PERHITUNGAN BUDGET

Timbun tanah

Jarak total panjang Total Biaya /


Jumlah Trip PP Total Biaya volume Harga Harga
No Pemakaian unit / Hari Tempuh VRA volume jalan Hari 3
Unit / unit Trip Rp/Hm/Km atau unit 3 ( Rp/Mtr Jalan) ( Rp/M )
(KM) (M ) (m') (8 Jam Nett)

I. Timbun tanah lebar jalan 4 m , tebal 30 cm.


A Jarak 40 km ke kuari
1 Dump truck 20 160 4 80 7.500 1.200.000 3,5 280 233 24.000.000
2 Excavator 1 - 550.000 550.000 1,0 - - 4.400.000 137.143 114.286
3 Buldozer 1 - 450.000 450.000 1,0 - 233 3.600.000
B Jarak 30 km ke kuari 32.000.000
1 Dump truck 20 150 5 100 7.500 1.125.000 3,5 350 292 22.500.000
2 Excavator 1 - 550.000 550.000 1,0 - - 4.400.000 104.571 87.143
3 Buldozer 1 - 450.000 450.000 1,0 - 292 3.600.000
C Jarak 20 km ke kuari 30.500.000
1 Dump truck 15 140 7 105 7.500 1.050.000 3,5 368 306 15.750.000
2 Excavator 1 - 550.000 550.000 1,0 - - 4.400.000 77.551 64.626
3 Buldozer 1 - 450.000 450.000 1,0 - 306 3.600.000
D Jarak 10 km ke kuari 23.750.000
1 Dump truck 10 160 16 160 7.500 1.200.000 3,5 560 467 12.000.000
2 Excavator 1 - 550.000 550.000 1,0 - - 4.400.000 42.857 35.714
3 Buldozer 1 - 450.000 450.000 1,0 - 467 3.600.000
E Jarak 5 km ke kuari 20.000.000
1 Dump truck 7 150 30 210 7.500 1.125.000 3,5 735 613 7.875.000
2 Excavator 1 - 550.000 550.000 1,0 - - 4.400.000 25.918 21.599
3 Buldozer 1 - 450.000 450.000 1,0 - 613 3.600.000
F Jarak 90 km ke kuari 15.875.000
1 Dump truck 30 180 2 60 7.500 1.350.000 3,5 210 175 40.500.000
2 Excavator 1 1 550.000 550.000 1,0 - - 4.400.000 277.143 230.952
3 Buldozer 1 1 450.000 450.000 1,0 - 175 3.600.000
48.500.000
II. Jarak Perhitungan (Pulang pergi jalan Kuari)
*NB 1 M' = 1,2 M3
1 M3 = 0,9 M'