You are on page 1of 10

Applied Energy 238 (2019) 1327–1336

Contents lists available at ScienceDirect

Applied Energy
journal homepage: www.elsevier.com/locate/apenergy

Multi-temporal assessment of power system flexibility requirement T


a,b,⁎ a b b
Thomas Heggarty , Jean-Yves Bourmaud , Robin Girard , Georges Kariniotakis
a
Réseau de Transport d’Electricité, La Défense, France
b
MINES ParisTech, PSL University, Center for Processes, Renewable Energies and Energy Systems (PERSEE), Sophia-Antipolis, France

H I GH L IG H T S

• Flexibility refers to a system’s ability to cope with variability and uncertainty.


• Method evaluates flexibility requirement for annual, weekly and daily timescales.
• Global sensitivity analysis is used to identify most impacting factors on flexibility.
• Flexibility requirement depends primarily on renewable generation penetration.
• Interconnection provides increasing flexibility as renewables penetrate the system.

A R T I C LE I N FO A B S T R A C T

Keywords: In power systems, flexibility can be defined as the ability to adapt to variability and uncertainty in demand and
Power system flexibility generation. Various ongoing changes in the power system are impacting the need for flexibility. We propose a
Renewable energy sources impacts novel methodology to (i) evaluate annual, weekly and daily flexibility requirements through a set of frequency
Load temperature sensitivity spectrum analysis based metrics, (ii) examine the sensitivity of these flexibility requirements to five variables:
Frequency spectrum analysis
the degree of network interconnection and the penetration of wind power, solar power, electric heating and
Global sensitivity analysis
cooling. The proposed methodology is validated on a case study focusing on the French power system, while
accounting for its electrically connected neighbours. We provide an estimation of how flexibility requirements
are likely to evolve in years to come; the use of global sensitivity analysis allows the identification of the
variables responsible for these evolutions. The presented methodology and results can be used to identify future
challenges, to evaluate the market potential of flexibility solutions and to assess the implications of policy
decisions.

1. Introduction their simultaneous modelling complex, calling for literature to take a


step back from the lever view and try to understand, define and
1.1. Context quantify flexibility [1–6]. Several definitions have been presented, all
are in general agreement; flexibility is understood as the power system’s
Flexibility has always been required in power systems in order to ability to cope with variability and uncertainty in demand and gen-
match supply and demand1. Driven by the need to meet green house gas eration.
emissions reduction targets, the gradual move from flexible conven- Variability and uncertainty in demand and generation occur on
tional generation to Variable Renewable Energy Sources (VRES) in- several timescales. On the long-term (more than a year), matching
duces growing variability and uncertainty, making the supply and de- supply and demand is made uncertain by the difficulty to predict VRES
mand matching exercise increasingly challenging [1]. A significant development, the evolution of consumer habits, economic growth etc.
number of levers may be activated to provide flexibility to a power On the medium term (annual, weekly and daily horizons), power
system which may be regrouped in four main categories: flexible gen- system operators must face cyclical variations in net load (load minus
eration, flexible demand, energy storage and network interconnection VRES generation). On the short-term (intra-day), power system opera-
[2]. The wide variety of their characteristics and constraints makes tion is constrained by uncertainty through incidents and forecastability


Corresponding author.
E-mail address: thomas.heggarty@rte-france.com (T. Heggarty).
1
In this paper, only flexibility for adequacy purposes is considered. In Europe, supply-demand matching is performed at the national scale, hence in this study, the
power system can be understood as the national grid.

https://doi.org/10.1016/j.apenergy.2019.01.198
Received 3 October 2018; Received in revised form 21 January 2019; Accepted 22 January 2019
0306-2619/ © 2019 Elsevier Ltd. All rights reserved.
T. Heggarty et al. Applied Energy 238 (2019) 1327–1336

Nomenclature (annual, weekly or daily)


FPR (T ) Flexible Power Requirement, for a given timescale (an-
Input parameters nual, weekly or daily)

Lti (t ) temperature insensitive load time series (MW) Long-term variables impacting flexibility requirement
Lheat (t ) electric heating load time series (MW)
Lcool (t ) electric cooling load time series (MW) pheat electric heating penetration (unitless)
W (t ) wind generation time series (MW) pcool electric cooling penetration (unitless)
S (t ) solar generation time series (MW) pwind wind penetration (unitless)
c, cc country, central country psolar solar penetration (unitless)
I interconnection capacity (MW)
Proposed metrics

FER (T ) Flexible Energy Requirement, for a given timescale

of demand and VRES generation. Requirement is therefore expressed in terms of power and energy. Such
This paper proposes (i) a set of metrics quantifying annual, weekly studies have focussed on short-term phenomena, such as the mismatch
and daily flexibility requirements (i.e. the amount of flexibility resource between scheduled generation and actual load [8] or reducing the
needed for each timescale, not presuming the lever that might supply difference between forecast and actual wind power generation [9].
it), and (ii) a methodology to analyse the sensitivity of these require- Longer timescale phenomena can also be observed with these metrics
ments to five uncertain long-term variables: the degree of network in- [10,11]. However, in these last two studies, power and energy metrics
terconnection and the penetration of wind power, solar power, electric do not express a flexibility requirement inherent to a load curve, but
heating and cooling. provide storage characteristics, which were jointly optimised with
generation, VRES curtailment or network (which are themselves flex-
ibility providers).
1.2. Review of flexibility metrics
The literature already provides ample metrics evaluating a system’s
need for intra-day flexibility. However, flexibility is a multi-timescale
Researchers have proposed a variety of flexibility metrics illus-
issue [17]. This paper builds upon and generalises state-of-the-art ap-
trating distinct properties or phenomena, leading authors to suggest
proaches to express flexibility requirement on the annual, weekly and
that flexibility cannot be understood through a single indicator [1,2,7].
daily timescales. Flexibility requirement, inherent to a load curve, is
Depending on their role, metrics can be split into three categories [7]:
expressed in terms of power and energy.
those who evaluate a resource’s ability to provide flexibility, a system’s
ability to provide flexibility and a system’s need for flexibility. Table 1
provides a non-exhaustive overview of metrics used to provide insight 1.3. Variables impacting flexibility requirement
for long-term planning.
Other studies aiming to evaluate a system’s need for flexibility use Power system flexibility requirement is affected by several un-
storage as a proxy for flexibility, i.e. they try to determine how much certain long-term variables; VRES penetration has been the most in-
storage would be needed to cope with variability and uncertainty. vestigated. An early study by Holttinen et al. [17] analysed the effect of

Table 1
Non-exhaustive overview of flexibility metrics for long-term planning purposes.
Type Role Metric Comment

Evaluating a resource’s ability to Compare different flexibility resources, commonly used as Ramp rate Characterise flexible generation, flexible load
provide flexibility input parameters in dispatch models Minimum up/down time or storage [12]
Start-up time
Response time
Minimum power output
Energy capacity Characterises storage or flexible load [13]
Rebound effect Characterise flexible load [13]
Recovery period

Evaluating a system’s ability to Analyse long-term power system data or the outputs of Weighted sums of resource Analysis can be performed without a dispatch
provide flexibility dispatch models, allowing a straightforward comparison of flexibility metrics model [14]
complex systems Loss Of Load Probability Standard adequacy metrics giving
Loss Of Load Duration probability, duration and volume of loss of
Expected Unserved Energy load [15]
Periods of Flexibility Deficit Number of periods where there is less flexible
resource available than required [3,16]
Insufficient Ramping Probabilistic equivalent to the Periods of
Resource Expectation Flexibility Deficit metric [3,16]
Expected Unserved Reflects the magnitude of the ramping
Ramping shortage [16]

Evaluating a system’s need for Analyse net load curves to evaluate implications of energy One or multiple hour ramp Derivative of net load over time, expressed in
flexibility policy decisions and improve the understanding of potential MW or as a percentage [4,5,17]
challenges Ramp acceleration Double derivative of net load over time [5]
Volatility Sum of ramp accelerations over a certain time
period [5]

1328
T. Heggarty et al. Applied Energy 238 (2019) 1327–1336

large wind penetrations on ramps, showing an increase in their mag- knowledge, there has been very little work on quantifying flexibility
nitude and change in their occurrence patterns, both diurnal and requirement. This paper bridges this gap by proposing a set of fre-
monthly. Using one and multiple hour ramps, Huber et al. [4] have quency spectrum analysis based indicators that allow the separation of
extended the analysis to both onshore wind and solar photovoltaics annual, weekly and daily flexibility requirements, the three relevant
impacts on European net load curves. Deetjen et al. [5] have performed timescales when considering load and net load (load minus VRES
a similar study on the ERCOT system, with a wide variety of ramp generation) variability.
derived indicators. Both of these studies highlight the fact that in- Flexibility requirement is affected by several uncertain long-term
creased solar photovoltaics penetration generates a significant addi- variables, which have up to now been investigated separately. This
tional ramping requirement, the effect of wind is much more limited. In paper provides novel insights by simultaneously examining flexibility
another study, Belderbos et al. [10] optimise a storage portfolio for requirement sensitivity to the penetration of wind power, solar power,
different so called remaining load profiles, where both VRES and con- electric heating and cooling, as well as to the degree of interconnection.
ventional generation are subtracted from load. Steinke et al. [11] aim to The impact of these variables on each timescale is examined, along with
determine the backup generation required in a high VRES share system, the interactions between variables. An estimation of how flexibility
examining the potential role of storage and interconnection. In both requirements are expected to evolve is provided; the use of Global
these last two studies, it can be seen that for increased VRES shares, the Sensitivity Analysis (GSA) enables the identification of the variables
storage energy capacity requirement is much more affected than the responsible for the expected evolutions.
power capacity requirement. Another strength of this study lies with the input data used, which
The specificity of network interconnection when compared to other gives a thorough probabilistic view: the load and VRES time series used
flexibility solutions makes it quite complicated to characterise it in the are based on 200 years of Météo-France synthetic weather data, ex-
same way. As such, the degree of interconnection can be an interesting pressing temporal, spatial and inter-variable correlations.
parameter to vary when evaluating flexibility requirement. Expressing This paper starts by presenting the proposed methodology (Section
the ability of grid interconnection to average net load over space has 2), then applies it to a case study (Section 3) focusing on the French
been a focus point of several aforementioned studies [4,11]. The Eur- power system, while accounting for its electrically connected neigh-
opean project e-Highway 2050 [18] developed a scenario based bours. Chosen for data availability reasons and authors’ personal in-
methodology to determine least regret options for European grid ex- terests, it is an interesting system to examine as all five of the con-
pansion. In two other studies, Fursch et al. [19] and Kristiansen et al. sidered long-term variables are expected to evolve significantly in years
[20] highlight the grid’s role in capacity expansion modelling. to come, as France undergoes its energy transition. Results for other
Another key variable affecting flexibility requirement is load tem- European countries are occasionally shown or mentioned to provide a
perature sensitivity, which so far has not been treated as such by the reference and discuss limitations in results. Sections 2 and 3 are given
literature. Papers on the subject adopt a policy approach, examples of an introduction to specify their purpose and internal structure. The
which are analyses of long-term climate change impacts on European conclusion (Section 4) summarises key findings, discusses differences in
load curves [21,22], or the implications of an ongoing increase of results had the case study been performed on another country and
temperature sensitivity of summer electricity demand on asset main- briefly mentions ongoing work.
tenance scheduling [23]. Several papers issue a warning to countries
considering heat electrification, in a move towards heat decarbonisa- 2. Methodology
tion [24–26]. The security of supply risk and the approximate asso-
ciated cost resulting from this added load variability is quantified. 2.1. Introduction

1.4. Key contributions and paper structure A general overview of the proposed methodology is shown in Fig. 1,
it also states in which subsection each step is detailed.
Flexibility reflects the power system’s ability to adapt to variability
and uncertainty in demand and generation, which occur on different 2.2. Data used
timescales. The research presented in this paper aims to determine (i)
how and (ii) why medium-term (annual, weekly and daily) flexibility Météo-France, the French national meteorological service, has de-
requirement will evolve under the influence of long-term (more than a veloped the ARPEGE-Climat model which, coupled with ocean, sea ice
year) variables. These are the first two steps towards determining how and surface models, simulates long-term climate evolution [27]. With
the system is to adapt to its changing environment. energy related applications in mind, Météo-France has used this model
Studies evaluating the need for flexibility have so far been short- to produce 200 years of synthetic weather time series, representative of
term (intra-day) focussed. On the medium-term, to the best of our our current climate [28]. Covering the whole globe, outputs are

Fig. 1. General overview of the proposed methodology.

1329
T. Heggarty et al. Applied Energy 238 (2019) 1327–1336

expressed at hourly and, for Europe, 0.5° latitude and longitude re- system cc Ic c
Lnet (t ) = Lnet (t ) + ∑ Lc
Lnet (t )
solutions. c (3)
RTE, the French Transmission System Operator (TSO), has derived
wind and solar generation as well as load data from these weather time where:
series, allowing temporal, spatial and inter-variable correlations to be
kept [29]. Used in numerous studies including the French adequacy cc central country
report, legal obligation of RTE [30], these time series are the basis of I interconnection capacity (MW)
the analysis presented in this paper, defined at hourly and national For the purpose of Global sensitivity analysis, several tens of thou-
resolutions, for France and all its electrically connected neighbours. sands of combinations of I , pwind , psolar , pheat and pcool are sampled from
Load is modelled using a bottom-up approach [30]; electric heating and uniform distributions within specific intervals.
cooling load could therefore be varied independently from temperature I c represents the capacity of country c’s link with the central
insensitive load. country. Divided by c’s mean load, it indicates the proportion of c’s net
load that is included in the system net load. For each neighbouring
2.3. Building the system net load curve country, a specific interval is defined based on current and prospective
interconnection capacities. A single relative position inside those in-
As shown in Eq. (1), each country’s load is composed of three parts: tervals is sampled. For example, if countries A and B have intervals of
a temperature insensitive one, a heating one and a cooling one. [2000,4000] and [0,1000], a result of the sampling could be
I A = 2800 MW and I B = 400 MW.
Lc (t ) = Ltic (t ) + pheat
c c
Lheat c
(t ) + pcool c
Lcool (t ) (1) pwind represents the share of load covered by wind generation,
where: averaged over the 200 years of synthetic data. Multiplied by the
200 year mean load over the 200 year mean wind generation, it acts as
t time, from hour 1 to hour 8760 ∗ 200 a scaling factor of a homothetic transformation, ensuring that the wind
c country generation time series covers the required load share. psolar works in a
pheat electric heating penetration (unitless) similar way. The sampling of pwind and psolar is done in the same way as
pcool electric cooling penetration (unitless) I: each country is given an interval reflecting local potential and ob-
Lti (t ) temperature insensitive load time series (MW) jectives and a single relative position in those intervals is sampled. In
Lheat (t ) electric heating load time series (MW) other words, VRES deployment is assumed to be synchronous across
Lcool (t ) electric cooling load time series (MW) countries, but each at its own pace.
Each country’s net load is defined as follows:
pheat and pcool are factors that reflect the volume of electric heating
and cooling load respective to an initial situation. Individual country
c c Lc c c Lc c policy regarding heating cannot be assumed to be synchronous (e.g.
Lnet (t ) = Lc (t ) − pwind W (t ) − psolar S (t )
Wc Sc (2) France is trying to reduce its electric heating demand while the UK and
where: Germany are considering heat electrification). Therefore, only the
central country’s pheat and pcool were varied. A country’s flexibility re-
quirement sensitivity to it’s neighbours’ load temperature sensitivity
pwind wind penetration (unitless)
could also be evaluated, but this would require adding variables to be
psolar solar penetration (unitless)
sampled, severely affecting computational time.
W (t ) wind generation time series (MW)
S (t ) solar generation time series (MW)
Lc , W c , S c 200 year mean load, wind and solar generation 2.4. Separating the signal components
The system net load curve can then be built, on the basis of which
flexibility requirements can be evaluated. This curve, defined in Eq. (3), Load curves show clear cyclical patterns of various time periods:
is composed of a central country’s net load and parts of its neighbours’ demand is higher during the day than during the night, higher during
net loads. weekdays than the weekend, and either higher in summer or winter

Fig. 2. Cumulative frequency spectrum share of national load curves.

1330
T. Heggarty et al. Applied Energy 238 (2019) 1327–1336

depending on geographical location. These patterns are sufficiently respectively, both in terms of power and energy (FPR (w ), FER (w ),
deterministic that, using a Fourier series based model, Yukseltan et al. FPR (d ), FER (d ) ).
[31] were able to predict Turkish national load within 3% Mean Ab- In order to reflect the benefit brought by interconnection, the re-
solute Percentage Error. Frequency based approaches have also been sulting flexibility requirements were then normalised by the system’s
adopted for storage sizing [8–10,32], for short-term VRES forecasting maximum load for the flexible power requirement and by the system’s
[33–35] or simply as a visualisation tool to complement the time do- mean annual demand for the flexible energy requirement (n.b. not net
main vision [36,37]. load).
Fig. 2 offers a view of national load curves in the frequency domain,
expressed as a cumulative share of power spectral density. The load
data used is the one described in Section 2.2, with 2017 electric heating 2.6. Global sensitivity analysis
and cooling penetrations. It can be seen that a selected few frequency
components (annual, weekly and its harmonics, daily and semi-daily) Flexibility requirement sensitivity to X = [I , pwind , psolar , pheat , psolar ]
contain most of the information carried in the signal. It can also be seen was evaluated using the global sensitivity analysis Sobol method [38].
that the balance between these frequency components varies from one This variance-based method quantifies the contribution of each input
country to another, the most obvious example being the very significant variable to the output’s variance. It has been used regularly on energy
annual component in the French load curve due to the high penetration related matters [39–43] and shows significant advantages over other
of electric heating. sensitivity analysis methods: it makes no assumption on the model’s
Flexibility requirements were to be quantified for three timescales: behaviour (e.g. linearity), provides straightforward interpretation
annual, weekly and daily. Hence, net load curve data was first fed through quantitative ranking of variable importance and is capable of
through a Discrete Fourier Transform (see Eq. (4)), then, using a similar evaluating interactions effects between variables [44]. However, the
method to the one used by Makarov et al. [8], band pass filters with method assumes variable independence and can be computationally
unit magnitude within the band and zero magnitude outside the band expensive, all the more so as the number of considered variables in-
were applied, with cut off frequencies at 20 and 180 year−1 i.e. periods creases [44,45].
of about 18 and 2 days. The DC offset was removed prior to the filtering Based on Monte Carlo runs of the flexibility requirement module
process. previously described, the method calculates first order (see Eq. (5)) and
N −1
total (see Eq. (6)) Sobol indices.
Xf = ∑ x t e−i2πft / N f = 0, …, N − 1
VXi (EX ∼ i (Y Xi ))
t=0 (4) Si =
V (Y ) (5)
The three resulting signals were then passed back into time domain
using the inverse Fourier Transform.
EX ∼ i (VXi (Y X ∼ i))
STi =
V (Y ) (6)
2.5. Evaluating flexibility requirement

The numerators in Eqs. (5) and (6) respectively represent ”the expected
For each year of the low-frequency time series, the difference be-
reduction in variance that would be obtained if Xi could be fixed” and
tween its minimum and maximum levels was recorded; the resulting
”the expected variance that would be left if all factors but Xi could be
vector of 200 values was defined as the annual flexible power re-
fixed” [45]. Si therefore gives the effect of factor by itself, while STi gives
quirement (FPR (a) ). Similarly, the integral of the low frequency time
the total effect of a factor, including its interactions with other factors.
series was computed, obtaining what could be equated as a ”stock
The Sobol method needs a single output value to work with, not a
level”. The difference between the minimum and maximum of this
vector. As a result, the sensitivity analysis was performed on the 95th
”stock level” was recorded; the resulting vector of 200 values was de-
percentile of flexibility requirement distributions. This is a fairly arbi-
fined as the annual flexible energy requirement (FER (a) ).
trary choice, however, varying the chosen percentile between 90 and
The process was repeated for each week of the mid-frequency and
100 was shown to have negligible impact on results.
each day of the high-frequency parts of the load curve signal, obtaining
200 ∗ 52 and 200 ∗ 365 values for weekly and daily requirements

Fig. 3. Flexibility requirements for different timescales and different countries. Electric heating and cooling levels are at 2017 levels, VRES generation has not been
deduced from the load, interconnection has not been taken into account.

1331
T. Heggarty et al. Applied Energy 238 (2019) 1327–1336

3. Case study normalised by the system’s maximum load (n.b. not net load). Similarly,
the energy requirement was normalised by the system’s mean annual
3.1. Introduction demand. For reference, in 2017, France had solar and wind penetra-
tions of about 2% and 5% respectively.
GSA has certain limits which prevent it from providing a full picture From a yearly perspective, solar generation and French electricity
of the flexibility problem. If it expresses flexibility requirement’s sen- demand are out of phase, hence solar penetration increases the annual
sitivity to input variables, it does not give the flexibility requirement flexibility requirement. For wind generation, the situation is more
itself nor its balance between different timescales, it does not convey complex: it is in phase with net demand up to a certain threshold under
the sign of the output’s sensitivity to an input variable (positive or which wind penetration reduces the flexibility requirement. This
negative contribution to flexibility) and it ignores effects outside of the threshold is high for the flexible energy requirement, however, due to
chosen intervals. its volatility, wind power quickly becomes detrimental where flexible
For these reasons, the case study will start by setting the context by power requirement is concerned.
applying the flexibility requirement sizing method to current load From the direction of isolines, it can be seen that when a VRES type
curves. The impact of the input variables on flexibility requirement will dominates, the flexible power requirement is determined solely by that
then be illustrated by a few 2 dimensional cuts of the 5 dimensional type’s penetration. This is not the case for the flexible energy require-
problem, for a wide range of values. Finally, a prospective power sys- ment which mostly depends on solar penetration.
tem’s flexibility requirements will be presented, GSA will be used to Maximising VRES penetration for a given annual flexibility re-
express each input variable’s contribution to flexibility requirement quirement will give a wind dominated electricity mix (more so for
evolution. energy than power). This conclusion is affected if electric heating pe-
netration is reduced: this causes a reduction in flexibility requirement,
3.2. Base case particularly in solar dominated mixes. For the energy requirement, it
also reduces the threshold beyond which wind becomes detrimental
The method described in Section 2.5 was applied to the data de- (this threshold is beyond 50% wind penetration for the 2017 French
scribed in Section 2.2. Load curves were constructed using 2017 electric situation). Another illustration of this can be seen by analysing the si-
heating and cooling levels, each country was treated by itself i.e. no tuation of different countries: where there is summer peak load or less
interconnections were taken into account, VRES generation curves were electric heating, high VRES mixes less in favour of wind generate lesser
not deducted from the load. annual flexibility requirements.
The results of the flexibility requirement evaluation are shown using Fig. 5 shows the annual flexibility requirements in terms of VRES
two violin plots in Fig. 3. This graphical representation shows the full and network interconnection development. A development of 1 corre-
distribution of flexibility requirements (200, 200 ∗ 52 and 200 ∗ 365 sponds to that of the Ampere Scenario in 2036, as described in RTE’s
values for annual, weekly and daily requirements respectively). The 2017 adequacy report [30]. This scenario corresponds to ambitious
width of each distribution has been normalised so that the area of each VRES development in western Europe and slightly conservative net-
violin in a plot is equal. A summary of the considered power systems’ work interconnection development; a brief description is provided in
modelled demands is shown in Table 2. Table 3. The balance between wind and solar and between border ca-
The flexible power requirement is of the same order of magnitude pacities is kept constant throughout the plots, meaning that the 2017
for the three considered time horizons. Conversely, the flexible energy situation is not represented. However, it would roughly be placed at 0.1
requirement is much higher for longer timescales: the annual require- VRES and 0.7 interconnection.
ment is 100 to 1000 times more important than the daily requirement. The main conclusion to draw from these graphs is that the expected
This general observation was also made in previous papers [8–10]. network development will compensate most of the increase in annual
It can also be noted that for the flexible power requirement, the flexible energy requirement caused by VRES development, but only a
balance between the three time horizons is not the same in each small fraction of the increase in annual flexible power requirement. One
country. In France, the electric heating penetration induces a very high can also note that, both for power and energy, network interconnection
annual flexibility requirement, relative to the country’s annual and provides more value as VRES penetration increases (reduced vertical
peak load. This sensitivity to temperature also generates particularly gap between isolines as VRES development increases) and that the
wide distributions of annual and weekly requirements, both in terms of value brought by interconnection decreases as new interconnection is
power and energy. added (increased vertical gap between isolines as interconnection de-
velopment increases).
3.3. Input variable impact on flexibility requirement Varying the balance between solar and wind slightly changes these
conclusions. From a yearly perspective, network interconnection pro-
Network interconnection, wind, solar, electric heating and cooling vides value no matter the electricity mix, but more so in wind domi-
penetrations all affect flexibility requirement in different ways, on nated ones. As can be understood by bearing Fig. 4 in mind, when solar
different time-scales and to various degrees. Bearing succinctness and plays a more prominent role, network development is unable to com-
clarity in mind, a select number of level-plots of flexibility requirement pensate the dramatic increase in flexible energy requirement.
with respect to pairs of input variables are presented. The effect of Fig. 6 shows the annual flexibility requirements in terms of VRES
varying other variables is discussed when relevant. and electric heating penetrations. VRES development is expressed in the
same manner as for Fig. 5; an electric heating penetration of 1 corre-
3.3.1. Annual flexibility requirement sponds to 2017 levels.
Fig. 4 shows the 95th percentile of the need for annual flexible Save for low VRES penetration cases, reducing the penetration of
power and energy observed in the French net load curve (FPR (a) and
FER (a) ). Again, the choice of the 95th percentile is fairly arbitrary, but
Table 2
varying the percentile between 90 and 100 had negligeable impact on
Summary of considered power systems’ demand.
the general shape of results. The requirements are expressed in terms of
solar and wind penetrations (0.3 wind indicates that on average, 30% of France Germany Great Britain Italy
annual energy demand is covered by wind generation). Electric heating
Mean annual load (TWh) 480 553 329 309
and cooling were set to their 2017 value, interconnection was set to Peak load (GW) 112.2 86.9 63.7 54.4
zero. As mentioned in Section 2.5, the power requirement was

1332
T. Heggarty et al. Applied Energy 238 (2019) 1327–1336

Fig. 4. 95th percentile of annual flexible power requirement FPR (a) in MW/MW (normalised by system maximum load, left) and energy requirement FER (a) in
TWh/TWh(normalised by system mean annual demand, right) in terms of wind and solar penetrations.

electric heating barely has any impact on the annual flexible power Table 3
requirement, the intermittent nature of wind being too much of a Ampere scenario 2036 description.
constraint. For high VRES cases, it even slightly increases the require- Country pwind psolar I /L
ment. However, reducing electric heating penetration is beneficial
where annual flexible energy is concerned and can compensate to some France 0.34 0.12 NA
degree the increasing requirement caused by increased VRES penetra- Great Britain 0.42 0.09 0.17
Belgium 0.26 0.08 0.48
tions.
Germany 0.40 0.13 0.07
As for electric cooling, it causes an insignificant decrease in annual Switzerland 0.02 0.09 0.50
flexibility requirement for very low VRES penetrations. There is too Italy 0.12 0.14 0.09
little electric cooling load in France for it’s penetration to have much of Spain 0.32 0.25 0.15
an impact in the foreseeable future.

electric cooling penetrations has next to no impact.


3.3.2. Weekly flexibility requirement The observations made in Section 3.2 concerning the balance of
Fig. 7 shows the 95th percentile of the need for weekly flexible requirements between different timescales partially hold. The flexible
power and energy observed in the French net load curve (FPR (w ) and energy requirement remains 2–3 orders of magnitude smaller on the
FER (w ) ), expressed in terms of solar and wind penetrations. Electric weekly timescale than the annual one. However, the dominating flex-
heating and cooling were set to their 2017 value, interconnection was ible power requirement can vary: network interconnection and electric
set to zero. As seen previously, the power requirement was normalised heating penetration reduction having more impact on the annual re-
by the system’s maximum load (n.b. not net load), the energy re- quirement than the weekly one, even in France, when wind penetration
quirement by the system’s average annual demand. Note that the scale is high, weekly flexible power requirement can be the most important.
for the flexible energy requirement is different from the one used in
Section 3.3.1.
From a weekly perspective, if solar penetration has a slight impact 3.3.3. Daily flexibility requirement
for low wind penetrations, flexibility requirement is primarily a func- Fig. 8 shows the 95th percentile of the need for daily flexible power
tion of the share of wind in the electricity mix. It is interesting to note and energy observed in the French net load curve (FPR (d ) and FER (d ) ),
that the interactions between wind and solar are of the same nature for expressed in terms of solar and wind penetrations. Electric heating and
both flexible energy and flexible power requirements, contrary to the cooling were set to their 2017 value, interconnection was set to zero.
annual timescale. Interconnection development has a very limited im- Note that the scale for the flexible energy requirement is different from
pact for low VRES penetrations, but induces a notable requirement the one used in Sections 3.3.1 and 3.3.2.
reduction in high VRES mixes. Reducing electric heating or increasing From a daily perspective, solar generation and electricity demand

Fig. 5. 95th percentile of normalised annual flexible power (left) and energy (right) requirement in terms of VRES and network developments.

1333
T. Heggarty et al. Applied Energy 238 (2019) 1327–1336

Fig. 6. 95th percentile of normalised annual flexible power (left) and energy (right) requirement in terms of VRES and electric heating penetrations.

are in phase, thus slightly reducing the flexibility requirements (both the expected network interconnection development and heating pene-
power and energy), up to a certain threshold. Beyond that threshold, tration reduction being insufficient to match the increase in require-
however, flexibility requirements are drastically increased (this phe- ment caused by wind (and to a much smaller degree, solar) power
nomenon is well illustrated by the famous ”duck curve”). For high solar development, (ii) the weekly flexible power requirement will become
penetrations, the flexible power requirement is higher than what was very variable, its maximum will double under the sole influence of wind
observed for annual and weekly requirements, and higher even than power development, exceeding the maximum annual requirement, (iii)
Pmax (i.e. curtailment is required if load is not adapted). Wind pene- the daily flexible power requirement will become very variable, its
tration has somewhat of an effect for low solar penetrations, slightly maximum will double almost entirely due to solar power development,
increasing the daily flexibility requirements (more so for energy than reaching the current level of annual requirement.
power). Varying network interconnection, electric heating or cooling If input variable values are sampled in the interval [Ampere 2036,
penetrations has next to no impact. 1.5 x Ampere 2036], GSA results are not particularly affected; if any-
The threshold beyond which solar starts causing an increase in daily thing, the dependency of French flexible power requirements on VRES
flexibility requirement varies with the considered country, it tends to levels is further enhanced.
occur at higher penetrations in southern European countries compared Similarly, the following conclusions may be drawn regarding flex-
to northern European ones. ible energy: (i) the annual flexible energy requirement will slightly
decrease, expected wind and network interconnection development and
electric heating penetration reduction compensating the upward effect
3.4. Prospective power system flexibility requirements
of solar power development, (ii) the weekly flexible energy requirement
will become more variable, its maximum will double solely due to wind
Fig. 9 shows the distributions of normalised flexibility requirements
power development, but will remain about 25 times smaller than the
in 2017 and in the Ampere Scenario in 2036 (see Table 3). Results are
annual requirement, (iii) the daily flexible power requirement will
evaluated on net load curves, network interconnections have been
become more variable, its maximum will double due to VRES devel-
considered, electric heating and cooling penetrations in 2036 are set at
opment, but will remain about 250 times smaller than the annual re-
0.89 and 2.5 respectively (relative to values of 1 for 2017).
quirement.
Fig. 10 shows the first order Sobol indices of I, pwind , psolar , pheat and
GSA results for flexible energy requirement are slightly sensitive to
pcool , for flexible power and energy requirements. The input variable
the chosen boundaries. If input variable values are sampled between 1
values were sampled in the interval [2017, Ampere 2036] using a
and 1.5 times Ampere Scenario development in 2036, (i) network in-
uniform distribution. The sum of first order indices being very close to
terconnection has an increased impact on the annual timescale, the
one, total Sobol indices have not been shown.
impact of electric heating and wind power is reduced, (ii) network in-
Combining results from Figs. 9 and 10 with observations made in
terconnection starts having a slight impact on the weekly timescale, (iii)
Section 3.2, the following conclusions may be drawn regarding flexible
solar power becomes the sole determinant on the daily timescale.
power: (i) the annual flexible power requirement will slightly increase,

Fig. 7. 95th percentile of normalised weekly flexible power (left) and energy (right) requirement in terms of wind and solar penetrations.

1334
T. Heggarty et al. Applied Energy 238 (2019) 1327–1336

Fig. 8. 95th percentile of normalised daily flexible power (left) and energy (right) requirement in terms of wind and solar penetrations.

4. Conclusions daily ones by one or two orders of magnitude, (iii) daily flexibility re-
quirements are highly dependent on solar penetration, (iv) weekly
This paper presents a new set of frequency spectrum analysis based flexibility requirements are highly dependent on wind penetration, and
indicators quantifying annual, weekly and daily flexibility require- (v) annual flexibility requirements are a function of several factors.
ments, expanding the current metric paradigm which has concentrated The presented flexibility requirement quantification methodology
on shorter timescales. The proposed methodology also allows the ex- and results can be used by system operators to identify and understand
amination of these requirements’ sensitivity to five variables: the degree future challenges, by flexibility providers to evaluate market potential
of network interconnection and the penetration of wind power, solar for their solution and by policy makers to assess the implications of
power, electric heating and cooling. These indicators have been applied their decisions.
to a case study, evaluating flexibility requirements for potential evo- Having determined how and why flexibility requirement is likely to
lutions of the French power system, accounting for interconnection evolve under the influence of a set of long-term variables, the next step
with electrically connected countries. A particular focus was given to is to explore how the power system can adapt to its changing en-
the 2017 situation and to an ambitious scenario for 2036. vironment. The aim of ongoing work is to obtain an optimal combi-
The Global Sensitivity Analysis has shown that the most impacting nation of flexibility solutions, to see how this optimum is affected by the
variables differ with the considered aspect of the flexibility problem. same set of long-term variables and to try and establish links between
Both daily and weekly requirements are set to increase, the prior pri- optimal combinations and sets of flexibility requirement. Solutions have
marily due to solar power development, the latter almost exclusively a wide variety of characteristics and constraints, they will compete for a
due to wind power development. On the annual timescale, electric limited economic potential for each requirement, may have contra-
heating penetration reduction, wind power development and network dictory effects on different timescales or may have cascading effects:
interconnection should overcome the increasing effect of solar power long-term levers could also provide short-term flexibility. The optimal
where flexible energy is concerned. In terms of flexible power, wind flexibility mix must therefore be determined using a holistic approach,
power should drive the requirement up. taking into consideration the entire energy system, different time hor-
These conclusions are valid for France, they may change with lo- izons, on a wide geographical scale.
cation, depending on VRES penetrations, on the balance between wind
and solar power and on the amount of electric heating. Several general
conclusions can however be drawn: (i) flexible power requirements are Acknowledgements
of the same order of magnitude for annual, weekly and daily timescales,
(ii) annual flexible energy requirements are greater than weekly and We would like to thank the anonymous reviewers for their valuable
comments. Data and funding for the research presented in this paper

Fig. 9. Flexibility requirements evaluated with I , pwind , psolar , pheat and pcool set at 2017 and Ampere scenario 2036 levels.

1335
T. Heggarty et al. Applied Energy 238 (2019) 1327–1336

Fig. 10. GSA results for flexible power (left) and flexible energy (right) requirements.

was provided by RTE, the French Transmission System Operator. Time [21] Eskeland GS, Mideksa TK. Electricity demand in a changing climate. Mitig Adapt
series were derived by RTE on the basis of data produced by Météo- Strat Glob Change 2010;15:877–97.
[22] Wenz L, Levermann A, Auffhammer M. North–south polarization of european
France, the French national meteorological service. electricity consumption under future warming. Proc Nat Acad Sci 2017:201704339.
[23] Hekkenberg M, Benders R, Moll H, Uiterkamp AS. Indications for a changing
electricity demand pattern: the temperature dependence of electricity demand in
References the netherlands. Energy Policy 2009;37:1542–51.
[24] Quiggin D, Buswell R. The implications of heat electrification on national electrical
[1] Holttinen H, Tuohy A, Milligan M, Lannoye E, Silva V, Müller S, et al. The flexibility supply-demand balance under published 2050 energy scenarios. Energy
workout: managing variable resources and assessing the need for power system 2016;98:253–70.
modification. IEEE Power Energy Mag 2013;11:53–62. [25] Eyre N, Baruah P. Uncertainties in future energy demand in uk residential heating.
[2] Lund PD, Lindgren J, Mikkola J, Salpakari J. Review of energy system flexibility Energy Policy 2015;87:641–53.
measures to enable high levels of variable renewable electricity. Renew Sustain [26] Boßmann T, Staffell I. The shape of future electricity demand: exploring load curves
Energy Rev 2015;45:785–807. in 2050s germany and britain. Energy 2015;90:1317–33.
[3] Lannoye E, Flynn D, O’Malley M. Transmission, variable generation, and power [27] Météo-France, CNRM, ARPEGE-Climate Version 5.2 Algorithmic Documentation;
system flexibility. IEEE Trans Power Syst 2015;30:57–66. 2011.
[4] Huber M, Dimkova D, Hamacher T. Integration of wind and solar power in europe: [28] Veysseire M, Martinoni S, Farges S. Scénarios à climat constant; 2016. https://bit.
assessment of flexibility requirements. Energy 2014;69:236–46. ly/2qLSe0d.
[5] Deetjen TA, Rhodes JD, Webber ME. The impacts of wind and solar on grid flex- [29] Delenne B, De Montureux C, Veysseire M, Farges S. Using weather scenarios for
ibility requirements in the electric reliability council of texas. Energy generation adequacy studies; 2015. https://bit.ly/2J5PTET.
2017;123:637–54. [30] RTE, Bilan Prévisionnel de l’équilibre offre-demande d’électricité en France,
[6] Kondziella H, Bruckner T. Flexibility requirements of renewable energy based Technical Report, RTE; 2017.
electricity systems–a review of research results and methodologies. Renew Sustain [31] Yukseltan E, Yucekaya A, Bilge AH. Forecasting electricity demand for turkey:
Energy Rev 2016;53:10–22. modeling periodic variations and demand segregation. Appl Energy
[7] Lannoye E, Flynn D, O’Malley M. Power system flexibility assessment-state of the 2017;193:287–96.
art. Power and Energy Society General Meeting, 2012 IEEE. IEEE; 2012. p. 1–6. [32] Barton JP, Infield DG. Energy storage and its use with intermittent renewable en-
[8] Makarov YV, Du P, Kintner-Meyer MC, Jin C, Illian HF. Sizing energy storage to ergy. IEEE Trans Energy Convers 2004;19:441–8.
accommodate high penetration of variable energy resources. IEEE Trans Sustain [33] Mellit A, Benghanem M, Kalogirou SA. An adaptive wavelet-network model for
Energy 2012;3:34–40. forecasting daily total solar-radiation. Appl Energy 2006;83:705–22.
[9] Oh E, Son S-Y. Energy-storage system sizing and operation strategies based on [34] Shamshirband S, Mohammadi K, Khorasanizadeh H, Yee L, Lee M, Petković D, et al.
discrete fourier transform for reliable wind-power generation. Renew Energy Estimating the diffuse solar radiation using a coupled support vector machine–-
2018;116:786–94. wavelet transform model. Renew Sustain Energy Rev 2016;56:428–35.
[10] Belderbos A, Virag A, D’haeseleer W, Delarue E. Considerations on the need for [35] Tascikaraoglu A, Sanandaji BM, Poolla K, Varaiya P. Exploiting sparsity of inter-
electricity storage requirements: power versus energy. Energy Convers Manage connections in spatio-temporal wind speed forecasting using wavelet transform.
2017;143:137–49. Appl Energy 2016;165:735–47.
[11] Steinke F, Wolfrum P, Hoffmann C. Grid vs. storage in a 100% renewable europe. [36] Alam MM, Rehman S, Al-Hadhrami LM, Meyer JP. Extraction of the inherent nature
Renew Energy 2013;50:826–32. of wind speed using wavelets and fft. Energy Sustain Dev 2014;22:34–47.
[12] Langrene N, van Ackooij W, Bréant F. Dynamic constraints for aggregated units: [37] Chang T-P, Liu F-J, Ko H-H, Huang M-C. Oscillation characteristic study of wind
formulation and application. IEEE Trans Power Syst 2011;26:1349–56. speed, global solar radiation and air temperature using wavelet analysis. Appl
[13] Zerrahn A, Schill W-P. Long-run power storage requirements for high shares of Energy 2017;190:650–7.
renewables: review and a new model. Renew Sustain Energy Rev 2017;79:1518–34. [38] Sobol IM. Global sensitivity indices for nonlinear mathematical models and their
[14] Ma J, Silva V, Belhomme R, Kirschen DS, Ochoa LF. Evaluating and planning monte carlo estimates. Math Comput Simul 2001;55:271–80.
flexibility in sustainable power systems. Power and energy society general meeting [39] Bossavy A, Girard R, Kariniotakis G. Sensitivity analysis in the technical potential
(PES), 2013 IEEE. IEEE; 2013. p. 1–11. assessment of onshore wind and ground solar photovoltaic power resources at re-
[15] NERC. Probabilistic Assessment Technical Guideline Document. Technical Report. gional scale. Appl Energy 2016;182:145–53.
North American Electric Reliability Corporation; 2016. [40] Lacirignola M, Blanc P, Girard R, Perez-Lopez P, Blanc I. Lca of emerging tech-
[16] Tuohy A, Lannoye E. Metrics for quantifying flexibility in power system planning. nologies: addressing high uncertainty on inputs’ variability when performing global
Technical Report. Electric Power Research Institute; 2014. sensitivity analysis. Sci Total Environ 2017;578:268–80.
[17] Holttinen H, Kiviluoma J, Estanqueiro A, Aigner T, Wan Y-H, Milligan MR. [41] Mavromatidis G, Orehounig K, Carmeliet J. Uncertainty and global sensitivity
Variability of load and net load in case of large scale distributed wind power. 10th analysis for the optimal design of distributed energy systems. Appl. Energy
International Workshop on Large-Scale Integration of Wind Power into Power 2018;214:219–38.
Systems as well as on Transmission Networks for Offshore Wind Power Farms, [42] Rogeau A, Girard R, Kariniotakis G. A generic gis-based method for small pumped
August 2010. 2010. p. 853–61. hydro energy storage (phes) potential evaluation at large scale. Appl Energy
[18] Lumbreras S, Banez-Chicharro F, Pache C. e-Highway 2050 - Enhanced metho- 2017;197:241–53.
dology to define optimal grid architectures for 2050, Technical Report, RTE, [43] Silva R, Pérez M, Berenguel M, Valenzuela L, Zarza E. Uncertainty and global
COMILLAS, ELIA, TU BERLIN; 2015. sensitivity analysis in the design of parabolic-trough direct steam generation plants
[19] Fürsch M, Hagspiel S, Jägemann C, Nagl S, Lindenberger D, Tröster E. The role of for process heat applications. Appl Energy 2014;121:233–44.
grid extensions in a cost-efficient transformation of the european electricity system [44] Saltelli A, Ratto M, Andres T, Campolongo F, Cariboni J, Gatelli D, et al. Global
until 2050. Appl Energy 2013;104:642–52. sensitivity analysis: the primer. John Wiley & Sons; 2008.
[20] Kristiansen M, Korpås M, Svendsen HG. A generic framework for power system [45] Saltelli A, Annoni P. How to avoid a perfunctory sensitivity analysis. Environ
flexibility analysis using cooperative game theory. Appl Energy 2018;212:223–32. Modell Software 2010;25:1508–17.

1336

You might also like