You are on page 1of 15

Renewable and Sustainable Energy Transition 1 (2021) 100005

Contents lists available at ScienceDirect

Renewable and Sustainable Energy Transition


journal homepage: www.elsevier.com/locate/rset

Full-Length Article

Onshore, offshore or in-turbine electrolysis? Techno-economic overview of


alternative integration designs for green hydrogen production into Offshore
Wind Power Hubs
Alessandro Singlitico∗, Jacob Østergaard, Spyros Chatzivasileiadis
Center for Electric Power and Energy (CEE), Department of Electrical Engineering, Technical University of Denmark (DTU), Kgs. Lyngby 2800, Denmark

a r t i c l e i n f o a b s t r a c t

Keywords: Massive investments in offshore wind power generate significant challenges on how this electricity will be inte-
Hydrogen grated into the incumbent energy systems. In this context, green hydrogen produced by offshore wind emerges as
Power-to-x a promising solution to remove barriers towards a carbon-free economy in Europe and beyond. Motivated by the
Energy islands
recent developments in Denmark with the decision to construct the world’s first artificial Offshore Energy Hub,
Offshore power
this paper investigates how the lowest cost for green hydrogen can be achieved. A model proposing an integrated
Electrolysis
Energy hubs design of the hydrogen and offshore electric power infrastructure, determining the levelised costs of both hy-
drogen and electricity, is proposed. The economic feasibility of hydrogen production from Offshore Wind Power
Hubs is evaluated considering the combination of different electrolyser placements, technologies and modes of
operations. The results show that costs down to 2.4 €/kg can be achieved for green hydrogen production offshore,
competitive with the hydrogen costs currently produced by natural gas. Moreover, a reduction of up to 13% of
the cost of wind electricity is registered when an electrolyser is installed offshore shaving the peak loads.

Introduction with penetrating the so-called hard-to-abate sectors (e.g. heavy-duty


road transport, aviation, shipping, and the steel industry), for which
Background more energy-dense carriers are required.
Water electrolysis, using green electricity to generate hydrogen, is a
Concrete actions to accelerate the transition to a net-zero greenhouse potential solution to these challenges. Storable for longer periods and
gas emissions society have been taken across the European Union (EU) in larger quantities than electricity, hydrogen can support the supply-
and beyond [1]. In February 2021, the Danish Parliament mandated the demand balance of the grid, help avoid grid reinforcements, and form
construction of the first artificial Energy Island in the North Sea as an ini- the basis of green fuels (e.g. methane, ammonia, and methanol) [12].
tial step to harvest the abundant far offshore wind potential [2,3]. This Acknowledging these benefits, EU members set the ambitious goal to
Energy Island [4] will act as a Hub, interconnecting 3 GW of offshore install electrolysers of 40 GW total capacity in Europe by 2030, and sup-
wind power plants (OWPPs) and transmitting the produced electricity port the installation of an additional 40 GW in the EU’s neighbourhood,
to shore, at much lower costs than OWPPs singularly connected to shore to have this imported to the EU [13].
[5] (Fig. 1).
Only in the EU, the OWPPs capacity is expected to increase from the
current 12 GW to 300 GW by 2050, of which 60 GW will be installed by Cost of green hydrogen produced through offshore electrolysis
2030 [7,8]. International consortia, including countries surrounding the
North Sea, are planning the next steps with the construction and future Despite the growing interest in hydrogen production, the literature
expansion of such offshore energy Hubs [9,10]. regarding offshore electrolysis using electricity produced from offshore
However, the integration of massive amounts of offshore wind intro- wind power is very limited. This is due to the cost of the electricity pro-
duces three main challenges. First, the high variability of wind power duced from offshore wind power parks, which has been higher than
production places the supply-demand grid balance at risk. Second, the other renewable resources. Today, the declining costs and the large
planned offshore installations require grid reinforcements in the order availability of offshore wind power makes this energy source a promis-
of billions of Euros [5,11]. Third, electricity will still face challenges ing option for the large-scale production of hydrogen. On the other hand,
offshore electrolysis has been seen as a promising solution to reduce the


Corresponding author.
E-mail address: alesi@elektro.dtu.dk (A. Singlitico).

https://doi.org/10.1016/j.rset.2021.100005
Received 20 May 2021; Received in revised form 20 August 2021; Accepted 24 August 2021
Available online 1 September 2021
2667-095X/© 2021 The Author(s). Published by Elsevier Ltd. This is an open access article under the CC BY license (http://creativecommons.org/licenses/by/4.0/)
A. Singlitico, J. Østergaard and S. Chatzivasileiadis Renewable and Sustainable Energy Transition 1 (2021) 100005

Abbreviations ELEN electrical energy


DES desalination unit
AC alternate current H hour
AEL alkaline electrolyser HS hub-to-shore
DC direct current HUB hub
HVDC high voltage direct current H2 hydrogen
OWPP offshore wind power plant IG inter-array grid
PEMEL proton exchange membrane electrolyser IN inlet
SOEL solid oxide electrolyser MAX maximum value
VSC voltage source converter MEAN mean value
MIN minimum value
Symbols NEQ non-equipment
A area, m2 OUT outlet
CapEx capital expenditures, M€ PIPE pipeline
CF capacity factor, % PS protected shore
CS cold start time, min RG real gas
D diameter, mm S section
DR discount rate, % ST station
e specific energy, kWh/m3 OWPP offshore wind power plant
E energy, GWh WAT water
f footprint, m2 Y year
L length, km
LCOE levelised cost of electricity, €/MWh
LCOH levelised cost of the hydrogen, €/kg
LT lifetime, -
OpEx operational expenditures, M€/a cost of the hydrogen delivered onshore and to minimise the investment
OH operating hours, h in the electrical grid connecting the OWPPs to shore.
N number, - Meier [14] performed a cost analysis for hydrogen production on
ṁ mass flow rate, kg/h an offshore platform in Norway, through electrolysis powered by a 100
m̃ molar mass, kmol/kg MW wind farm, resulting in a cost of production of 5.2 €/kg. Jepma and
M annual mass, kg/a Van Schot [15] found that hydrogen, produced on existing oil and gas
P power, GW platforms, can have a cost of 2.84 €/kg, considering a future scenario
p pressure, bar accounting for the rapid expansion of the offshore wind energy capacity
R ideal gas universal constant, kJ/kg/ K in the Dutch continental shelf of the North Sea, and also internalising
RC reference cost, - the savings due to the avoided grid extensions. In the following study,
RP reference power, MW Jepma et al. [16] calculated the cost of converting 100% of the power
RU reference unit, - of a wind farm to hydrogen in the order of 2.50–3.50 €/kg, using exist-
SF scale factor, - ing platforms and gas grids and total offshore conversion. If the saving
t time, h obtained by the avoided extension of the electrical grid are internalised
W water consumption, l/kg in the cost of the hydrogen, this would fall to 1–1.75€/kg.
T temperature, K Crivellari and Cozzani [17] presented an analysis of alternative
V̇ volumetric flowrate, m3 /h power-to-gas and power-to-liquid strategies for the conversion of off-
V volume, m3 shore wind power into different chemical energy vectors. The study
𝜑 power load, % showed that gaseous hydrogen produced offshore and transmitted
𝜂 efficiency, % through a new pipeline is the most expensive among the other alterna-
tives, with a cost of 212 €/MWh (equivalent to 6.4 €/kg), but it presents
Subscripts and superscripts the best performance in terms of CO2 equivalent emissions.
COMP compressor To date, the cost of producing both hydrogen and electricity from
EQ equipment a multi-GW offshore energy Hub, comprising multiple OWPPs, has not
ELEC electrolyser been assessed, and alternative topologies regarding the integration of
electrical and hydrogen infrastructure have not been explored.

Fig. 1. Evolution of the offshore power transmission infrastructure [6]. A, B: generic countries.

2
A. Singlitico, J. Østergaard and S. Chatzivasileiadis Renewable and Sustainable Energy Transition 1 (2021) 100005

Methodology

In Section 2.1, the alternative placements for the electrolyser are


described, characterising the offshore infrastructure necessary In Sec-
tion 2.2, the relation between the share of the electricity converted into
hydrogen and the share of the electricity delivered onshore is defined,
characterising the operations of the electrolyser. In Section 2.3, the units
of the equipment involved in the electrical and hydrogen infrastructures
are modelled, calculating the mass and energy balances between them,
defining their sizes. In Section 2.4, the techno-economic assessment of
the alternative placements configuration is carried out, considering the
calculated sizes of the equipment. The final result provides the LCOH
and the LCOE delivered onshore used to compare the different scenar-
ios. The model used is built in Matlab 2019b [22] and Cantera 2.4 [23].

Electrolyser placement

Three different electrolyser placements (Fig. 3), along with their re-
lated infrastructures, have been investigated:
Fig. 2. Original Hub position in the North Sea [21]. • Onshore: the electricity produced by all OWPPs is collected at the
Hub and transmitted to shore, where hydrogen is produced by a sin-
Motivation and objectives gle electrolyser, then compressed to grid pressure.
• Offshore: the electricity produced by all OWPPs is transmitted to
Considering that the production of green hydrogen will be closely the Hub, where hydrogen is produced by a single electrolyser, using
associated with the Offshore Energy Hubs, and the central role hydrogen desalinated seawater, then compressed and transported to shore via
is expected to play in the energy economy, one key question arises: how pipeline.
• In-turbine: the electrolysers, paired with desalination units, are lo-
can we achieve the lowest cost for green hydrogen delivered onshore?
To answer this question, this paper presents a holistic approach, cated inside or next to the tower of each wind turbine (WT). The pro-
proposing a techno-economic model which considers the complemen- duced hydrogen is transported to the Hub via pipelines that connect
tary design of both hydrogen and offshore electric power infrastructure, groups of WTs. On the Hub, the hydrogen is collected, compressed,
so far considered only separately [14–17]. Our approach allows us to and transported to shore via a pipeline.
identify the interactions and potential synergies between the two en-
Fig. 4 shows the flowchart of the configurations: onshore, offshore
ergy carriers, and determine the levelised cost of hydrogen (LCOH) and
and in-turbine. The placement of the electrolyser determines the section
electricity (LCOE). Our analyzes consider, among others, three main pa-
of the offshore power system at which the electricity is used, identified
rameters:
by the subscripts I, if in-turbine, II, if on the offshore Hub, III if onshore.
• the placement of the electrolyser: onshore, offshore or in-turbine;
• the share of the electricity routed towards hydrogen production: Electricity and hydrogen co-generation
“hydrogen-driven”, if priority is given to the electrolysers, or
“electricity-driven”, if only the excess electricity is directed to the When co-generating electricity and hydrogen, two opposite opera-
electrolysers; tion modes can be envisioned and they are described as follows:
• the type of electrolyser technology: alkaline, proton exchange mem-
• Hydrogen-driven: the electricity generated by the Hub firstly covers
brane, or solid oxide.
the nominal electrolyser capacity, while the remaining electricity is
The reference values for the calculated LCOH are the cost of grey and directed to shore. In this case, the electrolyser uses the base load
blue hydrogen. Grey hydrogen, produced from natural gas, costs 0.8–2.7 electricity production.
€/kg [18]; blue hydrogen, produced from natural gas as well but also • Electricity-driven: the electrolyser uses only the excess electricity
including the carbon capture, costs 1.3–2.4 €/kg [18]. The calculated generated. In this case, priority is given to covering the electricity
LCOE is compared with the current cost of offshore wind electricity in demand, and the electrolyser shaves the peak load.
Europe, which is 45–79 €/MWh [19].
These two alternative operation modes define different electrical en-
Case study and applicability to other regions ergy input for an electrolyser, due to the availability of the energy gener-
ated by the Hub. Hydrogen-driven operations ensure higher utilisation
The Hub and Spoke (H&S) configuration is a recently explored grid of the electrolyser, due to a more frequent electrical energy input, com-
connection system. This envisions the deployment of an offshore Hub, pared to electricity-driven operations, which rely on less frequent peaks
where AC-electricity from surrounding offshore wind power parks (OW- of energy production. An example of the effect of these two types of
PPs) is converted to DC, and then transported onshore via HVDC. For far operation on the electrolyser utilisation is represented in Fig. 5.
OWPPs, the H&S concept has been found more cost-effective than the The rate of utilisation of the electrolyser impacts on the cost of the
radial HVDC connections to individual wind OWPPs, benefiting from hydrogen produced. Therefore, this study analyzes these two types of
the economies of scale of collecting a large amount of power [20]. This operations and the whole range of possible hydrogen to electricity ra-
study proposes a reference case of a 12 GW Hub, as assumed by the tios: from 100% electricity and 0% hydrogen (no electrolyser installed)
North Sea Power Hub Consortium’s work [20], located 380 km from to 0% electricity and 100% hydrogen (or 12 GW electrolyser installed
Esbjerg (Denmark) [21] (Fig. 2). Although applied to a 12 GW Energy over a 12 GW Hub), resizing the electricity and hydrogen infrastructures
Island in the North Sea, the same objective of this study can be reached accordingly in each case.
for other regional contexts and different sizes, with the same method- The electric energy used for hydrogen at the section S, EPTX,S (t) is
ological process. calculated using Eq. (1).

3
A. Singlitico, J. Østergaard and S. Chatzivasileiadis Renewable and Sustainable Energy Transition 1 (2021) 100005

Fig. 3. Schematic representation of the electrolyser


placements.

𝐸𝑃 𝑇 𝑋,𝑆 (𝑡) = cluding their energy usage, E, and power, P, in units of gigawatt-hours
( ∑ ) and gigawatts, respectively.
⎧min 𝑃𝐸 𝐿𝐸 𝐶 ⋅ Δ𝑡, 𝐸𝐻𝑈 𝐵 (𝑡) − 𝑆𝑖=𝐼 𝐸𝐿𝑂𝑆 𝑆 ,𝑖 (𝑡) , 𝑖𝑓 ℎ𝑦𝑑𝑟𝑜𝑔𝑒𝑛 − 𝑑𝑟𝑖𝑣𝑒𝑛
⎪ ∑𝑆 (
⎨𝐸𝐻𝑈 𝐵 (𝑡) − 𝑖=𝐼 𝐸𝐿𝑂𝑆 ) 𝑆 ,𝑖 ( 𝑡 ) − min 𝑃 𝐻𝑈 𝐵 ⋅ Δ𝑡 − 𝑃 𝐸 𝐿𝐸 𝐶 ⋅ Δ𝑡, 𝐸𝐻𝑈 𝐵 (𝑡) (1)
⎪ ∑𝑆
⎩ − 𝐸
𝑖=𝐼 𝐿𝑂𝑆 𝑆 ,𝑖 ( 𝑡 ) , 𝑖𝑓 𝑒𝑙𝑒𝑐 𝑡𝑟𝑖𝑐 𝑖𝑡𝑦 − 𝑑𝑟𝑖𝑣𝑒𝑛 Offshore wind turbines
The Hub is assumed to be composed of wind turbines (WTs) of ca-
where EHUB (t) is the electricity generated by the entire Hub; PELEC is the pacity 15 MW [20], PWT . A representative hourly wind power yield is
nominal capacity of the installed electrolyser; ELOSS (t) is the sum of all generated from the hourly wind speed data from the Copernicus ERA5
the electric losses upstream of the electrolyser located at location S. Dataset [24], for the analyzed location, and considering the Interna-
Alternatively, the remaining electricity at the section S, EELEN,S (t), is tional Energy Agency’s specifications for a reference 15 MW turbine
calculated using Eq. (2). [25]. The summed hourly electricity production of each WT for an entire
year is identified as EHUB (t).
𝐸𝐸 𝐿𝐸 𝑁,𝑆 (𝑡) =
∑ (
⎧𝐸𝐻𝑈 𝐵 (𝑡) − 𝑆𝑖=𝐼 𝐸𝐿𝑂𝑆 𝑆 ,𝑖 (𝑡) − min 𝑃𝐸 𝐿𝐸 𝐶 ⋅ Δ𝑡, 𝐸𝐻𝑈 𝐵 (𝑡)
⎪ ∑𝑆 )
⎪ − 𝑖=𝐼 𝐸𝐿𝑂𝑆 𝑆 ,𝑖 (𝑡) , 𝑖𝑓 ℎ𝑦𝑑𝑟𝑜𝑔𝑒𝑛 − 𝑑𝑟𝑖𝑣𝑒𝑛 Inter-array grid
⎨ ( ∑𝑆 ) (2) The Hub is assumed to be constituted by a series of concentrically
⎪min 𝑃𝐻𝑈 𝐵 ⋅ Δ𝑡 − 𝑃𝐸 𝐿𝐸 𝐶 ⋅ Δ𝑡, 𝐸𝐻𝑈 𝐵 (𝑡) − 𝑖+𝐼 𝐸𝐿𝑂𝑆 𝑆 ,𝑖 (𝑡) , distributed OWPPs of 1 GW each. Each group of 5 WT, NWT , is then

⎩ 𝑖𝑓 𝑒𝑙𝑒𝑐 𝑡𝑟𝑖𝑐 𝑖𝑡𝑦 − 𝑑𝑟𝑖𝑣𝑒𝑛 connected to the Hub through 66 kV AC cables [20]. The length of each
string, LIG , is calculated as the sum of the distance between each WT,
Process design model LWT , and the average distance of each OWPP to the Hub, LHUB , using
Eq. (3), in units of kilometres.
Each technological unit is characterised in the following subsections,
( )
in which the main parameters of each technology are characterised, in- 𝐿𝐼𝐺 = 𝐿𝑊 𝑇 ⋅ 𝑁𝑊 𝑇 − 1 + 𝐿𝐻𝑈 𝐵 (3)

4
A. Singlitico, J. Østergaard and S. Chatzivasileiadis Renewable and Sustainable Energy Transition 1 (2021) 100005

Fig. 4. Flowchart of the three alternatives. Notes: only one group of WTs connected to the inter-array grid is represented, 𝐸𝐸 𝐿𝐸 𝑁 represents the total energy at each
section. WT: wind turbine; DES: desalination unit; ELEC: electrolyser.

The distance between each WT, LWT , is calculated using Eq. (4), in The electricity loss in the inter-array grid ELOSS,II (t) is calculated us-
units of kilometres. ing Eq. (8).

𝑃𝑊 𝑇 𝐸𝐿𝑂𝑆 𝑆 ,𝐼𝐼 (𝑡) = 𝑁𝑊 𝑇 ⋅ 𝐸𝐸 𝐿𝐸 𝑁,𝐼 (𝑡) ⋅ 𝜂𝐼𝐺 (8)
𝐿𝑊 𝑇 = 2 (4)
𝑃 𝑌𝑊 𝑇 where ηIG is the coefficient of electric energy loss in the inter-array grid,
assumed equal to 0.55% of the electric energy transmitted [27].
where PYWT is the power yield of the WT, assumed 4.5 MW/km2 [26].
The average distance of each n OWPP from the Hub, LHUB , is calcu-
lated using Eq. (5) in units of kilometres. HVDC transmission
| √ √ | √ The electric energy generated is collected on the Hub, on which the
1 |𝑛 𝑃𝑂𝑊 𝑃 𝑃 𝐴𝑂𝑊 𝑃 𝑃 ⋅ 4 | 𝑛 𝑃𝑂𝑊 𝑃 𝑃 4
𝐿𝐻𝑈 𝐵,𝑂𝑊 𝑃 𝑃 (𝑛) = ⋅ || ⋅ 2 −2 |+ ⋅2
| ⋅ (5) AC is converted into high voltage direct current (HVDC) through voltage
2 |4 𝑃 𝑌𝑊 𝑇 𝜋 | 4 𝑃 𝑌𝑊 𝑇 𝜋
| |
source converters.
The rated power for the offshore substation, HVDC cable and onshore
The nominal power of each string P̄ IG is calculated using Eq. (6).
substation PHVDC is the difference between the total power of the Hub
𝑃̄𝐻𝑈 𝐵 − 𝑃̄𝐸 𝐿𝐸 𝐶,𝐼 PHVDC and the total power capacity of the electrolyser PELEC if installed
𝑃̄𝐼𝐺 = (6) in-turbine or offshore.
𝑁𝐼𝐺
The electric energy loss in the HVDC transmission ELOSS,III is calcu-
where P̄ ELEC,I is the electrolyser total installed capacity at the location I, lated using Eq. (9).
of the infrastructure (i.e. in-turbine), equal to zero if the electrolyser is ( )
located elsewhere. NIG is the number of strings of the inter-array grid, 𝐸𝐿𝑂𝑆 𝑆 ,𝐼 𝐼 𝐼 (𝑡) = 𝐸𝐸 𝐿𝐸 𝑁 ,𝐼 𝐼 (𝑡) ⋅ 𝜂𝑆𝑇 ⋅ 𝑁𝐻𝑉 𝐷𝐶,𝑆𝑇 + 𝜂𝐻𝑆 ⋅ 𝐿𝐻𝑆 (9)
calculated using Eq. (7). where 𝜂 ST is the energy loss at the conversion station; NHVDC,ST is the
𝑃𝐻𝑈 𝐵 number of the substation, equal to 2; 𝜂 HS is the energy loss per km; LHS is
𝑁𝐼𝐺 = (7) the distance from the hub to the shore. In this case, 𝜂 ST is assumed to be
𝑃𝑊 𝑇 ⋅ 𝑁𝑊 𝑇

5
A. Singlitico, J. Østergaard and S. Chatzivasileiadis Renewable and Sustainable Energy Transition 1 (2021) 100005

operational, a cold start is assumed to be necessary for the operational


hour t.
ηELEC (t) is the efficiency of the electrolyser at the hour t. For ηELEC (t)
the nominal efficiency is considered (Table 1). The effect of the effi-
ciency degradation is calculated using Eq. (11).
( )
𝜂
𝜂𝐸 𝐿𝐸 𝐶 (𝑡 + 1) = 𝜂𝐸 𝐿𝐸 𝐶 (𝑡) ⋅ 1 − 𝐷𝐸𝐺 ⋅ 𝐵 (𝑡) (11)
1, 000
ηDEG is the degradation of the efficiency (Table 1). The number of op-
erational hours of the electrolyser is calculated using Eq. (12).
𝐿𝑇𝐻

𝑂𝐻 = 𝐵(𝑡) (12)
𝑡=1

where LTH is the lifetime of the plant in hours, in this case, assumed
equal to 8,760 per year for 30 years. During the lifetime of the plant,
the stack is replaced when 𝑡 = 𝑛 ⋅ 𝑂𝐻𝑀𝐴𝑋 for each n. Consequently, for
𝜂𝐸𝐿 (𝑛 ⋅ 𝑂𝐻𝑀𝐴𝑋 + 1), the nominal efficiency, 𝜂̄𝐸 𝐿𝐸 𝐶 , is restored.
The capacity factor of the electrolyser, CFEL , defined as the share of
operating hours of the electrolyser during its lifetime, is calculated using
Eq. (13).
Fig. 5. Duration curve of a 12 GW Hub, illustrating the hydrogen-driven and ∑𝐿𝑇𝐻
the electricity-driven operations. The green area identifies the electrical energy 𝐸𝐸 𝐿𝐸 𝐶 (𝑡) ⋅ 𝐵 (𝑡)
input of the electrolyser, in this example of 2 GW, for the two operation types. 𝐶 𝐹𝐻2 = 𝑡=1 (13)
𝑃𝐸 𝐿𝐸 𝐶 ⋅ Δ𝑡 ⋅ 𝐿𝑇𝐻
Dashed lines delimit the electrical energy input for a 4 GW electrolyser; the
orange area enclosed by the solid and dashed line represents the difference in The hydrogen mass flow rate is calculated using Eq. (14), in units of
the electrical energy input between a 2 GW and a 4 GW electrolyser in the same kilograms per hour.
operation mode.
𝐸𝐻2 (𝑡) ⋅ 106
𝑚̇ 𝐻2 (𝑡) = (14)
Table 1 𝐿𝐻 𝑉𝐻2
Electrolyser system operational parameters for alkaline (AEL), proton exchange
Membrane (PEMEL) and solid oxide electrolyser (SOEL).
where 𝐿𝐻 𝑉𝐻2 is the lower heating value of the hydrogen, equal to
33.3 kWh/kg.
AEL PEMEL SOEL Refs.
Operating pressure, pELEC [bar] 30 55 5 [29,30]
Operating temperature, TELEC [°C] 80 85 675 [30] Desalination unit
System electrical efficiency∗ , 𝜂̄𝐸 𝐿𝐸 𝐶 [%] 66 62 79 [30] If offshore or in-turbine, the water for the electrolyser system shall
Stack operating time, OHMAX [h] 82,500 85,000 61,320 [30,31] be supplied by a desalination unit. In this analysis, it is assumed that
Load range, 𝜑𝑀 𝐼 𝑁 -𝜑𝑀𝐴𝑋 [% 𝑃̄𝐸 𝐿𝐸 𝐶 ] 10–110 0–160 0–100 [29,30]
the desalination unit is based on reverse osmosis. The volumetric flow
Cold start up (after 24h stop), CS [min] 20 5 60 [30,32]
Degradation, 𝜂𝐷𝐸𝐺 [%/1,000 h] 0.10 0.10 0.50 [33]
rate of the water is calculated using Eq. (15), in units of cubic metres
Plant footprint, fELEC [m2 /GW] 95,000 48,000 7,000 [29,30] per hour.

On a lower heating value (LHV) basis; including the energy consumption of the 𝑉̇ 𝐻2 𝑂 (𝑡) = 𝑚̇ 𝐻2 (𝑡) ⋅ 𝑊𝐷𝐸𝑆 ⋅ 10−3 (15)
electrolyser stacks, gas water separators, demisters, gas drying, water manage-
ment, lye system (for AEL), system control, power supply [32]. where WDES is the water consumption for each kilogram of hydrogen
produced, assumed to be 15 l of water per kilogram of hydrogen [34].
The nominal volumetric flow rate of the desalination unit, 𝑉̄𝐷𝐸𝑆 , is as-
equal to 1% [28]; 𝜂 HS is assumed to be 0.0035% [28]; LHS is estimated sumed to be the maximum value of 𝑉̇ 𝐻2 𝑂 (𝑡).
to be 380 km from the Hub location to the Denmark shore [21]. The electric energy consumption of the desalination unit is calcu-
lated using Eq. (16).
Electrolyser system 𝐸𝐷𝐸𝑆 (𝑡) = 𝑉̇ 𝐻2 𝑂 (𝑡) ⋅ 𝑒𝐷𝐸𝑆 ⋅ 10−6 (16)
In this work, the three main types of electrolysers are analyzed,
whose operational parameters used in the model for the main electrol- where eDES is the energy consumption per cubic meter of water pro-
yser technologies are listed in Table 1. cessed, assumed to be 3.5 kWh m-3 [29].
The chemical energy of the hydrogen produced, EH2 (t), is calculated
using Eq. (10). Compression unit
The hydrogen produced is compressed into a pipeline. The formula
𝐸 𝐻 2 (𝑡 ) = for adiabatic compression [35], Eq. (17), is used to calculate the re-
( ∑24 ) quired energy, ECOMP (t).
⎧𝐸 𝐶𝑆 1 1−𝐵 (𝑡−𝑖)
( 𝑡 ) ⋅ 𝜂 ( 𝑡 ) ⋅ 1 − ⋅ ,
⎪ 𝐸 𝐿𝐸 𝐶 𝐸 𝐿𝐸 𝐶
286.76 ⋅ 𝑚̇ 𝐻2 (𝑡) ⋅ 𝑇𝑀𝐸𝐴𝑁 ( 𝛾 ⋅ 𝑁𝑆𝑇 )
60 24
⎨ 𝑃𝐸 𝐿𝐸 𝐶 ⋅ Δ𝑡 ⋅ 𝜑𝑀 𝐼 𝑁 ≤ 𝐸𝐸 𝐿𝐸 𝐶 (𝑡) < 𝑃𝐸 𝐿𝐸 𝐶 ⋅ Δ𝑡
(10)
⎪ 𝐸𝐶𝑂𝑀𝑃 (𝑡) = ⋅
⎩0 , 𝐸𝐸 𝐿𝐸 𝐶 (𝑡) < 𝑃̄𝐸 𝐿𝐸 𝐶 ⋅ Δ𝑡 ⋅ 𝜑𝑀 𝐼 𝑁 𝜂𝐶𝑂𝑀𝑃 ⋅ 𝐺𝐻2 ⋅ 3.6 ⋅ 109 𝛾 −1

⎡( 𝑝 ) 𝛾−1
𝛾⋅𝑁𝑆𝑇

where P̄ ELEC is the nominal capacity of the electrolyser; φMIN is the 𝐶𝑂𝑀𝑃 ,𝑂𝑈 𝑇
⋅⎢ − 1⎥ ⋅ Δ𝑡 (17)
minimum partial capacity of the electrolyser; CS is the cold start time ⎢ 𝑝𝐶𝑂𝑀 𝑃 ,𝐼 𝑁 ⎥
⎣ ⎦
in units of minutes; B is a Boolean parameter, whose value indicates
the operation of the electrolyser at the hour t-i, where B(t − i) = 1 if where 𝜂 COMP is the compression efficiency, assumed to be 50% [34] due
EHYD (t − i) > 0 (or the electrolyser is on), or B(t − i) = 0 (or the elec- to frequent load variations; 𝛾 is the ratio between the specific heat ca-
trolyser is off) otherwise. If for consecutive 24 h the electrolyser is not pacities for hydrogen (𝛾 = cp/cv); NST is the number of compression

6
A. Singlitico, J. Østergaard and S. Chatzivasileiadis Renewable and Sustainable Energy Transition 1 (2021) 100005

Fig. 6. LCOH, LCOE and CF for the hydrogen-driven operation. CF- is the capacity factor of the electricity infrastructure (i.e. HVDC transmission cable, HVDC
converters, substations, etc.) from the Hub to shore.

Fig. 7. LCOH, LCOE and CF for the electricity-driven operation. CF-El is the capacity factor of the electricity infrastructure (i.e. HVDC transmission cable, HVDC
converters, substations, etc.) from the Hub to shore.

stages, for simplicity assumed as 1; 𝐺𝐻2 is the gas gravity of the hydro- The nominal power of the compressor, P̄ COMP , is assumed to be the
gen, 0.0696, defined as the molar mass of hydrogen divided by the mo- maximum value of ECOMP (t) per hour.
lar mass of air; TMEAN is the mean temperature, assumed to be 285.15 K
[36]. Hydrogen pipeline
The three placements of the electrolyser determine the value of The sizes of the pipelines, from the WTs to the Hub and from the
pCOMP,IN and pCOMP,OUT : Hub to shore, are determined using Eq. (18) [35]
√ ( )

( ) √ 𝐷 5 ⋅ 𝑝2 − 𝑝2𝑃 𝐼𝑃 𝐸,𝑂𝑈 𝑇
( ) 1.1494 ( −3 ) 𝑇𝑏 √ 𝑃 𝐼𝑃 𝐸,𝐼𝑁
𝑉̇ 𝐻2 𝑇𝑏 , 𝑝𝑏 = ⋅ 10 ⋅ ⋅2 √
• Onshore: pCOMP,IN = pELEC (Table 1), pCOMP,OUT = pTRANS (assumed 24 𝑝𝑏 𝑍𝑀𝐸𝐴𝑁 ⋅ 𝑇𝑀𝐸𝐴𝑁 ⋅ 𝐺𝐻2 ⋅ 𝐿 ⋅ 𝜆
to be 70 bar).
(18)
• Offshore: pCOMP,IN = pELEC (Table 1), pCOMP,OUT = pPIPE,IN .
• In-turbine: pCOMP,IN = pPIPE,OUT , as outlet pressure of the pipeline where V̇ H2 (Tb , pb ) is the volumetric flowrate of the hydrogen at standard
connecting the string of WTs to the Hub, pCOMP,OUT = pPIPE,IN , as the conditions (Tb =288.15 K, Pb = 1 bar [35]), in units of cubic metres per
inlet pressure of the pipeline connecting the Hub to shore. hour; pPIPE,IN and pPIPE,OUT are the upstream and downstream pipeline
• The values of pPIPE,OUT and pPIPE,IN are determined in the following pressures in units of kilopascals; ZMEAN is the dimensionless compress-
subsection. ibility factor; 𝜆 is the dimensionless coefficient of friction; L is the length

7
A. Singlitico, J. Østergaard and S. Chatzivasileiadis Renewable and Sustainable Energy Transition 1 (2021) 100005

Fig. 8. Median LCOH obtained by a perturbation of ± 25% of the CapEx of each component. Median LCOH: the median of the LCOHs calculated considering 0.5 GW
to 12 GW electrolyser installed capacities.

Fig. 9. Median LCOH per distance of the Hub to shore.

of the pipeline in units of kilometres; D is the inner diameter of the units of square metres.
pipeline in units of metres.
Pipelines from the OWPPs to the Hub and from the Hub to shore are 𝐴𝐻𝑈 𝐵 = 𝑃𝐻𝑉 𝐷𝐶 ⋅ 𝑓𝐻𝑉 𝐷𝐶 + 𝑃𝐸 𝐿𝐸 𝐶 ⋅ 𝑓𝐸 𝐿𝐸 𝐶 (19)
deployed, having the following values: where fHVDC is the footprint of the offshore substation, here assumed to
be 4’860 m2 /GW [37], and fELEC is the footprint of the electrolyser. The
• For the pipelines from the OWPPS to the Hub: L = LIG ,
volume of the sand used to build the island, VHUB , and the area of the
pPIPE,IN = pELEC
shoreline assumed to be protected, APS , are simplified considering the
• For the pipelines from the Hub to shore: L = LHS , pPIPE,OUT = 70 bar
island has the shape of a truncated cone.
The volume of the hub, 𝑉𝐻𝑈 𝐵 , is calculated using Eq. (20).
See Appendix A for further details on the pipeline sizing.
1 ( )
𝑉𝐻𝑈 𝐵 = ⋅ 𝑠 ⋅ 𝜋 ⋅ 𝑟𝑆𝐵 3 − 𝑟𝐻𝑈 𝐵 3 (20)
3
Artificial island
where rHUB is the radius at the surface level, and rSB is the radius at the
The Hub hosting the offshore equipment is assumed to be a sand
seabed level, in units of metres, calculated using Eq. (21) and Eq. (22),
island, as this is considered to be more cost-effective than other types
respectively.
of offshore platforms in the case of a large hub in shallow waters [9].
The Hub shall have a surface, AHUB , able to host the HVDC offshore √
𝐴𝐻𝑈 𝐵
substation and the electrolyser. AHUB is calculated using Eq. (19), in 𝑟𝐻𝑈 𝐵 = (21)
𝜋

8
A. Singlitico, J. Østergaard and S. Chatzivasileiadis Renewable and Sustainable Energy Transition 1 (2021) 100005

Table 2
Levelised cost of the energy and levelised cost of the hydrogen equations. Note:
LCOEIII is also the final cost of the electricity delivered onshore.

Symbol Value Eqs.


𝐿𝑇𝑌 𝐿𝑇𝑌
∑ 𝐶𝑎𝑝𝐸 𝑥𝐸 𝐿𝐸 𝑁 ,𝐼 ,𝑌 +𝑂𝑝𝐸 𝑥𝐸 𝐿𝐸 𝑁 ,𝐼 ,𝑌 ∑ 𝐸𝐻𝑈 𝐵,𝑌
𝐿𝐶𝑂𝐸𝐼 (1+𝐷𝑅) 𝑌 ∕ (1+𝐷𝑅) 𝑌 (24)
𝑌 =0 𝑦=0
𝐿𝑇𝑌 𝐿𝑇𝑌
∑ 𝐿𝐶 𝑂𝐸𝐼 ⋅𝐸𝐸 𝐿𝐸 𝑁 ,𝐼 ,𝑌 + 𝐶 𝑎𝑝𝐸 𝑥𝐸 𝐿𝐸 𝑁 ,𝐼 𝐼 ,𝑌 +𝑂𝑝𝐸 𝑥𝐸 𝐿𝐸 𝑁 ,𝐼 𝐼 ,𝑌 ∑ 𝐸𝐸 𝐿𝐸 𝑁 ,𝐼 ,𝑌 −𝐸𝐿𝑂𝑆 𝑆 ,𝐼 𝐼 ,𝑌
𝐿𝐶𝑂𝐸𝐼𝐼 (1+𝐷𝑅)𝑌
∕ (1+𝐷𝑅)𝑌
(25)
𝑦=0 𝑌 =0
𝐿𝑇𝑌 𝐿𝑇
∑ 𝐿𝐶 𝑂𝐸𝐼𝐼 ⋅𝐸𝐸 𝐿𝐸 𝑁 ,𝐼 𝐼 ,𝑌 +𝐶 𝑎𝑝𝐸 𝑥𝐸 𝐿𝐸 𝑁 ,𝐼 𝐼 𝐼 ,𝑌 +𝑂𝑝𝐸 𝑥𝐸 𝐿𝐸 𝑁 ,𝐼 𝐼 𝐼 ,𝑌 ∑ 𝐸𝐸 𝐿𝐸 𝑁 ,𝐼 𝐼 ,𝑌 −𝐸𝐿𝑂𝑆 𝑆 ,𝐼 𝐼 𝐼 ,𝑌
𝐿𝐶𝑂𝐸𝐼 𝐼 𝐼 (1+𝐷𝑅)𝑌
∕ (1+𝐷𝑅)𝑌
(26)
𝑌 =0 𝑌 =0
𝐿𝑇𝑌 𝐿𝑇𝑌
∑ 𝐿𝐶 𝑂𝐸𝑠 ⋅𝐸𝑃 𝑇 𝑋,𝑆,𝑌 +𝐶 𝑎𝑝𝐸 𝑥𝑃 𝑇 𝑋,𝑌 +𝑂𝑝𝐸 𝑥𝑃 𝑇 𝑋,𝑌 ∑ 𝑀𝐻2 ,𝑌
𝐿𝐶𝑂𝐻 (1+𝐷𝑅)𝑌
∕ (1+𝐷𝑅)𝑌
(27)
𝑌 =0 𝑌 =0

Inversely, PEMEL achieves higher capacity factors (CFs) mainly due


𝑟𝑆𝐵 = 𝑟𝐻𝑈 𝐵 + ℎ∕𝑠 (22) to its lower electric consumption: PEMEL operates at a higher pressure,
55 bar [29], which limits the use of an external compression unit. This
where s is the slope of the truncated cone, assumed to be 75%; h is
allows a higher share of electricity to be used for hydrogen production
the depth of the seabed, assumed 30 m [20] to which is added 10% of
compared to AEL and SOEL.
elevation, to be over the sea level.
AEL’s lower LCOH compared with PEMEL and SOEL transcends
Moreover, the area of the shoreline assumed to be protected, APS , in
across all operating and placement scenarios in this article. Therefore,
units of square metres, is calculated, using Eq. (23).
for the sake of readability, the next sections refer only to the results as-
√ ( ) sociated with AEL, while the results for each type of electrolyser can be
𝐴𝑃 𝑆 = 𝜋 ⋅ 𝑟𝑆𝐵 2 + 𝜋 ⋅ 𝑟𝑆𝐵 ⋅ 𝑟𝑆𝐵 2 ⋅ 1 + 𝑠2
found in the Supplementary Material.
√ ( )
−𝜋 ⋅ 𝑟𝐻𝑈 𝐵 2 − 𝜋 ⋅ 𝑟𝐻𝑈 𝐵 ⋅ 𝑟𝐻𝑈 𝐵 2 ⋅ 1 + 𝑠2 (23)
Hydrogen-driven operation mode
Techno-economic analysis
The main results for the hydrogen-driven operation are presented in
The LCOE and the LCOH are used to compare the alternative config- Fig. 6. Three main factors affect the LCOH: the utilisation of the infras-
urations and calculated as shown in Table 2. The LCOE at each section tructure, the cost of the electricity supplied to the electrolyser, and the
of the electric power infrastructure is calculated using Eq. (24)–(27) and economies of scale for the different components.
expressed in units of Euro per megawatt-hour of electricity. The LCOH The utilisation of hydrogen or electricity infrastructures can be de-
is calculated using Eq. (27) and expressed in units of Euro per kilogram scribed by their CF. For the hydrogen-driven operation, the larger the
of hydrogen produced. electrolyser installed capacity, the lower its CF (Fig. 5). The CF is af-
DR is the discount rate, which reflects the financial return and the fected in two ways by the placement of the electrolyser. On one side,
project risk, here assumed to be 5% [16]; LTY is the lifetime of the the lower the electrical consumption of the ancillary equipment asso-
project as the lifetime of the system, 30 years [20]; EELEN , ELOSS and ciated with that placement is (i.e. desalination and compression units),
𝑀𝐻2 are the electric energy, energy loss and mass of hydrogen cumu- the more electricity is used by the electrolyser, increasing its CF. On
lated over the year Y. CapEx and OpEx are the sum of the CapEx and the other side, the more components of the electricity infrastructure up-
OpEx of each component deployed in the electric and PtX infrastructure stream of the electrolyser are, the larger the electrical losses are, reduc-
in the year Y. See Appendix B,Table B.1, for the details of the costs of ing the CF of the electrolyser.
each component. A second driver for the LCOH is the cost of the electricity supplied
It is important to notice that the electric energy used for hydrogen to the electrolyser. The use (or not) of the inter-array grid and HVDC
production, 𝐸𝑃 𝑇 𝑋,𝑆 , is considered to have a cost equal to the LCOES infrastructure, along with the associated electricity losses, to transport
calculated at the location S of the electric power infrastructure where electricity to the electrolyser determines the cost of the electricity used.
the electrolyser, desalination unit and compression unit are located. Therefore, the cost of electricity used by the electrolysers placed on-
shore is higher than the cost of electricity used by same-sized electrol-
Results and discussion ysers placed offshore, not using the offshore HVDC infrastructure, or
in-turbine, not even using an inter-array grid infrastructure.
Electrolyser technology comparison The third driver is associated with the economies of scale related
to the electrolysers and the pipelines. Because of their modularity, the
Among the three electrolyser technologies, AEL presents the lowest economies of scale of the electrolyser are evident only for sizes lower
LCOH, due to a better trade-off between costs and operational parame- than 100 MW, becoming highly noticeable for sizes lower than 10 MW
ters, but with only negligible differences in comparison to PEMEL and [33]. Therefore, in-turbine electrolysers, having capacities necessarily
SOEL. A significant difference in the LCOHs is observed in the in-turbine below the size of the WT (15 MW), are affected more strongly by
placement, in which SOEL register a higher LCOH. The full LCOH com- economies of scale.
parison between the three technologies and visualisations are provided In the case of pipelines of the same length, increasing the diameter,
in the Supplementary Material. the cost per capacity decreases. Therefore, in the case of small scales in-
This is due to the combined effects of higher CapEx for small sizes, turbine placement, the LCOH is penalised by a large number of pipelines
due to economies of scale, and lower operating pressure, which requires from the OWPPs to the Hub.
the use of external additional compression, absorbing part of the electric As shown in Fig. 6.A, placing the electrolyser on the Hub achieves
energy directed to hydrogen production, thus decreasing its hydrogen the lowest LCOH, with a minimum of 2.4 €/kg. Irrespective of the in-
production. Another major weakness of SOEL is the higher degradation stalled capacity, offshore electrolysis can produce hydrogen at a cost-
rate of its stack, which leads to a more frequent replacement compared competitive with the grey hydrogen. Fig. 6.B shows how LCOE varies
to the other two technologies. Therefore, despite the higher efficiency, with different electrolyser placements and installed capacity. In the case
the LCOH for SOEL is greater compared to the other two technologies. of hydrogen-driven operation, as the electrolyser capacity increases, the

9
A. Singlitico, J. Østergaard and S. Chatzivasileiadis Renewable and Sustainable Energy Transition 1 (2021) 100005

utilisation of the electricity infrastructure (i.e. CF-𝐸𝑙) decreases; this re- Moreover, for the in-turbine placement, both the pipeline and the
sults to LCOE increasing when large amounts of hydrogen are produced, compressor costs have a more significant impact compared to the other
in case the electrolyser is placed offshore or in-turbine. Besides the lower placements. This happens because, first, several small pipelines need
CF, the main driver for this increase is the fixed costs of HVDC and inter- to be installed to transfer the produced hydrogen from the OWPPs to
array cables, which heavily depend on their length and significantly the Hub, and second, due to pressure losses in these pipelines, larger
less on their capacity. Moreover, as expected, in case the electrolyser compressor capacities are needed on the Hub when compared to the
is placed onshore, the LCOE remains unaffected. For the largest part of offshore and onshore placements.
installed electrolyser capacities, LCOE remains widely competitive with It is also very interesting to observe that the costs of the desalination
current offshore wind installations, with the lowest LCOE estimated at unit and the artificial island have a negligible effect on the LCOH, both
45 €/MWh. in the hydrogen-driven and the electricity-driven operation.
In the case of the electricity-driven operation, the impact of the elec-
Electricity-driven operation mode trolyser is larger compared to the hydrogen-driven mode. This is be-
cause, at a parity of installed capacity (and CapEx), having a lower CF
Fig. 7 presents the LCOH and LCOE for the electricity-driven mode compared to the hydrogen-driven operation, the electrolyser produces
of operation. As the capacity of the electricity infrastructure is reduced, less hydrogen, thus resulting in a higher cost per unit of kilogram of
and – similar to the hydrogen-driven operation – the installed electrol- hydrogen delivered. Therefore, a change in the cost of the electrolyser,
yser capacity is increased by an equal amount, two effects are detected. and the hydrogen pipelines, affects more heavily the LCOH.
First, the utilisation of the offshore electricity infrastructure will al-
ways be higher than that of hydrogen (CF-𝐸𝑙> CF-𝐻2 ). The lower the
Impact of the distance from shore
electricity infrastructure capacity is (illustrated by a larger electrolyser
Since the exact location of the first Hub is still uncertain and several
capacity in Fig. 7.B), the higher the CF-𝐸𝑙 is, and, consequentially the,
Hubs are expected to be constructed in the North Sea, in this section, the
lower the LCOE will be. The minimum LCOE across all electrolyser
impact of the distance of the Hub from shore on the median LCOH was
placements is 39.4 €/MWh, achieved by offshore electrolysis. Compar-
investigated. This analysis is, therefore, limited to all the components
ing this with the case in which no electrolyser is installed highlights the
depending on the variable L in this study.
fact that offshore electrolysis used for peak shaving leads to a 13% reduc-
As shown in Fig. 9, there is a slight increase of the median LCOH
tion. Second, an increase of the electrolyser capacity increases also its
with increasing distances, but the changes are mild. Offshore electrol-
utilisation (CF-𝐻2 in Fig. 7.A). Therefore, while in the hydrogen-driven
ysis maintains the lowest median LCOH across the range of possible
operation economies of scale were counteracting the drop in hydrogen
distances, while in-turbine electrolysis maintains the highest.
infrastructure utilisation, here, inversely, the economies of scale and CF
It can be observed that the onshore electrolysis curve is steeper than
of the electrolyser co-act. As a result, the larger the installed capacity,
the other two curves; this happens because, for onshore electrolysis, the
the lower the LCOH. The lowest LCOH, equal to 2.7 €/kg, is found in
HVDC transmission plays a major role in determining the LCOH (Fig. 8).
the case in which all the generated electricity is used for hydrogen pro-
It is possible to conclude that the cost of HVDC lines is more sensitive to
duction.
distance compared with the hydrogen pipelines, used for offshore and
It is important to remind that in the electricity-driven operation the
in-turbine electrolysis. Therefore, as the LCOH for in-turbine and off-
priority is to cover the electricity demand, therefore the electricity losses
shore electrolysis is only marginally affected by the distance from shore,
of the electrical infrastructure upstream of the electrolyser affect the
even more distant applications (i.e. far-offshore) would be possible.
utilisation of the electrolyser. This is the reason why small capacities of
It is also interesting to observe that in the case of hydrogen-driven
onshore electrolysers are producing no hydrogen when the electricity
operation, for shorter distances also the hydrogen produced with on-
demand is 11.5 GW or higher (i.e. electrolyser capacity of 500 MW).
shore electrolysis is competitive with grey hydrogen.
A final remark about Fig. 7.B relates to the LCOE. Beyond electrol-
yser capacities of 8–10 GW, the LCOE starts increasing dramatically,
due to the reduced amount of electricity transported compared with the Conclusions
fixed costs of the offshore electricity infrastructure. Therefore, if more
than 85% of the offshore wind power is directed towards hydrogen pro- The holistic techno-economic assessment proposed in this study as-
duction, it might be preferable to have a full-hydrogen offshore Hub. sessed the cost of production of hydrogen and electricity from offshore
wind power in the North Sea, comparing three different electrolyser
Sensitivity analysis placements (in-turbine, offshore and onshore), three technologies (al-
kaline, proton-exchange membrane and solid-oxide electrolysers), and
Impact of cost of the components two modes of electrolyser operation (hydrogen-driven and electricity-
In this section, the impact of the cost of each component on the me- driven). Results showed that the different types of electrolysers are
dian LCOH is assessed. This sensitivity analysis aims to indicate the ef- equally competitive, with the alkaline electrolyser achieving marginally
fects on the LCOH of uncertainties that might affect the costs of each lower costs. In terms of electrolyser placement, offshore electrolysis re-
component. This is performed by individually changing ± 25% the cost sulted in the lowest cost of hydrogen. The minimum LCOH, obtained
of each component, intending to determine which components have a for offshore electrolysis and hydrogen-driven operation mode, was esti-
larger impact on the LCOH. This shall provide insights about which com- mated at 2.4 €/kg, which is competitive with the current costs of grey
ponents show the greatest potential for larger hydrogen cost reduction. and blue hydrogen.
As shown in Fig. 8, the cost of the WTs has a major impact, irrespec- In the case of the electricity-driven operation of the electrolyser, the
tive of the electrolyser placement and operation mode. For hydrogen- cost of electricity reduced up to 13% when compared to the LCOE with-
driven onshore electrolysis, the HVDC transmission is the second most out any electrolyser installed.
relevant component. These results show that the cost of the electrical Offshore electrolysis is still not mature in terms of required infras-
equipment upstream of the electrolyser is a major component of the tructure and integration with the offshore power systems, in particular
LCOH. for GW-scale electrolysis. Therefore, the input values for the hydrogen
Among the hydrogen infrastructure components, the cost of the elec- infrastructure have to be considered as estimations determined after dis-
trolyser affects the most the median LCOH; this is especially noticeable cussion with manufacturers and operators. Only the major components
in the in-turbine placement, where the cost of the electrolyser is pe- of the systems are considered, to limit the complexity of the model and
nalised by small scales. to generate results that would drive more in-depth studies. Moreover,

10
A. Singlitico, J. Østergaard and S. Chatzivasileiadis Renewable and Sustainable Energy Transition 1 (2021) 100005

( )
social and environmental analyzes were out of the scope. However, these 1 𝐾 2.51
aspects are also necessary to evaluate the feasibility of the placement. √ = −2 ⋅ log + √ (A.5)
2 𝜆 3.7 𝑅𝑒 ⋅ 2 𝜆
Taking the presented results as a starting point, the cost of offshore
green hydrogen can further reduce if the hydrogen infrastructure is more where K is the roughness factor in a pipeline, calculated using Eq. (A.6).
tightly integrated with:

𝐾= (A.6)
• existing oil and gas infrastructures: e.g. repurposing platforms and 𝐷
pipelines. where 𝜀 is the equivalent sand roughness, assumed 0.05 mm [38]; and
• offshore electricity infrastructures: e.g. combining the transmission Re is the Reynolds number for the flow in a pipe used for gas pipeline
of hydrogen and electricity in a single component, instead of having design [35], calculated using Eq. (A.7).
separate cables and pipelines, and, thus, avoiding double installa- ( )( 𝐺 ̇
( ) )
𝑃𝑏 𝐻𝑌 𝐷 ⋅ 𝑉𝐻2 ,𝑃 𝐼𝑃 𝐸 𝑇𝑏 , 𝑝𝑏 ⋅ 24
tion costs; providing services to the electrical grid, such as a flexible 𝑅𝑒 = 0.5134 ⋅ ( ) (A.7)
resource for grid balancing. 𝑇𝑏 𝜇 𝑇𝑏 , 𝑝𝑏 ⋅ 𝐷
• energy/industrial systems: e.g. benefitting from the synergies ob- where 𝜇 is the dynamic viscosity of hydrogen at standard conditions,
tained by using by-products of electrolysis, such as oxygen and heat, 8.64 10-5 poise.
and/or further converting hydrogen into e-fuels. The erosional velocity is calculated, uMAX in units of metres per sec-
ond [35], using Eq. (A.8).
Acknowledgments √
𝑍 ⋅ 𝑅 ⋅ 𝑇𝑀𝐸𝐴𝑁
𝑢𝑀𝐴𝑋 = 100 (A.8)
This research has been supported by the North Sea Energy Hub Pre- 29 ⋅ 𝐺𝐻𝑌 𝐷 ⋅ 𝑃
Feasibility Study project, funded by Det Energiteknologiske Udviklings-
og Demonstrations Program (EUDP) under Grant.nr. 64018-058. The Acceptable operational velocity, u, is assumed to be lower than 50%
authors would also like to thank the Advisory Board Meeting members: of the erosional velocity in units of metres per second [35].
ABB, Cenergy Holdings/Hellenic Cables, Dansk Energi, Dansk Industri, Having a known mass flow rate, the velocity u is related to the di-
Energinet, Green Hydrogen Systems, Haldor Topsøe, NKT, Semco Mar- ameter of the pipeline D, according to Eq. (A.9).
itime, Siemens, Siemens-Gamesa Renewable Energy, Vestas, Wind Den- 𝐷2
𝑚̇ 𝐻2 (𝑡) = 𝑢 ⋅ 𝜌(𝑇 , 𝑝) ⋅ 𝜋 ⋅ (A.9)
mark, Ørsted. 4
where 𝜌 is the density in units of kilograms per cubic metre.
Supplementary materials For the pipeline from the Hub to the shore, the diameter is calculated
using Eq. (A.9), with p = pTRANS , and 𝜌(TMEAN, pTRANS ). pPIPE,IN is then
Supplementary material associated with this article can be found, in calculated solving Eq. (22). pPIPE,IN is then equivalent to pCOMP,OUT and
the online version, at doi:10.1016/j.rset.2021.100005. it can be used in Eq. (21).
For the pipelines from the OWPPs to the Hub, diameter, D, and out-
Appendix A let pressure, pPIPE,OUT , are found maximising uPIPE,OUT, considering two
constraints: uPIPE,OUT < 0.5·uMAX and pb ≤pPIPE,OUT ≤ pPIPE,IN . The higher
The compressibility factor Z is calculated using Eq. (A.1). the velocity the lower is the diameter, having a fixed mass flow rate, thus
( 𝑝 )
𝑅,𝐼𝑁 𝑝 reducing the cost.
𝑝𝑃 𝐼𝑃 𝐸,𝐼𝑁
+ 𝑝 𝑅,𝑂𝑈 𝑇
𝑃 𝐼𝑃 𝐸,𝑂𝑈 𝑇
𝑍𝑀𝐸𝐴𝑁 = (A.1)
2 Appendix B
where pR is the pressure of the real gas, in kilopascal, calculated using
Eq. (A.2), considering the inlet and outlet pressures of the pipelines. Electrolyser economies of scale
Large scale electrolysers are still under development, so no commer-
𝑅 ⋅ 𝑇𝑀𝐸𝐴𝑁 𝑎 cial cost reference exists. However, an investigation conducted by Za-
𝑝𝑅 = ( ) − √ ( ) ( ( ) )
𝑣 𝑇𝑀𝐸𝐴𝑁 , 𝑝 − 𝑏 2 𝑇𝑀𝐸𝐴𝑁 ⋅ 𝑣 𝑇𝑀𝐸𝐴𝑁 , 𝑝 ⋅ 𝑣 𝑇𝑀𝐸𝐴𝑁 , 𝑝 + 𝑏 uner et al. [33] showed that the effect of economies of scale is more
(A.2) pronounced at lower nominal power levels than at higher levels. This
leads to an increased share of stack costs in the overall system for larger
where R is the universal constant of gas, 8.31434 J mol-1 K-1 ;
v is the
electrolysis systems, which reduces the overall effect of the economies
molar volume of the hydrogen in units of cubic metres per kilomole;
of scale. In this study, it is assumed that the scale factor for small units
and a and b: factors of the Redlich-Kwong equations, calculated using
is used to calculate the costs for electrolysers not larger than 10 MW,
Eqs. (A.3) and (A.4).
while the scale factor for large sizes is used for electrolysers larger than
5
10 MW. It is also assumed that no additional economies of scale are
𝑅2 ⋅ 𝑇𝐶2
𝑎 = 0.42748 ⋅ (A.3) accounted for in sizes larger than 100 MW. The average costs for the
𝑝𝐶 different technologies for 2030 has been sourced from the Energinet
𝑅 ⋅ 𝑇𝐶 Technology Catalogue [30]. (Table B.2).
𝑏 = 0.08664 ⋅ (A.4) The economies of scale of each piece of the equipment composing the
𝑝𝐶
electrolyser system (i.e. stack, power electronics, gas conditioning, gas
where TC is the critical temperature of hydrogen equivalent to 33.2 K; conditioning, balance of plant) are different. Therefore, the cost of the
pC is the critical pressure of hydrogen equivalent to 1,320 kPa. stack would not follow the economies of the entire electrolyser unit. The
The coefficient of friction factor, or Darcy-Weisbach, 𝜆 is calculated stack does not show potential for large cost reduction via economies of
by solving the Colebrook-White equation for gas in pipelines in turbulent because of its modular design [33]. The values used in the calculations
flows (Re > 4000), Eq. (A.5). are listed in Table B.3.

11
A. Singlitico, J. Østergaard and S. Chatzivasileiadis Renewable and Sustainable Energy Transition 1 (2021) 100005

Table B.1
Cost inventory for the calculation of LCOE and LCOH.

Component Symbol Value Comment RefsW.


Capital expenditures, CapEx [M€]
Wind power plant 𝐶𝑎𝑝𝐸 𝑥𝑂𝑊 𝑃 𝑃 ,𝐸𝑄 (14 + 7.55) ⋅ 𝑁𝑊 𝑇 14 M€ represents the [20]
cost of all components of
a reference 15 MW;
7.55 M€ represents the
costs of the substructure
underneath the turbine,
determined based on the
required mass of the
tower, transition piece
and monopile foundation
for an average depth of
30 m.
𝐶𝑎𝑝𝐸 𝑥𝑂𝑊 𝑃 𝑃 ,𝑁𝐸𝑄 100 ⋅ 𝑃𝑂𝑊 𝑃 𝑃 This equation represents [20]
the project development,
including all costs up to
the start of construction.

Inter-array grid 𝐶𝑎𝑝𝐸 𝑥𝐼𝐺,𝐸𝑄 𝐿𝐼𝐺,𝑖 ⋅ [94.94 ⋅ 10−3 + Cost equation of AC [39]
𝑖
cables based on a rated
86.22.05⋅⋅𝑃10−3
( 𝐼𝐺 ) voltage of 66 kV.
⋅ 𝑒 108 ]

𝐶𝑎𝑝𝐸 𝑥𝐼 𝐺,𝑁 𝐸𝑄 0.33 ⋅ 𝐿𝐼𝐺,𝑖 Installation costs for [39]
𝑖
offshore inter-array grid
cables.
𝑃𝐻𝑉 𝐷𝐶
Offshore substation 𝐶𝑎𝑝𝐸 𝑥𝑆 𝑆 ,𝑂𝐹 𝐹 117.9 ⋅ 𝑃𝐻𝑉 𝐷𝐶 + 𝑃𝑀𝐴𝑋
⋅ Curve fitting the average [40]
45.4 of the cost of an offshore
VSC-HVCDC. PMAX is
considered 2 GW.
𝑃𝐻𝑉 𝐷𝐶
Onshore substation 𝐶𝑎𝑝𝐸 𝑥𝑆 𝑆 ,𝑂𝑁 101 ⋅ 𝑃𝐻𝑉 𝐷𝐶 + 𝑃𝑀𝐴𝑋
⋅ Curve fitting the average [40]
61.6 of the costs onshore
VSC-HVDC substations.
PMAX is considered 2 GW.
VSC-HVDC transmission 𝐶𝑎𝑝𝐸 𝑥𝐻𝑉 𝐷𝐶 𝐿𝐻𝑆 ⋅ Curve fitting including [40]
𝑃𝐻𝑉 𝐷𝐶
[0.6 ⋅ 𝑃𝐻𝑉 𝐷𝐶 + 𝑃𝑀𝐴𝑋
⋅ 1.345] HVDC extruded copper
320–400 kV and the
installation and the
average of 2 single
cables; 2 trenches,
single-core, 10 m apart.
PMAX is considered 2 GW.
Electrolyser system 𝐶𝑎𝑝𝐸 𝑥𝐸𝐿 𝑃𝐸 𝐿𝐸 𝐶 ⋅ 𝑅𝐶𝐸 𝐿𝐸 𝐶 ⋅ Non-equipment costs: [34,41]
(1 + 𝐼𝐹 ⋅ 𝑂𝑆 ) ⋅ land, contingency,
𝑃𝐸 𝐿𝐸 𝐶 ⋅10 3
( 𝑅𝑃𝐸 𝐿𝐸 𝐶
)𝑆 𝐹𝐸 𝐿𝐸 𝐶 contractors, legal fees,
construction,
engineering, yard
improvements, buildings,
electrics, piping,
instrumentation and
installation and grid
connection. The cost for
the offshore
configuration is assumed
to be double the onshore
costs. (OS = 1 if the
electrolyser is located
in-turbine or offshore,
OS = 0 if the electrolyser
is located onshore,
reflecting Siemens
estimations).
Desalination unit 𝐶𝑎𝑝𝐸 𝑥𝐷𝐸𝑆 30.6 ⋅ 𝑉 𝐻2 𝑂 ⋅ 10−3 Reverse osmosis [16]
seawater desalinator
(Lenntech Reverse
Osmosis System) is used
as reference technology.
Compression unit 𝐶𝑎𝑝𝐸 𝑥𝐶𝑂𝑀𝑃 3000 ⋅ 𝑃𝐶𝑂𝑀𝑃 Considering a centrifugal [42]
compressor with electric
drivers, including power
lines, transformers, and
electronics.
Hydrogen pipeline 𝐶𝑎𝑝𝐸 𝑥𝑃 𝐼𝑃 𝐸 1.75 ⋅ 𝐿𝐻𝑆 ⋅ [0.314 + Pipeline for hydrogen [16]
0.574 ⋅ 103 ⋅ (𝐷) transmission in the North
+ 1.7 ⋅ 106 ⋅ (𝐷)2 ] Sea.
(continued on next page)

12
A. Singlitico, J. Østergaard and S. Chatzivasileiadis Renewable and Sustainable Energy Transition 1 (2021) 100005

Table B.1 (continued)

Artificial island 𝐶𝑎𝑝𝐸 𝑥𝐻𝑈 𝐵 The cost of dredged sand [43]


(3.26 ⋅ 𝑉𝐻𝑈 𝐵 + 804 ⋅ 𝐴𝐻𝑈 𝐵 ) ⋅ is assumed to be 3.26
10−6 €/m3 and the cost for
protecting the shoreline
of the island is assumed
to be 804 €/ m2 . The
cost of the artificial
island is assumed to be
allocated to the
electricity and hydrogen
generated proportionally
to the footprint of their
components, HVDC
offshore substation for
the electricity system,
and electrolyser for the
hydrogen
Operation and maintenance expenditures, OpEx [M€/a]
Wind power plant 𝑂𝑝𝐸 𝑥𝑂𝑊 𝑃 𝑃 1.9% ⋅ 𝐶𝑎𝑝𝐸 𝑥𝑂𝑊 𝑃 𝑃 ,𝐸𝑄 - [26]
Inter-array grid 𝑂𝑝𝐸 𝑥𝐼𝐺 0.2% ⋅ 𝐶𝑎𝑝𝐸 𝑥𝐼𝐺,𝐸𝑄 - [44]
VSC-HVDC transmission 𝑂𝑝𝐸 𝑥𝐻𝑉 𝐷𝐶 0.2% ⋅ 𝐶𝑎𝑝𝐸 𝑥𝐻𝑉 𝐷𝐶 CapExHVDC includes the [44]
cost of the substations
and the transmission
line.
Electrolyser system 𝑂𝑝𝐸 𝑥𝐸 𝐿𝐸 𝐶,𝐸 𝑄 𝐶𝑎𝑝𝐸 𝑥𝐸 𝐿𝐸 𝐶 ⋅ (1 − 𝐼𝐹 ⋅ (1 + 𝑂𝑆 )) ⋅ 3.44% ⋅ (𝑃𝐸 𝐿𝐸 𝐶 ⋅ 103 )−0.155 Including material cost [32]
for planned and
unplanned maintenance,
labour cost in central
Europe, which all
depend on a system
scale. Excluding the cost
of electricity and the
stack replacement,
calculated separately.
Scaled maximum to
𝑃̄𝐸 𝐿𝐸 𝐶 = 1 GW.
𝑃𝐸 𝐿𝐸 𝐶 ⋅103 𝑆 𝐹 𝑂𝐻
𝑂𝑝𝐸 𝑥𝐸 𝐿𝐸 𝐶,𝑆𝑅 𝑃𝐸 𝐿𝐸 𝐶 ⋅ 𝑅𝐶𝑆𝑅 ⋅ ( 𝑅𝑃𝑆𝑅
) 𝑆𝑅 ⋅ 𝑂𝐻𝑀𝐴𝑋
Approximation of stack [34,45]
𝑅𝐶𝑆𝑅 = 𝑅𝑈𝑆𝑅 ⋅ 𝑅𝐶𝐸 𝐿𝐸 𝐶 ⋅ (1 − 𝐼𝐹 ) ⋅ ( 𝑅𝑃
𝑅𝑃𝑆𝑅
)𝑆 𝐹𝐸 𝐿𝐸 𝐶 costs and replacement
𝑃̄𝐸 𝐿𝐸 𝐶
𝐸 𝐿𝐸 𝐶 cost depending on the
− 𝑃̄
𝑆 𝐹𝑆𝑅 = 1 − (1 − 𝑆 𝐹𝑆𝑅,0 ) ⋅ 𝑒 𝑆𝑇 𝐴𝐶 𝐾 ,𝑀𝐴𝑋 electrolyser equipment
costs. Paid only the year
in which the
replacement is needed.
𝑂𝑝𝐸 𝑥𝐸 𝐿𝐸 𝐶,𝑁𝐸 𝑄 4% ⋅ 𝐶𝑎𝑝𝐸 𝑥𝐸 𝐿𝐸 𝐶 ⋅ 𝐼𝐹 ⋅ (1 + 𝑂𝑆 ) It covers the other [34]
operational expenditure
related to the facility
level. This includes site
management, land rent
and taxes, administrative
fees (insurance, legal
fees…), site
maintenance.
Desalination unit 𝑂𝑝𝐸 𝑥𝐷𝐸𝑆 2.5% ⋅ 𝐶𝑎𝑝𝐸 𝑥𝐷𝐸𝑆 Operational expenditure [16]
of desalination when
assumed part of the
electrolyser system.
Compression unit 𝑂𝑝𝐸 𝑥𝐶𝑂𝑀𝑃 4% ⋅ 𝐶𝑎𝑝𝐸 𝑥𝐶𝑂𝑀P Fixed operational and [46]
maintenance costs.
Hydrogen pipeline OpExPIPE 2% ⋅ CapExPIPE Fixed operational and [16]
maintenance costs for
both CapExPIPE,HS and
CapExPIPE,WTH .
∑ ̇
8760
Freshwater OpExH2 O 9.23 ⋅ (1 − 0.6) ⋅ 10−6 ⋅ VH2 O,DES (t) In the case of offshore [47]
𝑡=1
electrolysis, water is
purchased from the grid.
9.23 € per cubic meter of
water is assumed as an
average price and a 60%
discount for large
consumers.
Conversions used from the original currencies: USD2014 = 0.752 EUR2014, EUR inflation from 2014 to 2017 = 1.81%; EUR inflation from 2010 to
2017 = 9.11%; SEK2003 to = 0.1096 EUR2003, EUR inflation from 2003 to 2017 = 25.33%; GBP2015 = 1.35 EUR2015, EURO inflation from 2015 to
2017 = 1.78%.

13
A. Singlitico, J. Østergaard and S. Chatzivasileiadis Renewable and Sustainable Energy Transition 1 (2021) 100005

Table B.2
Coefficients used for CapExEL calculations (sourced from [30,33]).

Reference cost, Installation fraction∗ , IF Reference power, Scale factor, SFELEC


RCELEC [€/kW] [%RCELEC ] RPELEC [MW] [<10 MW/>10 MW]
AEL 550 27 10 -0.24/–0.13
PEMEL 600 33 10 -0.21/–0.14
SOEL 600 63 15 -0.25/–0.22


Installation costs include: land, contingency, contractors, legal fees, construction, engineering, yard improvements, buildings, electrics, piping, instru-
mentation and installation and grid connection

Table B.3
Coefficients used for OpExEL,SR calculations (sourced from [33]).

Reference cost share∗ , Average max size, 𝑃𝑆𝑇 𝐴𝐶 𝐾 ,𝑀𝐴𝑋 Average scale factor, SFSR,0
RUSR [%] [MW]
AEL 45 4 0.12
PEMEL 41 2 0.11
SOEL 50 1 0.13

for a reference power, RPSR , of 5 MW.

References [18] International Energy Agency. Hydrogen production costs by production source 2020,
2021 https://www.iea.org/data-and-statistics/charts/hydrogen-production-costs-
[1] European Commission. The European green deal, 2019 Brussels, Belgium, by-production-source-2018 accessed March 14.
doi:10.1017/CBO9781107415324.004. [19] European Commission. Report from the commission to the European parliament
[2] Folketinget. Klimaaftale for energi og industri mv. 2020, 2020 Copenhagen, Den- and the council on progress of clean energy competitiveness. 2020. (https://eur-lex.
mark https://fm.dk/media/18085/klimaaftale-for-energi-og-industri-mv-2020.pdf. europa.eu/legal-content/EN/TXT/PDF/?uri=CELEX:52020DC0953&from=EN)
[3] IRENA. Hydrogen: a renewable energy perspective, 2019 Abu Dhabi [20] E.C.M. Ruijgrok, E.J. van Druten, Cost evaluation of north sea offshore wind post
https://www.irena.org/-/media/Files/IRENA/Agency/Publication/2019/Sep/ 2030, 2019 Petten, The Netherlands112522/19-001.830 112522 https://northseaw-
IRENA_Hydrogen_2019.pdf. indpowerhub.eu/sites/northseawindpowerhub.eu/files/media/document/Cost-
[4] Energistyrelsen. Cost benefit analyse og klimaaftryk af energiøer i Nordsøen og Evaluation-of-North-Sea-Offshore-Wind-1.pdf .
Østersøen Cost benefit analyse og klimaaftryk af energiøer i Nordsøen og Østersøen. [21] S.K. Swamy, N. Saraswati, P. Warnaar. North sea wind power hub ( NSWPH
2021. https://ens.dk/sites/ens.dk/files/Vindenergi/a209704-001_cost_benefit_ ): Benefit study for ( 1 + 3 ) potential locations of an offshore hub- island.
analyse_endelig_version.pdf. Petten, The Netherlands. 2019. (https://northseawindpowerhub.eu/sites/
[5] North Sea Wind Power Hub Consortium. The benefits: The modular Hub- northseawindpowerhub.eu/files/media/document/NSWPH-Benefit-study-for-
and-Spoke concept has substantial societal benefits and thus the po- potential-locations-of-an-offshore-hub-island-1.pdf)
tential to incentivise all involved stakeholders, 2019 https://northsea- [22] The MathWorks Inc. MATLAB and statistics toolbox release 2019, 2016 Natick, Mas-
windpowerhub.eu/sites/northseawindpowerhub.eu/files/media/document/ sachusetts, United States.
Concept_Paper_4-The-benefits.pdf. [23] D.G. Goodwin, H.K. Moffat, RL. Speth, Cantera: An object- oriented software toolkit
[6] Ørsted. A European Green Deal - How offshore wind can help decarbonise Europe. for chemical kinetics, thermodynamics, and transport processes, Caltech, Pasadena,
2019. https://orsted.com/en/about-us/whitepapers/a-european-green-deal. CA, 2017.
[7] The European parliament and the council of the european union. Off- [24] ECMWF. ERA5 hourly data on single levels from 1979 to present. 2018.
shore wind energy in Europe, 2020 https://www.europarl.europa.eu/ doi:10.24381/cds.adbb2d47.
RegData/etudes/BRIE/2020/659313/EPRS_BRI(2020)659313_EN.pdf. [25] E. Gaertner, J. Rinker, L. Sethuraman, B. Anderson, F. Zahle, G. Barter, IEA Wind
[8] European Commission. An EU Strategy to harness the potential of off- TCP Task 37: definition of the IEA 15 MW offshore reference wind turbine, 2020
shore renewable energy for a climate neutral future, 2020 https://eur-lex. United States, doi:10.2172/1603478.
europa.eu/legal-content/EN/TXT/PDF/?uri=CELEX:52020DC0741&from=EN. [26] The Danish Energy Agency. , Energinet, Technology data – generation of elec-
[9] North Sea Wind Power Hub Consortium. Modular Hub-and- tricity and district heating, 414, 2016 https://ens.dk/en/our-services/projections-
Spoke Concept to Facilitate Large Scale Offshore Wind. 2019. and-models/technology-data/technology-data-generation-electricity-and.
https://www.tennet.eu/fileadmin/user_upload/Our_Key_Tasks/Innovations/ [27] Greedy, Lyndon. TENNET, NL OFFSHORE WIND FARM TRANSMIS-
NSWPH/NSWPH_paper.pdf. SION SYSTEMS 66 kV Systems for Offshore Wind Farms 2015:35.
[10] U. Weichenhain, S. Elsen, T. Zorn, S. Kern, Hybrid projects : how to reduce costs https://www.tennet.eu/fileadmin/user_upload/Our_Grid/Offshore_Netherlands/
and space of offshore developments, North seas offshore energy clusters study, 2019 Consultatie_proces_net_op_zee/Technical_Topics/4_T1._Enclosure_nr_1b_-_66_kV_
Doi:, doi:10.2833/416539. systems_for_Offshore_Wind_Farms_by_DNV_GL.pdf.
[11] North Sea Wind Power Hub Consortium, Consortium. Concept https:// [28] U.S. Department of Energy. Assessing HVDC Transmission for Impacts of
northseawindpowerhub.eu/sites/northseawindpowerhub.eu/files/media/document/ Non ‐ Dispatchable Generation 2018:132. https://www.eia.gov/analysis/
Concept_Paper_3-Specific-solution-options.pdf studies/electricity/hvdctransmission/.
[12] Energinet. Winds of Change In A Hydrogen Perspective - PtX Strategic Action Plan. [29] IEA. The future of hydrogen - seizing today’s opportunities. Rep prep by IEA G20,
2019. https://en.energinet.dk/About-our-reports/Reports/PtX_strategic_action_plan. 2019 Japan, doi:10.1787/1e0514c4-en.
[13] European Commission. A hydrogen strategy for a climate-neutral Europe, 2020 [30] Danish Energy Agency and Energinet. Technology data for renewable fu-
https://eur-lex.europa.eu/legal-content/EN/TXT/PDF/?uri=CELEX:52020DC0301 els – technology descriptions and projections for long-term energy system
&from=EN. planning (2020 updated), 2017 https://ens.dk/en/our-services/projections-and-
[14] K. Meier, Hydrogen production with sea water electrolysis using Norwegian offshore models/technology-data/technology-data-renewable-fuels.
wind energy potentials: techno-economic assessment for an offshore-based hydrogen [31] O. Schmidt, A. Gambhir, I. Staffell, A. Hawkes, J. Nelson, S. Few, Future cost and
production approach with state-of-the-art technology, Int. J. Energy Environ. Eng. performance of water electrolysis: an expert elicitation study, Int. J. Hydrog. Energy
5 (2014) 1–12, doi:10.1007/s40095-014-0104-6. 42 (2017) 30470–30492, doi:10.1016/j.ijhydene.2017.10.045.
[15] C. Jepma, M. Van Schot, On the economics of offshore energy conversion: smart [32] L. Bertuccioli, A. Chan, D. Hard, F. Lehner, B. Madden, E. Standen, Development of
combinations, Converting offshore wind energy into green hydrogen on existing water electrolysis in the European union, 23, 2014.
oil and gas platforms in the North Sea, 2017 https://projecten.topsectorenergie. [33] A. Zauner, H. Böhm, D.C.R. Rosenfeld, Tichler Innovative large-scale energy storage
nl/storage/app/uploads/public/5d0/263/410/5d026341016a2991247120.pdf. technologies and Power-to-Gas concepts after optimization, D7.7 analysis on
[16] C. Jepma, G.J. Kok, M. Renz, M.K. van SchotWouters, North sea energy D3.6 towards future technology options and on techno-economic, optimization, 2019, pp. 1–89
sustainable energy production on the North Sea-Green hydrogen production and https://www.storeandgo.info/fileadmin/downloads/deliverables_2019/20190801-
CO2 storage: onshore or offshore? As part of topsector energy, TKI Offshore Wind STOREandGO-D7.7-EIL-Analysis_on_future_technology_options_and_on_techno-
& TKI New Gas, 2018 https://north-sea-energy.eu/documents/North%20Sea% economic_optimization.pdf.
20Energy%20I%20-%20D3.1.2-3.1.4,%20D3.1.6%20Towards%20sustainable% [34] E. Tractebel, H. Engie, Study on early business cases for h2 in energy stor-
20energy%20production%20on%20the%20North%20Sea_final-public.pdf. age and more broadly power to h2 applications, EU Comm, 2017, p. 228.
[17] A. Crivellari, V. Cozzani, Offshore renewable energy exploitation strategies in remote https://www.fch.europa.eu/sites/default/files/P2H_Full_Study_FCHJU.pdf.
areas by power-to-gas and power-to-liquid conversion, Int. J. Hydrog. Energy 45 [35] ES. Menon, Pipeline Planning and Construction Field Manual, Gulf Professional Pub-
(2020) 2936–2953, doi:10.1016/j.ijhydene.2019.11.215. lishing, Elsevier Inc., The Boulevard, Langford Lane, Kidlingron, Oxford, OX5 1GB,
UK, 2011.

14
A. Singlitico, J. Østergaard and S. Chatzivasileiadis Renewable and Sustainable Energy Transition 1 (2021) 100005

[36] A.C. Weber, LG. Papageorgiou, Design of hydrogen transmission pipeline [43] S. Gerrits, C. Kuiper, P. Quist, EJ. Van Druten, Feasibility Study of the Hub
networks with hydraulics, Chem. Eng. Res. Des. 131 (2018) 266–278, and Spoke Concept in the North Sea: Developing a Site Selection Model
doi:10.1016/j.cherd.2018.01.022. to Determine the Optimal Location, Delft University of Technology, 2017
[37] Electricity Ten Year Statement. , Appendix e: electricity ten year statement 2015, http://resolver.tudelft.nl/uuid:9de1680b-7c16-4c93-bf3e-2af5e198eee0.
2015, 2015, doi:10.1016/B978-0-08-091906-5.00027-6. [44] K. Das, N. Antionios Cutululis, Offshore wind power plant technology catalogue -
[38] M. Renz, M. Van Schot, C. Jepma. North Sea Energy Energy transport and en- components of wind power plants, AC collection systems and HVDC systems, Balt.
ergy carriers. 2020. https://north-sea-energy.eu/static/afcbb8ede73e006a185 Grid. (2017).
c2499f2735f34/FINAL-NSE3-D3.2-D3.3-D3.4-D3.4-D3.5-D3.6-Inventory-of-power- [45] Hydrogen from renewable power: technology outlook for the energy transi-
to-X-integration-options.pdf. tion, 2018 Abu Dhabi https://www.irena.org/publications/2018/sep/hydrogen-
[39] S. Lundberg, Performance comparison of wind park configurations, Chalmers from-renewable-power .
University of Technology, 2003 https://publications.lib.chalmers.se/records/ [46] M. Reuß, T. Grube, M. Robinius, P. Preuster, P. Wasserscheid, D. Stolten, Seasonal
fulltext/2691/local_2691.pdf. storage and alternative carriers: a flexible hydrogen supply chain model, Appl. En-
[40] National Grid. , Electricity ten year statement, UK Electr. Transm. 2015 (2015) ergy 200 (2017) 290–302, doi:10.1016/j.apenergy.2017.05.050.
1–145. [47] Water in figures. , Godthåbsvej, 83, 2019 DK-8660 https://www.danva.dk/media/
[41] Siemens. Personal communication on electrolyser offshore installation cost, 2020. 6355/2019_water-in-figures_web.pdf .
[42] Council of European Energy Regulators. Pan-European cost-efficiency benchmark
for gas transmission system operators, 2019 https://www.ceer.eu/documents/
104400/-/-/90707d6c-6da8-0da2-bce9-0fbbc55bea8c.

15

You might also like