BILL OF QUANTITY FOR THE CONSTRUCTION OF PROPOSED RESIDENCE POLICE QUARTER IN JAGDISHPUR
S.No. Description Unit Quantity Unit Rate Amount
In Fig. (in Rs) 1 Earth work in excavation in cum 486.6 178.4 86809.44 foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 2 Brick work with bricks of class 0 0 768211.74 designation 100A in foundation and plinth in: 3 cement mortar 1:6 (1 cement: 6 cum 206.87 3713.5 coarse sand) 4 Providing and laying in position 0 0 220875 machine batched, machine mixed and machine vibrated design mix cement concrete of specified grade for reinforced cement concrete structural elements, excluding the cost of centring, shuttering finishing and reinforcement, M-20grade reinforced cement concrete 5 All Work upto plinth level cum 57 3875 6 Walls, columns, pillars, posts, and cum 30.81 89 struts 7 Beams, plinth beams, girders, cum 143.46 4312.4 618656.904 bressummers, cantilevers, suspended floors lintels roofs and staircases including spiral staircases, shelves etc. 8 Thermo-Mechanically Treated bars kg 4417 65.1 287546.7 TMTC-500-16mm dia
9 Thermo-Mechanically Treated bars kg 4417 65.1 287546.7
TMTC-500-20mm dia
10 Providing and laying CERAMIC
GLAZED FLOOR TILES in different sizes (design, thickness & specifications asper Architectural drawing) with water absorption's less than 0.08% and conforming to IS : 15622 of approved make in all colours and shades, laid on 20mm thick cement mortar 1:4 (1 cement : 4 coarse sand) including grouting the joints with white cement and matching pigments etc., complete 11 (a) Size of Tile 30x30 cm sqm 435.55 877.1 382020.905 SATYAM SHRIRATNA BISEN