Date drilled 25/08/2021 25/08/2021 25/08/2021 04/10/2021 25/08/2021 22/09/2021 26/08/2021 26/08/2021
Top of
bedrock 1.03 1.23 1.50 0.22 - 0.00 1.10 0.20
(m)
Coring run
Open hole Open hole 2.00-15.00 Open hole Open hole 0.00-19.00 2.00-18.00 1.00-16.0
(m)
Total depth
0.00-7.00 0.00-7.00 13.00 18.00 19.00 19.00 16.00 15.00
(m)
Table 1: Borehole drilling records.
7.2 Classification
The main geological stratum encountered during the investigation is:
• Light yellow to cream, Fine to Coarse, Weak to Medium Strong, Lower Globigerina Limestone
of “Fair” to “Excellent” quality.
Photographs of the rock core recovered are shown in Appendix 3. The borehole logs are located in
Appendix 5.
Table 2 below shows the values of the quality of the rock cores recovered namely the Total Core
Recovery (TCR), the Solid Core Recovery (SCR), the Rock Quality Designation (RQD) and the Fracture
Index. These parameters are described in Figure 8 as per BS5930:2015.
REMARKS
Driller Philip Bonnano Circulation: F = Full,P = Partial Loss, L = Total Loss.
Drill Direction: Vertical; Site Type: Existing Building
Assistant Driller Doyle Sapiano Test = SPT, Vane, Soil Sampling.
REMARKS
Driller Philip Bonnano Circulation: F = Full,P = Partial Loss, L = Total Loss.
Drill Direction: Vertical; Site Type: Existing Building
Assistant Driller Doyle Sapiano Test = SPT, Vane, Soil Sampling.
REMARKS
Driller Philip Bonnano Circulation: F = Full,P = Partial Loss, L = Total Loss.
Drill Direction: Vertical;
Assistant Driller Doyle Sapiano Test = SPT, Vane, Soil Sampling.
REMARKS
Driller Aaron Bonnici Circulation: F = Full,P = Partial Loss, L = Total Loss.
Drill Direction: Vertical; Site Type: Existing Building
Assistant Driller Amit Manhas Test = SPT, Vane, Soil Sampling.
REMARKS
Driller Nicolour Florrian Circulation: F = Full,P = Partial Loss, L = Total Loss.
Drill Direction: Vertical;
Assistant Driller Dion Test = SPT, Vane, Soil Sampling.