Professional Documents
Culture Documents
Estimatio Book
Estimatio Book
Introduction
For the construction of all engineering works it’s essential to know before hand the
probable cost of construction work which consist of the cost of material, cost of
transportation, cost of labour, cost of scaffolding, cost of tools and plants, cost of
preparation and supervision changes, also cost of taxes and the profit of the
constructor. If the estimated cost is greater than the money available, then attempts
are made to reduce the cost by reducing the work or by changing the specifications.
From this the important of estimation for engineers may be understood. In
preparing estimation, the quantities of different items of work are calculated by
simple mensuration method and from these quantities the cost is calculated. The
subject of estimating is simple, nothing much to understand, but knowledge of
drawing is essential.
Accuracy in estimate is very important if estimate exceeded it becomes a very
difficulty problem for engineers to explain, to account for and arrange for the
additional money.
The calculation mainly consists of:
Length * breadth*height/thickness
Definition:
• It also useful to check the work done by contractor during and after the
execution, also the payment to the contractor is done according to the actual
measurement
• It gives an idea for the requirement of controlled material like; cement, steel,
sand, water and etc
And we use both stander brick (40 cmx20cmx20cm) (40cm x 20cm x 15cm)
Basic is units
units of length Meter (m)
Units of mass Kilo gram Kg
Units of time Second (s)
Units of electric current Ampere(A)
A.
B.
Item No Description Quantity Unit Rate Amount
or particulars
Foundation trenches are usually dug to the exact width of foundation with
vertical sides. Earthwork in excavation in foundation is calculated by taking
the dimension of each trench length x breadth x depth
The length and breadth of foundation concrete are usually the same as for
excavation, only the depth or thickness differs. The thickness of concrete
varies from 20 cm to 45 cm, usually 30 cm. foundation concrete consists of
lime concrete are weak cement concrete. The proportion of cement concrete
in foundation may be 1:4:8 or 1:5:10
• Soling : when the soil is soft or bad, one layer of dry brick or stone soling is
applied below the foundation concrete. The soling layer is computed in M2 (
length x breadth ) specifying thickness.
• Masonry
• R.C.C and R.B work: RCC or RB work may be in roof or floor slab, in
beams ,lintel, columns, foundation, etc and quantity are calculated in m3
Etc
• Fill plinth area with selected material and compacted 0.5m thick =
( ( 5.2)(5.4)) * 2 * 0.5 = 28.08m3
• Apply the coats of white washing on all internal and external wall surface=
• Apply three coats of Distempering on all internal and external wall surfaces
=
Step 3: find cost estimation in each volume or area means (Unit price and total
cost)
• Labor
• Meson
X =20 m2
unskilled labor =20m2
Therefore;
1 unskilled = 1m3
X = 8.16m3
Cross multiply and get 8.16 unskilled take in 9 unskilled
9 * $ 5 = $ 45
Say mason = * 9 * $ 15 = $ 6.75
Total cost = $ 45 + $ 6.75 = $ 51.75
Cost of 1m3 = = $ 6.34
Mortar
Sand : = 4.4m3
Labour:
Forman 1/20 * 26 * $ 20 = $ 26
Total cost of labour = $ 180 + $ 60 + $ 12 + $ 26 = $ 278
• Constract RCC tie beam 0.4m * 0.2m reinforced 12mm Φ with 6mm Φ
stirrups and 0.30m c/c ratio 1:2:4
Material
NB: If you take ratio 1:2:4 this ratio have especial unit weight 0.22 + 0.44 +
0.88 =1.54
If 1 bag = 0.035m3
X = 0.71m3
Sand : = 1.43m3
1 loads * $ 25 = $ 25
Steel:
0.4m 0.03m
0.03
12mm bars = 40.8 * 4 =163.2m + 2%( the part of bar which makes bending)
=166.465m
13pcs * $ 3 = $ 39
add your result 10% of extra wood like strutted = 1.306 pcs +13.06 pcs =
14.36pcs
Nails: 1kg * $ 2= $ 2
Labour:
12 unskilled 2 meson * $ 15 = $ 30
3 mixer 6 unskilled * $ 6 = $ 36
2 mixer * $ 7 = $ 14
1 forman * 20 = $ 20
Steel fixer
NB: 100 kg done steel fixer per day
The following table indicated to use 12mm bar and 6mm so that
Formula of steel in kg
Steel fund =
0.89kg * length of the steel 12m = 10.68kg * no# of bar 13.87 = 148.13kg
Then add two weight 148.13 kg + 33.92 kg = 182.05kg / 100kg = 1.821 steel fixer
Helper = ¼ * 2 * $ 5 = $ 2.5
Forman 1 * $ 20 = $ 20
Helper = ¼ * 2 * $ 5 = $ 2.5
Forman 1 * $ 20 = $ 20
1.5
3 3
Material
Deducted doors and windows = 1642.5 psc – 75psc = 1567.5 psc * $ 0.6 = $
940.5
Labour
NB: 100 pcs of block done meson per day
16 unskilled * $ 5 = $ 80
3 Mixer * $ 6 = $ 18
2 forman * $ 20 = $ 40
Sand : = 0.44m3
Aggregate: = 0.88m3
Aggregate = 4 * 1.54 * 1.63/7 = 1.44m3/3m3 = 0.48 loads say 1 loads * $25 =$25
Nails = 1.5kg * $ 2 = $ 3
Labour
Volume = 1.63m3
1 Meson * $ 15 = $ 15
3 unskilled * $ 5 = $ 15
1 mixer * $ 6 = $ 6
1 forman * $20 = $ 20
Steel fixer
Total weight = 103kg + 26.01kg = 129.04kg/100kg = 1.29 steel fixer say 1.5 * $ 15
= $ 22.5
1 Helper * $ 5 = $ 5
Carpenter = 8.16m2 /8m2 = 1carpenter * $ 15 = $ 15
• Fill the plinth area with selected material well compacted 0.3m thick
Labour
NB : 5m2 /unskilled/day
Forman = 1 * $ 20 = $ 20
Cost of labour = $ 40
Ground total = $ 160
Labour
Labour
NB : 1.4m3 /meson/day
3 unskilled * $ 5 = $ 15
1 mixer * $ 6 = $ 6
1 forman * $20 = $ 20
($98.48 + $ 25 + $ 70 +$ 7.03) + ($ 75 +$ 15 +$ 6 +$ 20 )
$ 316.51
Add ratio 1 + 6 = 7
Labour
NB : 12m2/meson/day
Unskilled = 22 * $ 5 = $ 110
• Rafters = 100*50
• Purlines = 75*50
• Struts = 75*50
• Purlines = 0.366m3
Total volume wood = 1.1398m3
Labour
Unskilled = ¼ * 11 = 3 * $ 5 = $ 15
Forman = 2 * $ 20 = $40
• Provide and fix fascia board size 0.20m wide for two side and use (
Laanbalaash)
Carpenter: 1 *$ 15 =$ 15
Forman: 1 * $ 20= $ 20
• Provide and fix ceiling boards 4mm thick with ceiling joint 50mm *
50mm
And 60 c/c
100.8m
100.8m * 2 = 201.8m
? = 201.8m
Therefore = 8.41pcs * 15% of struts and wastage = 1.26 + 8.4 = 9.66pcs
10pcs
10pcs * $ 26 = $ 260
Labour
Helper = 4 * $ 7 = $ 28
Forman = 1 * $ 20 = $ 20
• Apply the three coat of white washing on all internal and external wall
surface
100m2 = 35kg
326.6m2 =? 114.31kg
Water = 1 barrer * $ 2 = $ 2
Labour
Forman = 2 * $ 20 = 40
Therefore:
100m2 = 171kg
Labour
Unskilled = 2 * $ &7 = $ 14
Forman = 1 * $ 20 = $ 20