WORK PLAN FOR CHLORIDE EXIDE- KISUMU BRANCH

DATE NOVEMBER DECEMBER


1 Temporary relocation to new space General shop lighting
2 Temporary relocation to new space Branding work
Demolition of existing partitions, removal Branding work
of wall hangings, Disconection of existing
electrical, data and camera.
3
Temporary connection of power, Data and Branding work
camera to enable office functioning.
4
5 Receiving of materials on site. Furniture fitting and assembly.
Final work arrangement on site, making of Testing of all installed items- Lights, sockets,
ladders in readiness for work Data, Camera and detactors
6
Hacking of the floor to remove old tiles, Final shop arrangement
chasing of walls for new power lines, data
7 and camera.
Start of gypsum work- Office partition and Final shop arrangement
8 ceiling
Wall skimming Commisioning of the shop and Final Handover
9
Cont. Gypsum work, Hacking of floor, wall
10 chasing and skiming.
Cont. Gypsum work, Hacking of floor, wall
11 chasing and skiming.
Cont. Gypsum work, Hacking of floor, wall
12 chasing and skiming.
Cont. Gypsum work, Hacking of floor, wall
13 chasing and skiming.
14 Full paint work of the shop
15 Tilling of the shop
Cont. Gypsum work, Skimming, Paintwork,
16 Tilling
Laying of Conduit pipes for power, Data,
17 camera and smoke.
Cont. Gypsum work, Skimming, Paintwork,
18 Tilling and cabling.
Cont. Gypsum work, Skimming, Paintwork,
19 Tilling and cabling.
Cont. Gypsum work, Paintwork, Tilling and
20 cabling.
Cont. Gypsum work, Paintwork, Tilling and
21 cabling.
Cont. Gypsum work, Paintwork, Tilling and
22 cabling.
23 Finalizing gypsum work,
24 Finalizing gypsum work,
25 Finalizing gypsum work,
26 Finalizing paintwork
Fitting of new lights, sockets and switches
27
Re-installation of Cameras, data and
28 detectors
Cleaning of Tiles and removal of excess
29 paint on grills.
Cleaning of Tiles and removal of excess
30 paint on grills.