IMPROVEMENT & RECONDITIONING OF LINK ROAD KHARAK  
DYKE LENGTH 2.5KM, DISTRICT MIRPUR 
 
 

CENTRAL DESIGN OFFICE


MUZAFFARBAD
CURRENT CONDITION:
a) Pavement:
i) Only surface cracks.
ii) Small land patches
 Longitudinal distress cracking.
 Raveling
 Block erosion
 Pot holes
iii) Minor base treatment at few locations.

Pictures Provided Below:

b) Geometry:
 20’ Carriage way with no shoulders.
c) Traffic Volume:
 Only LTV traffic.
 Occasional truck traffic (1 to 2 trucks per month)

CONSLUSION:

Pavement structure Rehabilitation recommended for extension of Pavement service Life.


REHABILITATION PROPOSAL:

1. Overlay (Approx. 2200m)


o 2” Asphalt overlay Class A (NHA Specifications) over tack coat.
2. Distress treatment + Overlay (Approx. 300m).
o Treatment of distresses if Distress level is high Replace base course.
o Replace base course.
o Provide 2” AWC above.

Assistant Engineer Highways Deputy Director Highways Director Highways