columns or the


like
H 3 M2 1,600.00 4,800
Edges of slab; 150mm wide
J 6,000
Sides of column in foundation 12 M 500.00
K 12,800
Blockwork; sandcrete blocks; hollow; 8 M2 1,600
smooth both sides; in cement mortar

230mm thick; walls


L 628,800
Finishing
131 M2 4,800
15mm Cement sand rendering to expose
M faces of the wall 126,000

Pply approved colour of delotexcotes 126 M2 1,000


N paint, two coats on wall
60,500
Collection 121 M2 500.00

Page 2/1 1,518,150


Page 2/2 460,490
1,720,150

Element Nr 1 – substructure
Carried to summary N 1,978,590
SUPERSTRUCTURE
Frame
In-situ concrete: reinforced normal
Mix (1:2:4 – 20mm) aggregate

A Columns; 0.05 – 0.10m2 2 M3 42,000 84,000

Reinforcement; bars; high yield;


hot rolled B5 4449

B 12 – 8mm diameter 56 Kg 500.00 28,000

Formwork to reinforce in-situ


concrete form work generally

D Sides; vertical or battering; 36 M2 1,600 57,600


columns on the like

Frame
Carried to summary N169,600.00

In-situ concrete; reinforced; normal;


Mix (1:2:4 – 20mm) aggregate

A Beams; sectional area over 0.10m2 2 M3 42,000 84,000

Reinforcement
High tensile reinforcement to 4449
including bens & hooks
B 16 – 8mm diameter
Formwork to reinforced in-situ
concrete 142 Kg 500 71,000
fromwork generally

C Sides and soffits; beams and facia

Corrugeated pr troughed sheet roofing; 38 M2 1,600 60,000


aluminum; 900mm coil 0.45mm thick;
long sheets; no horizontal joints; standard
colour both sides

E Coverings; fixing to timber purlins at


900mm general spacing; with aluminium
hooks bolts and bitumen felt aluminium
washers; drilling timber; two
corrugations side laps; sloping not 236 M2 3,800 896,800
exceeding 50 degrees from horizontal

K Accessories fixing with aluminium self 48 M 1,500 72,000


tapping screws or the like; cappings;
standard to ridges; 0.55 x 525mm girth

L Gutters; 0.55 x 525mm girth


28 M 1000 28,000
M Eave trimmers; 0.55 x 150mm girth
18 M 1000 18,000

To collection N 1,229,800
Structural timber: hardwood: treated with soligums as Described
Item Description Qty Unit Rate Amount
A Raffters:150x150 215 M 450 96,750

B Purlins of the like: 75x50mm 165 M 350 57,700

Members of roof trusses 150x50 struits 126 M 450 56,700


C

D 150 x 150mm tie beam 446 M 400 178,400

One coat premier, one undercoat: one coat glass


finish
Cement rendered surface
E Roof cornices; external 25 M2 1000 25,000

To collection N 414,600
COLLECTION
Page 2/5 1,229,800
Page 2/6 414,600
Roof
Carried to summary N1,644,400

Walls and Partitions


Hollow sandcrete blockwork laid staraitcher bond with cement sand 1:6
Item Description Quantity Unit Rate Amount
A 255mm 247 M2 3,450 852,150
thick

Items Description Qty Unit Rate Amount


Doors and Windows

Vibrated reinforcement insitu concerete grade


30 (1:2:4mm agg. Filled into framework &
backed reinf. Both M/S)

A Lintel 2 M3 42,000 84,000


Reinforcement

High tensile reinforcement to BS 4449 in


cluding bens, hooks hocks, tying wire and
distance block in roof beam & slab

16-8mm diameter 142 Kg 520.00 73,840


B
Formwork

Sawn formwork to:

C Sides and soffits of lintel 43 M2 1,600 68,800


Metal Work

DOORS

Supply and fix purpose made complete set


with locks factory manufacture door well
install with the fixing cramp into the wall
A laped at the edges (American Steel Doors)
B
Door 1 size 1200x2100mm
1 Nr 65,000 65,000
Door 2 size 900x2100mm 5 Nr 40,000 200,000
A
B 4 Nr 40,000 160,000
Door 3 size 750x2100mm

SUB TOTAL N 425,000.00


Critall-hope other approved bronzed
aniodized standard factor preglazedalminium
casement windows including assembling,
5mm thick reflective glass and fix to
manufacturers details (Including netting)
10 Nr 38,000 380,000
Size 1200 x 1200mm 5 Nr 18,000 90,000
Ditto 600 x 600mm

Windows 8 Nr 12,000 96,000


Burglary proof fix to opening
Size 1200 x 1500mm 5 Nr 5,800 29,000
Ditto 600 x 600mm N1,020,000.00

Doors and Windows to Summary


Items Description Qty Unit Rate Amount

Finishing
Mortar; cement and sand (1:3); steel trowelled
13mm work; to concrete or block work base;
over 300mm wide

Walls 285
M2 850.00 242,250
850.00 148,750
A Walls; external 175 M2
B
Ceramic tile facing: BS 1281; White glazed:
egg-shell finish: to regular pattern: fixing with
adhesive: grouting with white cement

150 x 150 x 6mm; 3mm joints; straight both ways; 90 M2 2,600 234,000
to walls; to cement and sand base; over 300mm
C wide

One undercoat: One coat texcote finish

Cement render or concrete surfaces ; over 300mm


wide
800.00 84,800.00
Walls; external 106 M2
D
Two coats emulsion; cement render surfaces

Walls; internal 285 M2 350.00 99,750.00


E

Wall Finishes N 809,550.00


Carried to Summary
Items Description Qty Unit Rate Amount
C 300x300x15mm; 3mm joints straight both ways to 71 M2 3,300 234,300
floors; level; to cement and sand base

D 100x100x15mm; 3mm joint skirting’s; to cement 36 m 450.00 16,200.00


and sand base; 100mm extreme width
Non slip Ceramic floor tiles; bedding in 6mm
mortar jointing and pointing in cement mortal (1:3)

E 300x300x15mm; 3mm joints straight both ways to 30 M2 3,300 99,000


floors; level; to cement and sand base

F 100x100x15mm; 3mm joint skirting’s; to cement 52 M 450.00 23,400.00


and sand base; 100mm extreme width
Beds and backings mortar: cement and sand (1:3)
One coats beds: screeded to floors; to concrete base

25mm
G 164 M2 800.00 131,200.00
Floor Finishes
Carried to summary N 504,100.00

Noggins; 50x50mm 480 M 200.00 96,000.00

12mm PVC tongue and groove joint ceiling


linings; linings to form soffits; horizontal; to
hardwood fixing in accordance with
manufacturer’s instructions

95 M2 2300.00 218,500.00
Ceilings

Ceiling Finishes N 314,500.00


Carried to summary
ITEMS DESCRIPTION QTY UNIT RATE AMOUNT
Services
Sanitary Appliances/Fittings
Supply and fix the following
Allow a provisional sum of N380,000 for
sanitary appliances/fittings supply and fix - 380,000.00
A pipe work to be executed complete - Sum

Builder’s Work
Allowed a provisional sum of N20,000 in
B connection with the Elec. Installation
- 20,000.00
Sum
Allow a provisional sum of N350,000 for
electrical works 350,000.00
C

Service Carried to Summary


N 750,000.00
Items Description Qty Unit Rate Amount
Summary Page

A SUBSTRUCTURES 2/2 1,978,590.00

B Frame 2/3 169,600.00

C Roof 2/6 1,644,400

D Walls & Partitions (Block) 2/9 852,150.00

E Doors/Windows 2/10 1,020,000.00

F Walls Finishes 2/12 809,550.00

G Floor Finishes 2/13 504,100.00

H Ceiling Finishes 2/14 314,500.00

I Services 2/15 750,000.00

Bill Nr 3 Main Building


Carried to final Summary 8,043,490.00 8,043,490.00

PRIME COST OF CONSTRUCTION 66 Nr 8,043,490.00 530,870,340.00

ALLOW PROVITIONAL SUM FOR INTERNAL


INFRUSTRATURE ULTILITY AND SERVICE - - 59,400,000.00

TOTAL COST OF WORKS N590,270,340.00

AMOUNT IN WORDS: EIGHT MILLION, FORTY THREE THOUSAND, FOUR


HUNDRED AND NINETY NAIRA ONLY.

You might also like