You are on page 1of 14

MY 

Vaccination Tracker

51.42M
Doses administered

MORE DETAILS 

MALAYSIA CORPORATE FROM THE EDGE TOP STORIES Select Language ​▼

Edge Weekly

Cover Story: LSS4 awards: Boon or


bane for winners?
Kamarul Azhar / The Edge Malaysia

April 01, 2021 14:25 pm +08

This article first appeared in The Edge Malaysia Weekly, on March 22, 2021 - March 28, 2021.
Below: TNB’s LSS Bukit Selambau, which has a 30mw-generation capacity, began
operations last September. (Photo by Tenaga Nasional Bhd)

AFTER four months, the Energy Commission (EC) announced the winners of
the fourth cycle of the Large Scale Solar (LSS4) programme on March 12. The
government selected a total of 30 bids to develop solar farms, with export
capacity ranging from 10mw to 50mw.
However, the low price range of the LSS4 and the cost of solar modules, which
has been rising since last July, raise the question of whether the project would
be a boon or bane for the winning bidders.

“When bidding closed last October, a lot of companies put in low bids, as low
as 13.99 sen per kWh. Since July, however, the cost of solar modules has been
increasing, and I doubt the LSS4 is as lucrative as the previous three rounds,”
says a bidder for the LSS4.

The cost of producing electricity from solar power plants has been decreasing
over the last decade, and this has led to a surge in solar energy production
worldwide. Photovoltaic (PV) solar power has become among the cheapest
renewable energy (RE) sources.

Levelised cost of electricity (LCOE) for solar decreased to 6.8 US cents per kW
in 2019, from 37.8 US cents per kW in 2010, according to data from the
International Renewable Energy Agency.

Hydropower remains the cheapest source of RE in 2019 at 4.7 US cents per kW


(about 19.3 sen), followed by onshore wind at 5.3 US cents per kW (21.7 sen).
The most expensive RE is from concentrating solar power at 18.2 US cents per
kW, followed by offshore wind at 11.5 US cents per kW.

However, owing to the Covid-19 pandemic — which disrupted global supply


chains — and a sudden increase in demand for solar modules in the second
half of the year, the costs of solar projects have been rising.

A global solar PV module producer says project price in the European Union
has increased from around 20 US cents per watt in July 2020 to between
28.66 and 28.96 US cents per watt in February 2021.

The almost 45% increase was due to a rise in costs across the supply chain,
from logistics to commodities involved in the production of a PV cell and
module, such as polysilicon, glass, silver, aluminium and copper.

Therefore, some market observers point out, the low tariff bids for the LSS4
are quite unrealistic. While the winners were those who put in bids of 17.68 to
24.81 sen per kWh, these prices are still quite low for them to make good
returns, they say.
During the first LSS, the lowest bid was 
39 sen per kWh; for LSS2, the lowest bid
was 33.98 sen per kWh; and, for LSS3, it
was 17.78 sen per kWh.

Since 2016, a total of 2,457mw of LSS


projects has been awarded to the private
sector, including the 823.06mw awarded
under the LSS4 programme. The LSS
programme has become one of the anchor programmes for Malaysia in
boosting the share of RE to the total generation capacity.

The LSS programmes awarded so far make up almost 9% of total installed


capacity of electricity generation of 27,409mw in Peninsular Malaysia, Sabah
and Labuan. LSS4 alone makes up about 3% of the electricity generation
capacity in the peninsula, Sabah and Labuan.

Note that total electricity generation capacity for Peninsular Malaysia stood at
26,132mw as at end-2019, as per the EC’s 2019 annual report. The reserve
margin for the peninsula stood at 38% of total capacity, with the maximum
demand in 2019 at 18,566mw.

In Sabah and Labuan, total electricity generation capacity stood at 1,277mw as


at end-2019, with a 23% reserve margin. Maximum demand in the state and
federal territory was 1,001mw. Electricity generation in Sarawak is not
governed and distributed by the EC and Tenaga Nasional Bhd.
This means that if the LSS4 programme 
fails, owing to the high project price of
solar plants, the electricity system will
not be jeopardised, as there are still high
reserve margins in the peninsula, Sabah
and Labuan. However, it will be a
stumbling block to the country’s journey
towards increasing RE’s contribution to
the grid.

Solar project prices are high, but


there are ways to reduce costs
“Prices of the panels and cables have gone up. This is because of supply and
demand and raw material costs, especially the cost of copper for the cables, all
of which have contributed to the rise in project costs,” Steven Chiew, founder
of solar panel installation company Next Energy, tells The Edge.

“Typically, when it comes to the cost of a solar farm, in terms of EPCC


(engineering, procurement, construction, and commissioning), it is pretty
much the same across the country. How the players are offering such
attractive rates is due to other variable costs, such as land and infrastructure.”

Among the winners of the LSS4 are landowners such as ATK Development
Sdn Bhd, MK Land Resources Sdn Bhd, Taiping Solar Sdn Bhd and Asiabina
Properties Sdn Bhd. These companies may already have suitable parcels of
land in their books that are held at low cost.

KPower Bhd, one of the winners, is 


partnering with Perbadanan Kemajuan
Negeri Pahang (PKNP), to build a 50mw
solar plant on PKNP’s land in Pekan,
Pahang. KPower and PKNP formed a 95:5
special-purpose vehicle to bid for the
project, and the SPV will lease the land
from PKNP.

According to KPower’s group managing


director Mustakim Mat Nun, the EPCC
contract for the group’s LSS4 project in
Pekan will be awarded to the group’s own KPower Engineering Sdn Bhd.

“KPower Engineering will do the EPCC. Construction margin should be 10% to


12%,” Mustakim tells The Edge.

He agrees that solar panel prices have been on the rise. Nevertheless, he says,
KPower had locked in the price when it made its submission to the EC.

KPower estimated that the project would cost RM160.25 million, with RM153.4
million being the EPCC cost and the rest, financing-related. Eighty per cent of
the project cost will be funded via borrowings, and the rest will be from equity
injections.
Besides the project cost, the SPV will have to pay PKNP a land lease of
RM432,000 a year for the duration of the contract. Annual operation and
maintenance (O&M) costs of around 1% of the project cost will also be borne by
the SPV over the 21-year period.

It is not known whether the SPV will have to make the lease payments to
PKNP or whether the sum will be deducted from the share of profits from the
LSS project. The latter is quite unlikely, however, given that PKNP holds only
5% of the SPV.

Note that KPower has an internal rate of return (IRR) target of 7.5%.

Can KPower’s LSS make money?


A 50mw solar power plant will have a 66mw power output, according to
industry players. Based on the assumption of four hours of peak radiation a
day, the solar plant will be able to produce 96.4 million kWh of electricity a
year.

At KPower’s tariff of 17.91 sen per kWh, that means the SPV would be earning
RM17.3 million in revenue a year.

Given that 80% of the RM160.25 million project cost will be funded by
borrowings, and assuming an interest rate of 3% a year for a period of 15 years,
the SPV will have to pay RM10.6 million a year to service the loan.
After deducting O&M cost of RM1.6 million a year and land lease cost of
RM432,000, the SPV would have a profit of RM4.67 million a year. While this
shows that, at 17.91 sen per kWh, the SPV can still make a profit, it is lower than
the RM5.2 million annual profit after tax projected by KPower.

Of course, this calculation is subject to variables such as the assumption of


peak radiation a day, the cost of borrowings, the O&M expenditure and lease
costs. The project cost is also another variable that determines whether the
LSS can make a profit.

Note that the LSS4 projects might not kick off this year. Steven Chan, an
analyst from Kenanga Research who covers the industry, says solar project
costs are expected to decline in the second half of this year.

“The cost of solar modules is increasing because of the increase in demand in


China and India. But construction for LSS4 will start only next year, so it gives
time for the price to come down,” Chan tells The Edge.

The LSS4 winners will have to complete their projects and start producing
electricity to the grid by 2023. Liquidated and ascertained damages (LAD) will
be imposed on the winners if they fail to get the projects up and running by
then.

The LAD is thus a penalty that the LSS4 winners would want to avoid by hook
or by crook, and the plants will have to be completed and commissioned on
time. If the project price of solar plants does not decline as expected, the LSS4
could be a bane for the project winners.
Save by subscribing to us for your print and/or digital copy.

P/S: The Edge is also available on Apple's AppStore and Androids' Google
Play.

Subscribe to Mid-day
email alert

We deliver news to your


inbox daily

Email Address

SUBSCRIBE

FEATURED VIDEOS
  
10 Dec 2021 | 08:43pm 10 Dec 2021 | 07:30am  Morning Call, F… 09 Dec 2021 | 08:45
 Featured, Even…  Evening 5, Fea…
MORNING CALL: 10/12/21

 MOST READ

MOST WATCHED

1
Taman OUG set for
transformation

2
China prepared to open
fire on US troops that
come to Taiwan’s aid —
Global Times

3
Statement by Tony Pua
on Tun Mahathir's
upcoming book (Part III)
4
Jho Low, Nicky Liow still
not on Interpol Red
Notice list, says IGP

5
Senior manager loses
over RM600,000 in
bitcoin investment scam
Sale Sale

Kota Kota
Kemuning Kemuning

Rent Sale

Kota
Shah Alam Kemuning

Sale Sale

Kota Kota
Kemuning Kemuning

Sale Sale

Kota
Kemuning Shah Alam

Sale Sale Sale Sale Sale

Kota Kota Kota Kota Kota


Kemuning Kemuning Kemuning Kemuning Kemuning
Sale Sale Sale Sale Sale

Kota Kota Kota Kota


Puchong Kemuning Kemuning Kemuning Kemuning
Selangor

Bedrooms


Buy
Rent




e-Paper

Desktop Reader

Home
About Us
Join Us
Contact Us
Advertise with us
Subscription
Sitemap

Term of use
PDPA

Copyright © 1999-2021 The Edge Communications Sdn. Bhd. 199301012242 (266980-X). All rights reserved.
 

You might also like