Project Planner Period Highlight:1 Plan Actual % Complete Actual (beyond plan) % Complete (beyond plan)
PLAN PLAN ACTUAL ACTUAL PERCENT
ACTIVITY PREDECESSOR START DURATION START DURATION COMPLETE PERIODS 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 A Internal meeting (kick-off) 1 1 B Venue selection A 2 6 C Find a catering service B 8 5 D Negotiate with the catering companC 13 10 E Arranging the room(s) B 8 5 F Arranging the equipment E 13 5 G Programme content A 2 10 H Interactive activities A 2 15 I Programme logistics G, I 17 11 J List of participants A 2 6 K Delivery of invitations J 8 2 L Presenters and VIPs invitation J 8 2 M Liaise with presenters L 10 18 N Support participants L 10 18 O Invite media L 10 3 P Final set-up D, F, I, M, N, O 28 2 Q Reception and registration P 30 1 R Manage media presence P 30 1 S Registration P 30 1 T Support P 30 1 U Cleaning Q, R, S, T 31 1 V Debriefing and closure V 32 1