17.5 A manufacturing of disk for notebook computers wants an MTBF of at least 50,000 hours.

Recent test results for 10 units were one failure at 10,000 hours, another at 25,000 hours, and two
more at 45,000 hours. The remaining units were still running at 60,000 hours. Determine the
following:

a) Percent of failures

b) Number of faiures per unit-hour

c) MTBF at this point in the testing

17.6 What is the reliability of the following parallel production process? R1= 0.95, R2= 0.90,
R3=0.98
17.7 What is the overall reliability that bank loans Will be processed accurately if each of the 5
clerks shown in the chart has the reliability shown?
Hint: The three paths are donde in paralled, followed b yan additional independent

17.8 Merril Kim Sharp has a system composed of three components in parallel. The components
have the following reliabilities: R1=0.90, R2=0.95, R3=0.85 What it the reliability of the system?
17.9 A medical control system has three components in series with individual reliabilities as
shown: R1= 0.99, R2= 0.98, R3=0.90