You are on page 1of 3

Project Title Goa International Airport, Mopa, Goa

Name of the EPC Contractor M/s Megawide Constructions DMCC


Project Start Date 3-Mar-18
Project Finish Date (As per
Contract) 2-Sep-20

DPR Of Earth works for Goa Airport Project

R Balarama reddy (RBR ) Contractors ( From ch 3000 to 3750 )

Total Scope
Sl. No Item Description UoM for the Scope for Scope Achieved for the day
project the available
Contractor before tree Night
as per LOA cutting Day Shift Shift Total

1 C&G -Runway sqm 1,125,000 315,000 175,000 - - -


2 Excavation Cum 12,540,106 2,600,000 570,000 3,752 1,784 5,536

3 Disposal of 1,784 1,784 3,568


unsuitable soil Cum
4 Filling Cum 7,543,161 2,000,000 568,000 - - -

Manpower status

RBR Pioneer
Sl. No. Manpower
Day Night Day Night
1
Project Manager 1 - 1

2
Engineers 6 - 3
3 Supervisors 4 3 5
4 Foreman 5 2 1
5 Surveyors 2 - 1.00

6
Operators 11 4 23 2
7
Drivers 9 7 15
8
Eletrician - -
9 Mechanic -
10 Welder - -
11 labour 9 6 7
TOTAL 47 22 56 2
Airport Project Dt 23.04.18

rom ch 3000 to 3750 ) Pioneer Global Projects Pvt Ltd( From Ch 2000 to 2200 and Ch 2600 to 3000 )
Cumulative
achieved by
Achieved for the day
Cumulative Scope for Scope available Cumulative both the
the contractors
Achieved Till Contractor before tree Achieved Till
Date cutting Night Date during the day
as per LOA Day Shift Shift Total

42,750 380,000 - - - - - -
121,840 2,600,000 260,000 1,968 1,968 30,620 7,504.00

90,912 1,968 1,968 5,704 5,536.00

WIP 2,000,000 - - - - - -

Equipment status

RBR Pioneer
Sl. No. Equipment
Day Night Day Night

1 4 2 4
Excavators

2 4 5 2
Dozers with ripper
3 Dozers 2 2 2
4 Tippers 9 7 13
5 Grader 1 1

6 1 1
Vibromax Roller
7 6 2
Water tanker
8 1 1
Tower lights
Cumulative
achieved by
both the
contractors till
date

42,750
152,460

96,616

WIP

You might also like