You are on page 1of 2

Daffa Reandra

120310200025

Soal 1

Tabel 1 Tabel 2
Pkrja A B C D Pkrja A B C D
Order Order

I 15 20 18 0 I 0 5 3 0
II 14 16 21 0 II 0 2 7 0
III 25 22 23 0 III 3 0 1 0
IV 17 16 16 0 IV 1 0 0 0

Tabel 3 Tabel 4
Pkrja A B C D Pkrja A B C D
Order Order

I 0 3 1 0 I 0 5 3 0
II 0 0 5 0 II 0 2 7 0
III 4 0 1 1 III 3 0 1 0
IV 2 0 0 1 IV 1 0 0 0

Tabel 5 Tabel 6
Pkrja A B C D Pkrja A B C D
Order Order

I 0 3 1 0 I 0 3 1 0
II 0 0 5 0 II 0 0 5 0
III 4 1 1 1 III 4 1 1 1
IV 2 1 0 1 IV 2 1 0 1

Optimal cost = 15+16+16+0 = 47

Assignment = A/I , B/II , C/IV , D/III


Soal 2

Tabel 1 Tabel 2
Pkrja A B C D Pkrja A B C D
Order Order

I 15 20 18 19 I 0 5 3 4
II 14 16 21 18 II 0 2 7 4
III 25 22 23 19 III 6 3 4 0
IV 0 0 0 0 IV 0 0 0 0

Tabel 3 Tabel 4
Pkrja A B C D Pkrja A B C D
Order Order

I 0 3 0 4 I 0 5 3 4
II 0 0 4 4 II 0 2 7 4
III 6 1 1 0 III 6 3 4 0
IV 0 0 0 0 IV 0 0 0 0

Tabel 5 Tabel 6
Pkrja A B C D Pkrja A B C D
Order Order

I 0 2 0 4 I 0 2 0 4
II 1 0 5 5 II 1 0 5 5
III 6 1 1 0 III 6 1 1 0
IV 1 0 1 1 IV 1 0 1 1
Assignment = A/I , B/II , C/IV , D/III

Optimal cost = 15+16+0+19 =50