Professional Documents
Culture Documents
2
PMP Exam Preparation
T Project Time Management
* Project Time Management. Project Time Management includes the processes required to manage
the timely completion of the project.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
3
PMP Exam Preparation
13 PLAN SCHEDULE MANAGEMENT T
* Plan Schedule Management. The process of establishing the policies, procedures, and
documentation for planning, developing, managing, executing, and controlling the project schedule.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
4
13 PLAN SCHEDULE MANAGEMENT T
INPUTS OUTPUTS
» Project management plan Schedule management plan»
» Project charter
» Enterprise Environment
Factors
» Organizational Process
Assets TOOLS & TECHNIQUES
Expert judgment
Analytical techniques
Meetings
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 5
2013, Figure 6-3, Page 145.
13 PLAN SCHEDULE MANAGEMENT T
OUTPUTS
Schedule management plan»
* Schedule Management Plan. A component of the project management plan that establishes the
criteria and the activities for developing, monitoring, and controlling the schedule.
It includes:
• Project schedule model development
• Level of accuracy
• Units of measure
• Organizational procedures links
• Project schedule model maintenance
• Control thresholds
• Rules of performance measurement
• Reporting formats
• Process descriptions
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
6
14 DEFINE ACTIVITIES T
* Define Activities. The process of identifying and documenting the specific actions to be performed to
produce the project deliverables.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
7
14 DEFINE ACTIVITIES T
INPUTS OUTPUTS
» Schedule management plan Activity list »
» Scope baseline Activity attributes »
» Enterprise Environment Milestone list »
Factors
» Organizational Process
Assets TOOLS & TECHNIQUES
Decomposition
Rolling wave planning
Expert judgment
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 8
2013, Figure 6-5, Page 149.
14 DEFINE ACTIVITIES T
TOOLS & TECHNIQUES
Decomposition
* Decomposition. A technique used for dividing and subdividing the project scope and project
deliverables into smaller, more manageable parts.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
9
14 DEFINE ACTIVITIES T
TOOLS & TECHNIQUES
Rolling wave planning
* Rolling Wave Planning. An iterative planning technique in which the work to be accomplished in the
near term is planned in detail, while the work in the future is planned at a higher level.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
10
14 DEFINE ACTIVITIES T
OUTPUTS
Activity list »
* Activity List. A documented tabulation of schedule activities that shows the activity description,
activity identifier, and a sufficiently detailed scope of work description so project team members
understand what work is to be performed.
Activities are, in fact extensions of the WBS and should be detailed enough for all team members to
understand.
It is a project document
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
11
14 DEFINE ACTIVITIES T
OUTPUTS
Activity attributes »
* Activity Attributes. Multiple attributes associated with each schedule activity that can be included
within the activity list. Activity attributes include activity codes, predecessor activities, successor
activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints,
and assumptions.
*These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge,
(PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
12
14 DEFINE ACTIVITIES T
OUTPUTS
Milestone list »
* Milestone List. A list identifying all project milestones and normally indicates whether the milestone
is mandatory or optional.
• Mandatory: required by contract
• Optional: based upon historical information
It is a project document
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
13
15 SEQUENCE ACTIVITIES T
* Sequence Activities. The process of identifying and documenting relationships among the project
activities.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
14
15 SEQUENCE ACTIVITIES T
INPUTS OUTPUTS
» Schedule management plan Project schedule network
» Activity list diagrams »
» Activity attributes Project documents updates »
» Milestone list
» Project scope statement
» Enterprise Environment TOOLS & TECHNIQUES
Factors
» Organizational Process Precedence diagramming method
Assets (PDM)
Dependency determination
Leads and lags
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 15
2013, Figure 6-7, Page 153.
15 SEQUENCE ACTIVITIES T
TOOLS & TECHNIQUES
Precedence diagramming method
(PDM)
* Precedence Diagramming Method (PDM). A technique used for constructing a schedule model in
which activities are represented by nodes and are graphically linked by one or more logical
relationships to show the sequence in which the activities are to be performed.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
16
15 SEQUENCE ACTIVITIES T
TOOLS & TECHNIQUES
Precedence diagramming method
(PDM)
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc.,
2013, Figure 6-9, Page 157.
17
15 SEQUENCE ACTIVITIES T
TOOLS & TECHNIQUES
Precedence diagramming method
(PDM)
• Arrow diagramming method (ADM) is a network diagramming technique in which activities are
represented by arrows. ADM is also known as the activity-on-arrow (AOA) method
• Graphical Evaluation and Review Technique (GERT): Allow loops and conditional branches (if
conditions)
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
18
15 SEQUENCE ACTIVITIES T
TOOLS & TECHNIQUES
Dependency determination
*These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge,
(PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
19
15 SEQUENCE ACTIVITIES T
TOOLS & TECHNIQUES
Leads and lags
* Lag. The amount of time whereby a successor activity is required to be delayed with respect to a
predecessor activity.
* Lead. The amount of time whereby a successor activity can be advanced with respect to a
predecessor activity.
A LAG B
A
LEAD
B
20
15 SEQUENCE ACTIVITIES T
OUTPUTS
Project schedule network
diagrams »
* Project Schedule Network Diagram. A graphical representation of the logical relationships among
the project schedule activities.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –
Fifth Edition, Project Management Institute, Inc., 2013.
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc.,
2013, Figure 6-11, Page 160.
21
15 SEQUENCE ACTIVITIES T
OUTPUTS
Project documents updates »
• Activity lists
• Activity attributes
• Milestone list
• Risk register
22
16 ESTIMATE ACTIVITY RESOURCES T
* Estimate Activity Resources. The process of estimating the type and quantities of material, human
resources, equipment, or supplies required to perform each activity.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
23
16 ESTIMATE ACTIVITY RESOURCES T
INPUTS OUTPUTS
» Schedule management plan Activity resource
» Activity list requirements »
» Activity attributes Resource breakdown
» Resource calendars structure »
» Risk register Project documents updates »
» Activity cost estimates TOOLS & TECHNIQUES
» Enterprise Environment
Factors Expert judgment
» Organizational Process Alternative analysis
Assets Published estimating data
Bottom-up estimating
Project management software
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 24
2013, Figure 6-12, Page 161.
16 ESTIMATE ACTIVITY RESOURCES T
INPUTS
» Resource calendars
• Document the time periods that each project team member is available to work on the project.
• May not have the resource calendars the first time when is run this process, but eventually they
are needed to better estimate resources.
• Resource calendars is mentioned as direct output and direct input for the following processes:
Estimate Activity
Resource calendars map Durations
Conduct
Determine Budget Planning
Procurement Legend:
process
Executing
Develop Project process
Team
25
16 ESTIMATE ACTIVITY RESOURCES T
INPUTS
» Risk register
For example a risk about a resource availability can lead to a different output of Estimate Activity
Resources.
26
16 ESTIMATE ACTIVITY RESOURCES T
INPUTS
» Activity cost estimates
The cost of resources may be something to think about as different resources options are considered.
Estimate Activity
Resources
Determine Budget
Activity cost estimates
Estimate Costs
Identify Risks
27
16 ESTIMATE ACTIVITY RESOURCES T
INPUTS
» Enterprise Environment
Factors
EEF examples:
• Resource location
• Resource availability
• Resource skills
28
16 ESTIMATE ACTIVITY RESOURCES T
INPUTS
» Organizational Process
Assets
OPA examples:
29
16 ESTIMATE ACTIVITY RESOURCES T
TOOLS & TECHNIQUES
Alternative analysis
* Alternative Analysis. A technique used to evaluate identified options in order to select which options
or approaches to use to execute and perform the work of the project.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
30
16 ESTIMATE ACTIVITY RESOURCES T
TOOLS & TECHNIQUES
Published estimating data
In some industries there are published resource usage for different activities and unit costs for labor,
material etc.
In this technique, the activity is compared to the activities for which data exists and resources of the
closest comparable activity is selected from the data and used as the estimate.
31
16 ESTIMATE ACTIVITY RESOURCES T
TOOLS & TECHNIQUES
Bottom-up estimating
* Bottom-Up Estimating. A method of estimating project duration or cost by aggregating the estimates of
the lower-level components of the work breakdown structure (WBS).
• Advantage: it’s very accurate and gives lower-level managers more responsibility.
• Disadvantage: May be very time consuming and can be used only after the WBS has been well-defined.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
32
16 ESTIMATE ACTIVITY RESOURCES T
TOOLS & TECHNIQUES
Project management software
Project management software with different characteristics can be used to gather, process, store, and
share activity resource estimates:
• Client – Server applications
• Standalone applications
• Cloud applications
• Mobile applications
33
16 ESTIMATE ACTIVITY RESOURCES T
OUTPUTS
Activity resource
requirements »
* Activity Resource Requirements. The types and quantities of resources required for each activity
in a work
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
34
16 ESTIMATE ACTIVITY RESOURCES T
OUTPUTS
Resource breakdown
structure »
testers
developers
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
35
16 ESTIMATE ACTIVITY RESOURCES T
OUTPUTS
Project documents updates »
• Activity attributes
• Resource calendars
• Activity list
36
17 ESTIMATE ACTIVITY DURATIONS T
* Estimate Activity Durations. The process of estimating the number of work periods needed to
complete individual activities with estimated resources.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
37
17 ESTIMATE ACTIVITY DURATIONS T
INPUTS OUTPUTS
» Schedule management plan Activity duration
» Activity list estimates »
» Activity attributes Project documents updates »
» Activity resource
requirements
» Resource calendars TOOLS & TECHNIQUES
» Project scope statement
» Risk register Expert judgment
» Resource breakdown structure Analogous estimating
» Enterprise Environment Parametric estimating
Factors Three-point estimating
» Organizational Process Group decision-making techniques
Assets Reserve analysis
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 38
2013, Figure 6-14, Page 166.
17 ESTIMATE ACTIVITY DURATIONS T
INPUTS
» Activity resource
requirements
• Efficiency and productivity must be taken into account when moving from resource requirements
to duration estimates.
• For example if an activity has 16 hours of standard engineer effort estimated and there is
available an above average standard engineer, the duration (in case of 100% allocation) should
be less than 2 days.
39
17 ESTIMATE ACTIVITY DURATIONS T
INPUTS
» Resource calendars
• Besides efficiency and productivity, the resource possible allocation should be taken into account.
• For example if an activity has 16 hours of standard engineer effort estimated and a resources is available
only 50%, that means maybe 4 days of work.
Estimate Activity
Durations
Conduct
Determine Budget Planning
Procurement Legend:
process
Executing
Develop Project process
Team
40
17 ESTIMATE ACTIVITY DURATIONS T
INPUTS
» Project scope statement
Constraints and assumptions that are listed in the project scope statement may affect activity
durations.
For example:
• Resource availability
• Contract terms and conditions
41
17 ESTIMATE ACTIVITY DURATIONS T
TOOLS & TECHNIQUES
Analogous estimating
* Analogous Estimating. A technique for estimating the duration or cost of an activity or a project using
historical data from a similar activity or project.
Characteristics:
• Limited amount of data available
• Less costly
• Quicker
• Less accurate.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
42
17 ESTIMATE ACTIVITY DURATIONS T
TOOLS & TECHNIQUES
Parametric estimating
Characteristics:
• Enough data to create statistics
• More costly
• Slower – because a statistical model should be developed
• More accurate
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
43
17 ESTIMATE ACTIVITY DURATIONS T
TOOLS & TECHNIQUES
Three-point estimating
• Most likely (tM). The duration of the activity, based on realistic effort assessment for the required
work and any predicted expenses.
• Optimistic (tO). The activity duration based on analysis of the best-case scenario for the activity.
• Pessimistic (tP). The activity duration based on analysis of the worst-case scenario for the activity.
Depending on the assumed distribution of values within the range of the three estimates the expected
duration, tE, can be calculated using a formula. Two commonly used formulas are triangular and beta
distributions. The formulas are:
• Triangular Distribution. tE = (tO + tM + tP) / 3
• Beta Distribution (from a traditional PERT analysis). tE = (tO + 4tM + tP) / 6
44
17 ESTIMATE ACTIVITY DURATIONS T
TOOLS & TECHNIQUES
Group decision-making techniques
More accurate estimates and greater commitment may be obtained by working as a team on estimates.
Example of techniques include:
• Delphi technique
• Nominal group technique
• Brainstorming
45
17 ESTIMATE ACTIVITY DURATIONS T
TOOLS & TECHNIQUES
Reserve analysis
46
17 ESTIMATE ACTIVITY DURATIONS T
OUTPUTS
Activity duration
estimates »
47
17 ESTIMATE ACTIVITY DURATIONS T
OUTPUTS
Project documents updates »
• Activity attributes
• Assumptions made
skill levels
availability
basis of estimates for durations
48
18 DEVELOP SCHEDULE T
* Develop Schedule. The process of analyzing activity sequences, durations, resource requirements,
and schedule constraints to create the project schedule model.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
49
18 DEVELOP SCHEDULE T
INPUTS OUTPUTS
» Schedule management plan Schedule baseline »
» Activity list Project schedule »
» Activity attributes Schedule data »
» Project schedule network Project calendars »
diagrams Project management plan
» Activity resource TOOLS & TECHNIQUES updates »
requirements Project documents updates »
» Resource calendars Schedule network analysis
» Activity duration estimates Critical path method
» Project scope statement Critical chain method
» Risk register Resource optimization techniques
» Project staff assignments Modeling techniques
» Resource breakdown structure Leads and lags
» Enterprise Environment Schedule compression
Factors Scheduling tool
» Organizational Process
Assets
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 50
2013, Figure 6-16, Page 173.
18 DEVELOP SCHEDULE T
INPUTS
» Project staff assignments
51
18 DEVELOP SCHEDULE T
TOOLS & TECHNIQUES
Schedule network analysis
* Schedule Network Analysis. The technique of identifying early and late start dates, as well as early
and late finish dates, for the uncompleted portions of project schedule activities.
* Path Convergence. A relationship in which a schedule activity has more than one predecessor.
* Path Divergence. A relationship in which a schedule activity has more than one successor.
*These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge,
(PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
52
18 DEVELOP SCHEDULE T
TOOLS & TECHNIQUES
Critical path method
Critical Path Method (CPM). * A method used to estimate the minimum project duration and determine
the amount of scheduling flexibility on the logical network paths within the schedule model.
Critical Path Activity. * Any activity on the critical path in a project schedule.
Critical Path. * The sequence of activities that represents the longest path through a project, which
determines the shortest possible duration.
Total Float (Total Slack). * The amount of time that a schedule activity can be delayed or extended
from its early start date without delaying the project finish date or violating a schedule constraint.
Free Float (Free Slack). * The amount of time that a schedule activity can be delayed without delaying
the early start date of any successor or violating a schedule constraint.
*These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge,
(PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
53
18 DEVELOP SCHEDULE T
TOOLS & TECHNIQUES
Critical path method
Duration (DU or DUR). * The total number of work periods (not including holidays or other nonworking
periods) required to complete a schedule activity or work breakdown structure component. Usually
expressed as workdays or workweeks. Sometimes incorrectly equated with elapsed time. Contrast with
effort.
Early Finish Date (EF). * In the critical path method, the earliest possible point in time when the
uncompleted portions of a schedule activity can finish based on the schedule network logic, the data
date, and any schedule constraints.
Early Start Date (ES). * In the critical path method, the earliest possible point in time when the
uncompleted portions of a schedule activity can start based on the schedule network logic, the data
date, and any schedule constraints
Late Finish Date (LF). * In the critical path method, the latest possible point in time when the
uncompleted portions of a schedule activity can finish based on the schedule network logic, the project
completion date, and any schedule constraints.
Late Start Date (LS). * In the critical path method, the latest possible point in time when the
uncompleted portions of a schedule activity can start based on the schedule network logic, the project
completion date, and any schedule constraints.
*These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge,
(PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
54
18 DEVELOP SCHEDULE T
TOOLS & TECHNIQUES
Critical path method
EARLY EARLY
DURATION
START FINISH
A
LATE TOTAL LATE
START FLOAT FINISH
55
18 DEVELOP SCHEDULE T
TOOLS & TECHNIQUES
Critical path method
Total Float (Total Slack). * The amount of time that a schedule activity can be delayed or extended
from its early start date without delaying the project finish date or violating a schedule constraint.
Free Float (Free Slack). * The amount of time that a schedule activity can be delayed without delaying
the early start date of any successor or violating a schedule constraint.
Total Float = LS – ES or LF - EF
*These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge,
(PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
56
18 DEVELOP SCHEDULE T
TOOLS & TECHNIQUES
Critical path method
Forward Pass. * A critical path method technique for calculating the early start and early finish dates by
working forward through the schedule model from the project start date or a given point in time.
Backward Pass. * A critical path method technique for calculating the late start and late finish dates by
working backward through the schedule model from the project end date.
*These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge,
(PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
57
18 DEVELOP SCHEDULE T
TOOLS & TECHNIQUES
Critical path method
Forward Pass
0 2 2 2 4 6
A B
0 0 2 2 0 6
START FINISH
0 3 3 3 1 4
C D
Path A-B = 6
Path 2 2 5 ES DU EF
5 2 6
Path C-D = 4
ACTIVITY NAME
Total Float = LS – ES or Backward Pass
Total Float = LF - EF LS F LF
58
18 DEVELOP SCHEDULE T
TOOLS & TECHNIQUES
Critical chain method
Critical Chain Method (CCM). * A schedule method that allows the project team to place buffers on
any project schedule path to account for limited resources and project uncertainties.
• Instead of managing the total float of network paths, the critical chain method focuses on managing
the remaining buffer durations against the remaining durations of chains of activities.
• The method was developed by Goldratt
• This method tries to strike a balance between what is anticipated for the project from:
Parkinson‟s Law – work will expand to fill the time available
Student syndrome: procrastination
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
59
18 DEVELOP SCHEDULE T
TOOLS & TECHNIQUES
Resource optimization techniques
Resource Optimization Techniques. * A technique that is used to adjust the start and finish dates of
activities that adjust planned resource use to be equal to or less than resource availability.
* A technique in which start and finish dates are * A technique which adjusts the activities of a
adjusted based on resource constraints with the schedule model such that the requirement for
goal of balancing demand for resources with the resources on the project do not exceed certain
available supply. predefined resource limits.
Resources constrained Time constrained
*These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge,
(PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
60
18 DEVELOP SCHEDULE T
TOOLS & TECHNIQUES
Modeling techniques
• What-If Scenario Analysis. It is the process of evaluating scenarios in order to predict their effect,
positively or negatively, on project objective
• Simulation. It involves calculating multiple project durations with different sets of activity
assumptions, usually using probability distributions constructed from the three-point estimates
Monte Carlo Simulation. * A process which generates hundreds or thousands of probable
performance outcomes based on probability distributions for cost and schedule on individual
tasks. The outcomes are then used to generate a probability distribution for the project as a
whole.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
61
18 DEVELOP SCHEDULE T
TOOLS & TECHNIQUES
Schedule compression
Schedule Compression. * Techniques used to shorten the schedule duration without reducing the
project scope.
*These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge,
(PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
62
18 DEVELOP SCHEDULE T
OUTPUTS
Schedule baseline »
Schedule Baseline. * The approved version of a schedule model that can be changed only through
formal change control procedures and is used as a basis for comparison to actual results.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
63
18 DEVELOP SCHEDULE T
OUTPUTS
Project schedule »
Project Schedule. * An output of a schedule model that presents linked activities with planned dates,
durations, milestones, and resources.
*These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge,
(PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
64
18 DEVELOP SCHEDULE T
OUTPUTS
Project schedule »
65
18 DEVELOP SCHEDULE T
OUTPUTS
Schedule data »
Schedule Data. * The collection of information for describing and controlling the schedule.
Example of information that may be contained:
• Resource requirements by time period, often in the form of a resource histogram
• Alternative schedules, such as best-case or worst-case, not resource-leveled, or resource-
leveled, with or without imposed dates
• Scheduling of contingency reserves
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
66
18 DEVELOP SCHEDULE T
OUTPUTS
Project calendars »
The project calendars identify working days, time periods and shifts that are available for scheduled
activities.
67
18 DEVELOP SCHEDULE T
OUTPUTS
Project documents updates »
68
19 CONTROL SCHEDULE T
Control Schedule. * The process of monitoring the status of project activities to update project
progress and manage changes to the schedule baseline to achieve the plan.
It is concerned with:
• Determining the current status of the project schedule
• Influencing the factors that create schedule changes
• Determining if the project schedule has changed
• Managing the actual changes as they occur
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
69
19 CONTROL SCHEDULE T
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013, Page 187.
70
19 CONTROL SCHEDULE T
INPUTS OUTPUTS
» Project management plan Work performance
» Project schedule information »
» Work performance data Schedule forecast »
» Project calendars Change requests »
» Schedule data Project management plan
» Organizational Process TOOLS & TECHNIQUES Updates »
Assets Project documents updates »
Performance reviews Organizational Process Assets
Project management software updates »
Resource optimization techniques
Modeling techniques
Leads and lags
Schedule compression
Scheduling tool
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 71
2013, Figure 6-22, Page 185.
19 CONTROL SCHEDULE T
72
19 CONTROL SCHEDULE T
TOOLS & TECHNIQUES
Performance reviews
Performance Reviews. * A technique that is used to measure, compare, and analyze actual
performance of work in progress on the project against the baseline.
• Trend Analysis. * An analytical technique that uses mathematical models to forecast future
outcomes based on historical results. It is a method of determining the variance from a baseline of a
budget, cost, schedule, or scope parameter by using prior progress reporting periods’ data and
projecting how much that parameter’s variance from baseline might be at some future point in the
project if no changes are made in executing the project.
• Critical path method
• Critical chain method
• Earned value management is used to assess the magnitude of variation to the original schedule
baseline (will be detailed in Cost Management Area)
*These definitions are taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge,
(PMBOK® Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
73
19 CONTROL SCHEDULE T
TOOLS & TECHNIQUES
Project management software
74
19 CONTROL SCHEDULE T
OUTPUTS
Schedule forecast »
Schedule Forecasts. * Estimates or predictions of conditions and events in the project’s future
based on information and knowledge available at the time the schedule is calculated.
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Fifth Edition, Project Management Institute, Inc., 2013.
75
19 CONTROL SCHEDULE T
OUTPUTS
Project documents updates »
• Schedule Data
• Project schedule
• Risk register
76
T Project Time Management
77
T Project Time Management
still
25 Questions
20 minutes
79
PMP Exam Preparation