National Highways Authority of India
(Ministry of Road Transport and Highways)
Sh-s wi 6, Saet-10, acH, 7 Reet:
110075
G-5 & 6, Sector-10, Dwarka, New Delhi-110075
NHAI/Policy Guidelines/Miscellaneous Guidelines/2020
No. 18.53/2020, Dated 17" September, 2020
Subject: Issues encountered by Stakeholders during Implementation of Projects.
A detailed discussion was held with various stakeholders regarding issues encountered by
them during implementation of projects and on the basis of feedback/suggestions received from
them, following decisions were taken to address the issues raised by them for compliance by all
concerned:
si. Suggestion/Issue Decision taken ‘Action By
No.
‘A) GENERAL ISSUES
01. | Regular meetings at PIU level with | ROs & PDs to hold meetings through | All ROs and
AE/IE/Contractors through Video | VCs, especially during COVID Regime. PDs
Conferences.
| 02. | Clarification to be issued regarding | For various computations regarding | All ROs, PDs
Use of more than 3 digits after | progress percentage and related | and Finance
decimal in computation of various | payments, use of only 3 digits after | Officers in ROs
calculations regarding progress | decimal or as specified in the contract | and PTUs
percentage and related payments. | shall be used.
03. | Videography of Project at the time | NHAI may provide complete DPR | All CGM(T) and
of DPR and pre survey of Project | alongwith NSV/LIDAR data as per the | GM(T) at HQ.
should be provided to bidder along | availability to bidders. All ROs, PDs
with REP.
04, In case approved GAD of ROB is | Technical divisions shall ensure | All CGM(T) and
not available at the time of | approved GAD is avallable at the time | GM(T) at HQ,
| bidding, any deviation during | of bidding. However in case of any| All ROs, PDs
execution should be treated as | change in finally approved ROB
Change of Scope under the | drawing for execution compared to
Contract. drawing issued during bidding process,
the same shall be treated under CoS.
05. | Even after disbursement of the | PDs to ensure that after disbursement, | All PDs
Compensation, in many Projects, | proper documents related to taking
no document is available with | over of possession of land are obtained
HAI for taking over of possession | from CALAs/Revenue Authorities.
of land ftom land owner.
06, | Issuance of IPCs and payment | Timelines for IPC payment given in| All ROs, PDs
thereof as per the timeline and in | agreements should be strictly adhered | _and Finance
the manner provided in the | to. In case of deduction/ withholding of | Officers in ROs
agreement must be ensured, any payment, contractor should be duly | and PIUs
informed the reasons thereof. Further,
compliance of guidelines issued for
“Submission of bills related to project
payments of NHAI through PMS/Data
Lake Portal vide NHAI/Policy
Guidelines/ Project Payment/2020 No.
6.23/2020 dated 15" September, 2020
shall be ensured,
4
wemore than 90% progress has
_ already been achieved.
been achieved.
si. Suggestion/Issue Decision taken ‘Action By
No.
07. | Obligations of AE/IE to be strictly | ROs and PDs to ensure strict | All Os and
fulfilled / monitored such as | monitoring of obligations of AE/IE. PDs
providing Monthly Inspection
Report (the “Inspection Report”)
to the Authority and the
Contractor.
08. Payment of Miscellaneous Items in | In case all works are completed as per All ROs and
Schedule G and H. scope, payment against misc. items to PDs
be released without see
“4 additional details.
09, | Frequent extension of Bid Due | There shall not be more than 2| All CGM(T) and
|__| Date be avoided. extensions except in exceptional cases. | _GM(T) at HQ
B) CTS BAS IN OLD Mt EPC AC
01. Contrary to the provisions of NHAI | In case PD and RO have no material All ROs and
circular dated 02.08.2018, the | observation on AE's proposal, the date PDs
Provisional/ Completion certificate | proposed by AE may be agreed for
should be issued w.e.f. the date of | Provisional Certificate/ Completion
‘successful completion of the Tests, | Certificate.
as defined in Schedule K of
Agreement.
02. | NHAI, PIUs continue to insist on | The works once de-scoped, to be taken | _ All CGM(T),
the Contractor to take up works in | up with the mutual consent of both the | GM(T) at HQ &
some stretches after land is made | parties only. All PDs and
available even after de-scoping of ROs
works by competent authority.
03. In EPC Agreements, the Authority |_In future EPC bids, it may be All CGM(T),
insists for payment of electricity | incorporated that the Authority will GM(T) at HQ &
bill for highway lighting during | bear the cost of electricity charges of | All PDs and
maintenance period on the basis of | highway lighting. Ros
Manual provisions, which is
actually an obligation of a
Concessionaire in the O & M Period
in a PPP Agreement. 7
c) IREEME! SED ON ‘HYBRID MODI
01, | If EOT is necessary and granted | In case EoT is granted on Authority's | All CGM(T),
due to default of the Authority, | default, expenditure against | GM(T) at HQ &
maintenance of existing road | maintenance of the affected stretches | All PDs and
should be paid to the|of the existing road beyond the ROs
Concessionaire beyond Scheduled | scheduled completion date will be
__| Completion Date. borne by Authority,
02, C&G should be allowed _in | ROW demarcation and possession to be | All ROs & PDs
development period to identify any | allowed during Development Period.
encumbrances existing on the site,
03. | Applicability “oF Policy Circulars | The provisions of circulars issued by | All| CGM(T),
issued after Bid Due Date. NHAT after Bid Due date can be made | GM(T) at HQ &
applicable with mutual consent of both | All PDs and
the parties. ROs
04. | Circular dated 14.08.2020 of NHAT | Can be agreed on case to case basis | _AIlCGM(T),
with respect to reduction in scope | with mutual consent of both the GM(T) at HQ &
in HAM Projects should not be | parties, in case of HAM Projects, where All PDs and
applied for the projects where | more than 90% progress has already ROs
asi. Suggestion/Issue Decision taken ‘Action By
No.
COVID REI \TMNIRBHAI RAT
The Delegation of Powers in Para (ii) of Circular Policy No. 18,46/2020 dated 22.06.2020 is modified
to following extent
Relief Procedure Delegation of
: Powers
(i) [Extension “of Time —_to | Whenever an application is made by a | Project Director
Contractor/Concessionaire for | contractor/ concessionaire who is notin | for Extension of
meeting their obligation under the | default of any contractual obligations | Time of three
Contract for 03 months to upto 06 | and where FMC is invoked by a months
months depending on site | contractor/concessionaire and the
conditions. requirement of FMC are fulfilled,
interim/final extension of three months
of construction period without
imposition of any cost or penalty shall
be granted.
Extension of more than three months | Regional Officer
and upto 6 months may be decided and | for Extension of
granted without imposition of any cost | Time of more
or penalty based on specific| _ than three
circumstances of the case. months and
upto six.
months.
E] PROJECT PREPARATION
01. | Prior to finalization of Land] The DPR consultants are required to All PDs.
Acquisition Plan, the proposed | ensure correctness of land acquisition
centre line must be verified, process. All PDs to ensure that correct
alignment is transferred by DPR
| consultants on ground by demarcating
with reference points/boundary pillars,
02, | Provision of Sight Distance (ISD The plan and profile as well as | AllROs & PDs
and SSD) Schedule-B should clearly —show/
mention requirement of ISD or SSD.
ROs and PDs shall ensure the same at
the time of preparation of
or DPRs/Bidding documents.
03. | Location and type of Junctions to | The location and type of junctions | All ROs & PDs
be developed to be clearly defined | should be clearly mentioned in
in the Scope of Work and the | Schedule-B and required ROW to be
required ROW must be acquired. | acquired. ROs and PDs shall ensure the
same at the time of preparation of
DPRs/Bidding documents,
04. | Words “Tentative, approximate, | Schedule-B & C should clearly mention | All ROs & PDs
minimum etc.” must not be used in | the scope of work. ROs and PDs shall
defining the Scope ensure the same at the time of
preparation of DPRs/Bidding
documents.
05. Digitisation of survey conducted by | All survey data collected will be made All ROs and
various DPR consultants and | available to agencies, PDs to send | PDs, CGM(IT),
creation of data base under one | digitized data of their respective DPRs NHAI-HQ
platform needs to be done for all | to IT Division for uploading on DATA
projects PAN INDIA. Lake.
4/-=t—
si. ‘Suggestion/Issue
No.
Decision taken
‘Action By
06. [Provision for Rain Water
Harvesting should be clearly
defined in Scope of work in
Schedule B or C.
Schedule-B should clearly mention the
provision of Rain Water Harvesting
equirement in each project. ROs and
PDs shall ensure the same at the time
of preparation of | DPRs/Bidding
documents.
All ROs & PDs
07. | Standard drawings for Toll plazas,
| Toll Building, Way side amenities /
Service Areas, Truck bays/ Bus
bays, Traffic Aid post, Medical Aid
post/ROW boundary wall must be
issued to all bidders.
HAI to provide broad framework and
minimum — requirements. Detailed
architectural design should be based on
local characteristics. ROs and PDs shall
ensure the same at the time of
preparation of _-—_-DPRs/Bidding
documents,
AIIROs & PDS
08. | Scope of Works in the Project
should be precisely defined in
‘Schedule B & C.
Schedule-B & C should clearly mention
the scope of work. ROs and PDs shall
ensure the same at the time of
Preparation of + DPRs/Bidding
documents.
AILROs & PDs |
This issues with the approval of competent authority.
All Officers of NHAI HQ/RO/PIU/CMU
(Amarendra Kumar)
CGM(Coord)