Professional Documents
Culture Documents
2. Target costing
3. Life-cycle costing
4. Throughput accounting
5. Environmental accounting
ADVANCED COSTING METHODS
THROUGHPUT ACCOUNTING
MODERN MANUFACTURING
• low stocks
Throughput accounting aims to make the best use of a scarce resource (bottleneck) in a JIT environment.
The aim of throughput accounting is to maximise this measure of profitability, whilst simultaneously reducing operating
expenses and inventory (money is tied up in inventory).
The goal is achieved by determining what factors prevent the throughput from being higher. This constraint is called a
bottleneck, for example there may be a limited number of machine hours or labour hours.
In the short-term the best use should be made of this bottleneck. This may result in some idle time in non-bottleneck
resources, and may result in a small amount of inventory being held so as not to delay production through the bottleneck.
In the long-term, the bottleneck should be eliminated. For example a new, more efficient machine may be purchased.
However, this will generally result in another bottleneck, which must then be addressed.
Main assumptions:
• The only totally variable cost in the short-term is the purchase cost of raw materials that are bought from external
suppliers.
• Direct labour costs are not variable in the short-term. Many employees are salaried and even if paid at a rate per
unit, are usually guaranteed a minimum weekly wage.
The bottleneck is the focus of management’s attention. Decisions regarding the optimum mix
of products must be undertaken.
Step 3 requires that the optimum production of the bottleneck activity determines the
production schedule of the non-bottleneck activities. There is no point in a non-bottleneck
activity supplying more than the bottleneck activity can consume. This would result in
increased work-in-progress (WIP) inventories with no increased sales volume
Process A B C
The long-run benefit to P Ltd of increasing sales of its product is a present value of $25,000 per additional
unit sold per week.
• (1) Invest in a new machine for process A, which will increase its capacity to 550 units per week. This
will cost $1 m.
• (2) Replace the machine in process B with an upgraded machine, costing $1.5m. This will double the
capacity of process B.
• (3) Buy an additional machine for process C, costing $2m. This will increase capacity in C by 300 units
per week.
Required:
Note: The above options are not mutually exclusive, so your answer should consider combinations as well
as looking at them individually.
THROUGHPUT CALCULATION
Hard Tiles recorded a profit of $120,000 in the accounting period just ended, using
marginal costing. The contribution/sales ratio was 75%.
Material costs were 10% of sales value and there were no other variable production
overhead costs. Fixed costs in the period were $300,000.
Required:
Solution
$
Profit 1,20,000
Fixed Cost 3,00,000
Contribution 4,20,000
Contribution/Sales Ratio 75%
Sales 5,60,000
Material Cost 10% 56,000
Throughput 5,04,000
ADVANCED COSTING METHODS
THROUGHPUT ACCOUNTING
Note: The total factory cost is the fixed production cost, including labour. The total
factory cost may be referred to as 'operating expenses'. These are production/factory
costs only. In the exam, watch if questions include costs not related to production (e.g.
marketing), which wouldn't be included in the ratio
• However, if ranking products or divisions across the company it would be suitable to look
at TPAR figures to reflect differences in costs between factories.
Criticisms of TPAR
• It concentrates on the short-term, when a business has a fixed supply of resources (i.e.
a bottleneck) and operating expenses are largely fixed. However, most businesses
can't produce products based on the short term only.
• It is more difficult to apply throughput accounting concepts to the longer- term, when
all costs are variable, and vary with the volume of production and sales or another cost
driver. The business should consider this long- term view before rejecting products with
a TPAR < 1.
• In the longer-term an ABC approach might be more appropriate for measuring and
controlling performance.
ADVANCED COSTING METHODS
THROUGHPUT ACCOUNTING
Example
Z Limited manufactures a product that requires 1.5 hours of machining. Machine time is a bottleneck
resource, due to the limited number of machines available. There are 10 machines available, and each
machine can be used for up to 40 hours per week.
The product is sold for $85 per unit and the direct material cost per unit is $42.50. Total factory costs are
$8,000 each week.
Calculate
Solution
Return per factory hour = ($85 – $42.50)/1.5 hours = $28.33
• Cost per factory hour = $50,000/20,000 hours = $2.50 Note: The operating
expenses of $50,000 are the total factory cost.
• increase the sales price for each unit sold, to increase the throughput per unit
• reduce material costs per unit (e.g. by changing materials or switching suppliers), to increase the
throughput per unit
• reduce total operating expenses, to reduce the cost per factory hour
• improve the productivity of the bottleneck, e.g. the assembly workforce or the bottleneck machine, thus
reducing the time required to make each unit of product. Throughput per factory hour would increase and
therefore the TPAR would increase.
• the time taken to make each product fell from 2 hours to 1.75 hours
• the operating expenses fell from $50,000 to $45,000. The following changes would take place:
Throughput per factory hour = $(13.5 – 3)/1.75 hours = $6.0
• Cost per factory hour = $45,000/20,000 hours = $2.25 TPAR = $6.0/$2.25 = 2.67
The usual objective in questions is to maximise profit. Given that fixed costs are unaffected by the production decision in the short run, the
approach should be to maximise the throughput earned.
Step 5: allocate resources using this ranking and answer the question.
Step 4:rank the products in order of the throughput per unit of the bottleneck
resource. If all products are made in the same factory, then the ranking can be done
on return/hour as the cost/hour will be the same; however if not the ranking is done
on TPAR.
Step 3:calculate the throughput per unit of the bottleneck resource for each
product.
Machine time is a bottleneck resource and the maximum capacity is 400 machine hours each week. Operating costs,
including direct labour costs, are $5,440 each week. Direct labour costs are $12 per hour, and direct labour workers are paid
for a 38-hour week, with no overtime.
• (a) Determine the quantities of each product that should be manufactured and sold each week to maximise profit and
calculate the weekly profit.
• (b) Calculate the throughput accounting ratio at this profit-maximising level of output and sales.
ADVANCED COSTING METHODS
Multi-product decision making THROUGHPUT ACCOUNTING
Solution(a)
Step 1: Determine the bottleneck constraint.
The bottleneck resource is machine time. 400 machine hours available each week = 24,000 machine minutes.
Step 2: Calculate the throughput per unit for each product.
20,500
24,000 5760
Operating Profit 5440
Profit 320
ADVANCED COSTING METHODS
THROUGHPUT ACCOUNTING
Multi-product decision making
Solution(b)
Total factory costs (excluding direct materials) are $150,000. The company cannot make enough of any of the products to
sa;sfy external demand en;rely as machine hours are restricted.
Which of the following ac/ons would improve the company’s exis/ng throughput accoun/ng ra/o?
• A Increase the selling price of product Z by 10%
• B Increase the selling price of product Y by 10%
• C Reduce the material cost of product Z by 5%
• D Reduce the material cost of product Y by 5%
Product X Product Y Product Z
Selling price per unit $60 $40 $20
Process P: Each machine produces 6 units an hour and Skye has 8 machines working at 90% capacity.
Process Q: Each machine produces 9 units per hour and Skye has 6 machines working at 85% capacity.
One of Skye products is Cloud. Cloud is not particularly popular but does sell at a selling price of $20
although discounts of 15% apply. Material costs are $5 and direct labour costs are double the material cost.
Cloud spends 0.2 hours in process P but 0.3 hours in process Q.
Process P output is 6 × 8 × 0.9 = 43.2 per hour. Process Q output is 9 × 6 × 0.85 = 45.9 per hour. In
the absence of other information, then process P is slower, and so is the bottleneck.
Throughput: $
Throughput accounting principles can be applied in both the private and public sectors.
1)Take an X-ray,
3) recall patients who need further investigation/tell others that all is fine.
The ‘goal unit’ of this organisation will be to progress a person through all three stages. The number
of people who complete all the stages is the organisation’s throughput, and the organisation should
seek to maximise its throughput. The duration of each stage, and the weekly resource available, is
as follows:
Process Time per patient (hours) Total hours available per week
From the above table, the maximum number of patients (goal units) who can be dealt with in each
process is as follows:
(1) Ensure there is no idle time in the bottleneck resource, as that will be detrimental to
overall performance (idle time in a non-bottleneck resource is not detrimental to overall
performance).
In this example, increasing the bottleneck resource, or the efficiency with which it is
used, might be relatively cheap and easy to do because this is a simple piece of
administration while the other stages employ expensive machinery or highly skilled
personnel. There is certainly no point in improving the first two stages if things grind to
a halt in the final stage; patients are helped only when the whole process is completed,
and they are recalled if necessary.
END OF SESSION