Professional Documents
Culture Documents
PLANNING
Structure
7.1 Introduction
Objectives
7.1 INTRODUCTION
Globalization has left many service-oriented companies and manufacturing industries
with the alternative of pursuing world’s best practices. Many companies now
comprehend the need for the development of methodologies, as well as acquiring the new
productivity tool such as MRP (Material Requirement Planning), BOM (Bill of Material),
Master Production Schedule (MPS), MRP II etc., that will let them be in a commercial
position to offer competitive Manufacturing Resource Planning. It assure customers
about quality goods and services, and compliance them with international quality
requirements on different industry fields.
Material Requirement Planning (MRP) initiates with the principle that many materials
held in inventory are generally dependent on demands. Materials are of two types : raw
material kept in inventory and partially complete products held in process inventory.
The raw material quantity of a particular material with dependent demand that is needed
in any week, depend on the number of products to be produced that require the material.
The demand for raw materials and partially completed products does not have to be
forecasted, because if it is known what finished products must be produced in a week, the
amount of each material needed to produce these finished products can be calculated.
The basic structure of MRP system is shown in Figure 7.1. Normally it is a 19
Planning Function in computer-based system that takes the Master Production Schedule (MPS) as given,
Production Management explodes the MPS into the required amount of raw materials, parts, subassemblies, and
assemblies needed in each week of the planning horizon; reduces these material
requirements to account for materials that are in inventory or on order; and develops a
schedule of orders for purchased materials and produced parts over the planning horizon.
Error!
Input Data in MRP system
Material Requirement
Planning
Objectives
After studying this unit, you should be able to
• understand material requirement planning,
• learn the principle of MRP,
• know the important factors affecting MRP,
• explain bill of material and master production schedule, and
• understand manufacturing resource planning.
21
Planning Function in
Production Management 7.3 PRINCIPLES OF MRP
A material requirement planning is concerned primarily with the scheduling of activities
and the management of inventories. It is particularly useful where there is a need to
produce components, items or sub-assemblies which themselves are later used in the
production of a final product or, in non-manufacturing organisations, where the provision
of a transport or service for a customer necessitates the use or provision of certain
subsystems. For example, it may be used when a customer orders a computer from a
manufacturing organization, which must first manufacture or obtain various components
which are used in the final assembly of that computer for that customer. Similarly, in
treating a patient in a hospital, e.g. for a major operation, the hospital must, provide
accommodation for the patient, diagnostic tests, anesthetics and post-care facilities as
well as surgical facilities so that the patient's total requirements are satisfied. In these two
cases the product or service requested by the customer can be seen to be the final output
of the system, which derives from certain lower-level provisions. These lower-level
provisions are considered to be dependent on the customer’s final requirement. Given a
measure or forecast of the total number of customers, the demand at lower levels can be
obtained. The Materials Requirements Planning technique is used precisely for this
purpose. It takes as one of its inputs, the measured or forecast demand for the system's
outputs. It breaks down this demand into its component parts, compares this requirement
against existing inventories, and seeks to schedule the parts required against available
capacity. The MRP procedure produces a schedule for all component parts, if necessary
through to purchasing requirements, and where appropriate shows expected shortages
due to capacity limitations. The basic procedure is illustrated in Figure 7.2. This
procedure is undertaken on a repetitive basis. The explosion and scheduling procedure
begin to be repeated at regular intervals, perhaps corresponding to the intervals at which
demand forecasting is undertaken or as and when required as a result of changes in
known demand. The use of this procedure involves considerable data processing, even
for relatively simple availability of cheap computing power in the organizations.
Opening Master
Error! Inventory Schedule
Purchase Bill of
Schedule Requirements
MRP Opening
Closing
Inventory Capacity
Scheduling
for Operating Shortages
System Closing
Capacity
22
SAQ 2 Material Requirement
Planning
(a) Define the principles of MRP.
(b) How does scheduling affect the procedure of MRP?
The annual demand for this end item is estimated to be 25,000 units over a
50 week per year schedule, or an average of 500 units per week. It costs Rs. 800 to
change over the machines in the final assembly department to this end item when a
production lot is begun. It costs Rs. 1.10 per unit when one unit of this product
must be carried in inventory from one week to another; therefore, when one unit of
this product is in ending inventory, it must be carried over as beginning inventory
in the next week and incurs the Rs. 1.10 per unit carrying cost. Determine which of
these lots sizing methods results in the least carrying and changeover (or order)
costs for the eight week schedule :
(a) Lot for Lot (LFL),
(b) Economic Order Quantity (EOQ), or
(c) Period Order Quantity (POQ).
Solution
(a) Develop the total carrying costs over the eight week schedule for the
lot-for-lot method. Lot-For-Lot (LFL) production lots equal the net
requirement in each period.
Week Costs
1 2 3 4 5 6 7 8 Carrying Ordering Total
Net Requirements 200 400 900 500 200 200 200 1400
Beginning 0 0 0 0 0 0 0 0
Inventory
Production Lots 200 400 900 500 200 200 200 1400 0.00 6400.00 6400.00
Ending Inventory 0 0 0 0 0 0 0 0
Week Costs
1 2 3 4 5 6 7 8 Carrying Orderin Total
g
Net 200 400 900 500 200 200 200 1400
Requirements
Beginning 0 653 253 206 559 359 159 812
Inventory
Production 853 0 853 853 0 0 853 853 3592.60 4000.00 7592.60
Lots
Ending 653 253 206 559 359 159 812 265
Inventory
SAQ 5
(a) Where is MRP implemented?
(b) Explain different lot sizing methods.
26
Material Requirement
7.7 SHORTCOMINGS ASSOCIATED WITH MRP Planning
7.7.1 Uncertainty
Underlying MRP is the assumption that all required information is known with certainty.
However, uncertainties do exist. The two key sources of uncertainty are the forecasts for
future sales of the end item and the estimation of the production lead times from one
level to another. Forecast uncertainty usually means that the realization of demand is
likely to be different from the forecast of that demand. In the production planning
context, it could also mean that updated forecasts of future demands are different from
earlier forecasts of those demands. Forecasts must be revised when new orders are
accepted, i.e. prior orders are canceled, or new information about the marketplace
becomes available. That has two implications in the MRP system. One is that all of the
lot-sizing decisions that were determined in the last run of the system could be incorrect,
and even more problematic, former decisions that are currently being implemented in the
production process may be incorrect.
The analysis of stochastic inventory models shows that an optimal policy included safety
stock to protect against the uncertainty of demand. That is, we would order to a level
exceeding expected demand. The same logic can be applied to MRP systems. The
manner in which uncertainty transmits itself through a complex multilevel production
system is not well understood. For that reason generally, it is not recommended to
include independent safety stock at all levels of the system. Suitable safety levels can be
built into the forecasts for the end item. These will automatically be transmitted down
through the system to the lower levels through the explosion calculus.
27
Planning Function in SAQ 6
Production Management
(a) What are the main shortcomings of MRP?
(b) How uncertainties of manufacturing process affect MRP?
(c) Explain effects of capacity planning in MRP.
28
Material Requirement
7.9 BILL OF MATERIAL (BOM) Planning
A bill of material is a list of the materials along with their quantity required to produce
one unit of a product, or end item. Hence, each manufacturing product has a bill of
material. A bills of material file some time known as product structure file. BOM is a
complete list of all finished products, the quantity of each material in each product and
the structure of assemblies, subassemblies, parts, and raw materials and their relationship
with the products. Another term for a bill of material is indented bill of material. It a list
in which the parent is in the margin and its components are indented to show structure.
The bil1s of material file is generally up-to-date computerized files that must be revised
as products are redesigned. The main hurdle associated with BOM is its accuracy that
must be overcome in most MRP applications. With the confidence that the file is correct,
once the MRS is prepared, end item in the MPS can be exploded into the assemblies,
subassemblies, parts and raw materials required. These units may be either purchased
from outside suppliers or produced in in-house production departments.
BOM in fact identifies the component parts of final output product. At each level
different component, material or sub-assemblies are shown, so the bill of requirements
shows not only the total number of sub-parts but also the manner in which these parts
eventually come together to constitute the final product. The lead time between the levels
is also shown as illustrated in Figure 7.3. Each item is assigned to one level only, and
each item at each level has a unique coding. The different level may correspond to
different design. Where complex end products may be made in several different possible
configurations from a large number of parts or sub-assemblies which may be assembled
in different ways, it is common to use a modular bill of requirement structure.
Final
Product
Level 0
Sub-assembly Component
Unit 2.1 2/1
Component Component
1/1 1/2
Level 2
Sub-assembly Component
Unit 2.1.1 2.1/1
Level 3
SAQ 8
(a) What is the definition of BOM?
(b) What are different levels for preparing BOM?
29
Planning Function in
Production Management 7.10 MASTER PRODUCTION SCHEDULE (MPS)
The Master Production Schedule (MPS) is a line on the master schedule grid that reflects
the anticipated building schedule for those items assigned to the master scheduler. The
master scheduler maintains this schedule, and in turn, it becomes a set of planning
numbers that drives material requirements planning. It represents what the company
plans to produce expressed in specific configurations, quantities, and dates. MPS is not a
sale item forecast that represents a statement of demand. It must take into account the
forecast, the production plan, and other important considerations such as backlog,
availability of material, availability of capacity, and management policies and goals. The
basic structure along with different component pertaining to MPS system is illustrated in
Figure 7.4.
In aggregate planning operations managers develop medium-range plans of how they will
produce products for the next several months. These plans contains necessary
information required to manufactured the products such as amount of labor,
subcontracting, and other sources of capacity to be used. It also engages operations
managers to develop short-range production plan for the production of finished products
in next several weeks. Aggregate production plan of a manufacturing unit is shown in
Table 7.1 while the hypothetical master production schedule is shown in Table 7.2.
Master Production
Scheduling
Process
Customer Orders
(Detail of Customer
Order, Due Dates)
Error!
Forecasts
(Detail of
Customer Order,
Due Dates)
Inventory Status
(Balances,
Planned,
Receipts)
Production Capacity
(Output Rates,
Planned Downtime)
Day
Production Line I II III IV V VI VII VIII
Model line A1 05 10 25 30 30 40 20 10
Model line A2 45 10 05 10 − 20 50 70
Model line B1 20 20 04 15 20 14 20 −
Model line B2 10 20 10 50 10 10 30 −
Model line B3 50 06 30 15 40 20 15 −
Model line C1 69 20 50 6 50 80 30 −
Model line C2 09 14 04 6 06 08 04 −
Model line D1 34 36 − − − − 20 30
Model line D2 10 26 − − − − 20 04
Model line F1 30 40 10 04 05 40 − −
Model line F2 20 20 14 10 22 04 − −
Model line F3 30 20 10 40 05 04 − −
Model line G 45 56 − − − − − −
Model line H1 15 40 − − 50 − − −
Model line H2 15 10 − − 06 − − −
On the basis of production plan production schedule are divided into three categories :
• Long range production schedule
• Medium range production schedule
• Short range production schedule
Long range production schedule are used to plant facilities and equipments, major
suppliers, and production processes that become constraints on the medium and short
range production plans. Medium-range production schedule develops aggregate planning
that includes plans of concerning employment, aggregate inventory, facility modification,
and material supply contracts. These aggregate plans impose constraints on short
production plans. The short range production plans are plans for producing finished
goods or end items, which are used to drive production planning.
A product included in the master production schedule is divided into three categories :
31
Planning Function in • Firm Customer Orders
Production Management
• Forecasted Demand
• Spare Parts
Productions in each category vary from company to company. Is some cases one or more
categories may be omitted. Companies generally producing assembled products will have
to handle all three types. In the case of specific customer order, the company is usually
enforced to deliver the item by a particular due date to the sales department. In the
second category, production output quantities are based on statistical forecasting
techniques applied to previous demand patterns that are estimated by the sales staff and
other sources. For many companies, forecasted demand constitutes the largest portion of
the master schedule. The third category consists of repair parts that will either be stocked
in the company’s service department or sent directly to the customer. Some companies
exclude this third category for the master schedule since it does not represent end
products.
Master production schedule generally known as medium range plan. It always takes
account of lead time, order of raw materials, produce parts in the manufacturing units and
assembly of the end products. Depending on the types of product, lead time vary from a
day to many months. For a production order, MPS is usually considered to be fixed in the
near term, i.e. changes are not allowed for a short period because it is difficult to adjust
production schedule within such a short period of time. However, adjustments are
allowed for a long period. In this period, manufacturing units are trying to cope with
changing demand pattern or new products are introduced. Hence, aggregate production
plan is not only the input that control the master production schedule but may affect the
demand of new customer orders and changes in sale forecast over the near time.
Example 7.2
A manufacturing unit produces two products M and N on a produce to stock basis.
The estimated demand for the product M and N over the next six week are shown
in the following Tables 7.3 and 7.4.
Table 7.3 : Demands for Product M from All Sources
In week 1, the balance exceeds the desired safety stock; therefore no production of
product M is needed.
In week 2, the balance is also enough to provide the desired safety stock and no
production of product M is required.
In week 3, the balance would actually be negative if production of M where not
scheduled therefore a fixed lot size of 70 product M is scheduled in third week.
In week 4, the balance would actually be negative if production of M where not
scheduled therefore a fixed lot size of 70 product M is scheduled in fourth week.
In week 5, the balance would actually be negative if production of M where not
scheduled therefore a fixed lot size of 70 product M is scheduled in fifth week.
In week 6, the balance would actually be negative if production of M where not
scheduled therefore a fixed lot size of 70 product M is scheduled in sixth week. 33
Planning Function in Table 7.7 : MPS for Product N
Production Management
Week Beginning Total Balanc Required Ending
Inventory Demand e Production Inventory
1 80 40 40 − 40
2 40 50 (10) 80 70
3 70 60 10 − 10
4 10 60 (50) 80 30
5 30 70 (40) 80 40
6 40 50 (10) 80 70
In week 1, the balance exceeds the desired safety stock; therefore no production of
product N is needed.
In week 2, the balance would actually be negative if production of N where not
scheduled therefore a fixed lot size of 80 product N is scheduled in second week.
In week 3, the balance is also enough to provide the desired safety stock and no
production of product N is required.
In week 4, the balance would actually be negative if production of N where not
scheduled therefore a fixed lot size of 80 product N is scheduled in fourth week.
In week 5, the balance would actual negative if production of N where not
scheduled therefore a fixed lot size of 80 product N is scheduled in fifth week.
In week 6, the balance would actual negative if production of N where not
scheduled therefore a fixed lot size of 80 product N is scheduled in sixth week.
SAQ 9
(a) What is the aggregate production plan?
(b) What are the different categories of production schedule?
(c) What is the main effect of spare parts in MPS?
Purchasing Scheduling
Management
Batching Rules
Generally, software packages are made that offer a variety of batching rules.
Three of the more important batche rules are ‘Lot for Lot’, ‘EBQ’ and ‘Part Period
Cover’.
• Lot for Lot batches means batches that match the orders. Therefore if
a company is planning to make 10 of Product N followed by 20 of
Product M, then the batches throughout the process will match this
requirement. If both N and M require two of a certain sub assembly
35
Planning Function in then that will be made in quantities of 20 of N and 40 of M. It is the
Production Management batching implicitly followed in basic MRP.
• EBQ stands for Economic Batch Quantity. The batch size is
calculated by a formula that minimizes the cost through balancing the
set up cost against the cost of stock.
• Part Period Cover means making batches whose size cover a fixed
period of demand. A policy of making a week’s requirement in one
batch is an example.
Software Extension Programs
A large number of software programmes are included in the MRP II suite. Some of
these are further designed to help the scheduling procedure. Out of them, most
important is Rough Cut Capacity Planning (RCCP), an initial attempt to match the
order load to the capacity available, by calculating the load per resource.
Overloads are identified and orders can be moved to achieve a balance. This has
been described as knocking the mountains into the valleys.
Other additions are designed to extend the application of the MRP II package. For
example it may include an option for entering and invoicing sales orders. Another
common extension is into stock recording and a third into cost accounting. A full
MRP II implementation can therefore act as an integrated database for the
company.
SAQ 10
(a) What are the features of MRP II?
(b) What are the main differences between MRP and MRP II?
7.12 SUMMARY
Materials requirements planning (MRP) is a set of procedures for converting forecasted
demand for a manufactured product into a requirement schedule for the components,
subassemblies, and raw materials comprising that product. A closely related concept is
that of the master production schedule (MPS), which is a specification of the projected
needs of the end product by time period. The explosion calculus represents the set of
rules and procedures for converting the MPS into the requirements at lower levels. The
information required to do the explosion calculus is contained in the product structure
diagram and the indented bill-of-materials list. The two key pieces of information
contained in the product structure diagram are the production lead times needed to
produce the specific component, and the multiplier giving the number of units of the
component required to produce one item at the next higher level of the product structure.
Most of MRP systems are based on a lot-for-lot production schedule. The number of
units of a component produced in a period is the same as the requirements for that
component in that period. However, if setup and holding costs can be estimated
accurately, it is possible to find other lot-sizing rules that are more economical. We have
also treated the dynamic lot-sizing problem when capacity constraints exist. One of the
limitations of MRP is that capacities are ignored. This is especially important if lot sizing
is incorporated into the system. Finding optimal solutions to a capacity-constrained
inventory system subject to time-varying demand is an extremely difficult problem.
System nervousness is one problem that arises while implementing the MRP system, The
term refers to the unanticipated changes in a schedule that result when the planning
horizon is rolled forward by one period. Another difficulty is that in many circumstances,
36 production lead times depend on the lot sizes; MRP assumes that production lead times
are fixed; still another problem is that the yields at various levels of the process may not Material Requirement
be perfect. If the yield rates can be accurately estimated in advance, these rates can be Planning
factored into the calculations in a straightforward manner. However, in many industries
the yield rates may be difficult to estimate in advance. MRP II is implemented generally
to overcome some of the difficulties involved in implication procedure of MRP. It
integrates financial, accounting and marketing functions of the production planning
system.
37