CONTROLLED UNCLASSIFIED INFORMATION

TRANSMITTAL OF SHOP DRAWINGS, EQUIPMENT DATA CONTRACT NO. PAGE


MATERIAL SAMPLES, OR MANUFACTURER'S
W912ER18C0015 1 of 1
CERTIFICATES OF COMPLIANCE
DATE TRANSMITTAL NO.
PROJECT TITLE Jubail, Saudi Arabia

LOCATION MH-60R Facilities and Infrastructure 12/19/2021 21 30 00-10.1

Item Description Variation QA Code

56 Pipe flanges Yes B


57 Pipe fittings Yes B
SECTION III - GOVERNMENT REVIEW REMARKS

Item #56 and #57 Code B

Variation is acceptable at no additional cost/time to Government


The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the
general method of construction, materials, detailing and other information are satisfactory. This does not relieve the Contractor from the
obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and
replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish
samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical
specifications so prescribe.

Page 1 of 1
Attachment to ENG FORM 4025-R
CONTROLLED UNCLASSIFIED INFORMATION