1. Foam for electrical cable trail of JB (emergency lube oil pump) is not complete
2. Corrosion in many flange for GTC A/B/C in
sprinkler manifold. must be cleaning and painting by galvanized painting 3. Thermal insulation is not installed in compressors flanges inlet and discharge
4. Sun shield for many instruments transmitter not
installed 5. Sun and sand shield for local HMI for all turbines must installed 6. The chain in all jib crane not installed
7. Air fin of gas after cooler in all GTC is very dirty
need to be cleaned 8. pulley and wheel with a grooved must be cleaned in all gas after cooler in GTC A/B/C
9. Belt in air cooler in GTC must be changed
10. Grease nipple is not conform must changed 11. Chain block for lifting beam inside the package GTG and GTC is not installed 12. The CO2 systems in all GTG and GTC is not connected
13.Mechanical lock for all electrical motors in oil coolers
and gas after cooler must be removed 14-Bearing and shaft in all air cooler must be cleaned and inspected for any leakage of grease (inspection of grease seal) 15. All air filters for all gas turbines must be cleaned and preserved from sand during civil work, they are very dirty
16. All valve shafts must be cleaned with WD 40 in GTC
process, they are very dirty 17.GTC B and GTC A the package is not fully isolated to prevent CO2 Leak must install new plates and with new gasket and tested 18. The jacket of centrifugal compressors must be reinforced and cleaned 19.Clean all filter of atmospheric reference for PDI of filter house in all GTG and GTC 20. remove oil leakage in bleed valve actuator in GTG A 21. Clean the package of all Gas turbines from sand