Multirole Crewboat Classic Schedule Layout 04-Dec-22 22:28

Activity ID Activity Name Original BL1 Start Start BL1 Finish Finish Qtr 3 Qtr 4 Qtr 1 Qtr 2
Duration -1 1 2 3 4 5 6 7 8 9

243 20-Jul-22 20-Jul-22 27-Mar-23 27-Mar-23 27-Mar-23, Multir


Multirole Crewboat
164 09-Aug-22 09-Aug-22 27-Mar-23 27-Mar-23 27-Mar-23, MILE
MILESTONE SUMMARY
S1000 Keel Laying 0 09-Aug-22 09-Aug-22 Keel Laying, 09-Aug-22
S1010 Start Work 0 10-Aug-22 10-Aug-22 Start Work, 10-Aug-22
S1020 Launching 0 31-Jan-23 31-Jan-23 Launching, 31-Jan-23
S1030 Sea Trial 0 17-Mar-23 17-Mar-23 Sea Trial, 17-Mar-23
S1040 Delivery 0 27-Mar-23 27-Mar-23 Delivery, 27-Mar-
46 20-Jul-22 20-Jul-22 21-Sep-22 21-Sep-22 21-Sep-22, PROCRUMENT
PROCRUMENT
PR1000 CNC for Hull 20 20-Jul-22 20-Jul-22 16-Aug-22 16-Aug-22 CNC for Hull
PR1010 CNC For Superstructure 5 17-Aug-22 17-Aug-22 23-Aug-22 23-Aug-22 CNC For Superstructure
PR1020 CNC Logo, draft mark & Hull marking 1 24-Aug-22 24-Aug-22 24-Aug-22 24-Aug-22 CNC Logo, draft mark & Hull marking
PR1030 Piping Material 5 25-Aug-22 25-Aug-22 31-Aug-22 31-Aug-22 Piping Material
PR1040 Electrical Material 5 01-Sep-22 01-Sep-22 07-Sep-22 07-Sep-22 Electrical Material
PR1050 HVAC Material 5 08-Sep-22 08-Sep-22 14-Sep-22 14-Sep-22 HVAC Material
PR1060 Carpentry Material 5 15-Sep-22 15-Sep-22 21-Sep-22 21-Sep-22 Carpentry Material
165 21-Jul-22 21-Jul-22 07-Jan-23 07-Jan-23 07-Jan-23, DESIGN PHASE
DESIGN PHASE
D1010 General Arrangement & Other Support Drawing 10 21-Jul-22 21-Jul-22 31-Jul-22 31-Jul-22 General Arrangement & Other Support Drawing
D1000 Hull Construction & Assembly 25 31-Jul-22 31-Jul-22 26-Aug-22 26-Aug-22 Hull Construction & Assembly
D1020 Superstructure Construction & Assembly 20 26-Aug-22 26-Aug-22 15-Sep-22 15-Sep-22 Superstructure Construction & Assembly
D1030 Outfitting Items Drawing 21 15-Sep-22 15-Sep-22 07-Oct-22 07-Oct-22 Outfitting Items Drawing
D1040 Pipeline Diagram & Penetration drawing 25 16-Oct-22 16-Oct-22 10-Nov-22 10-Nov-22 Pipeline Diagram & Penetration drawing
D1050 Carpentry Drawing 30 26-Oct-22 26-Oct-22 25-Nov-22 25-Nov-22 Carpentry Drawing
D1060 Mechanical Drawing 21 03-Nov-22 03-Nov-22 24-Nov-22 24-Nov-22 Mechanical Drawing
D1070 Electrical SLD Drawing & Equipment Arrangement 25 15-Nov-22 15-Nov-22 10-Dec-22 10-Dec-22 Electrical SLD Drawing & Equipment Arrangement
D1090 Pipeline arrangement & Isometric Drawing 35 30-Nov-22 30-Nov-22 07-Jan-23 07-Jan-23 Pipeline arrangement & Isometric Drawing
D1080 HVAC Drawing 15 11-Dec-22 11-Dec-22 27-Dec-22 27-Dec-22 HVAC Drawing
221 10-Aug-22 10-Aug-22 25-Mar-23 25-Mar-23 25-Mar-23, CONS
CONSTRUCTION
HULL 120 10-Aug-22 10-Aug-22 10-Dec-22 10-Dec-22 10-Dec-22, HULL
H1000 Sorting CNC Plates 5 10-Aug-22 10-Aug-22* 15-Aug-22 15-Aug-22 Sorting CNC Plates
Unit 2 83 15-Aug-22 15-Aug-22 08-Nov-22 08-Nov-22 08-Nov-22, Unit 2
H1020 Fab Bulkhead 28 15-Aug-22 15-Aug-22 13-Sep-22 13-Sep-22 Fab Bulkhead
H1040 Tank Top and Bottom Part Fabrication 25 02-Sep-22 02-Sep-22 28-Sep-22 28-Sep-22 Tank Top and Bottom Part Fabrication
H1070 Frame Fabrication & Installation 22 16-Sep-22 16-Sep-22 09-Oct-22 09-Oct-22 Frame Fabrication & Installation
H1110 Deck Frame/Panel 15 30-Sep-22 30-Sep-22 15-Oct-22 15-Oct-22 Deck Frame/Panel
H1130 Longitudinal Bott & Side Shell 30 10-Oct-22 10-Oct-22 08-Nov-22 08-Nov-22 Longitudinal Bott & Side Shell
Unit 3 94 15-Aug-22 15-Aug-22 19-Nov-22 19-Nov-22 19-Nov-22, Unit 3
H1010 Bulkhead Fabrication 28 15-Aug-22 15-Aug-22 12-Sep-22 12-Sep-22 Bulkhead Fabrication
H1030 Tank Top and Bottom Part Fabrication 31 01-Sep-22 01-Sep-22 04-Oct-22 04-Oct-22 Tank Top and Bottom Part Fabrication
H1090 Frame Fabrication & Installation 28 23-Sep-22 23-Sep-22 21-Oct-22 21-Oct-22 Frame Fabrication & Installation
H1140 Deck Panel 22 10-Oct-22 10-Oct-22 01-Nov-22 01-Nov-22 Deck Panel
H1180 Longitudinal Bott & Side Shell 28 23-Oct-22 23-Oct-22 19-Nov-22 19-Nov-22 Longitudinal Bott & Side Shell
Unit 1 86 12-Sep-22 12-Sep-22 09-Dec-22 09-Dec-22 09-Dec-22, Unit 1
H1050 Bulkhead Fabrication 25 12-Sep-22 12-Sep-22 09-Oct-22 09-Oct-22 Bulkhead Fabrication
H1100 Tank Top and Bottom Part Fabrication 25 28-Sep-22 28-Sep-22 23-Oct-22 23-Oct-22 Tank Top and Bottom Part Fabrication
H1160 Frame Fabrication & Installation 21 13-Oct-22 13-Oct-22 03-Nov-22 03-Nov-22 Frame Fabrication & Installation
H1190 Deck Frame/Panel 25 26-Oct-22 26-Oct-22 20-Nov-22 20-Nov-22 Deck Frame/Panel
H1220 Longitudinal Bott & Side Shell 28 11-Nov-22 11-Nov-22 09-Dec-22 09-Dec-22 Longitudinal Bott & Side Shell
Unit 4 72 12-Sep-22 12-Sep-22 25-Nov-22 25-Nov-22 25-Nov-22, Unit 4
H1060 Bulkhead Fabrication 8 12-Sep-22 12-Sep-22 22-Sep-22 22-Sep-22 Bulkhead Fabrication
H1080 Frame Fabrication & Installation 22 20-Sep-22 20-Sep-22 12-Oct-22 12-Oct-22 Frame Fabrication & Installation
H1150 Deck Panel 28 12-Oct-22 12-Oct-22 08-Nov-22 08-Nov-22 Deck Panel
H1200 Longitudinal Bott & Side Shell 20 05-Nov-22 05-Nov-22 25-Nov-22 25-Nov-22 Longitudinal Bott & Side Shell

Actual Level of Effort Actual Work Critical Remaining Work Page 1 of 4 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Multirole Crewboat Classic Schedule Layout 04-Dec-22 22:28
Activity ID Activity Name Original BL1 Start Start BL1 Finish Finish Qtr 3 Qtr 4 Qtr 1 Qtr 2
Duration -1 1 2 3 4 5 6 7 8 9

Unit 6 57 09-Oct-22 09-Oct-22 05-Dec-22 05-Dec-22 05-Dec-22, Unit 6


H1120 Fab Top D/H Panel 18 09-Oct-22 09-Oct-22 27-Oct-22 27-Oct-22 Fab Top D/H Panel
H1170 Side Sheel D/H Panel 22 21-Oct-22 21-Oct-22 12-Nov-22 12-Nov-22 Side Sheel D/H Panel
H1210 Fab D/H Wall and Partition 20 05-Nov-22 05-Nov-22 25-Nov-22 25-Nov-22 Fab D/H Wall and Partition
H1250 Errection & Welding 15 20-Nov-22 20-Nov-22 05-Dec-22 05-Dec-22 Errection & Welding
Unit 7 28 12-Nov-22 12-Nov-22 10-Dec-22 10-Dec-22 10-Dec-22, Unit 7
H1230 Top W/H Deck 10 12-Nov-22 12-Nov-22 22-Nov-22 22-Nov-22 Top W/H Deck
H1240 Wall Panel Fab 15 19-Nov-22 19-Nov-22 04-Dec-22 04-Dec-22 Wall Panel Fab
H1260 Erection and Welding 10 30-Nov-22 30-Nov-22 10-Dec-22 10-Dec-22 Erection and Welding
OUTFITTING 150 24-Sep-22 24-Sep-22 25-Feb-23 25-Feb-23 25-Feb-23, OUTFITTING
O1000 Pumps Seating 7 24-Sep-22 24-Sep-22 01-Oct-22 01-Oct-22 Pumps Seating
O1010 Bollard & Stairway 25 01-Oct-22 01-Oct-22 26-Oct-22 26-Oct-22 Bollard & Stairway
O1020 Main Mast 16 17-Oct-22 17-Oct-22 02-Nov-22 02-Nov-22 Main Mast
O1030 Portable tank 20 27-Oct-22 27-Oct-22* 16-Nov-22 16-Nov-22 Portable tank
O1040 Bullwark & Handrail 25 10-Nov-22 10-Nov-22 05-Dec-22 05-Dec-22 Bullwark & Handrail
O1050 Pad Eye fender & Hull Marking 20 26-Nov-22 26-Nov-22* 16-Dec-22 16-Dec-22 Pad Eye fender & Hull Marking
O1060 Cranes Seating 10 10-Dec-22 10-Dec-22 20-Dec-22 20-Dec-22 Cranes Seating
O1070 Console 19 10-Dec-22 10-Dec-22 30-Dec-22 30-Dec-22 Console
O1080 Tie Down Pocket & Windlass Seating 18 17-Dec-22 17-Dec-22 07-Jan-23 07-Jan-23 Tie Down Pocket & Windlass Seating
O1090 Speed log & Echo sounder Houshing 10 26-Dec-22 26-Dec-22* 07-Jan-23 07-Jan-23 Speed log & Echo sounder Houshing
O1100 Wooden Deck Seating 12 29-Dec-22 29-Dec-22 12-Jan-23 12-Jan-23 Wooden Deck Seating
O1110 Hull & SS ventilation 20 04-Jan-23 04-Jan-23 24-Jan-23 24-Jan-23 Hull & SS ventilation
O1120 IMDG Store 6 09-Jan-23 09-Jan-23 15-Jan-23 15-Jan-23 IMDG Store
O1130 Platform Accomodation 10 13-Jan-23 13-Jan-23 23-Jan-23 23-Jan-23 Platform Accomodation
O1140 Hatch, Doors & Windows 25 16-Jan-23 16-Jan-23 11-Feb-23 11-Feb-23 Hatch, Doors & Windows
O1150 Platform Aft tank room to Steering GR Room 25 23-Jan-23 23-Jan-23 18-Feb-23 18-Feb-23 Platform Aft tank room to Steering GR Roo
O1160 Ship Name & Tyre Fender Installation 7 18-Feb-23 18-Feb-23 25-Feb-23 25-Feb-23 Ship Name & Tyre Fender Installation
PIPING 106 10-Nov-22 10-Nov-22 27-Feb-23 27-Feb-23 27-Feb-23, PIPING
Penetration 39 10-Nov-22 10-Nov-22 19-Dec-22 19-Dec-22 19-Dec-22, Penetration
I1000 Portable Tank & Below Deck 20 10-Nov-22 10-Nov-22 30-Nov-22 30-Nov-22 Portable Tank & Below Deck
I1020 Side Shell & Bottom 21 20-Nov-22 20-Nov-22 11-Dec-22 11-Dec-22 Side Shell & Bottom
I1030 Main Deck & Wheelhouse 17 02-Dec-22 02-Dec-22 19-Dec-22 19-Dec-22 Main Deck & Wheelhouse
Equipment Inst + Pipeline Fabrication 83 20-Nov-22 20-Nov-22 14-Feb-23 14-Feb-23 14-Feb-23, Equipment Inst + Pipeline Fabrica
I1010 Domestic system 21 20-Nov-22 20-Nov-22 11-Dec-22 11-Dec-22 Domestic system
I1040 Sanitary system 21 03-Dec-22 03-Dec-22 24-Dec-22 24-Dec-22 Sanitary system
I1050 AC Cooling 12 16-Dec-22 16-Dec-22 29-Dec-22 29-Dec-22 AC Cooling
I1060 F.O System 35 16-Dec-22 16-Dec-22 23-Jan-23 23-Jan-23 F.O System
I1070 Hydraulic 21 29-Dec-22 29-Dec-22 21-Jan-23 21-Jan-23 Hydraulic
I1090 ME & AE SWC 15 11-Jan-23 11-Jan-23 26-Jan-23 26-Jan-23 ME & AE SWC
I1100 Bilge System 15 19-Jan-23 19-Jan-23 03-Feb-23 03-Feb-23 Bilge System
I1130 Exhaust System 20 25-Jan-23 25-Jan-23 14-Feb-23 14-Feb-23 Exhaust System
I1170 Air Compressor 10 03-Feb-23 03-Feb-23 13-Feb-23 13-Feb-23 Air Compressor
Leak test and Line Installation 58 29-Dec-22 29-Dec-22 27-Feb-23 27-Feb-23 27-Feb-23, Leak test and Line Insta
I1080 Domestic, Sanitary & AC cooling Hyrdotest on Installed Line
7 29-Dec-22 29-Dec-22 07-Jan-23 07-Jan-23 Domestic, Sanitary & AC cooling Hyrdotest on Installed Line
I1110 Hydraulic Pressure Test 10 21-Jan-23 21-Jan-23 31-Jan-23 31-Jan-23 Hydraulic Pressure Test
I1120 F.O System Hydrotest 7 23-Jan-23 23-Jan-23 30-Jan-23 30-Jan-23 F.O System Hydrotest
I1140 Hydrotest on ME & AE SWC 7 26-Jan-23 26-Jan-23 02-Feb-23 02-Feb-23 Hydrotest on ME & AE SWC
I1150 Air Test on Installed F.O Line 12 30-Jan-23 30-Jan-23 11-Feb-23 11-Feb-23 Air Test on Installed F.O Line
I1160 Air Test on Installed ME & AE SWC Line 8 02-Feb-23 02-Feb-23 10-Feb-23 10-Feb-23 Air Test on Installed ME & AE SWC Line
I1180 Hydrotest Bilge Line & Installation 10 10-Feb-23 10-Feb-23 20-Feb-23 20-Feb-23 Hydrotest Bilge Line & Installation
I1190 Air Test on Installed Air Compressor Line 7 20-Feb-23 20-Feb-23 27-Feb-23 27-Feb-23 Air Test on Installed Air Compressor
ELECTRICAL 108 25-Nov-22 25-Nov-22 16-Mar-23 16-Mar-23 16-Mar-23, ELECTRICA
Cabble ladder and bracket installaton 42 25-Nov-22 25-Nov-22 09-Jan-23 09-Jan-23 09-Jan-23, Cabble ladder and bracket installaton

Actual Level of Effort Actual Work Critical Remaining Work Page 2 of 4 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Multirole Crewboat Classic Schedule Layout 04-Dec-22 22:28
Activity ID Activity Name Original BL1 Start Start BL1 Finish Finish Qtr 3 Qtr 4 Qtr 1 Qtr 2
Duration -1 1 2 3 4 5 6 7 8 9

E1000 Penetration 7 25-Nov-22 25-Nov-22 02-Dec-22 02-Dec-22 Penetration


E1010 Cabble Ladder below deck Installation 21 30-Nov-22 30-Nov-22 21-Dec-22 21-Dec-22 Cabble Ladder below deck Installation
E1020 Cabble ladder Superstructure Installation 15 13-Dec-22 13-Dec-22 29-Dec-22 29-Dec-22 Cabble ladder Superstructure Installation
E1040 Panels Bracket Fabrication & Installation 15 22-Dec-22 22-Dec-22 09-Jan-23 09-Jan-23 Panels Bracket Fabrication & Installation
Cable Laying 43 13-Dec-22 13-Dec-22 28-Jan-23 28-Jan-23 28-Jan-23, Cable Laying
E1030 Cabble Laying Below Deck 30 13-Dec-22 13-Dec-22 15-Jan-23 15-Jan-23 Cabble Laying Below Deck
E1050 Cable Laying Superstructure 25 03-Jan-23 03-Jan-23 28-Jan-23 28-Jan-23 Cable Laying Superstructure
Equipment installation and termination 70 05-Jan-23 05-Jan-23 16-Mar-23 16-Mar-23 16-Mar-23, Equipment in
E1060 Panels installation & Terminatuion on Below Deck 35 05-Jan-23 05-Jan-23 09-Feb-23 09-Feb-23 Panels installation & Terminatuio n on Below Dec
E1070 Panel Installation & Termination on Superstructure 15 26-Jan-23 26-Jan-23 10-Feb-23 10-Feb-23 Panel Installation & Termination on Superstructu
E1080 Installation on PA Intercom system 15 04-Feb-23 04-Feb-23 19-Feb-23 19-Feb-23 Installation on PA Intercom system
E1090 Installation of Fire and Gas Detection system 15 07-Feb-23 07-Feb-23 22-Feb-23 22-Feb-23 Installation of Fire and Gas Detection sy
E1100 Installation of Navigation Equipment on Top Deckhouse15 13-Feb-23 13-Feb-23 28-Feb-23 28-Feb-23 Installation of Navigation Equipmen
E1110 Installation of Console Equipment 21 16-Feb-23 16-Feb-23 09-Mar-23 09-Mar-23 Installation of Console Equipm
E1120 Installation of Ships Lighting 21 23-Feb-23 23-Feb-23 16-Mar-23 16-Mar-23 Installation of Ships Ligh
CARPENTRY 117 25-Nov-22 25-Nov-22 25-Mar-23 25-Mar-23 25-Mar-23, CARP
C1140 Passanger Seat Installation 7 09-Feb-23 09-Feb-23 16-Feb-23 16-Feb-23 Passanger Seat Installation
C1180 Wooden Deck 21 25-Feb-23 25-Feb-23 18-Mar-23 18-Mar-23 Wooden Deck
C1200 Finishing 7 18-Mar-23 18-Mar-23 25-Mar-23 25-Mar-23 Finishing
Insulation 39 25-Nov-22 25-Nov-22 05-Jan-23 05-Jan-23 05-Jan-23, Insulation
C1000 Insulation Below deck 15 25-Nov-22 25-Nov-22 10-Dec-22 10-Dec-22 Insulation Below deck
C1010 Insulation Deckhouse 15 28-Nov-22 28-Nov-22 13-Dec-22 13-Dec-22 Insulation Deckhouse
C1030 Insulation E/R & Wheelhouse 30 03-Dec-22 03-Dec-22 05-Jan-23 05-Jan-23 Insulation E/R & Wheelhouse
Install Frame & Wall Panel 56 03-Dec-22 03-Dec-22 31-Jan-23 31-Jan-23 31-Jan-23, Install Frame & Wall Panel
C1020 Install support frame below deck 21 03-Dec-22 03-Dec-22 24-Dec-22 24-Dec-22 Install support frame below deck
C1040 Installation support frame deckhouse & wheelhouse 21 06-Dec-22 06-Dec-22 28-Dec-22 28-Dec-22 Installation support frame deckhouse & wheelhouse
C1050 Installation wall panel below deck 30 21-Dec-22 21-Dec-22 23-Jan-23 23-Jan-23 Installation wall panel below deck
C1060 Installation wall panel deckhouse & wheelhouse 35 24-Dec-22 24-Dec-22 31-Jan-23 31-Jan-23 Installation wall panel deckhouse & wheelhouse
Flooring & Ceiling 51 05-Jan-23 05-Jan-23 25-Feb-23 25-Feb-23 25-Feb-23, Flooring & Ceiling
C1070 Flooring Skirting & Vinyl Below Deck 28 05-Jan-23 05-Jan-23 02-Feb-23 02-Feb-23 Flooring Skirting & Vinyl Below Deck
C1080 Flooring Skiriting & Vinyl Deckhouse & Wheelhouse 28 13-Jan-23 13-Jan-23 10-Feb-23 10-Feb-23 Flooring Skiriting & Vinyl Deckhouse & Wheelho
C1100 Installation Ceiling Below Deck 21 22-Jan-23 22-Jan-23 12-Feb-23 12-Feb-23 Installation Ceiling Below Deck
C1120 Installation Ceiling Deckhouse 18 02-Feb-23 02-Feb-23 20-Feb-23 20-Feb-23 Installation Ceiling Deckhouse
C1150 Installation Ceiling Wheelhouse 12 13-Feb-23 13-Feb-23 25-Feb-23 25-Feb-23 Installation Ceiling Wheelhouse
Installation Furniture 64 13-Jan-23 13-Jan-23 18-Mar-23 18-Mar-23 18-Mar-23, Installation
C1090 Crew Cabin 28 13-Jan-23 13-Jan-23 10-Feb-23 10-Feb-23 Crew Cabin
C1110 Accomodation Room 21 30-Jan-23 30-Jan-23 20-Feb-23 20-Feb-23 Accomodation Room
C1130 Passanger Saloon 18 09-Feb-23 09-Feb-23 27-Feb-23 27-Feb-23 Passanger Saloon
C1160 Toilet 15 17-Feb-23 17-Feb-23 04-Mar-23 04-Mar-23 Toilet
C1170 Galley 15 24-Feb-23 24-Feb-23 11-Mar-23 11-Mar-23 Galley
C1190 Wheelhouse 18 28-Feb-23 28-Feb-23 18-Mar-23 18-Mar-23 Wheelhouse
HVAC 82 27-Dec-22 27-Dec-22 21-Mar-23 21-Mar-23 21-Mar-23, HVAC
HV1000 Fabrication Ducting 12 27-Dec-22 27-Dec-22 10-Jan-23 10-Jan-23 Fabrication Ducting
HV1010 Installation Ducting Below Deck 20 07-Jan-23 07-Jan-23 27-Jan-23 27-Jan-23 Installation Ducting Below Deck
HV1020 Installation Ducting Deckhouse 20 23-Jan-23 23-Jan-23 12-Feb-23 12-Feb-23 Installation Ducting Deckhouse
HV1030 Installation Wheelhouse 14 08-Feb-23 08-Feb-23 22-Feb-23 22-Feb-23 Installation Wheelhouse
HV1040 Installation AC unit & Connect to Ducting 21 18-Feb-23 18-Feb-23 11-Mar-23 11-Mar-23 Installation AC unit & Conne
HV1050 Installation Louvre & Damper 15 06-Mar-23 06-Mar-23 21-Mar-23 21-Mar-23 Installation Louvre &
MECHANICAL 68 24-Nov-22 24-Nov-22 04-Feb-23 04-Feb-23 04-Feb-23, MECHANICAL
M1000 Bow Thruster Installation 15 24-Nov-22 24-Nov-22 09-Dec-22 09-Dec-22 Bow Thruster Installation
M1010 Sterntube & Rudder Trunk Installation 21 09-Dec-22 09-Dec-22 31-Dec-22 31-Dec-22 Sterntube & Rudder Trunk Installation
M1020 Fabrication & Installation P Bracket 12 26-Dec-22 26-Dec-22 09-Jan-23 09-Jan-23 Fabrication & Installation P Bracket
M1030 Fabrication Seating Genset & its Installatiion 5 09-Jan-23 09-Jan-23 14-Jan-23 14-Jan-23 Fabrication Seating Genset & its Installatiion

Actual Level of Effort Actual Work Critical Remaining Work Page 3 of 4 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation
Multirole Crewboat Classic Schedule Layout 04-Dec-22 22:28
Activity ID Activity Name Original BL1 Start Start BL1 Finish Finish Qtr 3 Qtr 4 Qtr 1 Qtr 2
Duration -1 1 2 3 4 5 6 7 8 9

M1040 Anchoring Set Installation 4 14-Jan-23 14-Jan-23 18-Jan-23 18-Jan-23 Anchoring Set Installation
M1050 M/E & Davit Crane Installation 5 18-Jan-23 18-Jan-23 23-Jan-23 23-Jan-23 M/E & Davit Crane Installation
M1060 Shaft, Propeller & Rudder Installation & Pre Alignment 7 23-Jan-23 23-Jan-23 31-Jan-23 31-Jan-23 Shaft, Propeller & Rudder Installation & Pre Alignment
M1070 Alignment & Chockfasting ME & Gearbox 4 31-Jan-23 31-Jan-23 04-Feb-23 04-Feb-23 Alignment & Chockfasting ME & Gearbox
PAINTING 45 13-Dec-22 13-Dec-22 31-Jan-23 31-Jan-23 31-Jan-23, PAINTING
P1000 Sanding Hull 10 13-Dec-22 13-Dec-22 23-Dec-22 23-Dec-22 Sanding Hull
P1010 Sanding Superstructure & Decks 15 23-Dec-22 23-Dec-22 10-Jan-23 10-Jan-23 Sanding Superstructure & Decks
P1020 Apply Primer Coat until Antifouling Below WL 5 10-Jan-23 10-Jan-23 15-Jan-23 15-Jan-23 Apply Primer Coat until Antifouling Below WL
P1030 Apply Putty Above WL 3 15-Jan-23 15-Jan-23 18-Jan-23 18-Jan-23 Apply Putty Above WL
P1040 Sanding Primer Coat Above WL 10 18-Jan-23 18-Jan-23 29-Jan-23 29-Jan-23 Sanding Primer Coat Above WL
P1050 Apply 2nd Coat Above WL 1 29-Jan-23 29-Jan-23 30-Jan-23 30-Jan-23 Apply 2nd Coat Above WL
P1060 Apply FInal Coat 1 30-Jan-23 30-Jan-23 31-Jan-23 31-Jan-23 Apply FInal Coat
55 31-Jan-23 31-Jan-23 26-Mar-23 26-Mar-23 26-Mar-23, HARB
HARBOR ACCEPTANCE TEST
T1000 Launching 0 31-Jan-23 31-Jan-23 Launching, 31-Jan-23
T1120 Sea Trial 3 13-Mar-23 13-Mar-23 16-Mar-23 16-Mar-23 Sea Trial
T1130 Cleaning, Finishing & Document Preparation 10 16-Mar-23 16-Mar-23 26-Mar-23 26-Mar-23 Cleaning, Finishin
Commissioning 40 01-Feb-23 01-Feb-23 13-Mar-23 13-Mar-23 13-Mar-23, Commissioning
T1010 Power Up MSB 2 01-Feb-23 01-Feb-23 03-Feb-23 03-Feb-23 Power Up MSB
T1020 Genset & Load Test 4 03-Feb-23 03-Feb-23 07-Feb-23 07-Feb-23 Genset & Load Test
T1030 Domestic & Sanitary System 3 07-Feb-23 07-Feb-23 10-Feb-23 10-Feb-23 Domestic & Sanitary System
T1040 Steering Gear & Bow Thruster 4 10-Feb-23 10-Feb-23 14-Feb-23 14-Feb-23 Steering Gear & Bow Thruster
T1050 Main Engine 4 14-Feb-23 14-Feb-23 18-Feb-23 18-Feb-23 Main Engine
T1060 FO Transfer & Purfier Sytsem 3 18-Feb-23 18-Feb-23 21-Feb-23 21-Feb-23 FO Transfer & Purfier Sytsem
T1070 Nav Light, Internal, External & EmergncyLight 3 21-Feb-23 21-Feb-23 25-Feb-23 25-Feb-23 Nav Light, Internal, External & Emergn
T1080 Navigation System 4 25-Feb-23 25-Feb-23 01-Mar-23 01-Mar-23 Navigation System
T1090 Fire, Gas & Aerosol Detection System 5 01-Mar-23 01-Mar-23 06-Mar-23 06-Mar-23 Fire, Gas & Aerosol Detection S
T1100 HVAC 3 06-Mar-23 06-Mar-23 09-Mar-23 09-Mar-23 HVAC
T1110 Entertaiment System & Other Non Class Items 4 09-Mar-23 09-Mar-23 13-Mar-23 13-Mar-23 Entertaiment System & Oth

Actual Level of Effort Actual Work Critical Remaining Work Page 4 of 4 TASK filter: All Activities
Primary Baseline Remaining Work Milestone © Oracle Corporation