BILL OF QUANTITY FOR THE CONSTRUCTION OF PROPOSED RESIDENCE POLICE QUARTER IN JAGDISHPUR

S.No. Description Unit Quantity Unit Rate Amount


In Fig.
(in Rs)
1 Earth work in excavation in cum 486.6 178.4 86809.44
foundation trenches or drains (not
exceeding 1.5m in width or 10 sqm on
plan) including dressing of sides and
ramming of bottoms, lift to 1.5 m,
including getting out the excavated
soil
and disposal of surplus excavated soil
as
directed, within a lead of 50 m.
2 Brick work with bricks of class 0 0 768211.74
designation 100A in foundation and
plinth in:
3 cement mortar 1:6 (1 cement: 6 cum 206.87 3713.5
coarse
sand)
4 Providing and laying in position 0 0 220875
machine
batched, machine mixed and machine
vibrated design mix cement concrete
of
specified grade for reinforced cement
concrete structural elements,
excluding
the cost of centring, shuttering
finishing
and reinforcement, M-20grade
reinforced cement concrete
5 All Work upto plinth level cum 57 3875
6 Walls, columns, pillars, posts, and cum 30.81 89
struts
7 Beams, plinth beams, girders, cum 143.46 4312.4 618656.904
bressummers, cantilevers, suspended
floors lintels roofs and staircases
including spiral staircases, shelves etc.
8 Thermo-Mechanically Treated bars kg 4417 65.1 287546.7
TMTC-500-16mm dia

9 Thermo-Mechanically Treated bars kg 4417 65.1 287546.7


TMTC-500-20mm dia

10 Providing and laying CERAMIC


GLAZED FLOOR TILES in different
sizes (design, thickness &
specifications asper Architectural
drawing) with water absorption's less
than 0.08% and conforming to IS :
15622 of approved make in all
colours and shades, laid on 20mm
thick
cement mortar 1:4 (1 cement : 4
coarse
sand) including grouting the joints
with white cement and matching
pigments etc., complete
11 (a) Size of Tile 30x30 cm sqm 435.55 877.1 382020.905