CSP 500 B
2000
1000
0
-50 -1000 0 50 100 150 200 250 300 350 400 Nominal
P (kN)
-2000 Factored
-3000 Pall
-4000 Mcr
-5000
Note:
-6000 + Tension
M (kNm) - Compression
2000
Nominal
0
P (kN)
-50 0 50 100 150 200 250 300 350 400 450 Factored
-2000
Pall
-4000 Mcr
Note:
-6000 + Tension
M (kNm)
- Compression
Interaction Diagram of PC Spun Pile
CSP 600 B
4000
2000
0 Nominal
P (kN)
-4000 Pall
Mcr
-6000
Note:
-8000 + Tension
M (kNm) - Compression
2000
0 Nominal
P (kN)
-4000 Pall
Mcr
-6000
Note:
-8000 + Tension
M (kNm) - Compression
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
STANDAR PT ADHI PERSADA BETON
D = 500 mm
Kelas: B
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
Referensi
Keterangan
: input
Tulisan : perhatian
Tulisan : pengecekan
121000 50 6050000
1. Data perhitungan
1.1. Dimensi beton
Panjang tiang pancang L= 20,000 m = 20000,000 mm
Diameter penampang D= 500,000 mm
Tebal penampang beton T= 90,000 mm
T
Diameter lubang D0 = D-2T = 320,000 mm d1
2
Luas penampang beton Ac = πD2/4-πD02/4 = 115924,769 mm
4
Momen Inersia penampang beton Ix = π(D4-D04)/64 = 2,553,E+09 mm D
Titik berat penampang ya = yb = D/2 = 250,000 mm
1000
f (MPa)
500
0
0 0,01 0,02 0,03 0,04 0,05 0,06 0,07
ε
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
Beton
Kuat tekan beton kubus K= 600,000
Kuat tekan beton fc' = 50,000 MPa
Modulus elastis beton Ec = 4700√fc' = 33234,019 MPa
Kuat tekan beton saat penarikan fci' = 0,8fc' = 40,000 MPa
Modulus elastis beton saat penarikan Eci = 4700√fci' = 29725,410 MPa
Regangan retak beton εcu = 0,003
3
Berat isi beton γc = 25,000 kN/m
Lingkaran luar
x = a/D = 0,158
y = Atem/Lling = 0,104
y = TBtem/R = 0,817
D0
Lingkaran dalam
x = a0/D0 = -0,035 D
y = Atem/Lling = -0,012
y = TBtem/R = 1,039 Penampang CSP
Luas dan titik berat tiap kondisi Desak dan lentur beton
Lingkaran luar Lingkaran dalam Penampang A (mm2) l (mm) Cc (kN) Mc (kNm)
Kondisi
Atem (mm2) TBtem (mm) Atem (mm2) TBtem (mm) 0,85fc'A Ccl
a≤T 20365,73 204,17 Lingk luar 20365,731 204,170 865,544 176,718
T<a<(T+D0) 20365,73 204,17 -965,35 166,30 Lingk dalam 0,000 0,000 0,000 0,000
(T+D0)≤a≤D 20365,73 204,17 80424,77 0,00 Δ 865,544 176,718
Kekuatan Lentur
Gaya tarik PC Bar Tp = 865,956 kN
Gaya desak beton Cc = 865,544 kN
Kuat lentur PC Bar Mp = 97,487 kNm
Kuat lentur beton Mc = 176,718 kNm
Kekuatan lentur Mn = Mp+Mc = 274,204 kNm = 27,519 ton m
Reduksi kekuatan lentur φ= 0,90
Kekuatan lentur tereduksi φMn = φ(Mp+Mc) = 246,784 kNm = 24,768 ton m
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
Dimensi pc bar
2
Luas total pc bar Aps = 0,001 m
4
Momen Inersia pc bar Ixs = Σnπd4/64+ΣAy2 = 0,000 m
4.2. Pengangkatan
Panjang segmen = 20 *m
Jarak titik pengangkatan dari ujung a = 0,2L1 = 4,000 m
Berat sendiri q = Acγc = 2,898 kN/m
Momen lentur tumpuan M1 = qa2/2 = 23,185 kNm
Momen lentur tengah bentang M2 = q(L1-2a)2/8-qa2/2 = 28,981 kNm
Tegangan pada M1
Serat atas fa1 = -Pi/Accomp+M1y/Ixcomp = -7,120 MPa (OK, fizin ≤ f ≤ fizin)
Serat bawah fb1 = -Pi/Accomp-M1y/Ixcomp = -11,393 MPa (OK, fizin ≤ f ≤ fizin)
Tegangan pada M2
Serat atas fa1 = -Pi/Accomp-M2y/Ixcomp = -11,927 MPa (OK, fizin ≤ f ≤ fizin)
Serat bawah fb1 = -Pi/Accomp+M2y/Ixcomp = -6,585 MPa (OK, fizin ≤ f ≤ fizin)
4.3. Erection
Jarak titik pengangkatan dari ujung a = 0,2L1 = 4,000 m
Berat sendiri q = Acγc = 2,898 kN/m
2
Momen lentur tumpuan M1 = qa /2 = 23,185 kN/m
Momen lentur tengah bentang M2 = (1/2)q(L2-2aL1)/(2(L-a)2) = 0,679 kN/m
Tegangan pada M1
Serat atas fa1 = -Pi/Accomp+M1y/Ixcomp = -7,120 MPa (OK, fizin ≤ f ≤ fizin)
Serat bawah fb1 = -Pi/Accomp-M1y/Ixcomp = -11,393 MPa (OK, fizin ≤ f ≤ fizin)
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
Tegangan pada M2
Serat atas fa1 = -Pi/Accomp-M2y/Ixcomp = -9,319 MPa (OK, fizin ≤ f ≤ fizin)
Serat bawah fb1 = -Pi/Accomp+M2y/Ixcomp = -9,194 MPa (OK, fizin ≤ f ≤ fizin)
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
5. Kekuatan geser
Dimensi dan properti material
Diameter sengkang spiral Dv = 4,000 mm
Jarak dari serat tekan terjauh ke pusat tulangan tarik d= 460,000 mm
Lebar badan (web) bw = 2T = 180,000 mm
Kuat tekan beton silinder fc' = 50,000 Mpa
Kekuatan leleh sengkang spiral fyt = 420,000 MPa
Jarak antar sengkang spiral s= 100,000 mm
Referensi
Keterangan
: input
Tulisan : perhatian
Tulisan : pengecekan
1. Data perhitungan
1.1. Dimensi beton
Panjang tiang pancang L= 20,000 m = 20000,000 mm
Diameter penampang D= 500,000 mm
Tebal penampang beton T= 90,000 mm
T
Diameter lubang D0 = D-2T = 320,000 mm d1
2
Luas penampang beton Ac = πD2/4-πD02/4 = 115924,769 mm
4
Momen Inersia penampang beton Ix = π(D4-D04)/64 = 2,553,E+09 mm D
Titik berat penampang ya = yb = D/2 = 250,000 mm
1000
f (MPa)
500
0
0 0,01 0,02 0,03 0,04 0,05 0,06 0,07
ε
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
Beton
Kuat tekan beton kubus K= 600,000
Kuat tekan beton fc' = 50,000 MPa
Modulus elastis beton Ec = 4700√fc' = 33234,019 MPa
Kuat tekan beton saat penarikan fci' = 0,8fc' = 40,000 MPa
Modulus elastis beton saat penarikan Eci = 4700√fci' = 29725,410 MPa
Regangan retak beton εcu = 0,003
3
Berat isi beton γc = 25,000 kN/m
Lingkaran luar
x = a/D = 0,181
y = Atem/Lling = 0,124
y = TBtem/R = 0,790
D0
Lingkaran dalam
x = a0/D0 = 0,001 D
y = Atem/Lling = 0,000
y = TBtem/R = 0,999 Penampang CSP
Luas dan titik berat tiap kondisi Desak dan lentur beton
Lingkaran luar Lingkaran dalam Penampang A (mm2) l (mm) Cc (kN) Mc (kNm)
Kondisi
Atem (mm2) TBtem (mm) Atem (mm2) TBtem (mm) 0,85fc'A Ccl
a≤T 24428,76 197,44 Lingk luar 24428,760 197,437 1038,222 204,983
T<a<(T+D0) 24428,76 197,44 28,73 159,84 Lingk dalam 28,726 159,841 1,221 0,195
(T+D0)≤a≤D 24428,76 197,44 80424,77 0,00 Δ 1037,001 204,788
Kekuatan Lentur
Gaya tarik PC Bar Tp = 1036,491 kN
Gaya desak beton Cc = 1037,001 kN
Kuat lentur PC Bar Mp = 130,745 kNm
Kuat lentur beton Mc = 204,788 kNm
Kekuatan lentur Mn = Mp+Mc = 335,533 kNm = 33,674 ton m
Reduksi kekuatan lentur φ= 0,90
Kekuatan lentur tereduksi φMn = φ(Mp+Mc) = 301,980 kNm = 30,307 ton m
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
Dimensi pc bar
2
Luas total pc bar Aps = 0,002 m
4
Momen Inersia pc bar Ixs = Σnπd4/64+ΣAy2 = 0,000 m
4.2. Pengangkatan
Panjang segmen = 20 *m
Jarak titik pengangkatan dari ujung a = 0,2L1 = 4,000 m
Berat sendiri q = Acγc = 2,898 kN/m
Momen lentur tumpuan M1 = qa2/2 = 23,185 kNm
Momen lentur tengah bentang M2 = q(L1-2a)2/8-qa2/2 = 28,981 kNm
Tegangan pada M1
Serat atas fa1 = -Pi/Accomp+M1y/Ixcomp = -9,751 MPa (OK, fizin ≤ f ≤ fizin)
Serat bawah fb1 = -Pi/Accomp-M1y/Ixcomp = -13,942 MPa (OK, fizin ≤ f ≤ fizin)
Tegangan pada M2
Serat atas fa1 = -Pi/Accomp-M2y/Ixcomp = -14,466 MPa (OK, fizin ≤ f ≤ fizin)
Serat bawah fb1 = -Pi/Accomp+M2y/Ixcomp = -9,227 MPa (OK, fizin ≤ f ≤ fizin)
4.3. Erection
Jarak titik pengangkatan dari ujung a = 0,2L1 = 4,000 m
Berat sendiri q = Acγc = 2,898 kN/m
2
Momen lentur tumpuan M1 = qa /2 = 23,185 kN/m
Momen lentur tengah bentang M2 = (1/2)q(L2-2aL1)/(2(L-a)2) = 0,679 kN/m
Tegangan pada M1
Serat atas fa1 = -Pi/Accomp+M1y/Ixcomp = -9,751 MPa (OK, fizin ≤ f ≤ fizin)
Serat bawah fb1 = -Pi/Accomp-M1y/Ixcomp = -13,942 MPa (OK, fizin ≤ f ≤ fizin)
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
Tegangan pada M2
Serat atas fa1 = -Pi/Accomp-M2y/Ixcomp = -11,908 MPa (OK, fizin ≤ f ≤ fizin)
Serat bawah fb1 = -Pi/Accomp+M2y/Ixcomp = -11,785 MPa (OK, fizin ≤ f ≤ fizin)
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
5. Kekuatan geser
Dimensi dan properti material
Diameter sengkang spiral Dv = 4,000 mm
Jarak dari serat tekan terjauh ke pusat tulangan tarik d= 460,000 mm
Lebar badan (web) bw = 2T = 180,000 mm
Kuat tekan beton silinder fc' = 50,000 Mpa
Kekuatan leleh sengkang spiral fyt = 420,000 MPa
Jarak antar sengkang spiral s= 100,000 mm
Referensi
Keterangan
: input
Tulisan : perhatian
Tulisan : pengecekan
1. Data perhitungan
1.1. Dimensi beton
Panjang tiang pancang L= 20,000 m = 20000,000 mm
Diameter penampang D= 600,000 mm
Tebal penampang beton T= 100,000 mm
T
Diameter lubang D0 = D-2T = 400,000 mm d1
2
Luas penampang beton Ac = πD2/4-πD02/4 = 157079,633 mm
4
Momen Inersia penampang beton Ix = π(D4-D04)/64 = 5,105,E+09 mm D
Titik berat penampang ya = yb = D/2 = 300,000 mm
1000
f (MPa)
500
0
0 0,01 0,02 0,03 0,04 0,05 0,06 0,07
ε
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
Beton
Kuat tekan beton kubus K= 600,000
Kuat tekan beton fc' = 50,000 MPa
Modulus elastis beton Ec = 4700√fc' = 33234,019 MPa
Kuat tekan beton saat penarikan fci' = 0,8fc' = 40,000 MPa
Modulus elastis beton saat penarikan Eci = 4700√fci' = 29725,410 MPa
Regangan retak beton εcu = 0,003
3
Berat isi beton γc = 25,000 kN/m
Lingkaran luar
x = a/D = 0,151
y = Atem/Lling = 0,098
y = TBtem/R = 0,825
D0
Lingkaran dalam
x = a0/D0 = -0,024 D
y = Atem/Lling = -0,009
y = TBtem/R = 1,027 Penampang CSP
Luas dan titik berat tiap kondisi Desak dan lentur beton
Lingkaran luar Lingkaran dalam Penampang A (mm2) l (mm) Cc (kN) Mc (kNm)
Kondisi
Atem (mm2) TBtem (mm) Atem (mm2) TBtem (mm) 0,85fc'A Ccl
a≤T 27649,95 247,41 Lingk luar 27649,946 247,411 1175,123 290,738
T<a<(T+D0) 27649,95 247,41 -1085,71 205,37 Lingk dalam 0,000 0,000 0,000 0,000
(T+D0)≤a≤D 27649,95 247,41 125663,71 0,00 Δ 1175,123 290,738
Kekuatan Lentur
Gaya tarik PC Bar Tp = 1175,549 kN
Gaya desak beton Cc = 1175,123 kN
Kuat lentur PC Bar Mp = 163,655 kNm
Kuat lentur beton Mc = 290,738 kNm
Kekuatan lentur Mn = Mp+Mc = 454,393 kNm = 45,603 ton m
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
Dimensi pc bar
2
Luas total pc bar Aps = 0,002 m
4
Momen Inersia pc bar Ixs = Σnπd4/64+ΣAy2 = 0,000 m
4.2. Pengangkatan
Panjang segmen = 20 *m
Jarak titik pengangkatan dari ujung a = 0,2L1 = 4,000 m
Berat sendiri q = Acγc = 3,927 kN/m
Momen lentur tumpuan M1 = qa2/2 = 31,416 kNm
Momen lentur tengah bentang M2 = q(L1-2a)2/8-qa2/2 = 39,270 kNm
Tegangan pada M1
Serat atas fa1 = -Pi/Accomp+M1y/Ixcomp = -7,391 MPa (OK, fizin ≤ f ≤ fizin)
Serat bawah fb1 = -Pi/Accomp-M1y/Ixcomp = -10,861 MPa (OK, fizin ≤ f ≤ fizin)
Tegangan pada M2
Serat atas fa1 = -Pi/Accomp-M2y/Ixcomp = -11,295 MPa (OK, fizin ≤ f ≤ fizin)
Serat bawah fb1 = -Pi/Accomp+M2y/Ixcomp = -6,957 MPa (OK, fizin ≤ f ≤ fizin)
4.3. Erection
Jarak titik pengangkatan dari ujung a = 0,2L1 = 4,000 m
Berat sendiri q = Acγc = 3,927 kN/m
2
Momen lentur tumpuan M1 = qa /2 = 31,416 kN/m
Momen lentur tengah bentang M2 = (1/2)q(L2-2aL1)/(2(L-a)2) = 0,920 kN/m
Tegangan pada M1
Serat atas fa1 = -Pi/Accomp+M1y/Ixcomp = -7,391 MPa (OK, fizin ≤ f ≤ fizin)
Serat bawah fb1 = -Pi/Accomp-M1y/Ixcomp = -10,861 MPa (OK, fizin ≤ f ≤ fizin)
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
Tegangan pada M2
Serat atas fa1 = -Pi/Accomp-M2y/Ixcomp = -9,177 MPa (OK, fizin ≤ f ≤ fizin)
Serat bawah fb1 = -Pi/Accomp+M2y/Ixcomp = -9,075 MPa (OK, fizin ≤ f ≤ fizin)
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
5. Kekuatan geser
Dimensi dan properti material
Diameter sengkang spiral Dv = 4,000 mm
Jarak dari serat tekan terjauh ke pusat tulangan tarik d= 560,000 mm
Lebar badan (web) bw = 2T = 200,000 mm
Kuat tekan beton silinder fc' = 50,000 Mpa
Kekuatan leleh sengkang spiral fyt = 420,000 MPa
Jarak antar sengkang spiral s= 100,000 mm
Referensi
Keterangan
: input
Tulisan : perhatian
Tulisan : pengecekan
1. Data perhitungan
1.1. Dimensi beton
Panjang tiang pancang L= 20,000 m = 20000,000 mm
Diameter penampang D= 600,000 mm
Tebal penampang beton T= 100,000 mm
T
Diameter lubang D0 = D-2T = 400,000 mm d1
2
Luas penampang beton Ac = πD2/4-πD02/4 = 157079,633 mm
4
Momen Inersia penampang beton Ix = π(D4-D04)/64 = 5,105,E+09 mm D
Titik berat penampang ya = yb = D/2 = 300,000 mm
1000
f (MPa)
500
0
0 0,01 0,02 0,03 0,04 0,05 0,06 0,07
ε
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
Beton
Kuat tekan beton kubus K= 600,000
Kuat tekan beton fc' = 50,000 MPa
Modulus elastis beton Ec = 4700√fc' = 33234,019 MPa
Kuat tekan beton saat penarikan fci' = 0,8fc' = 40,000 MPa
Modulus elastis beton saat penarikan Eci = 4700√fci' = 29725,410 MPa
Regangan retak beton εcu = 0,003
3
Berat isi beton γc = 25,000 kN/m
Lingkaran luar
x = a/D = 0,175
y = Atem/Lling = 0,119
y = TBtem/R = 0,796
D0
Lingkaran dalam
x = a0/D0 = 0,013 D
y = Atem/Lling = 0,005
y = TBtem/R = 0,986 Penampang CSP
Luas dan titik berat tiap kondisi Desak dan lentur beton
Lingkaran luar Lingkaran dalam Penampang A (mm2) l (mm) Cc (kN) Mc (kNm)
Kondisi
Atem (mm2) TBtem (mm) Atem (mm2) TBtem (mm) 0,85fc'A Ccl
a≤T 33741,54 238,86 Lingk luar 33741,536 238,865 1434,015 342,535
T<a<(T+D0) 33741,54 238,86 681,14 197,12 Lingk dalam 681,140 197,122 28,948 5,706
(T+D0)≤a≤D 33741,54 238,86 125663,71 0,00 Δ 1405,067 336,829
Kekuatan Lentur
Gaya tarik PC Bar Tp = 1405,702 kN
Gaya desak beton Cc = 1405,067 kN
Kuat lentur PC Bar Mp = 218,807 kNm
Kuat lentur beton Mc = 336,829 kNm
Kekuatan lentur Mn = Mp+Mc = 555,636 kNm = 55,764 ton m
Reduksi kekuatan lentur φ= 0,90
Kekuatan lentur tereduksi φMn = φ(Mp+Mc) = 500,072 kNm = 50,188 ton m
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
Dimensi pc bar
2
Luas total pc bar Aps = 0,002 m
4
Momen Inersia pc bar Ixs = Σnπd4/64+ΣAy2 = 0,000 m
4.2. Pengangkatan
Panjang segmen = 20 *m
Jarak titik pengangkatan dari ujung a = 0,2L1 = 4,000 m
Berat sendiri q = Acγc = 3,927 kN/m
Momen lentur tumpuan M1 = qa2/2 = 31,416 kNm
Momen lentur tengah bentang M2 = q(L1-2a)2/8-qa2/2 = 39,270 kNm
Tegangan pada M1
Serat atas fa1 = -Pi/Accomp+M1y/Ixcomp = -9,986 MPa (OK, fizin ≤ f ≤ fizin)
Serat bawah fb1 = -Pi/Accomp-M1y/Ixcomp = -13,389 MPa (OK, fizin ≤ f ≤ fizin)
Tegangan pada M2
Serat atas fa1 = -Pi/Accomp-M2y/Ixcomp = -13,814 MPa (OK, fizin ≤ f ≤ fizin)
Serat bawah fb1 = -Pi/Accomp+M2y/Ixcomp = -9,561 MPa (OK, fizin ≤ f ≤ fizin)
4.3. Erection
Jarak titik pengangkatan dari ujung a = 0,2L1 = 4,000 m
Berat sendiri q = Acγc = 3,927 kN/m
2
Momen lentur tumpuan M1 = qa /2 = 31,416 kN/m
Momen lentur tengah bentang M2 = (1/2)q(L2-2aL1)/(2(L-a)2) = 0,920 kN/m
Tegangan pada M1
Serat atas fa1 = -Pi/Accomp+M1y/Ixcomp = -9,986 MPa (OK, fizin ≤ f ≤ fizin)
Serat bawah fb1 = -Pi/Accomp-M1y/Ixcomp = -13,389 MPa (OK, fizin ≤ f ≤ fizin)
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
Tegangan pada M2
Serat atas fa1 = -Pi/Accomp-M2y/Ixcomp = -11,737 MPa (OK, fizin ≤ f ≤ fizin)
Serat bawah fb1 = -Pi/Accomp+M2y/Ixcomp = -11,638 MPa (OK, fizin ≤ f ≤ fizin)
PERHITUNGAN TEKNIS CONCRETE SPUN PILE
PT ADHI PERSADA BETON
5. Kekuatan geser
Dimensi dan properti material
Diameter sengkang spiral Dv = 4,000 mm
Jarak dari serat tekan terjauh ke pusat tulangan tarik d= 560,000 mm
Lebar badan (web) bw = 2T = 200,000 mm
Kuat tekan beton silinder fc' = 50,000 Mpa
Kekuatan leleh sengkang spiral fyt = 420,000 MPa
Jarak antar sengkang spiral s= 100,000 mm