Professional Documents
Culture Documents
Full-Scale Sludge Reduction in The Water Line of Municipal Wastewater Treatment Plant
Full-Scale Sludge Reduction in The Water Line of Municipal Wastewater Treatment Plant
Research article
A R T I C L E I N F O A B S T R A C T
Keywords: Nowadays, sludge management represents one of the most critical challenges in the field of sewage treatment for
Full scale application economic and environmental impacts. Therefore, the reduction of sludge has become a major issue for the op
Granular sludge system erators of municipal wastewater treatment plants. In the present paper, a new system, whose acronym is MULESL
Maintenance metabolism
(MUch LEss SLudge), is proposed and tested at full scale for reducing the quantity of sludge in the water line of
Sewage sludge
the sewage treatment plant. MULESL system takes the advantage of maintenance metabolism to significantly
Sludge minimization
reduce the sludge production. The effectiveness of MULESL system in removing the typical pollutants and
reducing sludge production was evaluated at full scale by using 3500 PE unit located in Putignano’s WWTP
(Puglia, Italy). This unit was obtained by retrofitting an existing activated sludge basin. The results obtained over
1-year period, during which MULESL unit treated the effluent of the preliminary treatment step, have indicated
that it was characterized by a specific sludge production as low as 0.13 kg of dry sludge per kg of COD removed;
77% lower than that recorded for primary and secondary treatments of the conventional plant during the same
period. This sludge reduction was obtained with a plant volume 27% smaller than that of the conventional water
line. Furthermore, the organic matter of the sludge was already stabilized, thus allowing to save investment costs
for digestion process facilities. Finally, MULESL unit guaranteed a mean removal efficiency higher than 95% for
COD, BOD5, TSS, TKN, NH3 and TN.
1. Introduction criterion, the current available approaches are divided in two great
groups: those acting in the water line of sewage treatment plant and
The management of sludge originating from wastewater treatment those acting instead in the sludge line (Wang et al., 2017).
plants (WWTPs) is currently one of the most critical issues of the whole Usually, they are not implemented simultaneously in the same
treatment cycle of municipal sewage. In fact, although the sludge vol WWTP. The first ones, however, are particularly interesting since they
ume produced by wastewater treatment plants represents only 1% of the handle the problem of the sludge at its origin, thus reducing the quantity
volume of sewage flowing in the plants, its treatment and final disposal to send to the sludge line of the plant.
entail very high capital and operating costs (up to 60% of total treatment Most of the proposed techniques for reducing sludge production in
costs; Wei et al., 2003; Andreoli et al., 2007). Unfortunately, these fig the water line are based on mechanisms such as cell lysis-cryptic growth
ures are expected to increase further, as a result of progressively more and maintenance metabolism (Foladori et al., 2010).
stringent effluent and sludge regulation criteria together with the The cryptic growth mechanism exploits the reutilization of intra
growing number of WWTPs (Collivignarelli et al., 2019). Therefore, cellular material released during cell lysis (Hao et al., 2010). The tech
among sewage treatment plants managers there is currently a strong nologies based on cell lysis-cryptic growth are implemented in the
interest in technological solutions to reduce the production of sludge to return activated sludge (or a fraction of it) of the biological reactor. The
be disposed of. lysed sludge is then recycled to the main biological reactor where the
Several approaches for sludge minimization have been proposed in reutilization of the organic material released during bacteria lysis oc
the last decade although their application at the full scale is still rela curs. A portion of this material is then oxidized in the catabolism phase,
tively limited. These approaches can be classified on the basis of the which leads to the reduction of sludge production.
location of the plant where minimization takes place. Based on this The technologies based on this mechanism are distinguished by the
* Corresponding author.
E-mail address: claudio.diiaconi@ba.irsa.cnr.it (C. Di Iaconi).
https://doi.org/10.1016/j.jenvman.2020.110714
Received 5 February 2020; Received in revised form 28 April 2020; Accepted 4 May 2020
Available online 27 May 2020
0301-4797/© 2020 Elsevier Ltd. All rights reserved.
C. Di Iaconi et al. Journal of Environmental Management 269 (2020) 110714
type of treatment that promotes the lysis that can be a chemical (such as 2. Materials and methods
ozonation, chlorination, Fenton treatment, etc; Saby et al., 2002; Sievers
et al., 2004; Gardoni et al., 2011), physical (ultrasound, thermal, elec 2.1. Plant description and operation
trical, etc; Pilli et al., 2011) or biological (i.e., anaerobic side-stream
reactor; Romero et al., 2015; Ferrentino et al., 2016) method. Howev In 2016 the first MULESL demonstrative unit with a treatment ca
er, only a few of them have been applied so far at full scale as the pacity of 3500 person equivalents (PE) was built by retrofitting an
chemicals and operating conditions necessary for achieving significant existing activated sludge basin (670 m3 volume) of Putignano’s WWTP,
reductions of sludge production can negatively affect the purification located in sourthern Italy.
process as well as make the process expensive (Foladori et al., 2010; The water line of the existing Putignano’s WWTP (28,000 PE) con
Wang et al., 2017). sists of preliminary treatment stage (for screening, desanding and
The processes that take advantage of the maintenance metabolism equalization operations), primary sedimentation (single clarifier with
are based on the increase of biomass concentration in the biological 472 m3 volume), biological stage with anoxic (1270 m3 volume) and
basin (that means long sludge retention times, SRT) in order to reduce aerobic (4570 m3 volume) compartments for carbon and nitrogen
the net growth yield. Maintenance energy mechanism is based on the removal, based on activated sludge process, secondary sedimentation (2
fact that microorganisms prefer to satisfy the energy requirement for clarifiers, total volume of 924 m3) and tertiary treatment, for phos
non-growth activities before producing new cells (Wei et al., 2003). In phorous removal and disinfection. The sludge line is based on anaerobic
fact, it is well know that decreasing substrate/biomass ratio it is possible digestion (2 digesters, total volume of 2610 m3) and centrifuge dew
to reduce the observed growth yield (Yobs). This is represented by the atering unit.
following equation (Semblante et al., 2014): MULESL basin was fed with the sewage coming from the preliminary
treatment stage (i.e., with the influent of the primary sedimentation),
1 1 kd SRT
¼ þ (1) whose composition is reported in Table 1, whereas MULESL outlet was
Yobs Ymax Ymax
connected to the tertiary treatment unit of the conventional WWTP.
which shows that Yobs is inversely proportional to SRT. In fact, moving Therefore, two water lines were operated in parallel at Putignano’s
from conventional activated sludge process to an extended aeration one, WWTP, the first based on the traditional primary and secondary treat
featured by a higher SRT, allows to reduce sludge production by about ment (characterized by a plant volume of 0.26 m3/PE; 0.35 m3/PE if
30% (Sid et al., 2017). Looking at equation (1), by increasing SRT it anaerobic digestion is also included) whereas the second one on the
could be possible to reach a situation in which the biomass net pro innovative process having a specific plant volume of 0.19 m3/PE.
duction is close to zero (Amanatidou et al., 2016). In the conventional The main feature of MULESL system lies in the complete separation
activated sludge systems, however, this strategy could be significantly of the biomass from the liquid phase obtained in the same basin. While
hampered by the fact that the concentration of biomass cannot be biomass is confined to a dedicated zone of the basin (known as the
increased beyond a certain value due to its low settling velocity in the biomass compartment; 270 m3 volume), by means of porous plastic
secondary clarifier that would require very large sedimentation tanks. material (wheel shaped elements) packed between two metallic
Moreover, long SRT could have a negative effect on the sludge charac containment planes provided with suitable diffusers, the wastewater is
teristics and aeration costs for biomass suspension in the reactor (Sem circulated between the liquid phase compartment (400 m3), where air is
blante et al., 2014). The problem linked to the large dimensions of continuously supplied by a blower connected with membrane disc dif
secondary settler can be solved by using a membrane biological reactor. fusers, and the biomass compartment, where the biological degradation
Nevertheless, the problems due to the high concentrations of suspended processes occur. By this way, the treated sewage is always free of
biomass, which would require frequent membrane cleaning and biomass/solids and can be easily disposed of. Biomass compartment
replacement, and high aeration flows persist (Wei et al., 2003). includes a plenum chamber for the distribution of wastewater and air,
In the present paper a new treatment system, whose acronym is above which the porous plastic material is supported (see Fig. 1).
MULESL (MUch LEss SLudge; patent n. 102017000130809), is proposed The two compartments of MULESL basin are separated by means of a
and tested at full scale for reducing the quantity of sludge in the water concrete vertical partition lower than the perimeter walls of the basin so
line of the WWTP. The potentiality of MULESL system is due to the that the liquid can overflow from the biomass to liquid phase zone (see
particular type of biomass (a mixture of self-immobilized biofilm and Fig. 1). Additionally, the two compartments are connected to each other
granular biomass), generated adopting particular operating conditions, by means of a pipe and pumping means (pump PR in Fig. 1) which allow
and retained in a porous material filling part of the reactor volume (Di the liquid to be recirculated (at flow rate of 400 m3/h) from the bottom
Iaconi et al., 2010). Granular biomass is a particular type of biofilm that of the liquid phase zone to the plenum chamber of the biomass
displays different physical and chemical characteristics compared to compartment (see Fig. 1).
activated sludge (Di Iaconi et al., 2007; Winkler et al., 2018). Thanks to In addition to the aeration provided in the liquid phase
its particular and unique physical characteristics (high density and own
shape and volume), it could be used most of the voids of the porous Table 1
plastic material thus reaching long SRTs, without the need of the sedi Composition (in terms of mean � standard deviation and values range) of
mentation stage, thus maximizing maintenance metabolism. Further municipal sewage fed to MULESL unit during the whole experimental campaign.
more, MULESL is able to simplify the water line scheme since primary Parameter Mean value (�st. dev.) Value range
and secondary treatment steps are replaced by a single stage. MULESL
pH – 6.9 (�0.4) 5.3–7.6
system can be retrofitted to existing plants by converting the activated Conductivity μS/cm 1141 (�175) 823 1590
sludge stage as well as implementing new designs. COD mg/L 1162 (�461) 480 2352
In the present paper, the performances of the first MULESL full-scale CODsol mg/L 492 (�132) 170–877
installation, obtained by retrofitting an existing activated sludge basin, BOD5 mg/L 483 (�124) 270–710
TSS mg/L 538 (�319) 162 1723
were evaluated in terms of conventional pollutants and sludge produc
VSS mg/L 495 (�296) 100 1548
tion; the latter was compared with the one of conventional activated TKN mg/L 81.6 (�24.5) 39.4–164.0
sludge process treating the same municipal sewage. NH3 mgN/L 46.5 (�11.6) 28.0–96.2
TN mg/L 81.9 (�24.4) 39.4–164.0
Ptot mgP/L 12.3 (�4.5) 5.5–22.1
Porto mgP/L 5.9 (�2.4) 2.0–14.0
E.coli MPN/100 mL 1.1⋅108 (�0.5⋅108) 3.9⋅107 1.6⋅108
2
C. Di Iaconi et al. Journal of Environmental Management 269 (2020) 110714
Fig. 1. MULESL scheme. PR: recirculation pump; PF: feeding pump; PS: sludge extraction pump.
compartment, pure gaseous oxygen was dosed in the recirculation pipe during the recirculation step, measured by pressure probes, reaches 1
at a flow rate of 15 Nm3/h, in order to operate at dissolved oxygen bar. The operation consists in flushing, during idle step, compressed air
concentrations higher than saturation ones, thus accelerating the bio for several minutes through a dedicated pipe provided in the plenum
logical process and then improving its effectiveness. It should be noted chamber. The compressed air jet determines the detachment of a portion
that pure gaseous oxygen injection takes place in a closed volume, such of sludge from the plastic supporting material. The detached biomass
as the recirculation pipe connected to the plenum chamber, thus crosses the lower containment plane’s diffusers and settles on the bot
ensuring its complete dissolution. This allows to reduce the power de tom of the plenum chamber where is extracted as liquid sludge by
mand for the liquid phase compartment aeration that is known to be less activating a dedicated pump (pump PS in Fig. 1) provided with a flow
effective (conventional aeration systems usually dissolve no more than meter and sampling port in order to calculate le quantity of sludge
25% of the available oxygen). MULESL basin carries out consecutive extracted. The extraction of the sludge continues until a certain value of
sequences of 4 steps: feeding, recirculation, discharge and idle. During turbidity, measured at the exit of pump PS, will be reached.
the feeding step, sewage coming from equalization basin is sent by
means of the filling pump (at flow rate of 120 m3/h; pump PF in Fig. 1) in
2.2. Experimental campaign
the plenum chamber of the biomass compartment where it raises up to
the upper portion of the porous material, while is subjected to a filtration
MULESL unit was operated for 12 months. The experimental
with removal of suspended solids, and falls then in the liquid phase
campaign was split in two periods. The first period (period A), which
compartment. When a predetermined level in the liquid phase
lasted about 7 months, referred to the transformation of activated sludge
compartment is reached, also the recirculation pump is activated which
used as inoculum in the typical biomass of the system, made up of
begins to recirculate the liquid from the liquid phase zone to the biomass
biofilm and granules bounded in a plastic porous. Operating conditions
one, thus beginning the recirculation step, while the feeding pump
of MULESL basin during this period play a decisive role for the formation
continues to fill sewage in the plenum chamber of the biomass
and the maintenance in time of such biomass. Experiments carried out at
compartment. Therefore, feeding and recirculation steps are overlapped
laboratory scale have shown that periodicity with which wastewater is
for a certain time interval. When a second prefixed level in the liquid
pumped into the system, organic load applied to the biomass compart
phase zone is reached, the feeding pump stops while recirculation pump
ment and superficial up flow liquid velocity through the porous medium
continues to keep the liquid flowing from the liquid to the biomass
play a crucial role for obtaining and maintaining such biomass (Di Iaconi
compartment (recirculation step).
et al., 2005, 2010). Treatment sequences of 8 h were used while the OLR
During discharge step, the treated effluent (same volume fed) is
was stepwise increased up to 0.5 kg COD per m3 of biomass compart
extracted from the liquid phase compartment by the same pump used for
ment per day.
recirculation operation (i.e., PR in Fig. 1) acting valves installed on
Period B was aimed at improving treatment capability once the
recirculation/discharge pipe (see Fig. 1). Finally, during idle step, the
typical biomass was obtained. In particular, hydraulic loading to
plant is prepared to begin a new sequence of steps as the one described.
MULESL basin was progressively increased up to 375 m3/d.
Moreover, during idle step the cleaning operation of the biomass
compartment is carried out if needed. The alternation of the treatment
sequence steps is conveniently controlled by an automation system 2.3. Analytical methods
based on a microprocessor and a timer which manages the functioning of
the various devices interlocked to the plant: feeding pump, recirculation MULESL plant performances were evaluated in terms of traditional
pump, aeration/oxygenation system, extraction pump of the treated gross parameters removal efficiency and sludge production. The
effluent. following typical gross parameters were measured 2 to 3 times a week in
While MULESL unit continues to operate there is a continuous in influent and effluent samples of MULESL unit: chemical oxygen demand
crease in biomass concentration, due to its growth and retained sus (COD), soluble chemical oxygen demand (CODsol), biochemical oxygen
pended solids present in the sewage, which at high values can lead to a demand (BOD5), total suspended solids (TSS), volatile suspended solids
partial clogging of the biomass compartment. Increased biomass con (VSS), total Kjeldahl nitrogen (TKN), ammonia (NH3), nitrate (NO3 ),
centration also increases pressure of the liquid in the plenum chamber nitrite (NO2 ) and total nitrogen (TN), E. coli. The latter was used for
during filling/recirculation operations, as a result of the reduction in evaluating the effectiveness of MULESL unit as disinfection system.
porous material porosity. In order to avoid such drawback, a cleaning COD, BOD5 and TN were determined by means of Dr Lange test kits
operation is carried out whenever the pressure in the plenum chamber (COD: LCK314; BOD5: LCK555; TN: LCK238). CODsol was measured
after sample filtration through a 0.45 μm filter. NH3 was measured by
3
C. Di Iaconi et al. Journal of Environmental Management 269 (2020) 110714
Hemera analyser whereas TSS and VSS were determined using standard inner ones of the material and the ones generated by its packing in the
methods (APHA 2005). TKN was calculated as the difference between biomass compartment) instead continues to grow as separated entity
TN and oxidized nitrogen. NO3 and NO2 were determined by ion (inclusion biomass). While the quantity of biomass increases, by the
chromatography (Thermo Scientific Dionex Aquion). E. coli was detec increase in the biofilm thickness and in the dimensions of the inclusion
ted and quantified by Colilert-18 assay according to the manufacturer’s biomass, the porosity of the porous filling material is reduced, with
instructions (IDEXX, Laboratories, Inc., 2013). Colilert-18 is based on consequent increase of liquid rising velocity in the biomass compart
the most probable number (MPN) procedure; thanks to the simultaneous ment. The increase of the effective rising speed due to the reduction of
analysis of a large number of wells (49 large wells and 48 small wells) the porous material provides plug-flow conditions through the biomass
and high sample volume (100 mL), it is able to provide greater accuracy compartment which have a smooth action on the inclusion biomass
and repeatability (ISO 9308-2:2012). particles which take the typical rounded and bevelled shape of a river
The specific sludge production (SSP) of MULESL treatment was pebbles (from here the term granular biomass). Such rounded particles
calculated from sludge and removed COD mass balances carried out over reach such dimensions that they cannot go out from the pores where
the 12 months of operation. In particular, it was calculated by means of they are developed (third phase), i.e. they become granules trapped in
the following equation: the filling material. As expected, the features of the filling material (in
� � � � � � particular the sizes of inner and interstitial voids) have a decisive role in
� � TSSeff kgTSS
y
þTSS washing
kgTSS
y
þTSSbiomass compart
kgTSS
y
holding these granules (Di Iaconi et al., 2009). Plastic elements in the
kgTSS
SSP ¼ � � shape of wheel with 9 mm height, 12 mm diameter, 800 m2/m3 specific
area, 0.96 g/cm3 density, 0.85 bed porosity and 120–250 mm3 voids size
kgCODrem kgCOD
CODrem y
were used for this aim. Yet, the rising velocity of the liquid through the
(2) biomass compartment is another important operating parameter of
MULESL systems as it affects the plug-flow conditions and hydrody
where TSSeff is the amount of suspended solids discharged with the
namic shear forces, which play an important compacting action of the
effluent during the year (y) of operation, TSSwashing is the amount of
biomass (Di Iaconi et al., 2005). Geometric rising speed values (defined
suspended solids removed by washing operations during the year of
as the ratio between the recirculation flowrate between the liquid flow
operation, TSSbiomass compart is the amount of sludge accumulated in the
and biomass compartments and the geometric section of the biomass
biomass compartment during the experimental period , and CODrem is
compartment) ranging between 3 and 4 m/h were used. Finally, the
the amount of COD removed during the 12 months of MULESL
feeding periodicity and OLR represent additional crucial operational
operation.
parameters since they lead to the alternation of feast and famine con
TSSbiomass compart was calculated by performing, at the end of the
ditions, which improve the level of biomass compactness that is vital for
experimental campaign, an intensive washing operation in order to
the biomass concentration increase in the biomass compartment.
remove completely the biomass from the porous material filling the
Treatment sequences of 8 h were used while the OLR was stepwise
biomass compartment. The presence of any residual biomass in the
increased up to 0.5 kg COD per m3 of biomass compartment per day,
biomass compartment was carefully checked after the washing opera
obtained by a gradual increase of the volumetric loading rate. The latter
tion by opening the upper containment plane of the biomass compart
was increased, however, coherently with the effluent quality in order to
ment. The detached biomass was measured in terms of volume and dry
safeguard the discharge quality requirements. Therefore, during period
and volatile sludge concentration. TSSeff was calculated based on hy
A, the removal efficiencies exceeded 95% for COD and TSS, and 90% for
draulic loading applied to the unit and effluent suspended solid content.
TKN and TN, with residual concentrations in the effluent always much
TSSwashing was calculated by summing the amounts of sludge removed
lower than the discharge limits.
during the washing operations. CODrem was instead estimated from the
OLR values applied to MULESL basin during the whole period, then
3.2. MULESL plant performances
multiplying each by the respective duration in days and by the relative
average COD removal efficiency.
Once the typical biomass of MULESL system was achieved, the plant
SRT (d) of MULESL unit was calculated by the following equation:
continued to operate for additional 5 months in order to maximize the
� �
treatment capacity (period B). In particular, the hydraulic loading to the
TSSbiomass compart kgTSS � �
y d plant was progressively increased up to 375 m3/d. MULESL plant per
SRT ðdÞ¼ � � � � � � ⋅365
kgTSS kgTSS kgTSS y formances were evaluated in terms of conventional pollutants removal
TSSeff þTSSwashing y þTSSbiomass compart y
y efficiency and sludge production.
(3)
3.2.1. Sludge production
3. Results and discussion
As reported in section 2.3, SSP was calculated by means of equation
3.1. MULESL plant start-up (period A) (2). It should be noted that washing operations were never carried out
since the head loss set-point of 1 bar was never achieved while plant was
MULESL plant was operated for 12 months. During the first 7 months running (i.e., 12 months). Therefore, SSP was calculated taking into
(period A) selected operating conditions were applied for generating the account only the amount of sludge present in the biomass compartment
typical biomass of MULESL system, consisting in biofilm and granules at the end of experimental period (i.e., TSSbiomass compart) and the sludge
bounded in a plastic porous material, starting from activated sludge lost with the effluent (i.e., TSSeff) during the 12 months of operation.
inoculum. Experiments carried out at laboratory scale revealed that the TSSbiomass compart and TSSeff turned out to be equal to 7020 and 427 kg of
generation of such biomass occurs in three consecutive distinct phases dry sludge, respectively. Based on these values and applying equation
(see Fig. S1). In the first phase, the activated sludge used as inoculum is (3), a SRT of 340 d is obtained. Finally, taking into account the amount
trapped in the porous material filling the biomass compartment of the of COD removed during the experimental period (i.e., 59,724 kg) and
system. In the successive phase, the fraction of the activated sludge applying equation (2), a SSP value of 0.13 kg TSS/kg COD removed was
adhered on the surface of the porous material leads to the generation of a obtained, corresponding to 16 gTSS/PE⋅d. This value is 3–5 times lower
thin biofilm covering the surface of the filling material. The activated than that reported in the literature for biological treatment units, based
sludge trapped in the interstitial pores of the filling material (both the on activated sludge process (Metcalf and Eddy Inc., 2003; Foladori et al.,
2010; Velho et al., 2019).
4
C. Di Iaconi et al. Journal of Environmental Management 269 (2020) 110714
5
C. Di Iaconi et al. Journal of Environmental Management 269 (2020) 110714
Fig. 4. TSS concentration profiles of influent and effluent with TSS removal Fig. 6. NH3 concentration profiles of influent and effluent with NH3 removal
efficiency of MULESL unit over the time during period B. efficiency of MULESL unit over the time during period B.
6
C. Di Iaconi et al. Journal of Environmental Management 269 (2020) 110714
MULESL unit showed low phosphorus removal efficiencies as well (i.e., Collivignarelli, M.C., Abb� a, A., Miino, M.C., Torretta, V., 2019. What advanced
treatments can be used to minimize the production of sewage sludge in WWTPs?
on average, 12%). Removal efficiencies as high as 40% were also
Appl. Sci. 9, 2650.
recorded during some days, which can be ascribed to the filtering Di Iaconi, C., Ramadori, R., Lopez, A., Passino, R., 2005. Hydraulic shear stress
capability of MULESL towards particulate phosphorus. calculation in a Sequencing Batch Biofilm Reactor with granular biomass. Environ.
Sci. Technol. 39, 889–894.
Di Iaconi, C., Ramadori, R., Lopez, A., Passino, R., 2007. Aerobic granular sludge
4. Conclusions systems: the new generation of wastewater treatment technologies. Ind. Eng. Chem.
Res. 46, 6661–6665.
Di Iaconi, C., Del Moro, G., Lopez, A., Ramadori, R., 2009. The essential role of filling
A new treatment system, whose acronym is MULESL (MUch LEss material in aerobic granular biomass generation in a periodic submerged biofilter.
SLudge), was proposed and tested at full scale for reducing the quantity World Rev. Sci. Technol. Sustain. Dev. 6, 144–155.
of sludge in the water line of the sewage treatment plant. MULESL unit Di Iaconi, C., De Sanctis, M., Rossetti, S., Ramadori, R., 2010. SBBGR technology for
minimising excess sludge production in biological processes. Water Res. 44,
for 3500 PE, fed with the influent of the primary sedimentation of
1825–1832.
Putignano’s WWTP, was monitored for 1-year in terms of sludge pro Ferrentino, R., Langone, M., Merzari, F., Tramonte, L., Andreottola, G., 2016. A Review
duction and typical gross parameters removal. Solid and COD mass of anaerobic side stream reactor for excess sludge reduction: configurations,
balances carried out over the whole operating period gave a specific mechanisms and efficiency. Crit. Rev. Environ. Sci. Technol. 46 (4), 382–405.
Foladori, P., Andreottola, G., Ziglio, G., 2010. Sludge Reduction Technologies in
sludge production value of 0.13 kg of dry sludge per kg of COD removed. Wastewater Treatment Plants. IWA Publishing, London.
This value was 77% lower than that obtained for primary and secondary Gardoni, D., Ficara, E., Fornarelli, R., Parolini, M., Canziani, R., 2011. Long term effects
treatments of Putignano’s WWTP during the same period. Furthermore, of the ozonation of the sludge recycling stream on excess sludge reduction and
biomass activity at full-scale. Water Sci. Technol. 63 (9), 2032–2038.
MULESL sludge was already stabilized, being characterized by an Hao, X., Wang, Q., Zhu, J., van Loosdrecht, M.C.M., 2010. Microbiological endogenous
organic matter content of 60%. MULESL unit guaranteed high and stable process in biological wastewater treatment systems. Crit. Rev. Environ. Sci. Technol.
performances with mean removal efficiency higher than 95% for COD, 40 (3), 239–265.
ISO 9308-2:2012. Water Quality – Enumeration of Escherichia coli and Coliform Bacteria
BOD5, TSS, TKN, NH3 and TN Finally, MULESL unit also acted as a good – Part 2: Mostprobable Number Method.
disinfection system ensuring 2.5 to 2.7 log units removal of E.coli with Metcalf, Eddy Inc., 2003. Wastewater Engineering: Treatment, Disposal, Reuse, fourth
effluent concentrations of 4.4⋅104 to 7.2⋅104. ed. McGraw-Hill, New York.
Pilli, S., Bhunia, P., Yan, S., LeBlanc, R.J., Tyagi, R.D., Srampalli, R.Y., 2011. Ultrasonic
pretreatment of sludge: a review. Ultrason. Sonochem. 18, 1–18.
Declaration of competing interest Romero, P., Coello, M.D., Arag� on, C.A., Battistoni, P., Eusebi, A.L., 2015. Sludge
reduction through ozonation: effects of different specific dosages and operative
management aspects in a full scale. J. Environ. Eng. 141, 12.
The authors declare that they have no known competing financial
Russo, N., Marzo, A., Randazzo, C., Caggia, C., Toscano, A., Cirelli, G.L., 2019.
interests or personal relationships that could have appeared to influence Constructed wetlands combined with disinfection systems for removal of urban
the work reported in this paper. wastewater contaminants. Sci. Total Environ. 656, 558–566.
Saby, S., Djafer, M., Chen, G.H., 2002. Feasibility of using a chlorination step to reduce
excess sludge production in activated sludge process. Water Res. 36 (3), 656–666.
CRediT authorship contribution statement Seeger, E.M., Braeckevelt, M., Reiche, N., Muller, J.A., Kastner, M., 2016. Removal of
pathogen indicators from secondary effluent using slow sand filtration: optimization
approaches. Ecol. Eng. 95, 635–644.
Claudio Di Iaconi: Conceptualization, Supervision, Data curation, Semblante, G.U., Hai, F.I., Ngo, H.H., Guo, W., You, S.-J., Price, W.E., Nghiem, L.D.,
Writing - original draft. Marco De Sanctis: Investigation, Writing - 2014. Sludge cycling between aerobic, anoxic and anaerobic regimes to reduce
original draft. Valerio Guido Altieri: Data curation, Investigation. sludge production during wastewater treatment: performance, mechanisms and
implications. Bioresour. Technol. 155, 395–409.
Sid, S., Volant, A., Lesage, G., Heran, M., 2017. Cost minimization in a full scale
Acknowledgment conventional wastewater treatment plants: associated costs of biological energy
consumption versus sludge production. Water Sci. Technol. 76 (9), 2473–2481.
Sievers, M., Ried, A., Koll, R., 2004. Sludge treatment by ozonation-evaluation of full-
This work was partially supported by the Italian National PON scale results. Water Sci. Technol. 49 (4), 247–253.
TARANTO Project (ARS01_00637) and MANGIAFANGHI project Thwaites, B.J., Short, M.D., Stuetz, R.M., Reeve, P.J., Gaitan, J.-P.A., Dinesh, N., van den
(“Sludge reducing during municipal wastewater") funded by Puglia re Akker, B., 2018. Comparing the performances of aerobic granular sludge versus
conventional activated sludge for microbial log removal and effluent quality:
gion (Italy) within “Regional Technological clusters” call -FSC 2007/ implication for water reuse. Water Res. 145, 442–452.
2013. Velho, V.F., Andreottola, G., Foladori, P., Costa, R.H.R., 2019. The effects of a full-scale
anaerobic side-stream reactor on sludge decay and biomass activity. Water Sci.
Technol. 79 (6), 1081–1091.
Appendix A. Supplementary data Velho, V.F., Foladori, P., Andreottola, G., Costa, R.H.R., 2016. Anaerobic side-stream
reactor for excess sludge reduction: 5-year management of a full-scale plant.
Supplementary data to this article can be found online at https://doi. J. Environ. Manage. https://doi.org/10.1016/j.jenvman.2016.04.020.
Vera, I., S�aez, K., Vidala, G., 2013. Performance of 14 full-scale sewage treatment plants:
org/10.1016/j.jenvman.2020.110714. comparison between four aerobic technologies regarding effluent quality, sludge
production and energy consumption. Environ. Technol. 34 (15), 2267–2275.
Wang, Q., Wei, W., Gong, Y., Yu, Q., Li, Q., Sun, J., Yuan, Z., 2017. Technologies for
References
reducing sludge production in wastewater treatment plants: state of the art. Sci.
Total Environ. 587–588, 510–521.
Amanatidou, E., Samiotis, G., Trikoilidou, E., Tsikritzis, L., 2016. Particulate organics Wei, Y., Van Houten, R.T., Borger, A.R., Eikelboom, D.H., Fan, Y., 2003. Minimization of
degradation and sludge minimization in aerobic, complete SRT bioreactors. Water excess sludge production for biological wastewater treatment. Water Res. 37,
Res. 94, 288–295. 4453–4467.
Andreoli, C.V., Pegorini, E.S., Fernandes, F., Santos, H.F., 2007. Sludge Treatment and Winkler, M.-K.H., Meunier, C., Henriet, O., Mahillon, J., Su� arez-Ojeda, M.E., Del
Disposal. In: Cleverson, Von Sperling, Fernandes (Eds.). IWA Publishing, London, Moro, G., De Sanctis, M., Di Iaconi, C., Weissbrodt, D.G., 2018. An integrative review
UK, 2007. of granular sludge for the biological removal of nutrients and recalcitrant organic
AWWA, 2005. Standard Methods for the Examination of Water and Wastewater, twenty- matter from wastewater. Chem. Eng. J. 336, 489–502.
first ed. American Public Health Association, Washington.