Satrio Indra Maulana

2109688
SPIG 3-B
1. LOKASI PEMERUMAN DI PANTAI SAWARNA BANTEN
2. JALUR PEMERUMAN UTAMA DI LAUT SAWARNA BANTEN
3. Durasi Pemeruman

JALUR PEMERUMAN UTAMA (Sounding line)


Lebar Interval lajur (SL):
• Interval SL = skala peta x 0.001
Skala 1:10.000 ~ Int SL = 10.000 x 0.001 = 100m
Jumlah lajur utama:
• Jml lajur SL= Lebar area survey / interval SL
Jml Lajur SL = 800 m /100 m = 8
Panjang jalur Pemeruman
• Total Pnjg SL= Pnjg area x jml lajur SL
Total Pnjg SL = 8 x 5500 m = 44.000 m (44 Km)

Jalur Silang (Cross Line)


Lebar lanjur CL:
• Interval CL = 15 x Interval CL
Intv CL = 15 x 100 m = 1.500
Jumlah Lajur Utama:
• Jml lajur CL = Pnjg area survey / interval CL
Jml lajur CL = 5500 m / 1.500 = 3,6 ~ 4
Panjang jalur perum
• Total Pnjg CL = Lebar area x jml lajur CL
Total Pnjg CL = 800 m x 4 = 2.400 m (2,4 Km)

PERHITUNGAN DURASI
Kecepatan Kapal Laut
3 Knot = 5,55 Km/jam
Durasi Pemeruman =
Total pnjg SL + Total Pnjg CL + Pnjg Area + Lebar Area
Kecepatan Kapal Laut
➢ Durasi pemeruman =
44 km + 2,4 km + 5,5 km + 0.8 km
5,55 km / jam
= 9,58 jam ~ 9,6 jam
= 9 Jam 36 Menit
HAL-HAL YANG DAPAT MENAMBAH DURASI SURVEI
➢ Estimasi perubahan karena Cuaca
Cuaca nya Cerah
Durasi 10% Dari Tatal durasi pemeruman
=9 jam 36 menit x 10%
= 53 menit

➢ Estimasi durasi instalasi dan kalibrasi peralatan ( pasang dan bongkar )


10 jam

➢ Estimasi Trasportasi dan logistic


Dari Kampus UPI ke Lokasi sawarna Baten
Dari Google Maps durasi 6 jam 46 menit

➢ Total Keseluruhan Durasi


=Durasi pemeruman + durasi Karena Cuaca + Durasi Kalibrasi alat + Durasi Keberangkatan
=9 jam 36 menit + 53 Menit + 10 jam + 6 jam 46 menit
= 27 jam 15 menit ~ 1 Hari 3 jam 15 Menit